Bengal Nagpur Railway Company, Limited v. Ratanji Ramji
Judgment Summary — Delivered by Mitter, J.
Factual and Procedural Background
The plaintiffs (now respondents) were members of a joint Mitâksharâ family who carried out certain works (earthwork, bridgework and miscellaneous work) on the Amdâ–Jâmdâ Branch for the Bengal Nagpur Railway Company. The plaintiffs' father, Ramji Madhoji (deceased at the time of this opinion), had signed printed schedules of rates and conditions (standard form) and delivered them to the District Engineer, Chaibasa. After two to three months' work, the father found the work unusually difficult and expensive and the scheduled rates inadequate. He and the railway corresponded; the plaintiffs allege the railway abandoned the signed schedules, prepared new schedules with higher rates (not accepted by the plaintiffs), and orally agreed to leave rates open and to pay reasonable rates on completion. Relying on assurances that reasonable, profit-yielding rates would be paid, the plaintiffs completed the works in December 1924. They claimed the company acknowledged liability to pay reasonable rates but relied on District Engineer's measured rates as sufficient.
Plaintiffs sued to recover Rs. 1,66,493-4-0 (with particulars in schedules A–D), asking in the pleadings for: (a) a sum stated as value of work, (b) interest of Rs. 40,629-12-0 or any adjudged amount, (c) further interest until realisation, (d) costs and (e) other reliefs. The defendants raised multiple defences (including limitation, the binding effect of the signed schedules and that rates were not liable to variation, that rate increases were granted only as a favour or under clause 15, that explosives were not supplied free, and that interest was not payable or excessive).
On 10 January 1929 plaintiffs applied for a local investigation; the court appointed a commissioner to assess fair rates. The commissioner's long report was filed (15 August 1930); objections followed. The Subordinate Judge, after evidence, granted a partial decree to plaintiffs for Rs. 1,51,846. The Bengal Nagpur Railway Company appealed against that decree. This opinion is the appellate court's decision.
Legal Issues Presented
- Whether the railway company's conduct amounted to abandonment (rescission) of the original written schedules so that the plaintiffs could claim reasonable or market rates (quantum meruit) instead of the original scheduled rates.
- If the original schedules were abandoned, whether plaintiffs are entitled to recover compensation under Section 70 of the Indian Contract Act (i.e., reasonable payment for services not intended as gratuitous) or damages under Section 73 of the Indian Contract Act.
- Whether the suit was barred by limitation (works completed >3 years before institution of suit).
- Whether the clause 15 (requiring formal notation/initialling of altered rates) prevented the plaintiffs from recovering enhanced rates when informal or correspondence-based increases occurred.
- Whether plaintiffs were entitled to interest (including interest pendente lite), and if so at what rate (whether 12% p.a. was excessive and whether interest should be allowed at all).
Arguments of the Parties
Plaintiffs' Arguments
- The signed schedules were abandoned by the railway company and the parties proceeded on the basis that final reasonable rates would be settled after sufficient progress; plaintiffs relied upon assurances and completed the work.
- The railway had been kept informed of difficulties and expenses so these could be considered in fixing final rates.
- Explosives had been supplied free under an oral arrangement, so plaintiffs' rates for cuttings excluded explosives cost.
- Because the company failed to pay dues despite demands, plaintiffs sought interest (claimed at 1% per month in the plaint; also later claimed interest from July 1925 onward).
Defendant's Arguments
- The suit is barred by limitation as works were completed more than three years before institution of the suit.
- The signed schedules constituted the contract's foundation; plaintiffs are bound by rates and terms in the schedules and cannot reopen rates.
- Any increases were either granted as a favour (not binding) or made in accordance with clause 15 (requiring alterations to be noted and initialled), and the contractor did not accept/initial the enhanced rates.
- The Assistant Engineer lacked authority to make proposals altering rates without sanction of District and Chief Engineers; the company never admitted liability to pay rates other than those in the signed schedules.
