Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Confederation Of Rea... v. Department Of Town A...

Competition Commission Of India
Apr 6, 2018
Smart Summary (Beta)

Structured Summary: Competition Commission of India — Case No. 40 of 2017 (CREDAI‑NCR v. DTCP & HUDA)

Factual and Procedural Background

The information was filed under Section 19(1)(a) of the Competition Act, 2002 by Confederation of Real Estate Developers Association of India - NCR ("CREDAI‑NCR" or the Informant) against the Department of Town and Country Planning, Government of Haryana (OP‑1 / DTCP) and Haryana Urban Development Authority (OP‑2 / HUDA) alleging contravention of Section 4 of the Competition Act, 2002 (abuse of dominant position).

Broad factual allegations in the information were that OP‑1/OP‑2 issued the Sohna Master Plan 2031 and entered into Letters of Intent, bilateral agreements and licences with developers for development of colonies in Sohna (Gurugram District). The Informant alleged that certain terms in the Sohna LOI / Sohna Agreement / Sohna Licence were unfair and discriminatory: developers were being compelled to pay External Development Charges (EDC) and Infrastructure Development Charges (IDC) on tight timelines and interest, while the OPs had not carried out the corresponding external development works and had no transparent mechanism or accountability for execution or expenditure of funds.

The Informant requested that the Commission direct the Director General (DG) to investigate; restrain the OPs from encashing bank guarantees and from demanding or increasing EDC/IDC/interest pending adjudication; direct renegotiation of agreements or restitution where appropriate; and impose penalties for abuse of dominance.

Procedurally, the Commission called a preliminary conference, directed OPs to file replies, received a counter‑affidavit from OP‑1, and heard the parties. OP‑1 challenged the Commission's jurisdiction and raised other defenses, including reliance on decisions/orders in High Court/Supreme Court proceedings. The Commission addressed the preliminary issue of jurisdiction before reaching the merits and ultimately directed the DG to investigate the matter.

Legal Issues Presented

  1. Whether the OPs (DTCP / HUDA) fall within the statutory definition of "enterprise" under Section 2(h) of the Competition Act such that the Commission has jurisdiction to entertain the information.
  2. Whether the developers who obtain licences from OP‑1 qualify as "consumers" under Section 2(f) of the Act for the purposes of the complaint.
  3. Whether the Commission should decline to proceed because substantially similar matters were pending before the Hon'ble Supreme Court or decided by the High Court.
  4. Whether, on a prima facie basis, the OPs are dominant in the relevant market and whether their conduct prima facie constitutes abuse of dominant position in contravention of Section 4 of the Act (particularly Section 4(2)(a)(i)).
  5. If jurisdiction exists and prima facie abuse is found, whether the matter should be directed for investigation by the Director General.

Arguments of the Parties

Informant (CREDAI‑NCR) — Key Allegations and Requests

  • The Sohna LOI / Sohna Agreement / Sohna Licence contain unilateral, unfair and discriminatory terms that impose onerous obligations on developers (including payment of EDC/IDC and interest) without adequate or timely performance of external development works by the OPs.
  • The OPs unilaterally fixed charges and payment schedules without disclosing basis/calculation or implementation timelines and without any enforcement mechanism for OPs' obligations.
  • OPs retained the power to revise EDC/IDC later (“subject to revision as per actual charges incurred”) and could demand additional payments and interest; developers face penalties despite lack of development or land acquisition by OPs.
  • The OPs' use and deployment of EDC/IDC funds lacked transparency; RTI requests did not yield itemised information and suggested diversion of funds to other projects.
  • Relief sought included directing DG to investigate, restraining encashment of bank guarantees, restraining collection of EDC/IDC/interest, directing renegotiation of agreements and returning interest where development not carried out, and imposing penalties under the Act.

OP‑1 (Department of Town and Country Planning, Government of Haryana) — Key Defenses and Contentions

