Lanco Infratec Limited v. The Chief General Manager (Contracts), Neyveli Lignite Corporation Ltd. .

Madras High Court
Oct 10, 2013
Smart Summary (Beta)

Factual and Procedural Background

The Petitioner, a leading business house engaged in Engineering, Procurement and Construction (EPC) among other sectors, participated in a tender process initiated by Neyveli Lignite Corporation (NLC) for a Steam Generator and Auxiliary Package for a new thermal power project. The tender notification was issued on 24th September 2012, with bids submitted by the Petitioner and two other bidders. The Petitioner submitted its technical and commercial bids on 10th December 2012. Due to the complex nature of the tender, deviations were allowed and clarifications were sought by NLC. Despite multiple communications and extensions granted by NLC, the Petitioner failed to satisfactorily clarify technical deviations. NLC proceeded to invite revised price bids from the other two bidders and planned to open them on 30th August 2013. The Petitioner filed a Writ Petition under Article 226 of the Constitution of India seeking a Writ of Mandamus to restrain NLC from opening the price bids without considering the Petitioner's clarifications. The High Court dismissed the Writ Petition and closed the connected Miscellaneous Petition, awarding no costs.

Legal Issues Presented

  1. Whether the High Court should exercise judicial review during the tender evaluation process to restrain the Respondent from proceeding with the bidding process without considering the Petitioner's clarifications.
  2. Whether the Petitioner was entitled to equality and fair treatment in the evaluation of competitive bids under Article 14 of the Constitution of India.
  3. The scope and extent of judicial review permissible in contractual matters involving public tenders, particularly in respect of procedural fairness and arbitrariness.

Arguments of the Parties

Petitioner's Arguments

  • The Petitioner complied with all clarifications sought by NLC and was entitled to have its revised price bid considered before opening bids of other tenderers.
  • NLC acted arbitrarily and hastily by giving only three days' notice to submit clarifications, which was unreasonable given the technical complexity of the contract.
  • The tender process was non-transparent and showed favoritism towards other bidders, violating the Petitioner's right to equality and fair treatment.
  • The Petitioner contended that the short notice period and abrupt ending of discussions violated principles of natural justice.
  • The Petitioner relied on judicial precedents supporting judicial review even in contractual matters to ensure fairness and transparency.

Respondent's Arguments (Neyveli Lignite Corporation)

  • The Petitioner repeatedly delayed furnishing required clarifications and failed to meet technical specifications despite multiple extensions.
  • NLC needed to conclude the contract promptly to avoid project cost escalation and delays, justifying the prescribed time limits.
  • The Petitioner’s consortium partner was not manufacturing the type of boiler required by NLC, and the Petitioner failed to provide valid technical clarifications.
  • The extension of bid validity period was procedural and did not imply acceptance of the Petitioner's bid.
  • NLC was justified in proceeding with the tender process by inviting revised bids from other tenderers due to the Petitioner's non-compliance.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sona Builders v. Union of India, 2001 (10) SCC 280 Judicial review is permissible in contractual matters to ensure fairness and prevent arbitrariness. Supported the principle that courts can intervene if tender conditions are arbitrary or unfair.
Canara Bank v. Debasis Das, 2003 (4) SCC 557 Scope of judicial review in administrative and contractual decisions. Reinforced judicial restraint but upheld intervention in cases of mala fide or arbitrariness.
Nobel Resources Limited v. State of Orissa, 2006 (10) SCC 236 Judicial review in public contracts and tenders. Affirmed that courts can review tender processes for compliance with fairness and legality.
Uma Nath Pandey v. State of U.P, 2009 (12) SCC 40 Judicial intervention in tender processes subject to public interest and procedural fairness. Emphasized limited judicial scrutiny to prevent arbitrariness.
Natural Resources Allocation, In Re, 2012 (10) SCC 1 Judicial review of allocation of public resources and contracts. Supported judicial oversight to ensure transparency and fairness.
Sterling Computers Limited v. M&N Publications Ltd., 1993 (1) SCC 445 Discretion in awarding contracts with judicial norms to prevent arbitrariness. Recognized the need for courts to allow administrative discretion within reason.
Tata Cellular v. Union Of India, 1994 (6) SCC 651 Extent of judicial review in contractual and administrative decisions. Outlined principles limiting judicial interference to procedural fairness and absence of mala fides.
Meerut Development Authority v. Association of Management Studies, 2009 (6) SCC 171 Nature of tender and rights of bidders. Clarified that bidders have right to equality and fair treatment but not to renegotiate terms.
Arun Kumar Agrawal v. Union of India, 2013 (7) SCC 1 Judicial review of complex economic decisions by State or its instrumentalities. Held courts should not substitute their judgment for bona fide commercial decisions of the State.
NTPC Ltd. v. Ansaldo Caldaie Boilers India (P) Limited, 2012 (4) SCC 471 Importance of compliance with technical specifications in tender contracts. Emphasized strict adherence to technical requirements in tender evaluation.

