Municipal Council v. P. K. Kannuswami Pillai

Madras High Court
Nov 5, 1929
Smart Summary (Beta)

Summary of the Opinion

Factual and Procedural Background

The plaintiff is the Municipal Council of Tiruvarur represented by its Chairman. On 6 February 1922 the Council held an auction for the right to collect tolls in the municipality for the year 1922–1923. The 1st defendant (Kannuswami Pillai) was declared the successful bidder at Rs. 19,925. The printed notice required the successful bidder, within ten days of acceptance, to deposit two months' rental as security and to pay the amount due in twelve equal instalments; the security deposit was to be adjusted in the last two months' rental. The notice also provided that interest was payable for any amount due at the rate of one anna per diem for every hundred rupees or fraction thereof.

On 28 February 1922 the first and second defendants jointly petitioned the Chairman stating that the bid stood in the name of the 1st defendant but had been made on behalf of both, and that both had made deposits; the Chairman accepted this and ordered that they be treated jointly. No formal written agreement (muchilika) was executed by the parties, though the defendants collected the tolls during the year. Toward the close of the municipal year the Council noticed the absence of a muchilika and demanded execution. The defendants had meanwhile complained to the Council about various grievances.

The municipality sued for the balance of the lease amount and interest, totaling Rs. 5,346-1-8. The 1st defendant pleaded that no completed contract existed, contested the appropriation of Rs. 293-12-0 as interest, denied liability for interest (or its penal rate), denied wilful default to execute the muchilika, and alleged municipal negligence and exceptional losses due to heavy rains and floods. The 2nd defendant contended he had not bid at the auction and so incurred no liability (or at worst only half the liability), and adopted the other defences of the 1st defendant.

The Subordinate Judge held there was no completed contract and that the suit was unsustainable under Section 69 of the Madras District Municipalities Act, relying on Raman Chetti v. The Municipal Council of Kumbakonam. The Judge also found the 2nd defendant not liable and, on interest, allowed only interest at 6% per annum on any lease arrears. The Subordinate Judge dismissed the suit and directed each party to bear its own costs. The municipal Council appealed.

Legal Issues Presented

  1. Whether there has been a complete contract between the parties as set out in the plaint, and if not, whether the suit is sustainable?
  2. Whether the suit is sustainable in the absence of a muchilika as required by Section 69 of the Madras District Municipalities Act?
  3. What is the exact amount due from the 1st defendant?
  4. Whether plaintiff is entitled to interest, and if so, to what amount?
  5. Whether the appropriation by plaintiff of Rs. 293-12-0 for interest is lawful and warranted?
  6. Whether there was a default on the part of the defendants to execute a muchilika as alleged in the plaint, or was the default due to the plaintiff?
  7. Whether defendants are estopped from pleading non-liability as alleged?
  8. To what equities are plaintiff and defendants entitled?
  9. Whether plaintiff is entitled to any relief and, if so, what relief?
  10. Whether the 2nd defendant who was not a bidder at the auction can be made liable for the suit claim?

Arguments of the Parties

Plaintiff (Municipal Council / Appellant)

  • The Council sought recovery of the lease balance and interest as claimed in the plaint.
  • On appeal the Council argued that Section 69's negative language should be interpreted to mean that while a contract non-compliant with statutory formalities is not binding on the Council, it may still bind the other contracting party — i.e., the defect should not bar the Council from suing for arrears.
  • The Council relied on distinctions between different statutory wording (comparison with Section 174 of the Public Health Act) and invoked authorities it considered favourable to its contention that the Council could sue despite non-compliance with formalities.
  • The Council contested findings of municipal negligence and other defenses raised by defendants (implicitly relying on precedents and statutory interpretation to sustain its claim).