  • Jurisdiction: OP‑1 contended it is not an "enterprise" under Section 2(h) because it performs planning and implementing functions under statutory enactments and is not engaged in production, supply or provision of services as contemplated by that definition.
  • Consumer status: Developers do not buy goods or avail services for consideration from OP‑1 as defined in Section 2(u)/(f), and therefore are not "consumers" under the Act.
  • Statutory character of agreements: The agreements and the terms (including EDC/IDC, interest, payment schedules and other charges) arise from the Haryana Development Act and the Rules of 1976 and are not anti‑competitive agreements under Sections 3 or 4 of the Act.
  • Judicial proceedings: The issues were already examined and dismissed by the Hon'ble High Court in CWP No. 9558 of 2015 (VPN Buildtech & others) by order dated 15.12.2015, and some matters were pending as Special Leave Petitions (e.g., Magnolia Propbuild SLP No. 5459 of 2016) before the Hon'ble Supreme Court; the Supreme Court had granted interim protection restraining encashment of bank guarantees (interim order 31.03.2016).
  • Justification for charging interest: Interest and penal interest provisions are part of the LC‑IV contract into which developers voluntarily entered; developers had an option to pay in lump sum without interest or in instalments with interest; penal interest for default is contractually provided.
  • Practical impossibility of proportional execution: External Development Works cannot realistically be executed in direct proportion to amounts paid by individual developers; many external facilities require comprehensive execution and are long‑gestation projects funded once collected from multiple developers.
  • Non‑payment by developers: Many licensees had not paid EDC instalments; OP‑1 contended that absence of funds from developers constrained initiation of external works and the allegations that OPs failed to perform are unfounded.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
VPN Buildtech Pvt. Ltd. v. State of Haryana and Others (CWP No. 9558 of 2015) — High Court of Punjab & Haryana, order dated 15.12.2015 OP‑1 relied on this High Court order as having examined and decided issues raised by developers concerning the unilateral/arbitrary nature of agreement terms and liability to pay tentative/ad hoc EDC, timing of EDC collection and liability for interest. The Commission recorded that OP‑1 had cited this High Court decision as having dismissed developers' petitions on these issues. The Commission noted the existence of that order but did not treat it as ousting its jurisdiction; instead it proceeded to consider the competition law aspects and whether an investigation is warranted.
Magnolia Propbuild Pvt. Ltd. v. State of Haryana and Others (SLP No. 5459 of 2016) — Special Leave Petition pending before the Supreme Court; interim order dated 31.03.2016 OP‑1 pointed to pending SLP(s) before the Supreme Court regarding similar grievances; the Supreme Court had, by interim order, restrained OP‑1 from encashing bank guarantees submitted on account of non‑payment of EDC. The Commission acknowledged the pendency of SLP(s) and the interim order restraining encashment of bank guarantees but held that concurrent remedies or pending proceedings in other fora do not automatically oust the Commission’s jurisdiction under the Competition Act; the Commission therefore proceeded to direct an investigation.

Court's Reasoning and Analysis

The Commission proceeded in a structured manner: it first considered the preliminary question of jurisdiction and then addressed the merits to determine whether a prima facie case for investigation under Section 4 existed.

1. Jurisdiction — "Enterprise" and "Consumer" definitions

The Commission analysed Section 2(h) which defines "enterprise" to include a person or a government department engaged in activities relating to production, supply or provision of services, except sovereign functions carved out (atomic energy, currency, defence, space). The Commission observed that merely being a statutory body or performing statutory duties does not automatically render the activities sovereign and excluded. The levy of EDC/IDC by OP‑1 has direct economic/commercial impact. Therefore the Commission concluded that OP‑1 falls within the ambit of "enterprise".

Similarly, the Commission examined the definition of "consumer" and noted that it includes intermediate consumers who avail services for commercial purposes. Developers pay fees/charges to OP‑1 and thereby avail services of a commercial/economic nature. The Commission concluded that the developers qualify as "consumers" under the Act.

2. Effect of parallel judicial proceedings

The Commission addressed the submission that because similar issues were pending before the High Court / Supreme Court, the Commission should not proceed. The Commission relied on statutory text and reasoning: the Competition Act's provisions are in addition to other laws (Section 62) and the Commission's jurisdiction is not per se ousted by remedies before other fora. The Commission found this contention devoid of merit and held it could proceed simultaneously with other proceedings, particularly as the other proceedings did not specifically address abuse of dominant position under Section 4.

3. Relevant market delineation

To examine Section 4 conduct, the Commission determined the relevant market. It considered the Informant's description and the facts as to CREDAI‑NCR's membership and the subject matter (development of group housing colony at Sohna). The Commission defined the relevant product market as "market for issue of licenses and development of infrastructure for residential plotted/ group housing/ commercial colonies" and the relevant geographic market as the "State of Haryana", reasoning that OP‑1/OP‑2's jurisdiction covers all urban areas of Haryana and cannot be confined to a single tehsil.

4. Dominance — prima facie position of strength

The Commission noted that OP‑1 is the only department that can issue licences to developers and OP‑2 is the only authority entrusted to undertake external development works in Haryana for such colonies. Developers are dependent on these statutory authorities. On this basis, the Commission concluded that, prima facie, OP‑1 and OP‑2 hold a dominant position in the delineated relevant market.

5. Abuse — prima facie assessment

Applying the factual allegations to Section 4, the Commission considered the Informant's contentions that: (i) OPs had not acquired land nor initiated external development works despite levying EDC/IDC; (ii) large sums (stated by Informant as Rs. 375.38 crores EDC and Rs. 137.18 crores IDC deposited) had been collected without transparent deployment; and (iii) the agreements were one‑sided, excluding liability of OP‑1 and imposing penal interest on developers. OP‑1's responses (non‑payment by developers, contractual basis of interest provisions, practical impossibility of proportional execution) were noted.