Court's Reasoning and Analysis

The Court examined the tender process and found that the Petitioner failed to meet the technical specifications despite multiple opportunities and extensions granted by NLC. The Petitioner’s submissions were piecemeal, incomplete, and delayed, which justified NLC’s decision to proceed with other bidders. The Court recognized that the tender was a high-value, complex contract requiring strict adherence to technical criteria. It emphasized that judicial review in tender matters is limited to ensuring fairness, absence of arbitrariness, and compliance with principles of natural justice, without substituting the Court’s opinion for that of the administrative authority. The Court noted that the Petitioner was given ample time and repeated reminders but failed to provide satisfactory clarifications. The short notice given in July 2013 was part of a continuing process of communication and not an isolated arbitrary act. The Court held that the Petitioner’s attempt to delay the process and claim unfair treatment lacked bona fides. The Court also relied on established precedents affirming that the State has discretion in awarding contracts, subject to fairness and non-arbitrariness, and that courts should exercise restraint in interfering during the tender evaluation process unless there is clear evidence of mala fide or violation of constitutional principles.

Holding and Implications

The Writ Petition is dismissed.

The Court upheld the Respondent's decision to proceed with the tender process without considering the Petitioner's delayed and incomplete clarifications. The dismissal entails that the tender evaluation and award process by NLC stands affirmed, and the Petitioner is not entitled to any relief. No costs were awarded. The judgment reinforces the principle that judicial review in public tender matters is limited to procedural fairness and non-arbitrariness, and courts will not interfere with bona fide commercial decisions taken within the discretion of the administrative authority. No new precedent was established beyond the application of existing principles to the facts of this case.

Show all summary ...

N.A.K Sharma, Advocate for Respondent.

W.P DISMISSED — M.P CLOSED — NO COSTS

Prayer: Writ Petition filed under Article 226 of the Constitution of India praying for a Writ of Mandamus forbearing the Respondent from proceeding any further with the bidding process by opening the price bids on 30.8.2013 or any subsequent date or dates without considering the clarifications submitted by the Petitioner to the Respondent under Letters dated 15.7.2013, 16.7.2013 and 23.7.2013 relating to Tender No. CO/CONTS/0014T/NNTPP/NTA1-SG/2012 dated 24.9.2012

JUDGMENT

1. The Petitioner wanted the High Court to exercise the power of Judicial Review in respect of a global contract floated by Neyveli Lignite Corporation worth Rs. 5,900 Crores in a piecemeal manner during the currency of Tender Evaluation Process and before finalising the composite Tender and Award of contract.

Brief facts:

The case of the Petitioner:

2. The Petitioner is a leading business house in the domains of Engineering, procurement and construction (EPC), Power, Solar, Natural resources and infrastructure in India. The Petitioner is also engaged in the construction of Metro Rail.

3. M/s. Neyeveli Lignite Corporation [hereinafter referred to as NLC], issued a Notification calling for bids for steam generator and auxiliary package for its new thermal power project. The Notification dated 24th September 2012 was published on 25th September 2012. The Petitioner, pursuant to the said Notification, submitted its technical and commercial bids on 10th December 2012. The technical bids were opened on 21st December 2012. There were three bidders: the Petitioner, M/s. Bharath Heavy Electricals Ltd., India and M/s. Ansaldo Caldaie S.p.a Italy. Since the scope of the work and technical requirements of the Tender were complex in nature requiring design and integration of multiple and complex components and systems, NLC allowed the Petitioner and other bidders to take technological and commercial deviations. The bidders were permitted to submit necessary documents to justify the deviation. NLC by its Letter dated 19th April 2013, sought certain clarifications on deviation suggested by the Petitioner. NLC called upon the Petitioner and its associates M/s. Harbin Boiler Company (hereinafter referred to as HBC), for a meeting on 2nd May 2013 at Neyveli to discuss technical and commercial deviations. The Petitioner and its associate attended the meeting. HBC provided support to the Petitioner for resolution of technical deviations. The Petitioner submitted all the necessary information pursuant to the communication sent by NLC. In the meantime, the Petitioner was directed to extend the bid validity up to 17th November 2013. The Petitioner readily complied with the said direction. However, there was no follow up action taken by NLC to call upon the Petitioner to submit its revised price bid. In the meantime, the Petitioner was informed that NLC has invited the other two bidders for submission of their revised price bid, which would be opened on 30th August 2013. According to the Petitioner, they have complied with all the requirements as indicated in the communications sent by NLC. NLC was bound to invite the Petitioner for submitting revised price bid. The Petitioner therefore seeks a Writ of Mandamus to forbear NLC from proceeding further with the bidding process, by opening the price bids on 30th August 2013 without considering the clarifications submitted on various occasions in relation to Tender No. CO/CONTS/0014T/NNTPP/NTA1-SG/2012 dated 24th September 2012.

