Ezekiel Abraham Gubray v. Ramjusroy Golabroy

Calcutta High Court
Apr 7, 1920
Smart Summary (Beta)

Factual and Procedural Background

This appeal arises from a suit for damages for breach of contract involving the sale and purchase of 100 tons of white Java sugar at a fixed price. The contract, dated 23rd March 1918, obligated the defendant firm to import the sugar from Java by steamer during March 1918, with a fifteen-day grace period after 31st March for shipment. Clause 2 of the contract detailed conditions regarding shipment timing, including provisions for force majeure events that could prevent shipment and allow cancellation by the seller.

On 9th May 1918, the defendant notified the plaintiff of contract cancellation citing force majeure due to an embargo on shipments from Java. The plaintiff disputed this, claiming damages for the price difference. The defendant explained that Dutch shipping companies had refused to accept goods mid-March 1918, preventing shipment. The plaintiff initiated suit on 29th May 1918.

Subsequently, in June 1918, the defendant tendered the goods, but the plaintiff refused delivery and proceeded with the suit. The trial court dismissed the suit, holding the defendant was entitled to cancel the contract under the circumstances. The plaintiff appealed this decision.

Legal Issues Presented

  1. Whether the defendant was entitled to cancel the contract under the force majeure clause due to the suspension of shipments by Dutch shipping companies in Java in March 1918.
  2. Whether the defendant’s inability to ship the sugar due to the refusal of Dutch steamers constituted a valid legal or physical impossibility to perform the contract.
  3. Whether the defendant was obliged to seek alternative shipping options despite increased freight costs, or whether economic unprofitability could excuse non-performance.
  4. The applicability and scope of the doctrine of frustration or impossibility in the context of commercial contracts affected by war-related disruptions.

Arguments of the Parties

Appellant's Arguments (Plaintiff)

  • The defendant should not benefit from the difficulty caused by the suspension of shipments as it could have shipped the goods before the disruption occurred.
  • The defendant must prove that specific goods were appropriated at Java for the contract; without such proof, the defense of impossibility is invalid.
  • Even if Dutch vessels were unavailable, the defendant should have used other shipping lines despite higher freight costs; economic unprofitability does not excuse non-performance.

Respondent's Arguments (Defendant)

  • The defendant was entitled to the fifteen-day grace period and was prevented from shipping by an extraordinary suspension of Dutch shipping operations in Java.
  • Appropriation of goods occurs at arrival, not prior shipment, and the suppliers had goods ready for shipment that could not be dispatched due to the shipping stoppage.
  • The suspension of shipments was a force majeure event beyond the defendant’s control, justifying cancellation under the contract clause.
  • Economic impossibility was accompanied by physical impossibility due to scarcity of ships caused by war-related factors, making performance impracticable.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Hadley v. Clarke Principle of suspension or discharge of contract due to force majeure or unforeseen events. Referenced to establish the legal framework for discharge of contract when shipment is prevented by extraordinary circumstances.
Geipel v. Smith Similar principle on suspension or discharge of contract under force majeure. Supported the court’s view on force majeure applicability in the present case.
Blyth & Co. v. Richards Turpin & Co. Economic unprofitability is not an excuse for non-performance of contract. Used to address the plaintiff’s argument that higher freight costs do not excuse non-performance.
Brown v. Royal Insurance Co. Commercial impossibility (extreme cost or difficulty) is not equivalent to impossibility of performance. Illustrated the general rule that economic hardship alone does not discharge contractual obligations.
Jones v. St. Johns College Reinforces the doctrine that increased difficulty or cost does not excuse performance. Supported the court’s analysis of commercial impossibility.
Thorn v. Mayor of London Similar principle regarding commercial impossibility and contract performance. Referenced to clarify limits of economic hardship as a defense.
Hongkong Dock Co. v. Neiherton Stopping Co. Doctrine of commercial impossibility and frustration of contract. Used to demonstrate judicial reluctance to excuse non-performance based solely on economic factors.
Tenants v. Wilson Express contract provisions for discharge in case of shortage; price rise alone insufficient for discharge. Illustrated that price rise does not automatically excuse performance without contractual provision.
Dixon v. Hendarson Confirmed that commercial unprofitability does not justify refusal to deliver if shipment is possible. Applied to reject plaintiff’s argument that defendant must have shipped despite higher costs.
Instone and Co. v. Speeding Marshall & Co. War-related rise in price does not entitle suspension of delivery if supply is still procurable. Clarified the limits of suspension due to war-related difficulties.
Karl Ettlinger & Co. v. Chagandas and Co. Similar to Instone case on war-related contract performance issues. Supported the court’s analysis of war-related disruption and contract obligations.
Baily v. De Crespigny Relaxation of the rule that absolute contracts are not dissolved by impossibility; introduction of implied terms. Used to explain the development of frustration doctrine as a gloss on impossibility.
Tamplin Steamship Co. v. Anglo Mexican Petroleum Products Co. Explanation of implied terms and frustration doctrine to excuse performance when conditions change fundamentally. Summarized the legal principle underlying release from contractual obligations due to unforeseen events.
Moss v. Smith Definition of impossibility as impracticability due to excessive or unreasonable cost. Supported the court’s approach to commercial impracticability in the present case.
Scheepvaart v. North African Coal Co. Rise in freights may indicate shortage of ships amounting to physical impossibility. Used to interpret scarcity of ships and freight increase as prevention of performance.
Bolckow Vaughan Co. v. Compania Minera Rise in freights due to war may equate to physical impossibility to perform contracts. Affirmed that scarcity of ships caused by war can justify non-performance.
Bolckow v. Compania (Court of Appeal) Affirmation of the principle that war-related freight rises can prevent contract fulfillment. Confirmed lower court’s ruling on scarcity of ships as a valid excuse.
Matsoukis v. Priestman & Co. Definition and scope of "force majeure" as broader than "act of God" or "vis major". Referenced to contextualize the force majeure clause in the contract.