- Specific contentions on allowances: the defendant maintained the schedule rates plus jungle allowance and certain mileage allowances were fair and adequate; special rates alleged by plaintiffs were denied; explosives were not supplied free and cost was recovered in accounts; plaintiffs were not entitled to claimed interest or it was excessive.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Rose and Frank Company v. J.R. Crompton and Brothers, Limited | Actual transactions between parties give rise to ordinary legal rights even where formal written agreement is not intended to be legally binding; where services are rendered (without specified remuneration) law may imply promise to pay quantum meruit. | Used to support the proposition that, where the railway obtained benefit of the work after abandoning the written rates, plaintiffs could claim reasonable remuneration (quantum meruit) under Section 70. |
| Morris v. Baron and Company (House of Lords) | Test (Lord Dunedin) to distinguish variation of contract from rescission: whether the second arrangement can be sued upon alone; whether contracts can coexist or first is displaced. | The test was applied to conclude that the original contract was gone (rescinded) because correspondence showed both parties agreed the old schedule rates must be abandoned. |
| Earl of Darnley v. Proprietors, etc., of London, Chatham, and Dover Railway | When parties depart from a written agreement and rely on a substituted verbal agreement, the party enforcing it must show both had the same understanding of new terms. | Cited to emphasize that the correspondence showed a mutual understanding that the old printed schedule rates must be abandoned, supporting rescission rather than mere variation. |
| Chajmal Das v. Brij Bhukan Lal (Judicial Committee) | Even where interest is not recoverable under contract or Interest Act, courts may award damages for wrongful detention of money; post-due-date interest recoverable as damages (quantum often similar to contractual rate). | Relied upon to justify awarding interest by way of damages for detention of money where liability to pay reasonable rates was implied; supported allowing interest even if no express contractual provision for interest. |
| Kalyan Das v. Maqhul Ahmad | Discussed in conjunction with Chajmal Das; court found no conflict when facts examined. | Used to rebut an argument that Chajmal Das could not be reconciled with later authority; court held the cases are reconcilable and Chajmal Das remains applicable on the facts here. |
| Cook v. Fowler | Principle that a claim in the nature of interest after stipulated period is in truth a claim for damages for late payment; tribunal should assess appropriate sum as damages. | Applied to frame interest claimed as damages for detention and to explain that the tribunal must consider circumstances in deciding an appropriate rate for damages. |
| Prosonnomoyi Ghoshani v. Gopal Lal Sinha | Held that interest by way of damages is not recoverable for mere wrongful detention of an ordinary debt (a contrary view by Mr. Justice Walmsley; another judge dissented). | Referred to as an authority that supports the appellant's contention; the court declined to follow that view in light of Judicial Committee and other precedents. |
| Kandappa Mudaliar v. Mutuswami Ayyar | Authority for allowing interest pendente lite (interest between filing of plaint and determination). | Cited to support allowance of interest for the period between filing and final determination. |
| J.H. Pattinson v. Srimati Bindhya Debi (Patna High Court) | Decision contrary to this Court's consistent view on allowing interest as damages (discussed in the opinion). | Not followed; mentioned to show conflict in authorities and to justify reliance on Judicial Committee decisions and this Court's prior decisions. |
| Mohamaya Prosad Singh v. Ram Khelawan Singh Thâkur; Khetra Mohan Poddar v. Nishi Kumar Saha | Cited as decisions of this Court consistently taking a view contrary to the Patna decision (supporting allowance of interest/damages in relevant circumstances). | Referred to as supporting authorities for allowing interest as damages and for the approach taken by the present court. |
Court's Reasoning and Analysis
The court proceeded in stages, following the facts and record as presented:
- Procedural step: The trial court had appointed a commissioner to assess fair and reasonable rates; the commissioner's report and subsequent objections were considered and a partial decree for Rs. 1,51,846 was entered for the plaintiffs, prompting the railway's appeal.
- On the core factual issue—whether the original scheduled contract remained binding—the court examined the correspondence and conduct of the parties. The court found clear indications that both parties manifested an intention that the printed schedule rates be abandoned and that some higher rates must form the basis of the contract. The correspondence included instances where the railway increased rates by 25% and gave assurances to the contractor that reasonable profitable rates would be provided.
- Applying the test from Morris v. Baron (Lord Dunedin's distinction between variation and rescission), the court concluded that the original contract had been rescinded (abandoned). In particular, clause 15 (requiring formal notation and initialling of altered rates) was disregarded in the correspondence and informal increases were made without the procedural formalities set out in that clause.
- Given abandonment and no final settlement of rates, the court held the legal position was that the plaintiffs were entitled to reasonable or market rates for the work done. The court invoked Section 70 of the Indian Contract Act to state that a person who lawfully does something for another, not intending it gratuitously, and where the other enjoys the benefit, is entitled to compensation.
- Concerning interest, the court treated the plaintiffs' claim for interest as being in the nature of damages for detention of the debt under Section 73 of the Indian Contract Act. The court surveyed conflicting authorities (including Chajmal Das, Patna High Court decisions and others), concluded that the Judicial Committee's decision in Chajmal Das supported awarding damages/interest for detention, and found it appropriate to award interest as damages. The court also rejected the argument that interest pendente lite should never be awarded, citing authority (Kandappa Mudaliar) permitting interest for the period between filing and judgment.
- On the appropriate rate of interest, the court reasoned that although a contractual rate might prima facie be adopted as the measure of damages, the tribunal must consider the circumstances. There was no evidence plaintiffs sustained actual damage or paid 12% on borrowings; consequently the court reduced the rate awarded from 12% to 9% per annum as fair in all circumstances.
- The appellate conclusion was to allow the appeal in part: the court affirmed the entitlement to reasonable rates and interest as damages but varied the decree by reducing the rate of interest to 9% per annum.