Case of NLC:

4. The Chief General Manager, Neyveli Lignite Corporation Ltd. filed a detailed Counter Affidavit disputing the claim made by the Petitioner. According to NLC, the Petitioner has been delaying the matter under one pretext or the other. The Petitioner wanted extension of time by two months even to submit the bid pursuant to the Notification issued by NLC. The Petitioner was asked to give certain clarifications with regard to technical specification on or before 2nd May 2013. The Petitioner furnished a reply dated 4th May 2013 with regard to certain items and undertook to give further reply at a later point of time. Since NLC wanted to complete Tender process as early as possible, the Petitioner was invited to participate in the techno-commercial discussion from 13th to 15th May 2013. During the said meeting, the Petitioner withdrew certain deviations taken by it in Part-1 of the bid. Certain other deviations were either accepted or resolved. Other major deviations remained and in some aspects the Petitioner promised to revert with replies/clarifications on or before 22nd May 2013. However, the Petitioner failed to submit clarification within the time granted. The Petitioner maintained at all point of time that it was in discussion with the associate (HBC) and after taking technical advise, they would revert. NLC thereafter, by Letter dated 1st June 2013, reminded the Petitioner to give its reply to the pending points without any further delay. Even though the Petitioner agreed to give reply, there was no follow up action. According to NLC, time was extended periodically with a view to furnish the required particulars. However, the Petitioner was dragging the matter under one pretext or the other. NLC wanted the Petitioner to indicate the furnace explosion/implosion withstand capacity. The specification given by the Petitioner was less than the specified value of minimum +/−660mm, and it was not acceptable to NLC. It was further contended that the clarifications given by the Petitioner were all incomplete and as such, a decision was taken to proceed further by negotiating with the other two tenderers.

Summary of Submissions:

5. Thiru V.T Gopalan, learned Senior Counsel for the Petitioner took me through various correspondence and documents and submitted that NLC wanted the contract to be given to a party already selected and there is a hidden agenda.

6. The following are the substantial submissions made on behalf of the Petitioner:

(i) The contract in question involves Rs. 5,907.11 crores. There were only few bidders. Since the contract involves highly technical specifications, NLC wanted certain clarifications to proceed further. The Petitioner clarified its position on various occasions. NLC has been communicating with the Petitioner. However, NLC put an end to the discussion abruptly by giving three days' Notice and thereafter, proceeded to consider the bids submitted by the other two tenderers. The limited time given to submit reply would prove the arbitrary and hasty nature of Tender process.

(ii) The first Tender was cancelled by the Petitioner. Thereafter, the second Tender was floated on 24th September 2012. Bidders have been negotiating with the NLC. Nature of clarification sought for by NLC require serious consultations with the collaborator. NLC erred in giving a very short period to submit reply to various points of highly technical nature.

(iii) The Tender in question is a non-statutory contract. NLC should have given reasonable time to the Petitioner to submit the clarification.

(iv) There is no pre-fixation of any time frame for opening the bids. Even then, NLC proceeded in a hasty manner with a view to help the other two tenderers. The Petitioner being a bidder, is entitled to equality and fair treatment in the matter of evaluation of competitive bids.

(v) The bids offered should be processed in a transparent manner free from any hidden agenda. The very fact that the Petitioner was kept in darkness with regard to submission of revised price bid would show that NLC wanted to show favourtism.

(vi) NLC has not indicated anything about the shortcomings. The Petitioner has no knowledge of what is falling short. NLC kept the entire transaction in secret. NLC by its Letter dated 10th July 2013, called upon the Petitioner to submit its reply on or before 15th July 2013. The time was inadequate and in fact, it was unreasonable in the facts and circumstances of the matter.

(vii) The available materials would make the position very clear that NLC had already decided that the bids submitted by the Petitioner should be rejected. NLC issued Notice giving three days time for compliance, knowing fully well that it is not possible to submit the required information within the short period.

(viii) The fixation of such arbitrary time, deliberately calculated to defeat the interest of the Petitioner, cannot be treated as reasonable compliance of the Principles of Natural Justice.

(ix) There was no urgency to proceed with the matter in view of the highly technical nature of contract.