Court's Reasoning and Analysis

The court carefully examined the facts surrounding the defendant’s inability to ship sugar from Java in March 1918. It found that the Dutch shipping companies had collectively refused to accept goods for shipment, effectively halting all export business from Java. Although the court did not find evidence of a formal embargo or legal prohibition by the Dutch government, the practical effect was a total suspension of shipping operations caused by extraordinary circumstances likely linked to the ongoing European war.

The court rejected the plaintiff’s arguments that the defendant should have shipped earlier or used alternative shipping lines at higher freight rates, holding that the defendant was entitled to the contractually allowed shipment period and that economic unprofitability alone does not excuse performance. However, the court recognized that the scarcity of ships and the consequent rise in freight rates due to war-related factors could amount to a physical or legal prevention of performance, consistent with established legal principles and precedents.

The court applied the doctrine of frustration and force majeure as implied terms in the contract, concluding that the defendant was justified in rescinding the contract because shipment was prevented by causes beyond the defendant’s control. The court emphasized that the prevention was not merely economic difficulty but a substantial commercial impossibility arising from the extraordinary suspension of shipping.

Holding and Implications

The appeal is dismissed with costs.

The court upheld the dismissal of the plaintiff’s suit, confirming that the defendant was entitled to cancel the contract under the force majeure clause due to the suspension of shipments beyond their control. The decision directly affects the parties by validating the defendant’s cancellation and denying the plaintiff’s claim for damages. No new legal precedent was established; rather, the ruling applied and reaffirmed existing principles regarding force majeure, frustration, and commercial impossibility in contract law.

Show all summary ...

Mookerjee, A.C.J:— This is an appeal by the plaintiff in a suit for damages for breach of contract. On the 23rd March, 1918, a contract was made between the plaintiff and the defendant firm under which the latter agreed to sell and the former agreed to purchase 100 tons of white Java sugar at Rs. 11-3-0 per maund. The defendant firm undertook to import the sugar in bags of 2 owt. each, by steamer from Java and to cause such shipment to be made in the month of March, 1918. The contract allowed the defendant fifteen days' grace to make the shipments after the 31st March, 1918.

2. Clause 2 of the contract which is material for the decision of the controversy between the parties was in these terms:

“Shipments to be made by steamers during March 1918, provided always that early shipment or late shipment (it not late by more than 15, days) or delay in arrival, caused otherwise than by shipment late by more than 15 days, will not entitle buyers to cancel this contract or to refuse to take delivery of any goods shipped in pursuance of this contract or intended by sellers for the fulfillment thereof or available for such fulfillment, and that in no event shall buyers have any claim upon sellers for any loss or damage suffered by seasons of early or late shipment whether late by 16 days or morel or of, delay in shipment or arrival. The dates of bills of lading in respect of goods shippeed or intended as aforesaid or available for the fulfilment hereof shall be conclusive evidence against buyers of date of shipment. Provided also that if shipment within the time allowed for shipment as aforesaid of any goods bought, procured or available for shipment in pursuance hereof shall be prevented by riots, strikes, lookout of operatives, dock labourers carriers or seamen, accidents at works upon railways, canals, docks, wharves, jetties, ware-houses or in pott of shipment, or by rivers being ice bound or by frost, show, tempest, flood, draught, earthquake, bankruptcy or failure of manufacturer or suppliers quarantine or other regulations of by war, seizure blockade or by any act of God or force majeure, including all causes of occurrences beyond control of sellers, of in the event of delivery or the gaols intended of available for delivery being prevented by any of the causes aforesaid, sellers alone shall have the option of cancelling this contract in respect of the quantity of goods the said shipment or delivery of which shall have been so prevented.”

3. On the 9th May, 1918, the defendant intimated to the plaintiff that the contract was cancelled, owing to force majeure under the clause just mentioned. On the 13th May, the plaintiff replied that the contract could not be lawfully cancelled and claimed damages at Rs. 2-2-0 per maund, which was the difference between the original contract rate and the then current market rate. On the 16th May, the defendant explained to the plaintiff that owing to embargo on shipments from Java, there was no shipment in March, 1918, that this had been reported to him on the 20th April, 1918, and that as the plaintiff had not expressed his willingness to extend the time, the defendant had cancelled the contract. Thereupon, the plaintiff instituted the present suit on the 29th May, 1918. On the 10th June the defendant informed the plaintiff that steamers had arrived from Java with March shipments of sugar and that his firm was ready to deliver 100 tons at the contract price.

4. On the 12th June, the goods were tendered but the plaintiff refused to accept the offer and stated that he would proceed with the suit. The suit was ultimately tried by Mr. Justice Rankin and was dismissed by him on the ground that in the events which had happened, the defendant was entitled to cancel the contract. Notwithstanding the elaborate argument advanced before us by Mr. Hyam in support of this appeal. We have arrived at the conclusion that the suit has been rightly dismissed. On the face of the contra, it is clear that the defendant was an importer and undertook to import the sugar from Java. On the 11th and 12th March, 1918, he had in fact contracted with Harrisons and Eastern Export ??? to purchase 150 ions sugar, under a contract identical in terms with those of the contract subsequently made by him with the plaintiff. The suppliers of Harrisons and Eastern Export were Harrisons and Crosfield Ld. of Batavia. The defendant alleges that about the middle of March, or perhaps a little later on, all the Dutch Shipping Companies refused to accept any goods at Java or to allow vassals to sail, so that all shipment of cargo was stopped and no bills of lading ware granted after that decision took effect, till normal business was resumed in the middle of May. The consequence was that the goods which Harrisons & Crosfield at Java who ware the suppliers of the Calcutta house of Harrisons & Eastern Export, had ready for shipment could not be despatched, though they had made a proper contract of affreightment with the Dutch Company. The suppliers of the defendant accordingly cancelled the contract with him, and he in his turn was constrained to rescind his contract with the plaintiff. The testimony of Captain Brauwer who was with his boat at Java at the time, of Mr. Major who was an assistant in the office of the Datoh Shipping Co. and of Mr. Simpson who was manager of Harrison & Eastern Export, makes it abundantly clear that about the middle of March, there was a sudden refusal on the part of the Dutch lines to accept or load goods for Calcutta. The real reason for this decision on the part of the authorities of the Dutch lines has not been established by proper evidence, and we agree with Mr. Justice Rankin that there is no proof of an embargo on shipping, so as to make applicable the principle of suspension or discharge of a contract, recognised in well-known judicial decisions such as those in Hadley v. Clarke (1), and Geipel v. Smith (2). Nor is it established by legal evidence that the Dutch Government prohibited the export of sugar without a license. But the fact is undeniable that in March, 1918, all Dutch steamers were held up in Dutch waters at Java, by a decision of their owners who were moved to inaction, not by ordinary reasons of trade, but by exceptional reasons connected most probably with the Eurpoean war; and it is not improbable that they apprehended rightly or wrongly, that should their ships come to British ports, they might be commandeered. The question thus arises, whether in these circumstances, the defendant became entitled to rescind the contract.

