Dinesh Kumar Agarwal And Another v. Indore Municipal Corporation, Indore And Two Others

Madhya Pradesh High Court
Mar 17, 2015
Smart Summary (Beta)

Factual and Procedural Background

The petitioners filed a writ petition challenging a notice dated 26/12/2014 issued by respondent Nos. 2 and 3 directing them to remove alleged illegal construction on land purchased by them in Indore. The petitioners claimed that the land was designated as Green Belt under the Master Plan but permitted construction of an outhouse, which they asserted they had built within the permissible area without any illegal encroachment. They stated they were paying property tax and electricity bills and sought quashing of the impugned notice. The Indore Municipal Corporation responded alleging that the petitioners constructed a large unauthorized structure without any sanctioned building plan, including multiple rooms and floors, and that the construction was illegal and liable for demolition. The Corporation maintained that compounding was only applicable to the offence and not to the illegal structure itself.

Legal Issues Presented

  1. Whether the petitioners’ construction on the Green Belt land was illegal and liable to be demolished despite their claim of permissible outhouse construction.
  2. Whether compounding under Section 308 of the Municipal Corporation Act, 1960 can regularize or protect the illegal construction.
  3. The extent of the Corporation’s authority to issue demolition notices in cases of unauthorized construction without sanctioned plans.

Arguments of the Parties

Petitioners' Arguments

  • The petitioners contended that they had purchased the land legally and constructed only an outhouse within the permissible limits under the Master Plan.
  • They argued that they had not constructed any illegal structure and had complied with tax and utility payments.
  • Reliance was placed on a judgment in Nand Kishore v. Nagar Palika Nigam (1986 MPWN 247) that compounding fees, once paid, preclude further action by the Corporation.
  • The petitioners sought quashing of the demolition notice issued by the Municipal Corporation.

Respondents' Arguments

  • The Indore Municipal Corporation refuted the petitioners’ claims, stating the petitioners had constructed a large structure without any sanctioned building plan or permission.
  • The Corporation emphasized that the structure was built on Green Belt land, which is prohibited for such construction.
  • They pointed out that the petitioners failed to produce any sanctioned map despite prior notices and hearings.
  • The notice was issued in the name of Rupesh Agrawal based on information from the site’s chowkidar.
  • The Corporation maintained that compounding applies only to the offence and does not legalize illegal structures, and therefore demolition action is justified.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Nand Kishore v. Nagar Palika Nigam [1986 MPWN 247] Compounding fees charged preclude further action by the Corporation. The Court found that compounding applies only to the offence and not to the illegal structure, thus the Corporation’s demolition notice was valid despite the compounding order.
Friends Colony Development Committee v. State of Orissa (2004 AIR SCW 5923) Illegal constructions threaten public infrastructure and environment; compounding should be rare and strict action is necessary against deliberate deviations. The Court relied on this judgment to uphold the Municipal Corporation’s right to demolish illegal structures to prevent public harm and discourage unauthorized construction.
Esha Ekta Apartments Chs Limited v. Municipal Corporation of Mumbai (2012) 4 SCC 689 Buildings constructed in violation of sanctioned plans cannot be regularized by courts exercising equity jurisdiction; flat buyers lack locus to challenge demolition. The Court applied this principle to affirm that illegal construction cannot be regularized and that the Corporation’s demolition action was lawful.
Esha Ekta Apartments Chs Limited v. Municipal Corporation of Mumbai (2013) 5 SCC 357 Planning authority must apply applicable regulations in force at the relevant time; CRZ notifications prevail over conflicting regulations. The Court upheld the Appellate Authority’s decision refusing regularization under later regulations, reinforcing strict adherence to applicable planning laws.
Priyanka Estates International Pvt. Ltd. v. State of Assam (2010 AIR SCW 1374) Court’s jurisdiction to award compensation to victims of unauthorized constructions; illegal builders should be punished; demolition is permissible with adequate notice to occupants. The Court used this precedent to support the Corporation’s authority to demolish illegal structures and emphasized the need to prevent normalization of unauthorized constructions.