Defendants (1st and 2nd defendants)

  • 1st defendant: there was no complete contract since the written agreement required by statute (muchilika) was not executed; therefore the Council cannot enforce the contract.
  • The plaintiff could not lawfully appropriate Rs. 293-12-0 as interest since that sum was not paid as interest; the plaintiff cannot claim the penal interest rate provided in the printed auction notice.
  • No wilful default on the part of defendants to execute the muchilika; defendants alleged losses caused by municipal negligence and by exceptional natural events (heavy rains and floods) reducing traffic and toll collections.
  • 2nd defendant: he did not bid at the auction and therefore incurred no liability to the Council; at worst he could be liable only for one moiety of the suit amount. He adopted the other defences raised by the 1st defendant.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Raman Chetti v. The Municipal Council of Kumbakonam Authority holding that a municipality cannot enforce a contract not made in conformity with statutory formalities (relevant to Sect. 69). The Subordinate Judge had followed this decision to dismiss the suit; the Court noted it as a controlling local precedent supporting non-enforceability.
Banian Chetti v. The Municipal Council of Kumbakonam Madras case where the court rejected the view that the unsealed agreement bound the municipality but held the agreement could not be enforced against the corporation when statutory formalities were absent. Used by the Court as a leading Madras authority aligning with the view that the municipality cannot enforce a contract made contrary to statutory requirements.
Ahmedabad Municipality v. Sulemanji Ismalji Authority quoted in Madras decisions addressing enforceability of municipal contracts lacking formalities (cited in support of Madras cases). Quoted by Madras judges and relied upon to show consistency with the view that statutory formalities are necessary for enforceability by municipal corporations.
Madura Municipal Council v. Veeranna Kone Madras decision following the view that contracts not complying with municipal statutory formalities are not enforceable by the municipality. Followed earlier Madras cases; cited by the Court as part of the body of local authority supporting the Subordinate Judge's conclusion.
Srirangam Municipal Council v. Bodi Contrary single-judge decision (Krishnan, J.) which allowed recovery on the footing of executed consideration despite lack of statutory formalities. The Court distinguished this case as a single-judge decision inconsistent with the weight of other Madras and Indian authorities and did not follow it.
Lawford v. Billericay Rural Council English authority supporting that an action may lie on executed consideration even when formalities are lacking (in non-statutory contexts). Noted by the Court but treated as inapposite where the contract is governed by a statute prescribing formalities; not followed for the present statutory context.
Douglass v. Egham Urban Council English authority cited as confirming Lawford regarding executed consideration in non-statutory situations. Similarly distinguished and not treated as applicable to contracts made under statutory regimes requiring specific formalities.
Abaji Sitaram Modak v. The Trimbak Municipality Contains an obiter remark noting that executed consideration may permit enforcement despite lack of seal, but the remark was not central to the case. Court treated the remark as obiter and not decisive; distinguished on facts and procedural posture.
Mohamed Ebrahim Molla v. Commissioners for the Port of Chittagong Held that a suit by Port Commissioners on an agreement entered in contravention of mandatory statutory provisions must be dismissed; it also summarized the law succinctly and permitted quantum meruit relief in the appropriate circumstances. Cited as a recent clear authority supporting dismissal of a statutory-body suit on a contract made contrary to statute, and as authority permitting recovery on a quantum meruit basis where appropriate.
Young & Co. v. Mayor of Royal Leamington Spa English authority establishing that where a corporation contracts under a statute and statutory terms are not observed, the contract cannot be enforced against the corporation. Relied on as establishing the general English rule that statutory formalities bar enforceability against corporations; used to support the view that non-compliance defeats enforcement.
Hunt v. Wimbledon Local Board Same general principle as Young & Co.: statutory formalities must be observed for enforceability by statutory corporations. Referenced as part of the English authorities establishing the rule that the Court applied to distinguish non-statutory cases.
Bournemouth Commissioners v. Watts Held that a third party could not escape liability because a local authority's contract lacked formality; a local authority may pay for benefit received. The Court distinguished this case because it concerned third-party liability and did not support allowing a statutory authority to sue on a defective contract.
Brooks, Jenkins & Co. v. Torquay Corporation Held that the municipal seal had been affixed in time, so statutory formalities were satisfied; used to show factual compliance rather than to justify suing on an uncomplied contract. Distinguished as a case in which requirements were actually complied with, not as authority for enforcing a contract made in contravention of statute.
Frend v. Bennett Established that want of formality in making a contract is a defence to a suit brought against a corporation; formalities protect ratepayers. Quoted for the proposition that lack of formalities is a defence and does not imply asymmetrical enforceability in favour of the corporation; used to rebut the appellant's argument.

Court's Reasoning and Analysis

The Court's principal question was whether the contract is null and void, and the suit unsustainable, because the statutory requirements of Section 69 of the District Municipalities Act were not complied with. The Court reviewed the relevant body of English and Indian authority and the precise wording of the statute.