Balancing the submissions at the prima facie stage, the Commission found that the terms of the LOI/Agreement/Licence, though rooted largely in statutory provisions, appeared one‑sided in favour of OPs and that OPs’ failure to undertake external development works while levying charges and interest appeared, prima facie, to be an abusive exercise of dominant position—specifically implicating Section 4(2)(a)(i) (imposition of unfair or discriminatory conditions) to the detriment of developers and ultimately end consumers (allottees/home‑buyers).

6. Conclusion on next steps

Given the prima facie findings on jurisdiction, dominance and potential abuse, the Commission directed the DG to carry out a formal investigation to probe the allegations, with a completion timeframe and procedural directions. The Commission expressly stated that its observations were prima facie and would not preclude the DG from conducting an independent and unimpaired investigation; nothing in the order constituted a final expression on merits.

Holding and Implications

Holding: The Commission directed an investigation by the Director General into the conduct of OP‑1 and OP‑2 regarding the levy and use of EDC/IDC, the terms of Sohna LOI/Agreement/Licence and alleged abusive conduct under Section 4 of the Competition Act. The DG was directed to complete the investigation within 60 days from receipt of the Order, and the Secretary was directed to forward the information and documents to the DG.

Immediate implications and direct effects:

  • The DG is formally mandated to investigate the matter and report back within 60 days.
  • The Commission clarified that its prima facie observations are not final determinations on merits; the DG must conduct the investigation independently and without being influenced by the Commission's interim observations.
  • The Commission retained jurisdiction to examine competition law aspects even though related litigation exists in other courts (High Court and pending SLPs before the Supreme Court); the pendency of those matters did not prevent the Commission from initiating an investigation under the Act.

No assertion of a new binding legal precedent is recorded in the order; the Commission proceeded on a prima facie basis to investigate alleged contraventions of Section 4 and did not finally decide the merits.

Order signed by Members: Sudhir Mital, Augustine Peter, U. C. Nahta and Justice G. P. Mittal. Dated: 06.04.2018, New Delhi.

Show all summary ...

Case No. 40 of 2017 Page 1 of 19

COMPETITION COMMISSION OF INDIA

Case No. 40 of 2017

In re:

Confederation of Real Estate Developers Association of India-NCR (CREDAI-NCR) Informant And

Department of Town and Country Planning, Government of Haryana …OP-1

Haryana Urban Development Authority …OP-2

CORAM

Mr. Sudhir Mital Member

Mr. Augustine Peter Member

Mr. U. C. Nahta Member

Justice G. P. Mittal Member

Appearances:

For Informant Ms. Payel Chatterjee, Advocate Mr. Atikant Kaur Sahni, Advocate Mr. Sushant Gupta, Director, CREDAI-NCR Mr. Salman Akhbar, Member, CREDAI-NCR For OP Mr. Shivam Kumar, Advocate

1

Order under Section 26 (1) of the Competition Act, 2002

1. The present information has been filed under Section 19(1)(a) of the Competition Act, 2002 (hereinafter, the 'Act') by Confederation of Real Estate Developers Association of India - NCR (hereinafter, the 'Informant'/ 'CREDAI-NCR') against Department of Town and Country Planning, Government of Haryana (hereinafter, 'OP-1'/ 'DTCP') and Haryana Urban Development Authority, (hereinafter, 'OP-2'/ 'HUDA') (hereinafter, OP-1 and OP-2 collectively referred to as the 'OPs') alleging contravention of the provisions of Section 4 of the Act.

2. According to the information, the Informant is the National Capital Region ('NCR') chapter of the Confederation of Real Estate Developers Association of India ('CREDAI') which is an organisation representing around 12000 real estate developers spread across 23 states. Further, all the leading real estate developers of NCR are the members of the Informant.

3. OP-1 is a department of the Government of Haryana empowered to regulate urban development in the State of Haryana. The policies of OP-1 aim at encouraging healthy competition amongst various private developers and public sector entities for integrated planned urban development. It also renders advisory services to various corporations and boards such as OP-2, Housing Board of Haryana, Haryana State Industrial & Infrastructure Development Corporation Ltd. and Haryana State Marketing Board.

4. OP-2 is an authority created under the Haryana Urban Development Authority Act, 1977 (hereinafter, the 'HUDA Act'). It has been delegated the task of planned development of urban areas in Haryana in order to:

(i) promote and secure development of urban areas in a systematic and planned way with the power to acquire, sale and dispose of property, both

2

movable and immovable; (ii) use the acquired land for residential, industrial, recreational and commercial purposes; (iii) make available developed land to Haryana Housing Board and other bodies for providing houses to economically weaker sections of the society; and (iv) undertake building works.