Court's Reasoning and Analysis

The Court examined the petitioners’ claim that their construction was lawful within the Green Belt area and found it contradicted by the Municipal Corporation’s detailed evidence of large unauthorized construction without any sanctioned plan. The Court noted that the petitioners failed to produce any sanctioned map despite prior notices and hearings. Reliance on the earlier judgment in Nand Kishore was held inapplicable as compounding only applies to the offence and not to the illegal structure itself. The Court extensively referred to the Supreme Court’s decisions emphasizing the illegality of unauthorized constructions, the limited scope of compounding, and the necessity of strict enforcement to prevent public harm and urban planning chaos. The Court observed that encroachment on Green Belt land and constructions without sanctioned plans undermine public interest and infrastructure. It rejected any plea for regularization or interference, affirming the Municipal Corporation’s right to proceed with demolition under the law.

Holding and Implications

The Court declined to interfere with the Municipal Corporation’s demolition notice and refused admission of the writ petition.

The direct effect is that the respondent Corporation is authorized to take appropriate action, including demolition, against the petitioners’ illegal construction. No new precedent was set; the decision reinforces existing legal principles that illegal constructions, especially on protected Green Belt land without sanctioned plans, cannot be regularized by compounding or court intervention. The ruling underscores the necessity of adherence to sanctioned plans and the authority of municipal bodies to enforce urban planning laws to protect public interest.

Show all summary ...

S.C Sharma, J.:— The petitioners before this Court have filed this present writ petition being aggrieved by the notice dated 26/12/2014 by which the respondent Nos. 2 and 3 have directed the petitioners to remove the alleged illegal construction.

2. Contention of the petitioners is that the petitioners have purchased land bearing Patwari Halka No. 10 Gram Tejpur Gadbadi, Tehsil & District Indore bearing Survey No. 65, Area 0.223 hectare vide registered sale deed on 26/7/1995 from Kavita Cooperative Housing Society Ltd., Petitioners have stated in the Writ Petition that as per the Master Plan the said land is declared as Green Belt and there is a provision to construct an outhouse on the said land and the petitioners have constructed an outhouse within the permitted area and have not constructed over even a single inch illegally. It has also been stated that the petitioners are paying property tax as well as electricity bill. Petitioners have further stated that a Show Cause Notice was issued by the Indore Municipal Corporation in the name of Rupesh Agrawal u/s. 307 of the M. P. Municipal Corporation Act, 1960 and the petitioners being aggrieved by the notice have filed this present Writ Petition stating that they have not constructed anything illegally and construction, if found illegal, can be compounded u/S. 308 of the Municipal Corporation Act, 1960. The petitioners have prayed for quashment of the impugned notice.

3. A detailed and exhaustive reply has been filed by the respondent - Indore Municipal Corporation and it has been stated that the petitioners have made an incorrect statement in the Writ Petition and have not come with clean hands. The petitioners have constructed without there being any sanctioned map sanctioned by any authority. The petitioners have constructed 4000 square feet over the land in question. It has been stated that two floors construction is in existence which includes seven rooms, two big halls, two verandas, one wash room etc., The respondents have stated that in absence of any permission, the entire structure is an illegal structure and it is not a case where the Corporation is demolishing the room meant for Chowkidar. It has been stated that the Chowkidar present at the spot namely; Mukesh, has informed the name of owner as Rupesh Agrawal and, therefore, the notice was issued in the name of Rupesh Agrawal. It has been further stated that the petitioners did respond to the notice issued by the Corporation and it is not a case where the petitioners were not heard by the Corporation. The petitioners were also earlier served with the notice dated 15/5/2012 and the petitioners did submit a reply to the notice, however, failed to produce any sanctioned map. Respondents have stated that there is no diversion, there is no sanctioned plan and merely because the petitioner has purchased a land from Samiti, it does not mean that the Corporation cannot demolish the illegal structure. The Corporation has stated that the building in question has been constructed over the Green Belt and, therefore, they have got every right to demolish the structure in question. The respondents have also stated that the compounding, if any, is not going to benefit the petitioners as it is the only offence which can be compounded and not the illegal structure.