5. The plaintiff has argued that the defendant is entitled to no consideration, as the difficulty in which he found himself might have been a voided if the goods had been shipped from Java before the middle of March. There is obviously no force in this contention. The defendant was entitled under the terms of the contract to make shipment on or before the 15th April, and his position plainly cannot be prejudiced, merely because he did not anticipate a cause which suddenly came into operation before the expiry of the time allowed for the performance of the contract. The plaintiff has farther argued that the defendant most prove that be or his suppliers had appropriated specific goods at Java towards the contract in suit, and that in the absence of such proof, he cannot avail himself of the benefit of the situation created by the suspension of shipping business by the Dutch Steamer Companies. This contention also is obviously groundless. The evidence leaves no room for doubt that no allocation of goods towards different contracts, is made before shipment at Java; appropriation is usually made only at about the time of arrival of the boats in Calcutta. Apart from oral evidence, this is also clear from clause 2 of the contract. It may be conceded that if the seller has no goods at all, ready for shipment, he cannot bake advantage of the circumstance that shipment was impossible; that defence should be available, only to a person who, but for the impossibility of shipment by reason of circumstances beyond his control, was in fact in a position to fulfil his engagement. In the present case, however, it is indisputable that the suppliers of the defendant had goods which were ready for shipment at Java and which would have been shipped but for the refusal of the Dutch lines to accept or load goods. This also disposes of the astonishing argument that the suppliers of the defendant should have loaded the goods on board ship, even though the Dutch lines would not accept goods and grant bills of lading for them.

6. The plaintiff has contended as a last resort, that assuming that the Dutch boats were not available, the defendant should have imported the sugar in ships of one of the other lines of ??? running between Java and Calcutta at that time, even though a very high rate of freight had to be paid for the purpose; in other words, that the defence of impossibility of performance is irrelevant, unless the defendant shows that no vessel was available for shipment of the goods, on the theory that even if a single boat was procurable, the defendant was bound to load the cargo therein, however abnormal the terms dictated by her owners. The contention in substance is that impossibility of performance of the contract is a valid defence, only when it is attributable to physical or legal prevention and not merely to economic unprofitableness. In support of this position, reliance has been placed upon the decision in Blyth & Co. v. Richards Turpin & Co. (3), where Scrutton, J., held that the mere fact that freights had arisen so high as to prevent the defendants from performing their contract at a profit was no excuse for non-performance of their obligation. Now, it may be assumed as the general rule that a party who has made an absolute promise is not discharged from liability, if it afterwards appears that it is impossible for him to perform the contract even though this is not due to any default on his part; for, as has been said, it is his own fault it he runs the risk of undertaking to perform an impossibility; in other words impossibility as an excuse for non-performance must, as a general rule, be a physical or legal impossibility and not merely an impossibility with reference to the ability and circumstances of the promisor. The application of the principle that “commercial impossibility”, that is, extreme and unforeseen cost or difficulty of performance, is no excuse for performance, which has been recognised in well-known cases, such as Brown v. Royal Insurance Co. (4); Jones v. St. Johns College (5); Thorn v. Mayor of London (6); Hongkong Dock Co. v. Neiherton Stopping Co. (7), is illustrated by cases arising oue of commercial transactions during the recent war, which tend to show that the Courts will not regard mere economic unprofitable ness as equivalent to impossibility of performance. Thus, in Tenants v. Wilson (8), where there was an express provision for discharge of the contract in the case of shortage at supply of the article agreed to be sold, the House of Lards was of opinion that a rise of price would not in itself constitute a hindrance to delivery within the meaning of the condition. This case was followed in Dixon v. Hendarson (9), where it was held that it was not shortage of tonnage, hub commercial unprofitable ness, which made the seller refuse delivery of wood pulp, as ships were obtainable to carry such pulp at an additional freight. In Instone and Co. v. Speeding Marshall & Co. (10), where a contract for the sale of coal to be delivered in monthly quantities, provided that in case of war or other hindrance intervening or interfering or affecting delivery, the sellers could suspend, either in part or in whole, any deliveries under the contract, Bailhache, J., held that the mere fact of a rise in the price of coal owing to the war, did not entitle the sellers to suspend deliveries of it, as sufficient coal was procurable at an enhanced price. The same view was adopted in Karl Ettlinger & Co. v. Chagandas and Co., (11). But it is important to note that the rigidity of the rule that an express unconditional contract is net generally dissolved by its performance being or becoming quite Impossible in fact, by reason of particular circumstances, has been relaxed, and exceptions has been engrafted thereon on grounds explained by Hannen, J., in Baily v. De Crespigny (12). Since then, during the recent war, the doctrine of frustration of adventure has become a gloss on the older theory of impossibility of performance which it has greatly developed under the guise of reading “implied terms” into contracts. The position is lucidly summarised by Lord Lore bourn in Tamplin Steamship Co. v. Anglo Mexican Petroleum Products Co. (13).