5. As per the information, OP 2 has been empowered under Section 51(1) of the HUDA Act to grant licenses to developers for development of real estate in the State of Haryana and OP 2 has delegated this power to OP-1. As per the Informant, OP-1, by virtue of this power, has been entering into Letter of Intent (hereinafter, 'LOI') with prospective developers and thereafter granting licenses to them under the HUDA Act for development of colonies in the State of Haryana.

6. It is stated in the information that on 15.11.2012, OP-1 had issued the Sohna Master Plan 2031 (hereinafter, 'Sohna Master Plan') for Group Housing Colony in the revenue estate of Tehsil Sohna of Gurugram District in Haryana. Based on this plan, various developers submitted their bids and thereafter, the Sohna Letter of Intent (hereinafter, 'Sohna LOI') were executed between each developer and the Director of OP-1. It is stated that before exeution of the LOI, the developers had fulfilled the conditions stipulated under the Haryana Development and Regulation of Urban Areas Development Act, 1975 (hereinafter, the 'Haryana Development Act') and the Haryana Development and Regulation of Urban Areas Development Rules, 1976 (hereinafter, the 'Rules of 1976') including submission of the bank guarantee towards External Development Charges (hereinafter, 'EDC'), Infrastructure Development Charges (hereinafter, 'IDC') and other charges and fees viz. conversion charges, license fees and scrutiny fees. Thereafter, bilateral agreements (hereinafter, 'Sohna Agreement') between developers

3

and Director of OP-1 were executed and licences (hereinafter, 'Sohna License') were issued to the developers.

7. It is alleged in the information that some of the terms and conditions of the Sohna License, Sohna LOI and Sohna Agreement are unfair and discriminatory. It is averred that through the Sohna LOI, the OPs impose unfair and extensive obligations on the developers in terms of the development works that the developer must carry out in the specified territory and the charges levied on them are also required to be paid within tight timelines. Further, the conditions therein obligate the developers to pay EDC as and when demanded. However, no claim for damages lies against the OPs for delay in provision of development facilities.

8. It is further alleged that the charges and payment schedule in the Sohna Master Plan has been decided by the OPs unilaterally without making available the basis of calculation of these charges or implementation schedule of the development work. The Informant has submitted that although the OPs were obligated under the Haryana Development Act to carry out development work, there is no mechanism for enforcement of these obligations under the Sohna LOI/ Sohna Agreement/ Sohna License.

9. The Informant has further alleged that under the terms of the Sohna License, EDC are subject to revision as per the actual charges incurred including any enhanced land acquisition costs, which is to be worked out later and the developer is liable to pay an additional amount as and when directed. Furthermore, the assumption on costs or timelines with respect to the development of infrastructure are also not disclosed.

10. In addition, the Sohna LOI obligates the developers to pay interest on delayed payment of EDC and IDC to the OPs. It is alleged that the OPs are levying

4

an exorbitant rate of interest on EDC and IDC on developers onerously without any authority under the Haryana Development Act. Further, the developers are forced to accept fulfilment of such supplementary obligations of payment of interest, which has not been contemplated in the Haryana Development Act.

11. Further, it is alleged that no activity on infrastructure development has been initiated by the OPs, which has further delayed the development of the projects. But under the license agreement, the charges and interest continue to be levied on the developers causing undue hardship in the development of their respective projects. It is alleged that in the light of inaction by the OPs, the developers are faced with the impossible task of fulfilling their obligations under the Sohna LOI, Sohna Agreement and Sohna License within strict timelines and potential penalties covering land that has not even been acquired by the OPs. Additionally, the developers are also simultaneously exposed to hefty claims from consumers under Consumer Protection Act, 1986 for failing to allot plots to them within the timelines stipulated under arrangements between the developers and consumers.

12. In view of the above facts, the Informant has prayed the Commission to direct the Director General (hereinafter, the 'DG') to cause an investigation into the affairs of the OPs in performing their obligations under the HUDA Act and Haryana Urban Development Act and abuse of their position in the State of Haryana; restrain the OPs from invoking the bank guarantee against the developers pending adjudication of this information; restrain the OPs and direct them to cease and desist from compelling developers to pay any pending EDC and IDC or any increase thereof along with interest; direct the OPs to renegotiate the licenses and bilateral agreements with realistic time- schedules based on mutually agreeable development milestones and payment schedules; direct the OPs to return interest on EDC and IDC paid in advance

5

by the developers in territories where they have carried out no development work; direct the OPs to revise the EDC and IDC as mutually feasible and as per reasonably acceptable development schedule; impose penalty on the OPs for abusing their dominant position to the prejudice of the developers; and pass such other and further order, as the Commission may deem fit and proper in the circumstances of the case.

13. The Commission considered the information in its ordinary meeting held on 31.08.2017 and decided to have a preliminary conference with the parties on 27.09.2017. On 27.09.2017, the Informant and the OPs appeared through their respective learned counsel. While the learned counsel for the Informant argued the matter, the learned counsel appearing on behalf of the OPs sought extension of time to file a response to the information. The Commission directed the OPs to file their reply within four weeks. Subsequently, a counter affidavit dated 08.12.2017 was filed by OP-1.