4. Learned counsel for the petitioner has placed reliance upon a judgment delivered in the case of Nand Kishore v. Nagar Palika Nigam reported in [1986 MPWN 247 S.N 176], decided on 26/4/1985 and his contention is that in the light of the judgment delivered by the learned Single Judge that once compounding fees is charged, Corporation cannot take any action.

5. This Court has very carefully gone through the aforesaid judgment. In the present case, it is the petitioner who has constructed contrary to the sanctioned lay out. The Appellate Committee has certainly passed an order, though the same is not on record, compounding the matter, but the fact remains that it is the offence which is compounded and not the illegal structure.

6. The apex Court in the case of Friends Colony Development Committee v. State of Orissa reported in (2004 AIR SCW 5923), in paragraph 20, 25 and 26 has held as under:

20. The pleadings, documents and other material brought on record disclose a very sorry and sordid state of affairs prevailing in the matter of illegal and unauthorized constructions in the city of Cuttack. Builders violate with impunity the sanctioned building plans and indulge deviations much to the prejudice of the planned development of the city and at the peril of the occupants of the premises constructed or of the inhabitants of the city at large. Serious threat is posed to ecology and environment and, at the same time, the infrastructure consisting of water supply, sewerage and traffic movement facilities suffer unbearable burden and are often thrown out of gear. Unwary purchasers in search of roof over their heads and purchasing flats/apartments from builders, find themselves having fallen prey and become victims to the design of unscrupulous builders. The builder conveniently walks away having pocketed the money leaving behind the unfortunate occupants to face the music in the event of unauthorized constructions being detected or exposed and threatened with demolition. Though the local authorities have the staff consisting of engineers and inspectors whose duty is to keep a watch on building activities and to promptly stop the illegal constructions or deviations coming up, they often fail in discharging their duty. Either they don't act or do not act promptly or do connive at such activities apparently for illegitimate considerations. If such activities are to stop, some stringent actions are required to be taken by ruthlessly demolishing the illegal constructions and non-compoundable deviations. The unwary purchasers who shall be the sufferers must be adequately compensated by the builder. The arms of the law must stretch to catch hold of such unscrupulous builders. At the same time, in order to secure vigilant performance of duties, responsibility should be fixed on the officials whose duty it was to prevent unauthorized constructions, but who failed in doing so either by negligence or by connivance.

25. Though the municipal laws permit deviations from sanctioned constructions being regularized by compounding but that is by way of exception. Unfortunately, the exception, with the lapse of time and frequent exercise of the discretionary power conferred by such exception, has become the rule. Only such deviations deserve to be condoned as are bona fide or are attributable to some mis-understanding or are such deviations as where the benefit gained by demolition would be far less than the disadvantage suffered. Other than these, deliberate deviations do not deserve to be condoned and compounded. Compounding of deviations ought to be kept at a bare minimum. The cases of professional builders stand on a different footing from an individual constructing his own building. A professional builder is supposed to understand the laws better and deviations by such builders can safely be assumed to be deliberate and done with the intention of earning profits and hence deserve to be dealt with sternly so as to act as a deterrent for future. It is common knowledge that the builders enter into under hand dealings. Be that as it may, the State Governments should think of levying heavy penalties on such builders and therefrom develop a welfare fund which can be utilized for compensating and rehabilitating such innocent or unwary buyers who are displaced on account of demolition of illegal constructions.

26. The application for compounding the deviations made by the builders should always be dealt with at a higher level by multi-membered High Powered Committee so that the builders cannot manipulate. The officials who have connived at unauthorized or illegal constructions should not be spared. In developing cities the strength of staff which is supposed to keep a watch on building activities should be suitably increased in the interest of constant and vigilant watch on illegal or unauthorized constructions.

7. In the light of the aforesaid judgment, this Court is of the considered opinion that the Indore Municipal Corporation has rightly issued the notice of demolition to the petitioner. The illegal structure of the petitioner is resulting in traffic congestion, unbearable burden upon the public at large and has to be demolished as it has not been constructed without any building plan.