Step 1 — Statutory requirement and lower-court finding: Section 69 requires contracts made by or on behalf of the Council to be in writing and signed (the text emphasises that contracts made otherwise are not binding on the Municipal Council). The Subordinate Judge had found there was no completed contract and had followed Raman Chetti in holding the suit unsustainable.

Step 2 — Survey of authorities: The Court considered multiple Madras and other Indian cases, noting that the majority favoured the view that a municipal or statutory corporation cannot sue to enforce a contract made in contravention of statutory formalities. It acknowledged a few contrary authorities (notably Srirangam Municipal Council v. Bodi and some English decisions that allow recovery on the footing of executed consideration) but found them distinguishable because the contrary English cases were not statutory cases or because they concerned third-party liability or factual compliance.

Step 3 — Comparison of statutory wording: The appellant had argued from a difference in language between Section 174(5) of the Public Health Act and Section 69(2) of the District Municipalities Act, urging that the negative wording of Section 69 should be read to allow the contract to bind the other party even though it did not bind the municipality. The Court rejected this interpretative argument, noting that subsequent legislative revision did not alter the provision despite adverse decisions having been made earlier, and that nearly all decided cases opposed the appellant's interpretation.

Step 4 — Principle applied: Relying on the weight of Indian decisions and relevant English authority (Young & Co., Hunt), the Court concluded that where a contract is made under a statute prescribing formalities and those formalities are not observed, the corporation cannot enforce the contract. No English authority was found to support asymmetrical enforceability (i.e., that the corporation may enforce but others may not).

Step 5 — Particular factual matters:

  • The Court disagreed with the Subordinate Judge's treatment of the defendants' claim regarding the exemption for cattle-tolls: the appellate Court found evidence (letters by defendants' agent dated 5 April 1922 and similar) showing the defendants were aware (or promptly raised the matter) and therefore the Court could not accept that the exemption was an unforeseen new term that would prevent the defendants from litigating it in this suit.
  • On allegations of municipal negligence and other asserted losses by the defendants, the Court deemed discussion unnecessary given its primary finding that the contract is not enforceable.

Step 6 — Liability of the 2nd defendant: The Subordinate Judge had held the 2nd defendant not liable because his name was not the successful bidder and no formal council resolution accepted him as co-lessee. The appellate Court treated the matter differently: on the facts, both defendants had represented themselves as joint contractors, the 2nd defendant had paid money, and the Chairman had officially accepted the amounts tendered by both. The Court held the 2nd defendant estopped by his actions from disputing liability and thus could be made liable (subject to the primary infirmity that the contract itself is unenforceable).

Step 7 — Quantum meruit relief and remand: Although the Court held that the Council cannot enforce the contract because of non-compliance with Section 69, it observed that parties before the Court agreed (and the Court saw no reason to refuse) that if the contract were invalid the Council could accept a decree on a quantum meruit basis. The Court found the present accounts insufficiently complete to fix a correct quantum meruit amount and therefore remanded the case to the lower court for disposal on those lines, allowing parties to adduce fresh oral and documentary evidence.

Holding and Implications

Holding: The Court affirmed the principle that a municipal contract not made in conformity with the mandatory provisions of the District Municipalities Act (Section 69) is not enforceable by the Municipal Council. The Court therefore held that the contract is not enforceable and agreed with the Subordinate Judge on the second issue (i.e., unsustainability under Section 69).

Direct consequences and relief ordered:

  • The decree of the lower court was reversed insofar as it dismissed the suit without providing for quantum meruit recovery: the Court remanded the case to the lower court to determine recovery on a quantum meruit basis (allowing fresh evidence) because the parties indicated willingness to accept such relief if the contract were invalid.
  • The Court held that the 2nd defendant is estopped and can be made liable under the joint representation and payments; thus both defendants can be treated as jointly liable for any quantum meruit award (subject to the remand accounting).
  • Costs: the appeal having substantially failed, respondents (defendants) recovered their costs in the appellate Court from the appellant (Municipal Council). Costs in the lower court were ordered to abide the result of the suit. Court-fee was to be refunded.