7. Thiru N.A.K Sharma, learned Senior Counsel for Neyveli Lignite Corporation made the following submissions:

(i) The Petitioner was given extension of time periodically to submit the technical specifications and explanation with regard to deviations;

(ii) Even though time was extended on many occasions, the Petitioner failed to give satisfactory explanation;

(iii) NLC wanted a particular kind of boiler. M/s. HBC has been manufacturing a different type of boiler and steam generators. The Consortium Partner of the Petitioner never indicated that they would be in a position to provide steam generator and auxiliaries as per the specification given by NLC.

(iv) Contract involves about Rs. 5,900 Crores. In case the matter is prolonged, NLC would sustain heavy loss and the project cost would increase substantially. NLC therefore wanted to conclude the contract at the earliest. It was only with this view, time limit was prescribed, before which the required information should be furnished. Notwithstanding such prescription of time, the Petitioner failed to submit the required clarification and technical information.

(v) It was a composite Tender. The Tender process would be over only by awarding contract, after opening the price bids. It was only on account of the said reason, the Petitioner was asked to extend the bid validity. The extension of validity period would not go to show that NLC has taken a decision to accept the bid submitted by the Petitioner.

(vi) The bid submitted by the Petitioner was not in accordance with the specification. NLC made it very clear that deviation with respect to boiler, minimum stable load, re-heater spray and explosion/implosion withstand capacity etc. cannot be condoned. Even then, there was no follow up action taken by the Petitioner to give clarification or to eradicate the deviation. NLC, was therefore justified in proceeding with the Tender process by inviting the other two bidders to submit the revised price bids.

Citations:

8. The learned Senior Counsel for the Petitioner placed reliance on the following Judgments in support of his contention that Judicial Review is permitted even in contractual matters:

(i) Sona Builders v. Union of India, 2001 (10) SCC 280;

(ii) Canara Bank v. Debasis Das, 2003 (4) SCC 557;

(iii) Nobel Resources Limited v. State of Orissa, 2006 (10) SCC 236;

(iv) Uma Nath Pandey v. State of U.P, 2009 (2) CTC 185 (SC) : 2009 (12) SCC 40;

(v) Natural Resources Allocation, In Re, (Spl. Ref. No. 1/2012), 2012 (10) SCC 1.

9. There is no dispute with regard to the legal position that if an action of State is violative of Article 14 of the Constitution of India, even in contractual matters, Writ Petition is maintainable.

10. The learned Counsel for the Respondent cited the following Judgments:

(i) Tata Cellular v. Union Of India., 1994 (6) SCC 651;

(ii) Meerut Development Authority v. Association of Management Studies, 2009 (6) SCC 171;

(iii) PSA Ennore Pte. Ltd. v. Union of India, 2010 Writ L.R 307 (DB);

(iv) NTPC Limited v. Ansaldo Caldaie Boilers India P. Ltd., JT 2012 (2) SC 511.

Discussion:

11. M/s. Neyveli Lignite Corporation Ltd. is a Central Public Sector Undertaking. NLC was awarded Navaratna status by Government of India in recognition of its performance. NLC proposed to commission a new mega thermal power project at Neyveli. Since it is a major project, NLC appointed M/s. Lahmeyer International (India) Private Limited as its Project Consultant. The project is proposed to be executed under three packages viz., (i) Steam Generator & Auxiliaries Package (NTA1) (ii) Steam Turbine Generator Package (NTA2); (iii) Balance of Plant Package (NTA3). NLC floated Tender under international competitive bidding process.

12. We are concerned only with the Steam Generator & Auxiliaries Package. The Tender Notification contain the relevant dates. The bidders were expected to submit their bids on or before 17th November 2012. The bids were to be submitted under two cover system. Para 3.8(9) of the Instructions to Bidders contains a specific clause that failure to furnish all information required in the Tender specifications or submission of bid not substantially responsive to the Tender specifications in every respect or bids received in incomplete shape shall be liable for rejection. Para 3.8(10) provides that material deviation would include any deviation to vital clauses listed in the technical specifications.

13. The Petitioner submitted its bid pursuant to the Notification issued by NLC. There were two other bidders. Since it is a high value contract for supply of specialized technical equipment for power generation, the Tender process permitted the intending bidders to seek clarifications on commercial and technical aspects at the pre-bid stage. The Petitioner also wanted certain clarifications to be given by NLC. The Petitioner by letter dated 23rd October 2012, requested NLC to extend the time for submission by two months. It is also matter of record that NLC, pursuant to the said request extended time till 21st December 2012 for submission of bid by the Petitioner.

