Subhas Chandra Chakraborty v. State Of West Bengal & Ors.

Calcutta High Court
Aug 28, 2012
Smart Summary (Beta)

Factual and Procedural Background

This appeal challenges the order dated 6th March, 2004, whereby the learned Single Judge dismissed the writ petition on merits without granting relief to the appellant-petitioner. The appellant-petitioner was denied pensionary benefits due to non-fulfillment of the minimum qualifying service of 10 years at the date of super-annuation, having completed only 9 years, 11 months, and 17 days, falling short by 13 days. The appellant-petitioner contended that the delay was caused by the respondent authorities’ failure to issue the appointment letter in time despite his empanelment as a successful candidate. The petitioner was appointed only on 14 May 1987 following a court order. The appellant-petitioner sought condonation of the 13 days deficiency under Clause 7(e)(iv) of the West Bengal Recognised Non-Government Educational Institution Employees (Death-cum-Retirement Benefit) Scheme, 1981, which permits condonation of deficiency up to six months.

The Director of School Education, West Bengal, had referred the matter to the School Education Department for condonation of the deficiency, but the Government refused on the ground that condoning the deficiency would lead to reopening of several hundred similar cases. The State respondents maintained that the rejection was lawful and in accordance with the Scheme of 1981. The appeal was filed against the dismissal of the writ petition seeking pensionary benefits.

Legal Issues Presented

  1. Whether the 13 days deficiency in qualifying service can be condoned under Clause 7(e)(iv) of the West Bengal Recognised Non-Government Educational Institution Employees (Death-cum-Retirement Benefit) Scheme, 1981, to enable the appellant-petitioner to receive pensionary benefits?
  2. Whether the Government’s refusal to condone the deficiency on the ground of possible floodgate litigation is legally valid and sustainable?

Arguments of the Parties

Appellant's Arguments

  • The appellant-petitioner was empanelled for appointment but was denied timely appointment by the authorities, causing delay in joining service.
  • The appellant-petitioner completed only 13 days short of the required 10 years qualifying service due to the authorities’ lapses.
  • The 13 days deficiency should be condoned as per Clause 7(e)(iv) of the 1981 Scheme, which allows condonation up to six months.
  • The denial of pensionary benefits on the ground of deficiency is unjust, especially given the court intervention that enabled the appointment.

Respondent's Arguments

  • The State Government rejected the claim for pensionary benefits due to the shortfall in qualifying service.
  • The refusal to condone the deficiency was based on the concern that condonation would lead to reopening of hundreds of similar cases.
  • The decision was taken strictly in accordance with the provisions of the Scheme of 1981 and lawful grounds.
  • The North 24-Parganas District Primary School Council supported the State’s position.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Coal India Ltd. v. Saroj Kumar Mishra, AIR 2007 SC 1706 Rejection of claims on the ground of possible floodgate litigation is not a valid legal ground. The court relied on this precedent to hold that the Government’s refusal to condone the deficiency solely on the fear of floodgate litigation was not sustainable and cannot deprive a citizen of a valuable right.

Court's Reasoning and Analysis

The court analyzed the facts and the relevant provision of Clause 7(e)(iv) of the 1981 Scheme, which empowers the Government to condone deficiency in qualifying service up to six months. It found that the appellant-petitioner’s shortfall of 13 days was well within this limit. The court observed that the delay in joining service was due to the respondent authorities’ failure to issue timely appointment despite the appellant’s empanelment and successful candidacy, necessitating court intervention to secure appointment.

The court rejected the Government’s justification that condoning the deficiency would open floodgate litigation, relying on the Supreme Court’s authoritative ruling in Coal India Ltd. v. Saroj Kumar Mishra, which held that the possibility of floodgate litigation cannot be a valid ground to deny a citizen’s valuable right. The court emphasized that the authorities are duty-bound to exercise their power under the Scheme in appropriate cases and cannot refuse on speculative grounds.

Consequently, the court held that the Government’s refusal to condone the 13 days deficiency was illegal and erroneous. The learned Single Judge’s approval of the Government’s decision was also found to be in error.

Holding and Implications

The court allowed the appeal by setting aside the impugned order of the learned Single Judge and quashing the Government’s refusal to condone the deficiency in qualifying service.

The Secretary, School Education Department, West Bengal, was directed to exercise the power under Clause 7(e)(iv) of the 1981 Scheme to condone the 13 days deficiency and enable the appellant-petitioner to receive pensionary benefits promptly. The court mandated that the condonation order be passed within two weeks and pensionary benefits disbursed within four weeks thereafter.

No new precedent was established beyond the application of existing principles. The decision directly benefits the appellant-petitioner by securing pensionary benefits and clarifies that administrative authorities cannot refuse condonation merely due to apprehension of floodgate litigation.