Implications regarding precedent and legal principle:

  • The decision follows and applies existing Indian and English authority that where a statutory body contracts under a statute prescribing formalities, non-compliance with those formalities prevents the statutory body from enforcing the contract. The Court relied principally on a substantial body of Madras and other Indian case law and on English authorities establishing the general rule; it distinguished contrary authorities as inapplicable.
  • No novel legal principle was announced; the Court applied established principles and remediated the practical injustice by allowing quantum meruit recovery where appropriate and where parties agree to that route.

End of summary based exclusively on the provided opinion text.

Show all summary ...

The plaintiff in this case is the Municipal Council of Tiruvarur represented by its Chairman. On the 6th of February, 1922 the Municipal Council held an auction of the right to collect tolls in the Municipality for the year 1922-1923 and to the 1st defendant was knocked down the right to collect tolls for Rs. 19,925. The printed notice under which the auction was held required the successful bidder, within ten days of the acceptance of his bid, to make a deposit of two months rental as security and pay the amount due in twelve equal instalments, the security deposit being adjusted in the rental of the last two months. The notice further provided that for any amount due, the bidder should pay the interest at the rate of one anna per diem for every hundred rupees or fraction thereof. The 1st defendant bid for and accepted the lease of the toll gates subject to the above conditions. On the 28th of February, 1922 defendants 1 and 2 jointly put in a petition to the Chairman of the Municipal Council in which they represented that though the bid stood in the name of the first defendant Kannuswami Pillai, it was really made on behalf of and for the benefit of both petitioners, namely defendants 1 and 2. They further stated that they made a deposit on that day of Rs. 660-6-8 (by 1st defendant) and Rs. 1,600-6-8 (by 2nd defendant) and prayed that a muchilika might be taken from both of them jointly and both might by treated as lessees of the toll gates. This petition was accepted and ordered by the Chairman accordingly. For some reasons or other no muchilika was executed by either of the parties though the tolls were being collected by the defendants, and it was not until the close of the official year 1922-1923 that a notice was issued to the defendants to execute a muchilika. The defendants in the meantime had been complaining by petitions to the council about certain grievances. The council brings this suit for the balance of the lease amount due—Rs. 4,497-15-8 plus 105-10-0 balance of interest for irregular payments and Rs. 742-8-0 interest on the balance of the lease amount, making a total of Rs. 5,346-1-8. The 1st defendant pleaded that there was no completed contract between himself and the municipality, that the plaintiffs were not entitled to appropriate, as they had done, the amount of Rs. 293-12-0 towards interest as it was not paid as such, that the plaintiffs cannot claim interest and the rate claimed is penal, that there was no wilful default on the part of the defendants to execute the muchilika and that (for certain reasons which are given) the defendants were subject to loss on account of the negligence of the municipality and they were further subjected to heavy loss owing to unforeseen heavy rains and high floods in the rivers and the consequent absence of traffic by roads. The 2nd defendant stated that as he did not bid at the auction, he had incurred no liability to the municipal council, that he adopted the other defences raised by the 1st defendant and that, in any event, he cannot be made liable for the full amount claimed in the plaint and at the worst he can be made liable only for a moiety of the suit amount.

The following issues were raised:—

1. Whether there has been a complete contract between the parties as set out in the plaint, and, if not, whether the suit is sustainable?

2. Whether the suit is sustainable in the absence of a muchilika as required by Sect. 69 of the Madras District Municipalities Act?

3. What is the exact amount due from the 1st defendant?

4. Whether plaintiff is entitled to interest, and if so, to what amount?

5. Whether the appropriation by plaintiff of Rs. 293-12-0 for interest is lawful and warranted ‘?

6. Whether there was a default on the part of the defendants to execute a muchilika as alleged in paragraph 8 of the plaint, or was the default to take the same due to the plaintiff as pleaded in paragraphs 8 and 12 of the written statement?

