Smt. Nagu Bai And Others v. State Of Karnataka
Factual and Procedural Background
The appeals arise from an order by the Single Judge dismissing writ petitions filed by appellants who were vendees of disputed land after acquisition proceedings were completed. The 1st and 2nd appellants, mother and son, purchased a share of agricultural land from the 3rd appellant by a registered sale deed in April 1995. The land had been subject to conversion approval for non-agricultural use and was used by appellants 1 and 2 to run a Liquid Petroleum Gas Agency with substantial investment in infrastructure.
The respondents entered the land in February 2000 intending to form a layout under acquisition proceedings initiated by the Mysore Urban Development Authority. Preliminary and final notifications under the Karnataka Urban Development Authority Act were published in 1992 and 1994 respectively. The land purchased by appellants 1 and 2 was included in these acquisition proceedings.
Neither appellants nor the 3rd appellant received notice pursuant to the preliminary notification. The appellants purchased the property under the bona fide belief that permission for non-agricultural use had been granted. They did not receive compensation awarded by the government. It was alleged that the final notification was published after the statutory one-year period and the award under Section 11 of the Land Acquisition Act was not made within two years from the final notification as required by Section 11A, causing the acquisition proceedings to lapse.
The Single Judge dismissed the writ petitions on the ground that appellants 1 and 2, as subsequent purchasers after the final notification, could not maintain the petitions. No finding was recorded regarding appellant 3’s petition. The appellants filed these appeals against that dismissal.
Legal Issues Presented
- Whether the acquisition proceedings lapsed due to the failure to make the award under Section 11 within two years from the date of publication of the final notification as mandated by Section 11A of the Land Acquisition Act, 1894.
- Whether appellants 1 and 2, as subsequent vendees of the land after issuance of the final notification, have the locus to challenge the acquisition proceedings.
- Whether delay and laches barred the writ petitions filed by the appellants.
Arguments of the Parties
Appellants' Arguments
- The award under Section 11 was made beyond the two-year period prescribed by Section 11A, causing the acquisition proceedings to lapse and the notifications to become void ab initio.
- The appellants purchased the land under the bona fide belief of valid permission for non-agricultural use and were unaware of acquisition proceedings due to lack of notice.
- The delay in challenging the acquisition notifications was excusable due to non-receipt of notices and unawareness of proceedings.
- Appellants 1 and 2, although subsequent purchasers, are entitled to a declaration that acquisition proceedings lapsed due to statutory non-compliance.
Respondents' Arguments
- The writ petitions were not maintainable as appellants 1 and 2 were subsequent purchasers after the final notification.
- The acquisition notifications were not challenged timely, and the writ petitions were barred by delay and laches.
- The formation of the layout was in public interest and declaring acquisition lapsed would adversely affect this public purpose.
- Appellants had no notice under Section 9 regarding compensation, but this did not justify delay in challenging acquisition.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Abdul Majeed Saheb v. District Collector, AIR 1997 SC 2130 | Interpretation of Section 11A of the Land Acquisition Act mandating award within two years and consequence of lapse of acquisition if not done. | The Court relied on this Supreme Court ruling to hold that failure to make the award within two years causes the acquisition proceedings to lapse and become void. |
| Naganna v. The State of Karnataka, ILR 1998 KAR 3508 | Section 11A mandates lapse of acquisition proceedings if award is not made within two years. | The Court followed this decision to affirm that the acquisition proceedings lapsed due to statutory non-compliance. |
| Mahadev v. State of Karnataka, W.P No. 26691-93/2000 | Application of Section 11A lapse principle in acquisition proceedings. | The Court noted this case as following Naganna’s principle, reinforcing the lapse doctrine. |
Court's Reasoning and Analysis
The Court examined the statutory framework introduced by the Land Acquisition (Amendment) Act, 1984, particularly Section 11A, which imposes a mandatory two-year period for making an award under Section 11 after the publication of the final notification. The legislative intent was to prevent undue hardship on landowners caused by indefinite delays in acquisition proceedings.
The Court noted that the award in the present case was made beyond the two-year period, and no proviso or explanation exempted this delay. It relied on the authoritative Supreme Court decision in Abdul Majeed Saheb, which held that failure to comply with Section 11A results in lapse of the entire acquisition proceedings, rendering them void ab initio.