14. In the counter-affidavit, OP-1 has submitted that the present complaint is not maintainable, as OP-1 does not fall within the definition of 'enterprise' as defined in Section 2(h) of the Act. It is not engaged in any activity relating to the production, storage, supply, distribution, acquisition or control of articles or goods or the provision of services of any kind. It only deals with the planning of urban areas and is the implementing agency for the provisions of the Haryana Development Act and Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Act, 1963 (hereinafter, the 'Punjab Development Act'). It is averred that as none of the functions being performed by OP-1 under these Acts fall within the definition of 'enterprise' as defined in the Section 2(h) of the Act, the present complaint ought to be dismissed.

6

15. Further, OP-1 has argued that since the developers neither buy any goods nor hire or avail any service as defined in Section 2(u) for consideration from OP-1, neither the Informant nor the developers getting licence for development of colonies are the consumers of OP-1 as defined in Section 2(f) of the Act. Moreover, the agreements executed by the developers are required to be executed as part of the Rules of 1976 framed under the Haryana Development Act and the same do not fall within the ambit of anti- competitive agreements or abuse of dominant position under Sections 3 and 4 of the Act. Hence, the present complaint against OP-1 is not maintainable and is liable to be dismissed.

16. Furthermore, regarding the issues raised by the Informant relating to payment of EDC in accordance with the terms and conditions of the bilateral agreement executed between OP-1 and the developers, OP-1 has submitted that these issues have been already examined and decided by the Hon'ble High Court of Punjab and Haryana at Chandigarh in CWP No. 9558 of 2015 titled VPN Buildtech Pvt. Ltd. v. State of Haryana and Others and other connected petitions, vide order dated 15.12.2015.

17. OP-1 has submitted that even before the Hon'ble High Court, the developers had contended that the conditions stated in the agreements are unilateral and arbitrary and hence, they are not liable to pay the tentative/ad hoc EDC amount as stipulated in the agreements. Further, it was contended that the OPs are not entitled to collect further instalments of EDC amount till the External Development Works are carried out and also no amount of interest is payable by them on the delayed payment of instalments of EDC. In addition, the developers had contended that they are liable to pay the EDC in proportion to the expenditure incurred by the OPs on execution of the External Development Works around their colony and that the practice and procedure

7

adopted by the OPs requiring the developer to pay the entire amount of EDC without linking the same to the extent of development being carried out is illegal and unjustified. A plea was also raised that certain charges such as land cost, cost of grid sub-station, administrative charges, cost of maintenance of energy charges and cost of price escalation should not be counted while calculating the total cost of EDC.

18. However, the Hon'ble High Court vide order dated 15.12.2015 dismissed these petitions. Against this order, some of the developers filed Special Leave Petitions (hereinafter, 'SLP') before the Hon'ble Supreme Court, which are still pending including the main SLP No. 5459 of 2016 titled Magnolia Propbuild Pvt. Ltd. v. State of Haryana and Others. In the meanwhile, the Hon'ble Supreme Court, vide interim order dated 31.03.2016, has restrained OP-1 from encashing the bank guarantees submitted on account of non- payment of EDC. Thus, it is submitted that as the matter for the same cause of action is already pending adjudication before the Hon'ble Supreme Court, the present complaint ought not to be entertained by the Commission.

19. OP-1 has also contended that in the above circumstances, the plea raised before the Commission that the terms and conditions of Sohna LOI, Sohna Agreement and Sohna Licence are unilateral and arbitrary is misconceived and without merit. It is only an attempt to avoid paying the EDC amount, which the developers have expressly undertook to pay in instalments in consideration of the licences granted to them by the OPs for developing colonies. The developers, having derived benefits under the very agreements by developing the colonies and selling the premises therein, are now seeking to avoid their financial obligations. Hence, grant of any relief would be unfair and financially disastrous for the OPs and hamper the development works in the State of Haryana.

8

20. Responding specifically to the allegations in the information, OP-1 has stated that, up to October 2017, about 41 licences had been granted in the Urban Estate of Sohna for development of residential plotted/group housing/commercial/IT park colonies. These licences were granted to the developer companies and their associate companies/individual land owners after they had complied with the terms and conditions of the LOI and executed LC-IV agreement with OP-1.

21. OP-1 has contended that before grant of licence the developers themselves had undertaken to pay the due amount of EDC. No plea was raised by them at that time that payment of EDC should be linked to the execution of the External Development Works by the Government. However, when the developers failed to comply with their undertakings, they raised a plea that the conditions of payment of EDC were unilateral.