“When our Courts have held innocent contracting parties absolved from farther performance of their promises, it has been upon the ground that there was an implied term in the contract which entitled them to be absolved. Sometimes it is put that performance has become impossible and that the part; concerned did not promise to perform an impossibility. Sometimes it is put that the parties contemplated a certain state of things which fell out otherwise. In most of the cases it is said that there was an implied condition in the contract which operated to release the parties from performing it, and in all of them I think that was at bottom the principle upon which the Count proceeded. It is in my opinion, the true principle, for no Court has an absolving power, but it can infer from the nature of the contract and the surrounding circumstances that a condition which is not expressed was a foundation on which the parties contracted.”

7. This tendency of the Courts to give effect to what is conceived by them to have been the true intention of the parties is illustrated by more than one decision relevant in the circumstances of the present case. There is obviously much good sense in the observation of Maule, J. in Moss v. Smith (14).

“In matters of business, a thing is said to be impossible when it is not practicable; and a thing is impracticable when it can only be done at as excessive or unreasonable cost. A man may be said to have lost a shilling when he has dropped it into deep water, though it might be possible by some very expensive contrivance to recover it.”

8. This commonsense view was adopted by Scrutton, J. in Scheepvaart v. North African Coal Co. (15) where be held that a rise in freights may be evidence of a shortage of ships within the meaning of a clause in a contract containing that expression. To the same effect are the observations of Bailhache, J. in Bolckow Vaughan Co. v. Compania Minera (16) where he points out that a rise in freights may be equivalent to such a scarcity of ships as to amount to physical impossibility:

“The question to be first decided is whether a rise in freights due to an excepted cause, in this case war, can ever amount to prevention of fulfillment of & contract to deliver oversea goods? I am of opinion that there may be such a rise in freights due to war as to entitle a seller, who has to pay freight, to say that he was thereby prevented by war from making delivery. The expression ‘rise in freights’ in this connexion, and in this case in particular, really means that war has caused a scarcity of ships for commercial purposes of which the rise in freights is at ones the sign and the measure. Scarcity of ships due to war and rise of heights doe to war are interchangeable expressions, but as the thing that matters to a seller who is seeking a ship to enable him to make delivery is the pries he must pay for her, he more usually speaks of the rise in freights. It would simplify matters to say that no rise in freights can amount to prevention of performance, but I think that is impossible in a case where a rise in freights due to war connotes scarcity of ships due to war. Suppose that all British ships were commandeered by the Admiralty, leaving only neutral ships for private commerce. In each a case a seller might truly say, “War has prevented my chartering”, and it would be equally correct for him to express himself as being prevented by scarcity of ships or by a rise in freights, a rise which in such a case would, of course, be enormous. Prevention in a commercial sense is in my judgment sufficient, and what is prevention in that sense is a question of degree which could theoretically be expressed either in terms of tonnage or freight, but for practical purposes can be most intelligibly stated in terms of height.”

9. This decision was affirmed by the Comb of Appeal; Bolckow v. Compania (17).

10. We are of opinion that the circumstances of the present case attract the application of the principle just enunciated. The evidence proves conclusively that there was such a shortage of tonnage owing to the decision of the Dutch Shipping Companies in Java, that exports came to a complete standstill. There were no transactions to record and business was for all practical purposes totally suspended. Cap. Brauwer, who was actually there with his board, states that besides 41 Dutch ships, there were only the interned German lines. Even if we assume, however, that there were a few other boats, there can be no room for reasonable doubt that the decision of the Dutch Shipping Companies in effect paralysed Java export business. This, in our opinion, is sufficient to constitute prevention of shipment within the meaning of clause 2 of the contract; and we have already seen that such prevention was attributable to “causes or occurrences beyond control of sellers”. In this view, it becomes unnecessary to consider the exact cope of the expression “force majeure” which, according to Bailhache, J. in Matsoukis v. Priestman & Co. (18) is taken from the Code Napoleon and has a ??? extensive meaning than “act of ???” or “vis major”, though it may be doubtful whether it Includes all “causes on cannot prevent and for which you are not responsible”. We hold accordingly but the defendant has justified his cancellation of the contract with the plaintiff.

11. The result is that the appeal is dismissed with costs.

Fletcher, J.:— I agree. Appeal dismissed.