14. NLC after opening the technical bids and conducting a preliminary scrutiny of techno-commercial bids, wanted clarifications on many issues including deviations proposed by the Petitioner.

The Relevant Correspondence:

15. The following details would give a clear picture with regard to the Notices sent to the Petitioner by NLC to clarify its position with regard to certain deviations, time given for answering the clarifications, actual date of receipt of clarifications by NLC, matters in respect of which clarifications were not given by the Petitioner and submission of piecemeal and incomplete clarifications.

(i) NLC by letter dated 19th April 2013, called upon the Petitioner to give clarification on certain vital issues on or before 2nd May 2013. The Petitioner furnished reply by email on 4th May 2013 with respect to certain items and agreed to give a further reply at a later point of time;

(ii) NLC convened a meeting of all the prospective tenderers for a discussion with regard to clarification of bids. The meeting was conducted from 13th May 2013 to 15th May 2013. The Associate of the Petitioner and the officials of NLC attended the meeting. The Petitioner during the course of meeting withdrew certain deviations taken in Part I of its bid. Certain other deviations were either accepted or resolved. Certain material deviations remained unanswered. The Petitioner agreed to clarify with respect to those deviations on or before 22nd May 2013.

(iii) The Petitioner failed to submit the replies/clarifications by 22nd May 2013.

(iv) The Petitioner, by e-mail dated 24th May 2013, submitted a reply to some of the pending points. However, with respect to few other material points, the Petitioner stated that they were in discussion with HBC and a reply would be sent shortly.

(v) The clarification with regard to certain major issues, such as provision of After Burning Grate, Water Lances, Re-Heater Spray, Minimum Stable Load without oil support as well as furnishing of filled Data Sheets, Boiler Bunker Layout Drawings, etc. remained pending.

(vi) NLC by Letter dated 1st June 2013, reminded the Petitioner to submit its reply with regard to the pending points without any further delay.

(viii) The Petitioner by e-mail dated 4th June 2013, promised to respond soon.

(viii) Since the Petitioner failed to clarify the pending points, NLC by letter dated 7th June 2013, requested the Petitioner to furnish reply in full form on or before 12th June 2013.

(ix) Since the Petitioner failed to submit the Filled Data Sheets, which in the normal course should have been annexed to Part I of the bid, NLC by e-mail, called upon the Petitioner to submit the Filled Data Sheets.

(x) The Petitioner by e-mail dated 11th June 2013, furnished reply to some of the points and submitted Filled Data Sheets numbering only 64 Sheets.

(xi) Even though Data Sheets contain numerous technical parameters and the bidder was required to fill up the specifications/parameters, so as to enable NLC to ascertain whether the specifications/parameters offered were within the Technical Specifications annexed to the package and within statutory/regulatory/acceptable specifications, the Petitioner deliberately kept the Data Sheets unfilled. The Petitioner indicated that the required information would be furnished during detailed engineering or as per specification requirement.

(xii) NLC by Letter dated 14th June 2013 called upon the Petitioner to withdraw all the deviations and confirm compliance to technical specification on or before 21st June 2013, failing which it was indicated that the bid will be processed as per Tender conditions based on available documents. NLC along with the said communication annexed a list of pending issues awaiting clarification.

(xiii) NLC by Letter dated 18th June 2013 called upon the Petitioner to offer its comments on the filled data sheets. NLC in the said Letter very specifically stated that response of the Petitioner that the information would be furnished during detailed Engineering, does not answer the pending points.

(xiv) The Petitioner by e-mail dated 21st June 2013 submitted a set of revised Filled Data Sheets and replied only few pending points.

(xv) Since the reply dated 21st June 2013 was incomplete, NLC by Letter dated 28th June 2013 sought further clarification.

(xvi) The Petitioner by e-mail dated 28th June 2013 replied that for Water Lances and After Boiling Grate they would take responsibility. However the Petitioner wanted further time to submit its answers to the remaining issues.

(xvii) The Petitioner by e-mail dated 29th June 2013 informed NLC that they are in the process of discussion with their OEM and shall revert shortly on other pending issues.

(xviii) NLC by Letter dated 10th July 2013 informed the Petitioner about the importance of ten pending points. The Petitioner was asked to submit its reply positively by 15th July 2013. It was specifically stated that the reply has to be filed before the prescribed date and no further extension of time would be granted and no correspondence shall be entertained thereafter.

(xix) The Petitioner by e-mail dated 15th July 2013 stated that they have already withdrawn the deviations with regard to Water Lances and After Burning Grates (ABG) and promised to produce a Letter to that effect from M/s. Harbin Boiler Company. The Petitioner by the very same e-mail furnished the Bunker Bay drawing for the first time. It was found that the Bunker Bay had been shifted to the rear side of the Boiler as against the Tender specification requiring it to be located in the front portion. Similarly instead of rectangular boiler, the Petitioner showed it as Circular.