22. Under the LC-IV agreement, the developers had opted to pay EDC amount in instalments, alongwith interest and additional penal interest at the rate of 3% p.a., in case of default in payment of instalments. However, EDC amount due as per schedule fixed in the agreement was not paid by all the developers. In fact, some developers did not even pay the first and second instalments. As a result, an amount of around Rs.121399.7 lacs is still outstanding against the licencees. OP-1 has stated that in such a situation, the allegations that any steps for execution of the External Development Works around the colony area of the developers had not been initiated or that the terms and conditions of the agreements are arbitrary and unjustified.

23. Further, OP-1 has stated that since all the developers to whom licence has been granted in the Urban Estate of Sohna have not made full payment of the due amount of EDC, the external development works can be taken up in full swing only after due payment has been made by the developers; otherwise,

9

the development works would come to grinding halt due to paucity of funds. The incomplete projects would neither benefit the developers nor the ultimate beneficiaries i.e. allottees. Otherwise also, the Government will not be able to divert its funds from other projects for this work.

24. Responding to the contention of the Informant that the execution of the External Development Works should be in proportion to the amount paid by the developers, OP-1 has explained that the word 'proportion' as used in Section 3(3)(a)(ii) of the Haryana Development Act only means that the developer is required to pay the amount of EDC in proportion to the area for which licence has been obtained by it qua the total area of the town proposed to be developed as per the Development Plan prepared under Section 5 of the Punjab Development Act. Thus, the clause regarding payment of EDC amount mentioned in Section 3(3)(a)(ii) of the Haryana Development Act as well as Rule 11 of the Rules 1976 and in the LC-IV agreement is with respect to the quantum of EDC amount payable and is not linked to the amount/quantum of External Development Works carried out at any given point of time.

25. Further, OP-1 has stated that it is also not practically possible to execute the development works in proportion to the amount paid by the developer. It is not feasible that if the developer pays say Rs. 1.00 crore, HUDA should first spent Rs. 1.00 crore on part execution of the development works. The services as envisaged to be provided as per clause (g) of Section 2 of the Haryana Development Act cannot be executed in parts. For example, the land required for construction of colleges, hospitals, sports complex or other similar purposes cannot be acquired in parts. Similarly, if some water pipes for bringing water to the city are required to be laid down, they cannot be purchased or laid out in parts. The External Development Works are executed over a period of time and these are long gestation projects linked to the growth

10

of population of the town. It is unreasonable to expect that the State could execute all the External Development Works immediately without being funded in toto for the same from the developers getting the licences.

26. Regarding charging of interest/ penal interest on delayed payments, OP-1 has submitted that according to the terms and conditions of the LC-IV agreement, the developers have the option to pay the EDC amount in lump sum without interest within 30 days from the date of grant of licence or in eight to ten equal half yearly instalments alongwith interest. It is also provided that in case of default in payment of instalments on due dates, additional 3% p.a. penal interest would be charged. Thus, the provision for interest and penal interest is an integral part of the contract executed between OP-1 and the developers. Accordingly, the developers are liable to pay interest on the delayed payment of the EDC.

27. In addition to above, OP-1 has stated that as per the terms and conditions of LC-IV Agreement, initially the services like water supply, sewerage and drainage etc. are to be provided by the developers and they are supposed to take care of the immediate needs of the plot/flat holders. These services are later on connected to the services provided by the HUDA. Therefore, even with the completion of internal services within a colony, provision of which is the responsibility of the developer, it should be possible for the plot/flat holders to take possession of their plot/flat and raise construction thereon.

28. OP-1 has denied that the OPs have used their dominant position in the relevant market to impose unfair conditions for grant of licences. Further, it is also denied that the terms and conditions of the Sohna LOI are unfair or that there is extensive obligation on the developers in terms of the development works.

11

29. OP-1 has stated that as per the terms and conditions of the Haryana Development Act and the Rules of 1976 made thereunder, the internal development works have to be completed by the developer. No cost of execution of the internal development works is recovered by the OPs. The licence fee is also prescribed in the Rules. The EDC amount to be paid by the developer is in proportion to the area for which licence is granted. The amount is determined by OP-1 and the Applicant for licence is aware about the EDC/IDC and the conversion charges that are to be paid in case license is granted. These charges are fixed and the developer is aware about the payment schedule. This is also intimated to the developer in the LOI.

30. Furthermore, the agreement does not state that the development works would be executed in proportion to the amount of EDC paid by the developer. Rather it was made clear to the developers of Sohna that it would take some time for HUDA to initiate the development works in Sohna and until then they would have to make their own internal arrangement for providing such facilities. Therefore, it cannot be alleged by the Informant that the OPs have abused their dominant position. In fact, the developers getting licence in the Urban Estate of Sohna have not paid the due amount of EDC payable by them as per the terms and conditions of the agreement and are now wrongly alleging that the OPs have failed to perform their obligation regarding execution of the External Development Works.

