Power Machines India Ltd. Petitioner v. Collector, G.B. Nagar And Another S

Allahabad High Court
Aug 10, 2016

1. Heard learned counsel for the parties.

2. The petitioner has filed the present writ petition for the quashing of the recovery citation nos. 107484 and 107486 dated 20.4.2016 (Annexure nos. 1 and 2 to the writ petition respectively).

3. Similar dispute was raised before the High Court of Jabalpur in Writ Petition No. 12127 of 2016 whereby the same recovery citation dated 20.4.2016 was quashed by the judgment dated 19.7.2016

4. In view of the aforesaid, the present writ petition has become infructuous and the same is dismissed as such.

5. During the pendency of the writ petition some amount was recovered by the Collector, Gautam Budh Nagar from the bank account of the petitioner. This Court by an order dated 31.5.2016 directed the Collector concerned to keep the amount in a separate account.

6. Since recovery citation issued against the petitioner has been quashed, therefore, the amount liable is to be refunded to the petitioner. The petitioner shall made an appropriate application in this regard before the Collector concerned for refund of the amount, on which an appropriate order shall be passed by the Collector concerned within two weeks.