(xx) The Petitioner submitted an unsigned Letter from M/s. Harbin Boiler Company, which was also not as per specification.

(xxi) The Petitioner by e-mail dated 23rd July 2013 gave confirmation with respect to two pending points. However, other pending points remain unanswered.

16. The factual matrix clearly shows that the Petitioner has been buying time under one pretext or the other. The Petitioner failed to answer the basic issues relating to After Burning Grate (ABG), Water lances, Reheater Spray, Minimum Stable load without oil support. The correspondences exchanged between the parties would give a prima facie impression that the Petitioner was not sure as to whether they would be in a position to supply the boiler as per the specification given by NLC.

17. NLC time and again extended the dead line so as to enable the Petitioner to answer the query. The communications sent by the Petitioner to NLC one after another very clearly indicates that the Petitioner was only in the stage of preparatory process to comply with the Tender requirements.

18. The documents produced by NLC shows that the technical doubts entertained by the Petitioner were all answered as early as on 29th October 2012. It is also not in dispute that the consortium partner of the Petitioner M/s. Harbin Boiler Company Limited is not manufacturing the type of steam generator shown in the specification given by NLC. HBC was not prepared originally to supply After Burning Grate and Water Lances as per specification. NLC wanted to supply After Burning Grate strictly as per their requirement as shown in the Tender Notification. It was only on 16th July 2013, M/s. Harbin Boiler Company Limited has sent an unsigned communication confirming to the design and supply of After Burning Grate and Water Lances. Since it was an unsigned letter NLC was not bound to consider it for proceeding further. Even according to the Petitioner, the value of the contract is Rs. 5,907.11 crores. The Petitioner should have taken the issue little seriously, given the nature of contract and the cost factor. The fact that NLC was tolerant should not be taken in the negative manner. NLC waited for months together taking into account the fact that there are only three bidders. It was only to give an opportunity to the Petitioner to prove its technical competence to supply steam generator and auxiliary package, time was extended on innumerable occasions.

19. There is no dispute that in the usual course of Tender process, in case technical bid submitted by a bidder does not confirm to the eligibility criteria, it would summarily be rejected. NLC, considering the volume of work and money involved, granted sufficient time to the Petitioner to comply with technical specifications. However, the Petitioner was giving only evasive replies and never adhered to the time schedule. NLC was not bound to give periodical extension in an indefinite manner. In case extension is given and the matter is dragged, naturally, cost would escalate. The project cost would go up considerably in the event of delay. It was only under such circumstances, NLC issued an ultimatum to the Petitioner directing rectification of deficiencies earlier noted before a particular period. It is a matter of record that even then, the Petitioner was not in a position to answer several basic issues which goes to the root of the matter.

20. The learned Senior Counsel for the Petitioner has taken up a contention that even after opening the technical bid, the Petitioner was directed to keep the Bank guarantee alive. According to the learned Senior Counsel, this act would show that the technical bid of the Petitioner was not rejected. I am not inclined to accept the said submission. The Tender Notification very clearly shows that it is a composite Tender and the bidders have to keep the Bank guarantee alive till the Award of contract. The contract being a composite one, it would be awarded only after opening the price bid.

21. The learned Senior Counsel for the Petitioner mainly focussed on the contention regarding limited time given to the Petitioner to answer the issues and deviations. According to the learned Senior Counsel, letter was sent on 10th July 2013. Since 13th and 14th July 2013 were holidays for the Company (Saturday and Sunday) there were only three days time to submit the reply. The learned Senior Counsel by placing reliance on the Division Bench decision of this Court in Commissioner, Corporation of Chennai v. R.S Vaideeswaran, 2009 (6) CTC 623 and Sona Builders v. Union of India, 2001 (10) SCC 280 submitted that this Court has already held that two days' Notice is not a reasonable notice. The argument on the basis of three days' Notice is liable to be rejected for more than one reason:

(a) This is not a statutory Notice given for undertaking a particular act or a Show Cause Notice giving two or three days' Notice. The Notice period here has to be computed from the initial period. The bids were opened on 21st December 2012. Thereafter, discussions with regard to deviations commenced. Since the Petitioner failed to adhere to the time schedule, NLC started issuing notices from 19th April 2013. The Notice dated 10th July 2013 was nothing but continuation of the earlier Notices. It was not first of its kind. It is too strange on the part of a bidder, who is in the race for securing a contract worth Rs. 5,900 crores to come up with a contention that Saturday and Sunday were holidays and as such time was too short to reply.