31. Also, OP-1 has stated that it is incorrect that the developers have no opportunity to negotiate the clauses of the licence agreement. It is stated that the agreement clauses have been mentioned in the Rules of 1976 itself. Therefore, the developers are aware about the clauses even before they submit application for grant of licence. If the terms and conditions of the agreement do not suit them, they are free not to submit an application for grant of licence.

12

32. Finally, OP-1 has submitted that the Government is not denying its responsibility to execute the External Development Works in the urban estate of Sohna. Every penny received from the developer companies on account of EDC would be spent for execution of the External Development works in Sohna Urban Estate only.

33. The Commission has considered the material available on record and has also heard the parties. At the outset, it is noted that OP-1 has firstly challenged the jurisdiction of the Commission to investigate the instant matter. Accordingly, the Commission finds it appropriate to first deal with the preliminary issue of jurisdiction, before delving into the merits of the case.

34. It has been submitted that the OPs do not fall within the definition of 'enterprise' and, therefore, the present information against them is not maintainable. On the contrary, the Informant has alleged that the OPs are covered within the ambit of definition of 'enterprise', as given in Section 2(h) of the Act.

35. In this regard, the Commission observes that Section 2(h) of the Act defines 'enterprise' as a person or a department of the Government, which is engaged in any activity, relating to the production, storage, supply, distribution, acquisition or control of articles or goods, or the provision of services, of any kind. The definition is very wide and covers every type of engagement in any activity. The only exception which is carved out in the said definition is the sovereign functions of the Government including all activities carried on by the departments of the Central Government dealing with atomic energy, currency, defence and space.

36. In the instant case, it is observed that even if the activity of issuing licenses by OP-1 were to be construed as exercise of sovereign power, the levy of

13

EDC/IDC by it on the developers and consequently upon the end-consumers i.e. allottees/ home-buyers, cannot be construed as such. Moreover, the mere fact that OP-1 is in a particular position by virtue of statutory provisions with respect to certain activities and there is absence of profit therefrom, does not imply that it is performing a sovereign function necessitating its exclusion from definition of enterprise. Clearly, the activities of OP-1 in the form of levying of EDC/ IDC have a direct economic/commercial impact. In other words, OP-1 is performing actions relating to economic/commercial activities, which in turn is affecting provision of development and construction services by the developers. Thus, in view of foregoing, the Commission is of the opinion that OP-1 is covered within the ambit of the term 'enterprise' as defined in the Act.

37. Another contention raised by OP-1 is that the developers are not consumers under the Act. In this regard, the Commission observes that the definition of 'consumer' under the Act includes not only end consumers but also intermediate consumers i.e. those who buy goods or avail services for any commercial purpose. The OPs here are engaged in provision of commercial/economic services, which are being availed by the developers on payment of requisite fee and charges levied on them. Thus, the Commission finds that the developers in this case are covered within the definition of 'consumer' under the Act.

38. Next, OP-1 has submitted that as the matter is pending before the Hon'ble Supreme Court, the information before the Commission on similar grounds should not be entertained. The Commission finds this contention devoid of any merit for the reason that the availability of remedies before any other fora or under any other law do not oust the jurisdiction of the Commission per se. It is the duty and the mandate of the Commission to eliminate practices having an adverse effect on competition, promote and sustain competition, protect the interests of consumers and ensure freedom of trade carried on by other

14

participants, in markets and for fulfillment of such objectives, the Commission can proceed with the instant matter simultaneously with the proceedings of the Hon'ble Supreme Court.

39. As per Section 62 of the Act, the provisions of this Act are in addition to the provisions of any other law for the time being in force. Further, Section 61 of the Act provides that no civil court shall have jurisdiction to entertain any suit or proceeding in respect of any matter which the Commission is empowered by or under this Act to determine. Certainly, it is not the case of the OPs that the matter pending before the Hon'ble Supreme Court involves issues relating to abuse of dominant position by the OPs in violation of Section 4 of the Act. Thus, the Commission may examine the instant matter in order to ascertain if there is any anti-competitive conduct or practice in the markets in terms of the provisions of the Act.

40. Now, in order to examine the conduct of the OPs under Section 4 of the Act, firstly determination of relevant market, in both its product and geographic dimension, is required.

41. The Informant in the present case has delineated the relevant product market as the 'market for development of infrastructure and real estate' and the relevant geographical market as the 'State of Haryana'. It is noted that as per the information, the Informant in the matter comprise of a group of persons (Informant's members) who are engaged in the development of real estate, particularly housing colonies, in the National Capital Region, which are thereafter sold to individual plot holders. The grievance of Informant with OP-1 and OP-2 in the instant matter relates to development of Group Housing Colony in the revenue estate of Tehsil Sohna, Gurugram District in Haryana.