8. The Apex Court in the case of Esha Ekta Apartments Chs Limited v. Municipal Corporation of Mumbai reported in (2012) 4 SCC 689, in paragraphs 21 to 25 has held as under:

21. In these cases, the trial Court and the High Court have, after threadbare analysis of the pleadings of the parties and the documents filed by them concurrently held that the buildings in question were constructed in violation of the sanctioned plans and that the flat buyers do not have the locus to complain against the action taken by the Corporation under Section 351 of 1888 Act. Both, the trial Court and the High Court have assigned detailed reasons for declining the petitioners' prayer for temporary injunction and we do not find any valid ground or justification to take a different view in the matter.

22. The submission of Dr. Abhishek Manu Singhvi that the constructed area should be measured with reference to the total area of the plot cannot be accepted for the simple reason that the State Government had sanctioned change of land use only in respect of 13049.45 sq. meters.

23. In view of the above, we may have dismissed the special leave petitions and allowed the Corporation to take action in furtherance of notices dated 19.11.2005 and orders dated 3/8.12.2005, but keeping in view the fact that the flat buyers and their families are residing in the buildings in question for the last more than one decade, we feel that it will be in the interest of justice that the issue relating to the petitioners' plea for regularization should be considered by this Court at the earliest so that they may finally know their fate.

24. We, therefore, direct the petitioners to furnish the particulars of the writ petitions filed for regularization of the construction which are pending before the High Court. The needful be done within a period of two weeks from today. Within this period of two weeks, the petitioners shall also furnish the particulars and details of the developers from whom the members of the societies had purchased the flats. List the cases on 16th March, 2012 (Friday).

25. If the petitioners fail to comply the aforesaid directions, the special leave petitions shall stand automatically dismissed.

9. The apex Court, later on, in respect of the same parties, ie., Esha Ekta Apartments Chs Limited v. Municipal Corporation of Mumbai reported in (2013) 5 SCC 357, in paragraphs 41 to 43 has held as under:

41. At the cost of repetition, it will be apposite to note that the Deputy Chief Engineer had rejected the request made by the architect for exemption of the area of staircase, lift and lift lobby from FSI by observing that the same is not in conformity with Clause 35(2)(c) of the 1991 Regulations because the Corporation had decided the proposal prior to coming into force of those regulations and the permissible FSI had already been exhausted. The Appellate Authority agreed with the Deputy Chief Engineer that the 1991 Regulations cannot be invoked for regularization of the disputed construction because the same were enforced much after rejection of the amended plans and the plot in question is situated in CRZ area.

42. In our view, the reasons assigned by the Deputy Chief Engineer and the Appellate Authority are in consonance with the law laid down by this Court in Suresh Estates Private Limited v. Municipal Corporation of Greater Mumbai (supra). The facts of that case were that after purchasing a plot measuring 8983 sq. mtrs. situated at Dr. Babasaheb Jaykar Marg, appellant Nos. 1 and 2 submitted plans to develop the same by constructing a luxury hotel in terms of the D.C Rules. In the application, the appellants mentioned that they are entitled to additional FSI as per Rule 10(2) of the D.C Rules. The Corporation made a recommendation to the State Government that in view of the CRZ notification and the D.C Rules, additional FSI be granted to the appellants. The Ministry of Environment and Forest sent communication dated 18.8.2006 to the Principal Secretary, Urban Development Department, Government of Maharashtra clarifying that the D.C Rules, which existed on 19.2.1991 would apply to the areas falling within the CRZ notification and the word “existing” means the rules which prevailed on 19.2.1991 It was also mentioned that the draft regulations of 1989, which came into force on 20.2.1991 would not apply. At that stage, the appellants filed a writ petition before the High Court with the complaint that the Corporation had not communicated its decision within 60 days. The same was disposed of by the High Court with a direction to the State Government to decide the application of the appellants within six weeks. Before this Court, it was argued on behalf of the Corporation that the D.C Rules would not apply to the development permission sought by the appellants and the 1991 Regulations are applicable in the matter. According to the Corporation, the 1991 Regulations do not provide for additional FSI for the proposed hotel project. It was further argued that the restrictions contained in the CRZ notification will be attracted because the plot is situated in CRZ area. This Court noted that the 1991 Regulations were notified on 20.2.1991 and came into force on 25.3.1991 whereas CRZ notification was issued on 2.2.1991 and observed:

19. The word “existing” as employed in the CRZ notification means the town and country planning regulations in force as on 19-2-1991. If it had been the intention that the town and country planning regulations as in force on the date of the grant of permission for building would apply to the building activity, it would have been so specified. It is well to remember that CRZ notification refers also to structures which were in existence on the date of the notification. What is stressed by the notification is that irrespective of what local town and country planning regulations may provide in future the building activity permitted under the notification shall be frozen to the laws and norms existing on the date of the notification.

20. On 2-2-1991 when the CRZ notification was issued, the only building regulations that were existing in city of Mumbai, were the DC Rules, 1967. In view of the contents of CRZ II notification issued under the provisions of the Environment (Protection) Act which has the effect of prevailing over the provisions of other Acts, the application submitted by the appellants to develop the plot belonging to them would be governed by the provisions of the DC Rules, 1967 and not by the draft development regulations of 1989 which came into force on 20-2-1991 in the form of the Development Control Regulations for Greater Bombay, 1991.

21. The argument that in view of the provisions of Section 46 of the Town Planning Act, 1966, the Planning Authority has to take into consideration the draft regulations of 1989 and, therefore, the appellants would not be entitled to additional FSI is devoid of merits.

22. Section 3 of the Environment (Protection) Act, 1986 inter alia provides that the provisions of the Act and any order or notification issued under the said Act will prevail over the provisions of any other law.

23. The phrase ‘any other law’ will also include the MRTP Act, 1966. As noticed earlier the Notification dated 19-2-1991 issued under the provisions of the Environment (Protection) Act, 1986 freezes the building activity in an area falling within CRZ II to the law which was prevalent and in force as on 19-2-1991. The draft regulations of 1989 would therefore not apply as they were not existing law in force and prevalent as on 19-2-1991.

24. In view of the peculiar circumstances obtaining in the instant case, the Court is of the opinion that Section 46 of the MRTP Act, 1966 would not apply to the facts of the instant case. Further, when the sanctioned DC Regulations for Greater Bombay, 1991 do not apply to areas covered within CRZ II, since those Regulations came into force with effect from 25-3-1991, its previous draft also cannot apply. The draft published is to be taken into consideration so that the development plan is advanced and not thwarted. The draft development plan was capable of being sanctioned, but when the final development plan is not applicable, its draft would equally not apply as there is no question of that plan being thwarted at all. As far as development in the area covered by CRZ II is concerned, one will have to proceed on the footing that the draft plan after CRZ notification never existed. Even otherwise what is envisaged under Section 46 of the MRTP Act is due regard to draft plan only if there is no final plan. The DC Rules of 1967 were in existence as on 19-2-1991 and therefore the plan prepared thereunder would govern the case.

26. The draft regulations of 1989 were not in force as on 19-2-1991 and, therefore, would not apply to the plot in question. What is emphasised in Section 46 of the MRTP Act, 1966 is that the Planning Authority should have due regard to the draft rules (sic regulations). The legislature has not used the phrase ‘must have regard’ or ‘shall have regard’. Municipal Corporation of Greater Mumbai which is the Planning Authority had given due regard to the draft DC Regulations of 1989 in the light of CRZ notification and recommended to the Government to grant additional FSI of 3.73 times permissible as per the Development Control Rules, 1967 over and above 1.33 permissible, to the appellants. Having regard to the facts of the case this Court is of the opinion that the contention that the Planning Authority has to take into consideration the draft regulations of 1989 and, therefore, the appellants would not be entitled to additional FSI, cannot be accepted and is hereby rejected. (Emphasis supplied)

43. In view of the aforesaid judgment of the three Judge Bench, it must be held that the Appellate Authority had rightly declined to invoke the 1991 Regulations for entertaining the prayer made by the architect Shri Jayant Tipnis for regularization of the constructions made in violation of the sanctioned plan.

