- Bookmark
- Share
- CaseIQ
Smt. Shanti Dey Santi Dey v. Sri Suvodeep Saha
Factual and Procedural Background
This appeal arises from an order dated 9th February 2016 passed by the District Judge, North 24-Parganas at Barasat, in an application under Section 9 of the Arbitration and Conciliation Act, 1996. The learned Court refused the prayer for extension of an interim order on the purported ground of non-compliance with Section 11 of the Arbitration and Conciliation Act, 1996. The appeal challenges this refusal. The application under Section 9 involved interim measures related to arbitration proceedings, and the case concerns whether the time for commencement of arbitral proceedings could be extended beyond the statutory ninety-day period introduced by the Arbitration and Conciliation (Amendment) Act, 2015.
Legal Issues Presented
- Whether the ninety-day period for commencement of arbitral proceedings under sub-section (2) of Section 9 of the Arbitration and Conciliation Act, 1996, as amended by the 2015 Amendment Act, is mandatory or directory.
- Whether the Court below erred in refusing to extend the interim order solely on the ground of non-compliance with Section 11, without considering the possibility of extending the time for commencement of arbitral proceedings.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Court analyzed the provisions of sub-section (2) of Section 9 of the Arbitration and Conciliation Act, 1996, as amended by the Arbitration and Conciliation (Amendment) Act, 2015. The Court noted that while the amendment prescribes commencement of arbitral proceedings within ninety days of the interim order, the phrase "or within such further time as the Court may determine" indicates that the ninety-day limit is directory rather than mandatory. Furthermore, the Court observed that no penalty is prescribed for failure to commence arbitral proceedings within this period. The Court also noted that the lower Court rejected the extension request solely on the ground of non-compliance with Section 11, without considering the discretion to extend the time. Based on these observations, the Court set aside the order under appeal and directed the lower Court to reconsider the prayer for interim relief afresh.
Holding and Implications
The appeal is allowed and the order under appeal is set aside.
The lower Court is directed to reconsider the prayer for extension of the interim order, taking into account the discretionary power to extend the time for commencement of arbitral proceedings beyond ninety days. Meanwhile, an interim order of status quo is granted for three weeks or until further orders, in respect of the schedule property and bank accounts of the partnership. This decision directly affects the parties by restoring the possibility of extension of interim relief but does not establish a new precedent beyond clarifying the directory nature of the ninety-day period under the amended Section 9.
1. No one has appeared to oppose the appeal in spite of notice.
2. This appeal is against an order dated 9th February, 2016 passed by the District Judge, North 24-Parganas at Barasat in an application under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the 1996 Act’) being Miscellaneous Case No. 30 of 2014 whereby the learned Court refused the prayer for extension of interim order on the purported ground of non-compliance of Section 11 of the 1996 Act. Sub-section (2) of Section 9 of the 1996 Act, as incorporated by the Arbitration and Conciliation (Amendment) Act, with effect from 23rd October, 2015, provides as follows:
“9. Interim measures etc. by Court.-
……………………………………………………………………………………………….
(2) Where, before the commencement of the arbitral proceedings, a Court passes an order for any interim measure of protection under sub-section (1), the arbitral proceedings shall be commenced within a period of ninety days from the date of such order or within such further time as the Court may determine.”
3. The arbitral proceedings are, in terms of sub-section (2) of Section 9, to be commenced within a period of ninety days from the date of order of this Court under Section 9 or within such further time, as the Court might determine. In this case, the orders were passed before Section 9 was amended. Within ninety days from the date on which the amendment came into force, arbitral proceedings should have been commenced. However, the use of the words “or within such further time as the Court may determine” makes it patently clear that the time stipulation of ninety days is directory and the Court might extend the time for commencement of arbitral proceedings. Moreover, there is no penalty prescribed in the 1996 Act as amended by the Arbitration and Conciliation (Amendment) Act of 2015 for default in commencement of arbitral proceedings within ninety days.
4. We are informed that an application under Section 11 has already been filed in this Court being AP No. 221 of 2016. The amendment is also recent. It appears that the learned Court below has rejected the prayer for extension only on the ground of non-compliance of Section 11 without considering the question of extending the time.
5. The order under appeal is set aside. The learned Court below shall consider the prayer for interim relief afresh.
6. In the meanwhile, for a period of three weeks from date or until further orders, whichever is earlier, there will be an interim order of status quo in respect of the schedule property, as well as the bank accounts standing in the name of the partnership.
7. The appeal and all connected applications are disposed of.
8. Urgent photostat certified copy of this order, if applied for, be supplied to the appellant subject to compliance of all requisite formalities.
Alert