7. Whether defendants are estopped from pleading non-liability as alleged in paragraph 9 of the plaint?

8. To what equities are plaintiff and defendants entitled?

9. Whether plaintiff is entitled to any and if so, to what relief?

10. Whether the 2nd defendant who was not a bidder at the auction can in any way be made liable for the suit claim?

The most important issues are issues 1 and 2, Sect. 69 Cl. 1 of the Madras District Municipalities Act of 1920 lays down that every contract made by or on behalf of Council shall be in writing and shall be signed by two Municipal Councillors. This admittedly was not done. The lower Court finds that both the parties were to blame for the non-execution of the muchilika and that finding has not been canvassed before us. The learned Subordinate Judge held on issue 1 that there was no completed contract and on issue 2 following the decision in Raman Chetti v. The Municipal Council of Kumbakonam(1) that the suit was not sustainable under Sect. 69 of the Act. He gave findings on the other issues also. As regards issue 10 he found that the 2nd defendant was not liable. As regards issues 4 and 5 his finding is as follows:—

“The plaintiff claims interest at one anna per Rs. 100 per diem as laid down in Ex. A-1. But the Council had accepted the amounts without charging that interest as can be seen from pages 7 and 9 of Ex. J, and the balance also has been struck as Rs. 4,201-3-8. It is argued that there having been no contract in writing, the plaintiff has no right to ignore some conditions and enforce other conditions. If it is an implied contract, then the plaintiff will only be entitled to charge interest at a reasonable rate, that is, at 6 per cent. per annum. I find that if plaintiff is entitled to any amount as lease arrears, the 1st defendant will be Jiable to pay interest on the arrears at 6 per cent. per annum and not for the late payments accepted by the plaintiff without any demur. The plaintiff has no right to appropriate Rs. 293-12-0 subsequently, since the entries in page 7 show that no appropriation for interest for late payment had been intended.”

As regards issue 7 he held that there was no estoppel. As regards issue 8 he appears to hold that the plaintiff introduced a new restriction after the lease was granted by which collection of tolls on cattle was prohibited that if the defendants are entitled to claim any damages in respect of that and other irregularities, they must do so by a separate suit and that they are not entitled to any equities in the suit. As regards issue 3 he says that there is no prayer in the suit for damages for use and occupation and that the plaintiff would be entitled to get only what the defendants had derived from the toll income. As regards issue 9 he held that the plaintiff is not entitled to any relief and dismissed the suit directing each party to bear his costs owing to non-execution of the muchilika. The plaintiff-municipal council has appealed.