10. The apex Court has turned down the claim of the flat buyers for regularization on the ground of equity. The apex Court has held that if the Courts exercise equity jurisdiction to regularise illegally constructed flats, this will encourage violators and others to commit further such illegalities. It was held that the flat owners are having remedy to sue the sellers of flat/developers for refund of their money/for damages.

11. The apex Court in the case of Priyanka Estates International Pvt. Ltd. v. State of Assam reported in (2010 AIR SCW 1374) in paragraph 75 to 82 has held as under:

75. The jurisdiction and power of courts to indemnify a citizen for injuries suffered due to such unauthorised or illegal construction having been erected by builder/coloniser is required to be compensated by them. An ordinary citizen or a common man is hardly equipped to match the might and power of the builders.

76. In the case in hand, it is noted that number of occupiers were put in possession of the respective flats by the builder/developer constructed unauthorisedly in violation of the laws. Thus, looking to the matter from all angles it cannot be disputed that ultimately the flat owners are going to be the greater sufferers rather than builder who has already pocketed the price of the flat.

77. It is a sound policy to punish the wrong-doer and it is in that spirit that the courts have moulded the reliefs of granting compensation to the victims in exercise of the powers conferred on it. In doing so, the courts are required to take into account not only the interest of the petitioners and the respondents but also the interest of public as a whole with a view that public bodies or officials or builders do not act unlawfully and do perform their duties properly.

78. In the case in hand, admittedly, at no point of time Appellant No. 1-M/s. Priyanka Estates International Pvt. Ltd. was able to show to its prospective purchasers the Occupancy Certificate or Completion Certificate issued by the authorities concerned. The same could not even be shown to us and without it, Appellant No. 1 could not have embarked into sale of flats as it was mandatorily required.

79. The instant case is not a case of breach of contract. It is a clear case of breach of the obligation undertaken to erect the building in accordance with building regulations and failure to truthfully inform the warranty of title and other allied circumstances.

80. Even though at the first instance, we thought of invoking this Court's jurisdiction conferred under Article 142 of the Constitution of India so as to do complete justice between the parties and to direct awarding of reasonable/suitable compensation/interest to the flat owners, whose flats are ultimately going to be demolished, but, with a very heart, we have restrained ourselves from doing so, for variety of reasons and on account of various disputed questions that may be posed in the matter. However, we grant liberty to those, whose flats are ultimately going to be demolished, to exhaust the remedy that may be available to them in accordance with law.

81. We also feel it necessary and expedient to direct the Respondent-authorities that if ultimately flat owners, whose flats are going to be demolished shall be given at least three months' time to vacate the same. This would enable them to mitigate the losses that may be incurred by them. We accordingly direct so.

82. In the light of the foregoing discussions, these appeals are dismissed with the directions contained hereinabove. Respondent-authorities shall be at liberty to proceed with demolition of half of the 5 floor, if not ultimately compounded; 6, 7 and 8 floors as mentioned hereinabove.

12. In the light of the judgment delivered by the apex Court in the case of Priyanka Estates (supra), the respondent Corporation is free to take appropriate action by demolishing the same. It has become a normal practice to encroach the Government land, to encroach Marginal Open Space and to encroach the area meant for parking and when the irregularities are brought to the notice of the encroacher/to the person who has illegally constructed a building in contravention of the sanctioned plan, efforts are made to ensure that the same is regularised. Such type of practise has to be deprecated otherwise it will result in total anarchy and will also result in rise in the unauthorised construction beyond the sanctioned plans.

13. Keeping in view the judgment delivered by the apex Court in the case of Priyanka Estates International (supra), the respondent Corporation is certainly free to take appropriate action. It has become a normal practise to construct without sanction. The Green Belt which is reserved for greenery is being encroached by the concrete jungle. This Court cannot be a party to such an illegal constructions which are without there being any sanctioned map and, therefore, as there is no sanctioned map and as the petitioners have submitted a reply to the Corporation and the Corporation has not sanctioned any map at any point of time, the Corporation is certainly free to take appropriate action in accordance with law. No case for interference is made out by this Court in the peculiar facts and circumstances of the case. Accordingly, the admission is declined.