Show all summary ...

Pranab Kumar Chattopadhyay, J.:— This appeal has been preferred challenging the order dated 6th March, 2004 passed by a learned Judge of this court whereby and whereunder the said learned Judge dismissed the writ petition on merits without granting any relief to the appellant-petitioner herein.

The appellant-petitioner herein is aggrieved since the pensionary benefits of the said appellant-petitioner were denied for non-fulfillment of minimum qualifying service.

It is not in dispute that the appellant-petitioner herein was required to complete 10 years of qualifying service on the date of super-annuation for the purpose of enjoying the pensionary benefits. In the present case, said appellant-petitioner completed only 9 years 11 months 17 days of service on the date of super-annuation and thus, there is a clear deficiency of 13 days service to complete the prescribed period of 10 years qualifying service in order to be eligible for enjoying the pensionary benefits in accordance with law.

Mr. Chatterjee, learned Counsel representing the appellant-petitioner submits that the appellant-petitioner was duly empanelled for appointment to the post of Primary School Teacher but the authority concerned did not issue appointment letter in time in favour of the said appellant-petitioner as a result whereof, the appellant-petitioner could not join the service earlier inspite of being empanelled as a successful candidate. Mr. Chatterjee further submits that the appellant-petitioner was appointed by the authority concerned on 14 May, 1987 purusant to the specific order passed by this court in the writ petition filed by the appellant-petitioner herein.

It is the specific case of the appellant-petitioner that the respondent authorities wrongfully and illegally denied appointment to the said appellant-petitioner in time and due to the intervention of the court, ultimately, the appellant-petitioner herein was able to join the service on 14 May, 1987.

Mr. Chatterjee submits that the appellant-petitioner could not complete the prescribed period of 10 years qualifying service before attaining the age of super-annuation due to the laches and/or lapses on the part of the respondent authorities. Mr. Chatterjee also submits that the aforesaid 13 days delay should not be a bar to deny pensionary benefits to the appellant-petitioner specially when there is a clear provision in the West Bengal Recognised Non-Government Educational Institution Employees (Death-cum-Retirement Benefit) Scheme, 1981 for condoning the deficiency upto six months in the qualifying service of the employees of non-government/sponsored/aided educational institutions.

Clause 7(e)(iv) of the aforesaid Scheme of 1981 is set out hereunder:

“Cl. 7(e)(iv). Upon any condition which it may think fit to impose, Government may condone a deficiency of six months in the qualifying service of the employees of non-Government/Sponsored/Aided Educational Institutions/Organisations.”

Furthermore, from the records we find that pursuant to the earlier order passed by a learned Judge of this court, Director of School Education, West Bengal considered the aforesaid aspect and referred the matter to the School Education Department for condoning the aforesaid deficiency of 13 days in the qualifying service of the appellant-petitioner. The relevant extracts from the order dated 10 April, 2002 passed by the Director of School Education, West Bengal are set out hereunder:

“After careful consideration of the all aspects of the matter it is decided to send the case to the School Edn. Deptt. to condone the said deficiency of 13 days in the qualifying service as per Para 7e(iv) of G.O No. 136-Edn (B) dt. 15.5.85 The matter is thus disposed of. All concerned be informed accordingly.

Sd/

Director of School Education

West Bengal

No. 149/1(5)LC Date: 10/4/2002”

The Assistant Secretary, School Education Department, Government of West Bengal thereafter, by the written communication dated 29 May, 2003 informed the appellant-petitioner regarding inability of the State Government to condone the aforesaid deficiency in the minimum qualifying service of the said appellant-petitioner. The aforesaid written communication of the Assistant Secretary, School Education Department dated 29 May, 2003 is set out hereunder:

“Government of West Bengal

School Education Department

Law Branch

Bikash Bhavan, Salt Lake, Kolkata-91

No. 331-SE(Law)/PL/5S-116/02 the 29 May, 2003

From: Shri S.K Ghosh Assistant Secretary to the Govt. of West Bengal

To: Shri Subhas Chakraborty Kaccharipara, P.O Basirhat, Chakraborty Bhavan, Dt. 24-Pgs (N)

Sub: A.S.T No. 1413 (W) of 1999 W.P No. 10506 (W) of 1999 Subhas Chakraborty

v.

Govt. of West Bengal & Ors. (Condonation of deficiency in qualifying service for pensionary benefit)

Sir,

With reference to your letter dated 02.09.2002 on the above noted subject, I am directed to inform you that the Government of West Bengal regrets its inability to condone the deficiency in minimum qualifying service to make you eligible for pension, as this will lead to reopen several hundred cases which have been turned down earlier, which are no less deserving than yours.