The Court further clarified the meaning of "lapse" as termination or cessation of the legal proceedings, emphasizing that the acquisition notifications ceased to be operative by operation of law.
Respondents’ argument regarding public interest and delay was rejected, with the Court emphasizing that statutory compliance is paramount and failure to meet timelines cannot be excused. The Court acknowledged that appellants 1 and 2, though subsequent purchasers, are entitled to challenge the lapse of acquisition proceedings in order to protect their property rights.
Accordingly, the Court set aside the Single Judge’s dismissal for maintainability, declaring the acquisition proceedings lapsed and void, and recognizing the appellants as owners in possession.
Holding and Implications
Holding: The appeals are allowed in part. The order of the Single Judge dismissing the writ petitions on grounds of maintainability is set aside. It is declared that the acquisition proceedings initiated in respect of the appellants’ lands lapsed and became void due to failure to make the award within the two-year period prescribed by Section 11A of the Land Acquisition Act, 1894. The appellants continue as owners in possession of the disputed land.
Implications: The decision enforces the mandatory statutory timeline under Section 11A, reinforcing that acquisition proceedings must be completed within prescribed periods or else lapse. It clarifies that subsequent purchasers may challenge acquisition lapse to protect their rights. No new precedent was created beyond affirming established principles, and the ruling directly affects the parties by restoring their ownership rights and invalidating the acquisition notifications.
JUDGMENT
Ashok Bhan, J.:—
These appeals are directed against an order passed by the Single Judge dismissing the Writ Petitions on the ground of maintainability on behalf of the appellants, they being vendees of the land in dispute after the completion of the acquisition proceedings.
2. 1st and the 2nd appellants are the mother and the son. Sy. No. 9/1 measuring 2.16 guntas belongs to the family of the third appellant. Share of the third appellant in the said survey number was 0.14 guntas of land. Appellants 1 and 2 purchased the said property for valuable consideration from the 3rd appellant by a registered sale deed dated 28th of April 1995. The land in question was shown as an agricultural land as per the sketch 2-5-71-72. Third appellant applied for conversion of land on 26th of May 1993. The Revenue Department fixed the conversion fee with certain conditions. Third appellant paid the amount through a bank draft dated 30 of December 1992 in challan No. 6. The permission granted by the Deputy Commissioner dated 6/7-1-1993 was produced as Annexure ‘B’ with the Writ Petition.
3. Appellants 1 and 2 are running the business of Liquid Petroleum Gas Agency (L.P.G) under the Indian Oil Corporation to distribute the Gas to their customer. As such in order to meet the conditions of the Indian Oil Corporation while issuing licence for distribution, appellants 1 and 2 purchased the land to construct a godown to store the Gas Cylinders. They invested huge amount to build the godown and the compound wall. There are 20 workers working in the Gas Agency. They were running the business and meeting the needs of the customers. When this being the position, respondents entered upon the land on 26th and 28th of February, 2000 with the intention of forming a layout. On enquiries it was revealed that the land in question was acquired for the purpose of forming the layout by the Mysore Urban Development Authority Preliminary notification under Section 17(1) of the Karnataka Urban Development Authority Act (for short, ‘the Authority Act’) was published in the official gazette on 25th of June 1992. The final notification under Section 19(1) and (2) was published in the Karnataka Gazette dated 22nd of December 1994. The land purchased by the appellants 1 and 2 from appellant No. 3 was included in the acquisition made by the respondents to execute the scheme sanctioned by the Government for laying a layout.
4. That neither appellants 1 and 2 nor appellant No. 3 received any notice in pursuance to the preliminary notification. Appellants 1 and 2 purchased the property under the tionafide belief that the permission was granted by the Deputy Commissioner for using the land for non-agricultural purpose on 6/7-1-1993 i.e, after the issuance of the preliminary notification dated 25th of June 1992. Neither of the appellants received the compensation awarded by the Government on the acquisition of the land. The delay in challenging the notifications was attributed to the fact that the appellants were unaware of the proceedings. It was alleged that the final notification issued under Section 19(1) and (2) of the Authorities Act which is equivalent to Section 6 of the Land Acquisition Act, 1894 (hereinafter referred to as ‘the Act’) was published after the expiry of one year after the date of publication of the preliminary notification. It was also alleged that the respondents did not make the award under Section 11 of the Act within the period of two years from the date of publication of the final notification as required under Section 11A of the Act. As the award was not made within two years of the publication of the final notification the entire acquisition proceedings lapsed.
