Shri Avantika Contractors (I) Ltd. v. Union Of India & Ors.
Satish K. Agnihotri, C.J
IA No. 4 of 2018
1. On being mentioned, the matter is taken up on Board.
2. This is an application seeking an interim direction, directing the respondents to stay the invocation of Bank Guarantee with regard to construction of ITBP road from Thangu to Muguthang in the State of Sikkim vide agreement No. 02.EE/CCD/2010-1. Mr. B.S Banthia, learned counsel appearing for the petitioner submits that the petitioner has preferred a Special Leave Petition against the order dated 06.12.2017 rendered by this Court, whereby the Court observed that the respondent may proceed with the tender process, but final decision shall not be taken till the next date of hearing and the matter was adjourned to 08.03.2018
3. The Supreme Court disposed of the petition on 19.01.2018 and protected the petitioner till 25.01.2018 from encashment of Bank Guarantee.
4. This application seeks stay of invocation of Bank Guarantee. Mr. Karma Thinlay, learned Central Govt. Advocate appearing for the respondents seeks for two days time to file response. Time is granted.
5. Status quo in respect of Bank Guarantee shall be maintained by both the parties till the next date of hearing.
6. Let the matter be listed before the Vacation Bench on 30.01.2018