Yours faithfully,

Sd/-

(Assistant Secretary)”

Going through the aforesaid written communication of the Assistant Secretary, School Education Department dated 29 May, 2003, we find that the Government of West Bengal refused to condone the deficiency in minimum qualifying service of the appellant-petitioner in order to make the said appellant-petitioner eligible for pension on the ground that the same will lead to reopen several hundreds of cases which have been turned down earlier.

The learned Advocate representing the State-respondents, however, submits that the State Government has rejected the claim of the appellant-petitioner on appropriate grounds and the appellant-petitioner herein is not entitled to enjoy pensionary benefits due to the aforesaid deficiency in minimum qualifying service. The learned Advocate of the State-respondents further submits that the Government has taken appropriate decision in respect of the appellant-petitioner strictly in accordance with law and following the specific provisions of the Scheme of 1981.

The learned Advocate representing the North 24-Parganas District Primary School Council adopted the arguments advanced on behalf of the State of West Bengal.

We are, however, not at all impressed by the aforesaid arguments advanced on behalf of the respondent authorities herein.

Undisputedly, the Government of West Bengal refused to condone only 13 days deficiency in minimum qualifying service of the appellant-petitioner in order to make the said appellant-petitioner eligible for pension only on the ground that the same will reopen several hundreds of cases which have been turned down earlier.

We are unable to appreciate the reasons furnished by the Government of West Bengal to deny the claim of the appellant-petitioner herein for condonation of deficiency in qualifying service for pensionary benefits.

When an authority is empowered to take any decision under the scheme or statute for the benefit of an employee, then the said authority cannot refuse to take such decision only on the ground that the same will open the floodgate of litigation.

The Hon'ble Supreme Court has repeatedly held that possibility of floodgate litigation cannot be a valid ground to deprive a valuable right of a citizen. In the case of Coal India Ltd. v. Saroj Kumar Mishra reported in AIR 2007 SC 1706, Hon'ble Supreme Court observed:

“23. The floodgate argument also does not appeal to us. The same appears to be an argument of desperation. Only because, there is a possibility of floodgate litigation, a valuable right of a citizen cannot be permitted to be taken away. This Court is bound to determine the respective rights of the parties.”

The specific provision engrafted in the Scheme of 1981 authorises the State Government to condone the deficiency in qualifying service upto six months in respect of an employee in order to enable the said employee to enjoy pensionary benefits.

In the present case, the appellant-petitioner could not join the service earlier due to the laches and/or lapses on the part of the respondent authorities inspite of being empanelled as a successful candidate. Ultimately, due to the intervention of this court, said appellant-petitioner could join the service at a belated stage as a result whereof, there was only 13 days deficiency in qualifying service of the appellant-petitioner herein which should have been condoned by the State of West Bengal upon exercising power under Clause 7(e)(iv) of the Scheme of 1981.

The reason furnished by the Government of West Bengal while rejecting the prayer for condoning the deficiency in qualifying service of the appellant-petitioner cannot be held to be valid and proper ground as the authorities concerned are under an obligation and duty bound to exercise the power under the Scheme of 1981 for condoning the deficiency in the qualifying service of an employee upto a period of six months in appropriate case and cannot refuse to exercise such power apprehending a possibility of floodgate litigation. In the present case, there was no valid ground for refusing to condone the deficiency of 13 days in minimum qualifying service of the said appellant-petitioner in order to make him eligible for enjoying the pensionary benefits.

The learned Single Judge, in our opinion, has committed an error by approving the erroneous and illegal decision of the State Government which was communicated to the appellant-petitioner by the written communication dated 29 May, 2003.

For the aforementioned reasons, the order passed by the Government of West Bengal and communicated to the appellant-petitioner by the Assistant Secretary, School Education Department by the written communication dated 29 May, 2003 cannot be sustained and the same is accordingly, quashed.

The Secretary, School Education Department, Government of West Bengal is directed to exercise authority in terms of Clause 7(e)(iv) of the Scheme of 1981 by condoning the deficiency in qualifying service of the appellant-petitioner in order to enable the said appellant-petitioner to enjoy pensionary benefits at an early date.

Since a considerable time has already lapsed, we direct the Secretary, School Education Department to pass appropriate order condoning the deficiency in qualifying service of the appellant-petitioner herein within a period of two weeks from the date of communication of this order positively. The respondents are also directed to take immediate appropriate steps thereafter so that the admissible pensionary benefits of the appellant-petitioner are disbursed within a period of four weeks from the date of condonation of the deficiency in qualifying service of the appellant by the Secretary, School Education Department in terms of this order.

With the aforesaid observations and directions, we allow this appeal after setting aside the impugned order under appeal passed by the learned Single Judge.

In the facts of the present case, there will be no order as to costs.

Let urgent xerox certified copy of this order, if applied for, be given to the learned Advocates of the parties on usual undertaking.

Tarun Kumar Das, J.:— I agree.