The important question in this case is whether the contract is null and void and the suit unsustainable because the terms of Sect. 69 of the District Municipalities Act were not complied with. The matter has come up several times before the Courts in England and India. In India we are governed by the District Municipalities Act and as the decisions in India on the particular point in question are practically all in favour of the view taken by the learned Subordinate Judge and as the matter has been very often discussed in various judgments, we do not think it necessary to enter into a very lengthy examination of the authorities here. I shall first take the cases directly on the point where the want of compliance with the statutory obligations has been admitted as a defence to a suit brought by a municipality. We have two cases in Madras. One is Banian Chetti v. The Municipal Council of Kumbakonam. In that case the municipality sued to recover damages and arrears from the defendant, a toll contractor, who had purchased at public auction the right of collecting tolls for three years. The defendant, though the entered on possession and was collecting tolls, did not execute the written agreement which was required by the provisions of Sect. 45 of the Municipalities Act. Disputes arose between the plaintiff and defendant and after about 17 months of enjoyment, the defendant was put out of possession and a resale of the remainder of the term resulted in a loss to plaintiff. The plaintiff sued to recover the loss sustained by the resale and the arrears due. The defendant pleaded inter alia that, there being no contract, fulfilling the requirements of Sect. 45, plaintiff's suit was unsustainable. The Subordinate Judge held that the agreement, though not binding on the Municipality, was binding on the defendant and gave a decree for plaintiff. The learned Judges held that the view of the Subordinate Judge that it does not bind the Municipal Council but does bind the other party is erroneous. They quoted The Ahmedabad Municipality v. Sulemanji Ismalji(2). This Madras case in so far at least it was a claim for arrears, is exactly on the same footing as the present case. This decision was followed in The Madura Municipal Council v. Veeranna Kone(3), another Madras case. The only decision to the contrary in this Presidency is Srirangam Municipal Council v. Bodi(4), decided by Krishnan, J. sitting alone. In that case the defendant had bought in auction the right to collect fees for slaughtering cattle in the Municipal slaughter house. The suit was for balance of money due and was dismissed by the lower Court on the ground that no written contract was executed as required by Sect. 45 of the old District Municipalities Act, IV of 1884. It was argued that though no claim could be made on the basis of the written contract, a decree should have been given at any rate, on the footing of executed consideration, the defendant having been found to have enjoyed the right for the whole year. The learned Judge held that the authority quoted, Lawford v. Billericay Rural Council(5) was in favour of such a decree being given. He also quotes Douglass v. Ehyl Urban Council(6), as confirming the view taken in Lawford v. Billericay Rural Council. He says that the decision in Raman Chetti v. The Municipal Council of Kumbakonam does not really deal with the question and that the observation in Ramaswamy Chetty v. The Municipal Council, Tanjore is based on Young & Co. v. Mayor of Royal Leamington Spa. As was pointed out in The Madura Municipal Council v. Veerarna Kone the learned Judge seems to have failed to note that the cases he relied on were not cases where the contract was governed by any statute. One other Indian case is relied on for the appellant and that is Abaji Sitaram Modak v. The Trimbak Municipality. The remark in that case is obiter. The issue on which the case was tried was whether the remission of a certain sum out of the amount due under a contract with the Municipality was valid; and it was found that the meeting which granted the remission not being properly summoned, such remission was invalid. The learned Judges observe, “This discussion leads us to consider a point, which was raised before us for the first time, and then only as a result of investigations made in the course of the hearing before us. It appears that the contract under which defendant I became entitled to levy and collect the tolls was not under seal, and so failed to comply with Sect. 30 (of Bombay Act II of 1884) to which I have already alluded. The Advocate-General, relying for this purpose on sect. 23 of the Indian Contract Act, has asked us to hold that there was no contract at all under which the Plaintiff-Municipality can claim. Apart from the fact that this is travelling outside the pleadings of the parties we think, there is another reason why we cannot give effect to the contention. It is well recognised law in England that though a contract by a corporation must ordinarily be under seal, still where there is that which is known as an executed consideration, an action will lie though this formality has not been observed.” This is really obiter as the judges held that the plea was travelling outside the pleadings of the partics. As in Srirangam Municipal Council v. Bodi the distinction between a contract made under a statute and one not made under a statute appears to have been lost sight of. On the other hand the most recent case on the point is Mohamed Ebrahim Molla v. Commissioners for the Port of Chittagong(7), where it was held that a suit brought by the Port Commissioners of Chittagong on an agreement entered into in contravention of the mandatory provisions of Sect. 29 of the Chittagong, Port Act, 1914, must be dismissed as the contract was not enforceable. This judgment contains a very useful and succinct summary of the law on the point to which we will allude presently. In view of the fact therefore, that the particular matter before us has been decided twice by two benches of this Court against the appellant's contention and also by the Calcutta High Court, while on the other side there are only the decision of a single judge in Srirangam Municipal Council v. Bodi and the remark in Abaji Sitaram Modak v. The Trimbak Municipality a very brief summary of the argument put forward by the learned Advocate for the appellant will be sufficient.

He admits that there is no English case which holds that, where the right to contract is given by a statute, a statutory body can maintain an action on a contract though the provisions of the statute have not been complied with, while such non-compliance will be a defence to an action brought against them on the contract. What has been held with regard to corporations is that, when such bodies are not contracting under a statute, they can maintain a suit on a partly executed contract though it has not been given under seal while they cannot do so as regards an executory contract. The matter has been succinctly put in Mohamed Ebrahim Molla v. Commissioners for the Port of Chittagong. The learned Judges say:

“It is a rule of common law in England that with certain exceptions, a corporation is bound by those contracts only which are made under the Corporate Seal. The exceptions are:—(i) where the contract is executed, (ii) in small matters of very frequent occurrence and (iii) where it is impossible to affix the seal, as in cases of great urgency”.

It has been clearly laid down in a number of cases, of which the leading cases are Young and Co., v. Mayor of Royal Leamington Spa and Hunt v. Wimbledon Local Board, that where a corporation enters into a contract under a statute and the terms of the statute are not observed, the contract cannot be enforced against the corporation. But no English case has been quoted in which it was held that this is not mutual and that the corporation can on their side enforce such a contract. It is unnecessary to discuss the rulings which deal with statutory corporations which do not contract under a statute. The learned advocate however relied on two cases to show that a corporation could enforce a contract which did not comply with the statutory provisions. These were Bournemouth Commissioners v. Watts and Brooks, Jenkins & Co., v. Torquay Corporation.