(b) The Petitioner was expected to meet the technical specifications indicated in the bid document. Deviations without effecting the structure of package were permitted. The Petitioner failed to meet the technical specifications. The Petitioner wanted to supply Boiler and Steam Generators manufactured by its Consortium Partner notwithstanding the fact that those items were not the one NLC wanted to erect at Neyveli.

22. The learned Senior Counsel while narrating the background of the Petitioner-Company and its experience submitted that the Petitioner was awarded several contracts in recognition of its past performance and adherence to time schedule.

23. The learned Counsel for NLC by placing reliance on the recent Order terminating the contract given to the Petitioner by Metro Rail submitted that the contract for a sum of Rs. 178 Crores awarded to the Petitioner in August 2011 for construction of elevated stretch between Officers Training Academy and Chennai Airport was cancelled on account of slow progress. The learned Counsel again by placing certain Reports submitted that the Petitioner had a net debt of Rs. 34,770 Crores as on 30th June 2013. Since those details are not germane to decide this Writ Petition, there is not need to refer those submissions.

24. Even though the learned Senior Counsel for the Petitioner accused NLC of giving only three days time to rectify certain major deficiencies, the fact remains that even after the expiry of two months from the deadline, the Petitioner has no case that they have complied with the requirements pointed out by NLC earlier in respect of which, final Notice was given on 10th July 2013. This shows the lack of bona fides on the part of the Petitioner and the justification put forward by NLC that the Petitioner wanted to drag on the matter till they are in a position to meet the Tender requirements.

25. The Petitioner now wanted this Court to exercise Judicial Review during the currency of Tender evaluation process. The contract is a major one involving several crores of rupees. Even though the Tender process with regard to the other two packages viz., Steam Turbine Generator Package (NTA2) and Balance of Plant Package (NTA3) proceeded as scheduled, the fact remains that the process regarding Steam Generator & Auxiliaries Package (NTA1) was kept in abeyance on account of the failure of Petitioner to furnish required information. It is not open to this Court exercising the power of Judicial Review to test the correctness of the steps taken by NLC and to substitute its opinion. In fact, NLC has appointed an expert consultant and the Tender was drafted in such a way that NLC would be in a position to offer the contract to a bidder, who satisfies all the technical specifications and is in a position to execute the work within the prescribed period. The Petitioner took extension of time even for submitting the bid. Thereafter the Petitioner took months together to submit its response with regard to technical specifications. In case the matter is dragged like this, it would not be possible for NLC to award the contract and to execute the project before the prescribed period.

The Law:

26. The Supreme Court in Sterling Computers Limited v. M&N Publications Ltd., 1993 (1) SCC 445, observed that the authorities should be given discretion in the matter of awarding contract without violating the norms:

“12. In contracts having commercial element, some more discretion has to be conceded to the authorities so that they may enter into contracts with persons, keeping an eye on the augmentation of the revenue. But even in such matters they have to follow the norms recognised by Courts while dealing with public property. It is not possible for Courts to question and adjudicate every decision taken by an authority, because many of the Government Undertakings which in due course have acquired the monopolist position in matters of sale and purchase of products and with so many ventures in hand, they can come out with a plea that it is not always possible to act like a quasi-judicial authority while awarding contracts. Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been taken in bona fide manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by Justice Holmes, that Courts, while judging the Constitutional validity of executive decisions, must grant certain measure of freedom of ‘play in the joints’ to the executive.”

27. The Supreme Court in Tata Cellular v. Union Of India., 1994 (6) SCC 651, indicated the extent of Judicial Review in contractual matters:

“94. The principles deducible from the above are:

(1) The modern trend points to judicial restraint in administrative action.

(2) The Court does not sit as a Court of Appeal but merely reviews the manner in which the decision was made.

(3) The Court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible.

(4) The terms of the invitation to Tender cannot be open to judicial scrutiny because the invitation to Tender is in the realm of contract. Normally speaking, the decision to accept the Tender or award the contract is reached by process of negotiations through several tiers. More often than not, such decisions are made qualitatively by experts.

(5) The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury Principle of Reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or actuated by mala fides.

(6) Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure.”

28. The Supreme Court in Meerut Development Authority v. Association of Management Studies, 2009 (6) SCC 171, indicated the salient features of Tender and the nature of right of bidders:

“26. A Tender is an offer. It is something which invites and is communicated to notify acceptance. Broadly stated it must be unconditional; must be in the proper form, the person by whom Tender is made must be able to and willing to perform his obligations. The terms of the invitation to Tender cannot be open to judicial scrutiny because the invitation to Tender is in the realm of contract. However, a limited Judicial Review may be available in cases where it is established that the terms of the invitation to Tender were so tailor-made to Suit the convenience of any particular person with a view to eliminate all others from participating in the bidding process.