15

42. Keeping in view the above facts, the grievance of the Informant and the relevant provisions of the Act, the Commission is of the considered opinion that the relevant product market in the instant case is 'market for issue of licenses and development of infrastructure for residential plotted/ group housing/ commercial colonies'. With regard to the relevant geographic market, the Commission observes that the jurisdiction of the OPs covers all the urban areas of Haryana and cannot be restricted to a particular tehsil from which the grievance of the Informant emanates. Thus, the relevant geographic market in the present case would be the 'State of Haryana'. Accordingly, the relevant market is delineated as 'the market for issue of licenses and development of infrastructure for residential plotted/ group housing/ commercial colonies in the State of Haryana'.

43. Next, with respect to the issue of dominance of the OPs in the relevant market, the Commission notes that OP-1 and OP-2, by virtue of being statutory authorities under the Haryana Development Act and HUDA Act for issue of licenses and development of infrastructure in the State of Haryana, appear to be in a position of strength whereby they can operate independently of the competitive forces prevailing in the market. OP-1 is the only department that can issue license to developers for development of colonies and OP-2 is the only authority to undertake external development works in the State of Haryana. The developers, who are consumers of these services are entirely dependent on these authorities for these services, owing to their statutory powers. Thus, prima facie, the OPs appear to be in a dominant position in the relevant market delineated supra.

44. Regarding abuse of dominant position, the Commission notes from the information that under the Sohna Master Plan, several proposals were made to facilitate development of infrastructure facilities such as providing connectivity and transportation, public utilities etc. for which land was to be

16

acquired and developed by the OPs. However, in several instances, OP-1 has failed even to acquire the land for these purposes, even though licenses have been granted to several developers for development under the Sohna Master Plan and EDC/ IDC amount is being levied upon them.

45. Further, the Commission observes that the Informant has submitted that its members have till date deposited Rs. 375.38 crores and Rs. 137.18 crores towards the EDC and IDC amounts respectively with the OPs without any progress on the development works. It has been alleged that even the deployment and use of these funds by the OPs does not seem to be on transparent basis. To elucidate this, the Informant has stated that despite seeking information regarding receipt and expenditure of EDC/ IDC amount with respect to Sohna region under Right to Information Act, 2005, no specific response was given by OP-1. OP-1 merely provided its total year wise receipt and expenditure of EDC/ IDC amount, a bare perusal of which shows that about 60 percent of the total IDC amount was used as loan for refund purposes in other schemes floated by OP-2. This indicates that OP-1 may be collecting EDC/ IDC amount for a particular area and applying the same for some other location in the State of Haryana.

46. In addition, the Commission notes the main allegation of the Informant is that the agreements executed by the OPs with the developers are one-sided and loaded heavily in favour of OP-1. It has been alleged that by virtue of the terms and conditions in Sohna LOI, Sohna Agreement and Sohna Licence, OP-1 has excluded itself from any obligations and liabilities, and has compelled the developers to agree to the terms of these documents in toto. It has been further alleged that the conduct of the OPs to impose charges without undertaking any development works or communicating any information on the status of Master Plan and not allowing developers to claim any damages

17

or modification to the clauses imposing penal interest is unfair and onerous on the developers.

47. Having considered the submissions of the Informant and the response of OP-1 thereto, the Commission is of the opinion that even though the terms of Sohna LOI, Sohna Agreement and Sohna Licence relating to EDC/ IDC emanate largely from the statutory provisions of the relevant statutes, prima facie the terms of these documents appear to be one-sided and in favour of the OPs. Further, the alleged conduct of the OPs such as failure to adhere to its obligations under the Sohna Master Plan in a time-bound manner and imposing onerous obligations on the developers to pay EDC/ IDC, prima facie, appears to be abusive. In response to the allegations, OP-1 has not denied that it has not provided External Development Works in accordance with the Sohna Master Plan, rather it has justified that it is not possible to provide such services unless the entire EDC/ IDC amount is paid by the developers alongwith interest and penal interest. The Commission finds that the conduct of the OPs whereby they have not undertaken any External Development Works related to the Sohna project is ultimately affecting the end consumers i.e. the allottees/ home-buyers, as because of non- development by the OPs, the completion of the project is getting delayed and the same is rendered uninhabitable. Thus, in view of foregoing, the Commission is of the opinion that the conduct of the OPs prima facie appears to be in contravention of the provisions of Section 4(2)(a)(i) of the Act.

48. Accordingly, the DG is directed to cause an investigation into the matter, complete the investigation within a period of 60 days from the receipt of this order and submit its report.

49. It is, however, made clear that nothing stated in this order shall tantamount to expression of final opinion on the merits of the case and the DG shall conduct

18

the investigation without being swayed in any manner whatsoever by the observations made herein.

50. The Secretary is directed to send a copy of this order along with the information and the documents received in relation to this matter to the DG forthwith.

51. It is ordered accordingly.

Sd/- (Sudhir Mital) Member

Sd/-

(Augustine Peter) Member

Sd/-

(U. C. Nahta) Member

Sd/-

(Justice G. P. Mittal) Member

New Delhi

Date: 06.04.2018

19