5. Learned Single Judge without adverting to any of the contentions raised by the appellants dismissed the Writ Petitions holding that the appellants being the purchaser of the property subsequent to the issuance of the final notification issued under-Section 19(1) and (2) of the Authorities Act, the Writ Petitions on their behalf were not maintainable in view of the law laid down by the Supreme Court learned Single Judge did not record any finding regarding the maintainability of the Writ Petition on behalf of appellant No. 3 presumably because the appellant No. 3 was left with no interest or title in the property in dispute.
6. Aggrieved against the dismissal of the Writ Petitions the present appeals have been filed.
7. The only point pressed at the time of arguments by the Sri T.R Subbanna, learned Senior Advocate, is that the award under Section 11 having been made beyond the period of two years from the date of issuance of the final notification, the entire proceedings lapsed. The proceedings terminated by lapse of time and no right or title vested in the respondents to takeover the lands compulsorily on the basis of the notifications issued for acquiring the land. The notification became void ab initio.
8. It is not in dispute before us that Section 11A of the Act applies to the acquisition made under the Authorities Act. It is also not in dispute that there was no order of stay by any Court in regard to the land in question. It is also not in dispute that the award under Section 11 was made by the Land Acquisition Office after the expiry of two years from the date of the publication of the final notification.
9. Parliament of India amended the Land Acquisition Act, 1894 by Act No. 68/1984 (hereinafter referred to as ‘the amending Act’) which received the assent of the President on 24th of September 1984. Prior to the Amending Act it was being increasingly noticed by the Courts that after the issuance of the preliminary notification under Section 4, the final notification under Section 6 was not issued for a number of years. It was observed that presumably it was being done to peg down the prices as the market value was required to be paid was as it existed on the date of issuance of the preliminary notification. Further that after the publication of the final notification the award was not made for a number of years. The Courts frowned upon such practice and in certain cases the High Courts quashed the proceedings or the awards made as the case may be. Noticing the frowning and dis-approval of the Courts the Legislature stepped in and amended the Act by the Amending Act No. 68/1984 to remove the hardship caused to the land owners. Proviso to Section 6(1) was added providing that no declaration in respect of any particular land covered by a notification under Section 4(1), published after the commencement of the Land Acquisition (Amendment) Act, 1984, shall be made after the expiry of one year from the date of publication of the notification. Explanation was added that the period during which any action or proceedings to be taken in pursuance to the notification issued under Section 4(1) was stayed by an order of a Court then the same while computing the period for issuance of the final notification shall be excluded. Section 11A fixed the period within which the award could be made. The same reads.
“Period within which an award shall be made.- The Collector shall make an award under Section 11 within a period of two years from the date of the publication of the declaration and if no award is made within that period, the entire proceedings for the acquisition of the land shall lapse:
Provided that in a case where the said declaration has been published before commencement of the Land Acquisition (Amendment) Act, 1984 the award shall be made within a period of two years from such commencement.
Explanation: In computing the period of two years referred to in this Section, the period during which any action or proceedings to be taken in pursuance of the said declaration is stayed by an order of a Court shall he excluded.”
10. Supreme Court of India in Abdul Majeed Saheb v. District Collector . AIR 1997 SC 2130. observed:
“Section 11-A was brought on statute by Amendment Act 68 of 1984. It was notorious that the State, after publication of declaration under Section 6 went on delaying for years, to pass the awards putting obstruction to the owner of the land for enjoyment; resultantly, loss and undue disadvantage ensued to the owner of the land. To mitigate such hardship, the Parliament introduced Section 11-A and directed the Land Acquisition Officer to make the award within two years from the date of publication of last of the steps under Section 6(2) publishing the declaration under Section 6. As a consequence, the Land Acquisition Officer is statutorily under an obligation, at the pain of invalidation of the acquisition itself, to make the award within two years unless it falls within one of the provisios or the Explanation added thereto. In this case, neither the proviso nor the Explanation stands attracted to the facts. Consequently, since the Land Acquisition Officer did not make the award within two years from the date of the declaration viz., June 17, 1988, the entire acquisition shall stand lapsed.”