These cases however are distinguishable. In Bournemouth Commissioners v. Watts the first case, it was a third party who sought to take advantage of the want of formality in the contract and it was held that there was nothing to prevent the local authority paying for the work of which it had the benefit and as regards the fact that the contract was not sealed this did not excuse the 3rd party who was liable for such work and did not afford a defence to such 3rd party. In this second case it was held that the municipal seal had been affixed in time and hence the requirements of Sect. 174 of the Public Health Act had been complied with and by reason of this a new contract had been entered into of which the part execution of the old contract could be taken to be consideration.

The learned Advocate for the Appellant argues that in India the position is peculiar and that, while a body contracting under a statute cannot enforce an unexecuted contract when all the terms of the statute are not complied with, yet when the contract has been wholly executed, the position is that, while they can urge this as a defence in a suit brought against themselves on the contract, it cannot be urged as a defence to a suit brought by them on the contract. For this be realise on the difference in the wording between Sect. 174, cl. 5 of the Public Health Act and Sect. 69 (2) of the District Municipalities Act. While the former runs:

“Every contract entered into by an urban authority in conformity with the provisions of this section and duly executed by the other parties thereto, shall be binding on the authority by whom the same is executed………”

Sect. 69 of the District Municipalities Act pats the matter negatively. It says:

“A contract executed or made otherwise than in conformity with the provisions of this and the last preceding section shall not be binding on the Municipal Council.”

It is argued that we should infer from this difference in language that a contract executed otherwise than in conformity with the provisions of the District Municipalities Act, while it will not bind the Municipality, will bind the other party to the contract. It is certainly somewhat remarkable that this negative language should have been employed in the Act but on the other hand, it has been pointed out that though the Act was revised after the decisions in Raman Chetti v. The Municipal Council of Kumbakonam and The Madura Municipal Council v. Veeranna Kone had been given no change was made in the section. If the meaning sought to be attached to it on behalf of the Appellant is correct, these decisions are opposed to such interpretation. In view of the fact that all the decided cases on the point excepting Srirangam Municipal Council v. Bodi are opposed to such an interpretation, we do not think that this argument can be accepted. It is difficult to see if the argument be accepted how an executory contract would differ from one executed.

Another argument adduced is that these formalities are only necessary in the interests of the rate-payers and that it is not open to any one else to take advantage of them. The case of Frend v. Bennett, is quoted for this purpose. What was held in this case was what has been so frequently decided—that want of formality in making a contract is a defence to a suit brought against the Corporation. The remark of Cockburn, C.J, which is relied on, viz.,

“I think the Local Board had no power to contract so as to bind the rates, unless they did so in the manner pointed out by the Statute,”

cannot be held to imply that they can enter into contracts enforceable by themselves but not enforceable by the other party. We therefore agree with the finding of the learned Subordinate Judge that the contract is not enforceable. This settles most of the other issues. But we cannot help observing that we are unable to agree with the remarks of the lower Court on issue 8 and with its decision thereon. As the learned Subordinate Judge has made some severe remarks against the Municipal manager in this connection, we will on this issue have to see if the Municipal Council introduced restrictions with regard to tolls on cattle which did not appear at the time of the original contract. It is certainly difficult to see why the defendants should not plead such a breach of the contract in this suit if it is true and why they should be driven to file a fresh suit. But it seems to us clear that the defendants knew of this restriction at the time of the contract. The learned Subordinate Judge relies on the fact that the Government Order granting this exemption is dated only the 25th of April 1922, while the contract was on the 6th of February 1922 and says the Council had no right to grant the exemption beforehand. We are not concerned here with the question whether the Council had any right to grant this exemption but whether in fact that exemption was known at the time of the contract to the defendants. The learned Subordinate Judge finds that the manner in which this exemption was entered in the resolution book is suspicious, but we have the letter Ex. VII-c written by the defendants on the 5th of April 1922, i.e, only 5 days after the defendant started collecting tolls, to the Municipal Chairman. In that letter they state:—

“In pursuance of an order of Government, tolls are being levied for cattle at the Municipal toll-gates in Tanjore, Kumbakonam, Mannargudi and Negapatam, in the Tanjore District in the Municipal gates in other Districts and in all the Local Fund toll-gates in the Tanjore District. The yield of paddy in the Taluks of Nannilam, Negapatam and Tiruturaipundi is very low this year. When we, who have taken a lease at a high rent, think over the probable collections during this festival season, we are led to apprehend much loss.