27. The bidders participating in the Tender process have no other right except the right to equality and fair treatment in the matter of evaluation of competitive bids offered by interested persons in response to notice inviting Tenders in a transparent manner and free from hidden agenda. One cannot challenge the terms and conditions of the Tender except on the above stated ground, the reason being the terms of the invitation to Tender are in the realm of the contract. No bidder is entitled as a matter of right to insist the authority inviting Tenders to enter into further negotiations unless the terms and conditions of notice so provided for such negotiations.”

29. The Supreme Court in Arun Kumar Agrawal v. Union of India, 2013 (7) SCC 1, considered the scope of Judicial Review of complex economic decision taken by the State or its instrumentalities. The Supreme Court held:

“41. We notice that the ONGC and the Government of India have considered various commercial and technical aspects flowing from the PSC and also its advantages that ONGC would derive if the Cairn and Vedanta deal was approved. This Court sitting in the jurisdiction cannot sit in judgment over the commercial or business decision taken by parties to the agreement, after evaluating and assessing its monetary and financial implications, unless the decision is in clear violation of any statutory provisions or perverse or for extraneous considerations or improper motives. States and its instrumentalities can enter into various contracts which may involve complex economical factors. State or the State undertaking being a party to a contract, have to make various decisions, which they deem just and proper. There is always an element of risk in such decisions, ultimately it may turn out to be a correct decision or a wrong one. But if the decision is taken bona fide and in public interest, the mere fact that decision has ultimately proved to be a wrong, that itself is not a ground to hold that the decision was mala fide or done with ulterior motives.”

30. NLC wanted After Burning Grates and a specified steam generators as suggested by its technical consultant. The documents available on record very clearly shows that the Consortium Partner of the Petitioner was not manufacturing steam generators as shown in the Tender bulletin issued by NLC. When it was realised that NLC would not accept any other type of steam generators, the Petitioner obtained an unsigned Letter from its Consortium Partner agreeing to supply Steam Generators as per Tender specification.

31. The importance of the condition regarding supply of Steam Generators was indicated by the Supreme Court in NTPC Ltd. v. Ansaldo Caldaie Boilers India (P) Limited, 2012 (4) SCC 471:

“35. The importance of the above condition is manifested in the functioning of the Steam Generator which handles high pressure steam for the purpose of turning the turbines for generating electricity. The design and engineering of the evaporator and the boiler itself has to be such as to withstand the very high temperatures and pressures generated. The importance of the variable pressure operations is of great importance as far as generation and wastage of energy is concerned. The importance of the evaporator in controlling pressure during operations is to automatically regulate the flow of water, generation of pressure and temperature of the steam to the desired level.”

Concept of Judicial Review:

32. There is no dispute that Judicial Review is essentially against the decision making process and not against the merits of the decision. This is more in the realm of contract. The State should have the freedom to prescribe terms and conditions of contract. In case a Tender Notification is issued, it is open to all concerned to apply if they are interested to take part and eligible to participate in the process. If the Tender conditions are tailor-made to suit the chosen few, and the process is arbitrary and action is violative of the equality clause enshrined under Article 14 of the Constitution of India, the Court would be justified in exercising the jurisdiction under Article 226 of the Constitution of India to correct the decision and to ensure a level playing field to all the competitors. However the question here is whether the Court would be justified in interfering with the Tender process in each and every stage. In case of Courts interference in every now and then at the instance of those who are in the race and convinced that they would not be in a position to secure the contract, it would paralyse the very system. The Government agencies would not be in a position to proceed independently in the event of such routine exercise of Judicial Review. There should be materials before the Court that the concerned bidder was fully qualified and in spite of eligibility, his Tender was not considered on extraneous reasons. The party must demonstrate that there is a conscious attempt to part with the privilege in favour of those, who are not eligible for such benefits and not withstanding the eligibility of others, who are in a better position to make a claim. The Court is expected to strike a balance in such cases. The larger public interest must guide the Court in a case of this nature involving substantial public money.

Conclusion:

33. The Petitioner wanted its technical bid to be evaluated after submitting clarifications with regard to technical specifications. NLC evaluated technical bids on the basis of available materials and found that the Petitioner failed to comply with technical specifications. Thereafter NLC called upon the other two bidders to submit its supplemental/Addendum Price. It was only at that point of time the Petitioner woke up from slumber and filed this Writ Petition. There is absolutely no merit in the contention taken by the Petitioner.

34. In the upshot, I dismiss the Writ Petition. Consequently, the connected MP is closed. No costs.