(Emphasis Supplied)
Following the said decision a Single Judge of this Court in Naganna v. The State of Karnataka . ILR 1998 KAR 3508. declared that the entire acquisition proceedings statutory stood lapsed for the default of not passing the award within the prescribed period. It was held that Section 11A of the Act mandates the Land Acquisition Officer to make the award under Section 11 within a period of two years from the date of declaration and if it is not so done then the entire proceedings stood lapsed. This decision was up held by the Division Bench in W.A No. 4252-56/1998 dated 25 November 1998. The decision in Nagappa's case was later on followed in W.P No. 26691-93/2000 (Mahadev v. State Of Karnataka*, DD 11-12-2000).
11. Section 11A was brought on the statute by amending Act to mitigate the loss and undue hardship caused to the owner of the land. It was made obligatory for the Land Acquisition Officer to make the award under Section 11 statutorily within the period of two years from the date of publication of the final notification. In case the award was not made within that period the entire proceedings for acquisition of land were made to lapse. Section 11A did not only cast an obligation on the Land Acquisition officer to make the award under Section 11 within the period of two years from the date of declaration, but also provided the consequence, if such a declaration was not made. The consequence of not making the award was that the entire proceedings of acquisition of land would lapse, as pointed out by the Supreme Court in Abdul Majeed Saheb's case, supra. The Land Acquisition Officer was statutorily under an obligation, at the pain of invalidation of the acquisition itself, to make the award within two years unless it fell within one of the provisos or the explanation provided thereto. In the present case, neither the proviso nor the explanation stands attracted to the facts. As the award was admittedly made beyond the period of two years from the date of declaration the entire acquisition stood lapsed.
12. According to Webster's Encyclopedic Unabridged Dictionary, the word lapse’ in the context of laws means:
“The termination of a right or privilege through neglect to exercise it or through failure or some contingency.
To become void; as a legacy to some one who dies before the testator.
To cease being in force; terminate.”
Similar is the meaning given to the word lapse in the Law Lexicon. The acquisition proceedings stood terminated. The Land Acquisition Officer did not make the award within two years of the publication of the final notification. The notification itself became void and ceased to be in operation. As the award was made after the expiry of two years from the date of issuance of the final notification it has to be held that the entire acquisition proceedings lapsed; stood terminated from its inception and therefore became void. It was by operation of law in view of the mandatory nature of the provisions of Section 11A.
12. Learned Counsel for the respondent submitted that neither the preliminary notification nor the final notification was neither challenged nor questioned by the appellant and that if it is declared that the acquisition proceedings are lapsed, the formation of layout would be adversely affected and public interest will suffer. We do not find any force in this submission. The Supreme Court as well as this Court has taken the view that if the award is not made within two years of the final publication, the entire proceedings lapse and therefore no right would come to vest in the authorities to take possession of the land in question.
13. If the respondents were interested in saving the acquisition of the lands in question, it ought to have passed the award within two years. Even now it can issue new notification. Alternatively, it is open to the respondent to negotiate with the owners of the land and take a consent award. But these are not the matters where any direction can be given by the Court.
14. Another contention raised on behalf of the respondents is that the Writ Petition was liable to be dismissed on the ground of delay and latches. Either of the appellants had not been served with the notice. Appellant No. 3 had applied for change of user of the agricultural land for non-agricultural purposes after the issuance of the preliminary notification. Deputy commissioner granted the permission subject to payment of certain fee which was paid. Either of the appellants were not served with the notice under Section 9 for awarding the compensation. Appellants approached the Court as soon as the respondents tried to enter upon the land. Keeping in view the fact that the Deputy Commissioner had granted permission for change in the user of land after the issuance of the preliminary notification and the fact that either of the appellants were not served with the notice for receiving compensation, the delay if any stands explained.
15. Appellant Nos. 1 and 2 being the subsequent vendees may not be entitled to challenge the acquisition proceedings, but they would certainly be entitled to get a declaration that the acquisition proceedings lapsed and became void as the Land Acquisition Officer failed to make the award within two years from the date of publication of the final notification. The order of the Single Judge dismissing the Writ Petitions on account of its maintainability is therefore set aside
16. Appeals are allowed in part. Order of the Single Judge is set aside. It is declared that the proceedings initiated in regard to the lands of the appellants referred to above lapsed and became void. The appellants continue to be the owners in possession of the land in dispute.