I therefore solicit orders for the levy of fees, except in the case of local cattle, for all cattle coming from other places as is being done in all other Municipalities. Great loss will be caused to us if an order be not passed to that effect.

I therefore pray that fees may be ordered to be levied for cattle other than the local ones.”

There is no hint here that the exemption was not known or declared to the parties at the time of the contract. What they state is that such exemption has been refused by the Government in other places and it ought not to be granted in Tiruvarur, specially in view of the bad season. Again the defendant's agent writes in Ex. VII(t) repeating that in Tanjore and other Municipalities toll is levied for cattle and saying,

“In the taluks of Nannilam, Negapatam and Tiruturaipundi, the produce of paddy is very much less this year. It appears from what was collected during the Utsavam time and what is being collected up to date that there will be a very great loss. An order must therefore be made for collecting toll for the cattle coming from outside except the local cattle as in all other Municipalities. We who have taken lease for a big amount, are likely to incur a heavy loss. * * *

I therefore request that an order may be passed for collecting tax for outside cattle except the local cattle now at least.”

Here again the claim is not put on any breach of the contract or on the introduction of a fresh term but on what is the practice elsewhere and on the bad season. If the defendants had thought it was contrary to the terms of the contract or was a term newly introduced, they would have certainly said so. It was not till long afterwards in a letter Ex. VII (m) written on the 5th of September 1922 that the agent of the 1st defendant wrote:

“After the sale was confirmed in oar favour we came to understand later on that the Councillors had decided at a meeting that fees should not be levied for cattle. Thereupon we have submitted two petitions to the Municipal Chairman, one on 5th April, 1922, and the other on 19th June 1922 requesting that, inasmuch as the notice inviting tenders did not mention that fees should not be levied for cattle, the resolution passed at the meeting of the Council should be set aside.”

It will be seen that the letters of 5th April 1922, and 19th June 1922 raised no such contention that the parties were not aware of terms of the contract which were altered at a later meeting of the Council.

As regards the other acts of negligence alleged by the defendants against the municipality, it is unnecessary to discuss them in view of our finding that the contract is not enforceable.

With regard to issue 10, we cannot agree with the finding of the learned Subordinate Judge that even if the contract was enforceable the 2nd defendant is not liable under it. The learned Judge says:

“The bidder was only the 1st defendant but the 2nd defendant stated subsequently that he was also a partner with the 1st defendant and that his name also should be included as a lessee. Ex. D is that application and even the Chairman did not pass any orders on it accepting the 2nd defendant as a lessee. Even if the Chairman had done so, it would be invalid since there was no resolution of the Council to that effect. The offer by the 2nd defendant not having been accepted and the bidder having no right to transfer or sub-lease without the sanction of the Council, I have to find that the 2nd defendant cannot be made liable as a joint contractor or joint lessee.”

Of course on the finding that the contract is not enforceable the 2nd defendant is not liable under it, but neither is the 1st defendant. This is not a case of a transfer or sub-lease as imagined by the lower Court but a case of a party after his bid has been accepted representing to the Municipality that he bid on behalf of himself and another person and asking that such other person should be regarded as a co-contractor. The second party joins in this and pays money on which the Chairman officially ‘accepts the amount tendered by both.’ Throughout both have been representing themselves as contractors and who have taken a joint lease. The 2nd defendant we consider is clearly estopped by his action from disputing liability under the contract and his contract is enforceable. Both the parties are agreed before us—and they are willing too—that if the contract is found invalid they should accept a decree on a Quantum meruit basis. We do not see any reason why this should not be allowed. Similar relief was allowed in Mohamed Ebrahim Molla v. Commissioners for the Port of Chittagong where it was held that the Port Commissioners could not sue on the contract. Although accounts have been furnished showing profit and lose, we think that they are not sufficiently complete to enable us to fix the correct figure. We will send the case down for disposal to the lower court on these lines, while reversing the decree though agreeing with the lower court on the second issue. Parties may adduce fresh evidence oral and documentary before the lower Court. The appeal having substantially failed in this Court, respondents will recover their costs here from the appellant. Costs in the lower Court will abide the result of the suit. Court-fee will be refunded.

N.R.R