Holding and Implications
APPEAL ALLOWED IN PART
Holding (core ruling):
- The court found that the original printed schedule contract had been abandoned (rescinded) by mutual conduct and correspondence, and because no final rates were settled, the plaintiffs were entitled to reasonable/market rates for the work done, applying Section 70 of the Indian Contract Act and the principle of quantum meruit.
- The plaintiffs were entitled to interest by way of damages for wrongful detention of the sums due (invoking Section 73 and authorities such as Chajmal Das), including interest pendente lite; however the appellate court reduced the rate awarded by the trial court to 9% per annum (from 12%).
- The decree of the Subordinate Judge was varied to reflect the reduced rate of interest; the appeal was otherwise not fully allowed, hence "allowed in part." (The Subordinate Judge had earlier awarded a partial decree for Rs. 1,51,846 to the plaintiffs.)
Implications:
- Direct effect on the parties: the plaintiffs are entitled to recover reasonable/market rates for the work completed and to interest as damages at 9% per annum; the trial court's decree is modified accordingly. The railway's contention that plaintiffs were bound to original schedule rates was rejected on the facts.
- Broader legal implications: the court applied established principles (quantum meruit under Section 70; damages for detention under Section 73; and the Morris test distinguishing variation from rescission). The opinion analyses and reconciles conflicting authorities on interest and damages but does not purport to lay down a novel or sweeping new rule beyond applying these principles to the facts. (No explicit pronouncement that a new precedent is being established appears in the opinion.)
Disposition recorded in the opinion: "Appeal allowed in part."
The Judgment of the Court was delivered by
Mitter, J.:— The action, which has given rise to this appeal, was brought by the plaintiffs, now respondents, to recover Rs. 1,66,493-4-0 from Bengal Nagpur Railway Company on account of price of work done by the plaintiffs as members of a joint Mitâksharâ family in a certain section of the construction known as the Amdâ-Jâmdâ Branch.
The case stated in the plaint is that the defendants offered to the father of the plaintiffs, Ramji Madhoji, who is now dead, contract work in the said construction, subject to his signing certain schedules, which are usual printed forms of agreement; that the plaintiffs' father signed the schedules for earthwork, bridgework and miscellaneous work and delivered the schedules to the District Engineer of, Chaibasa; that after carrying on the works for two or three months, plaintiffs' father discovered the work to be unusually difficult and expensive and the scheduled rates to be grossly inadequate and the conditions contained in the schedule were hard and unjust; that the contractors expressed their inability to work at the rates agreed upon and pressed for cancellation of the contract and for settlement of higher rates and better conditions; that this led to a discussion and the result of the discussion was that the defendant company had abandoned the plaintiffs' schedules and had prepared new schedules containing higher rates, which, however, were not accepted by the contractor (plaintiffs) and further that the defendants proposed to leave the question of rates open with a view to ascertain later on an estimate, of the contractors' expenses after sufficient progress of the work and that the defendant company-assured the plaintiffs of their well-established policy to pay final rates at which contractors can make a profit and that reasonable rates will be paid; that, on the faith of these assurances, the plaintiffs went on with the work and completed the same; that, during the progress of the work, the contractors kept the defendant company duly informed of the difficulties and the costs from time to time, so that these might be taken into consideration at the final determination of the rates; that, although attempts were made by the defendant company as well as by the plaintiffs to settle final rates in advance, the attempt failed but the work was not stopped on the mutual understanding that the final rates would be ascertained on the completion of the work; that the work was completed in December, 1924, but, notwithstanding attempts to settle the rates, no agreement was reached; that the company, while admitting its liability to pay reasonable rates, maintained that the rates worked up by the District Engineer in the measurement book were sufficient. In paragraph 8 of the plaint, the plaintiffs state their main objections to the rates worked up by the District Engineer as aforesaid. The plaintiffs admit that, in pursuance of an oral arrangement, the contractor was supplied by the defendants with explosives free of charge for blasting purposes and, consequently, the plaintiffs' rates for the cuttings are based on their expenses and do not include the cost of explosives. The plaintiffs further state that, in spite of repeated demands, the defendant company failed to pay their dues and, as the defendant company were having the benefit of plaintiffs' money, the plaintiffs were entitled to get interest at 1 per cent, per month since July, 1925. The plaintiffs, accordingly, prayed for the following reliefs:—viz., a decree for—
(a) Rs. 1,26,863-8-0 or any other amount found due as the value of the work done by plaintiff for defendant.
(b) Rs. 40,629-12-0 or any other amount of interest adjudged due.
(c) Further interest for the period of the suit, until realisation, on the total claim, Rs. 1,67,493-4-0.
(d) Costs of the suit.
(e) Other reliefs.
The plaint gives an account of the work done and charges for the same in three schedules. Schedule A is the final bill for the earthwork, schedule B is the final bill for the bridgework and the schedule C is the final bill for miscellaneous work. Schedule D of the plaint, after giving the total value of the several kinds of work done and after making deductions on account of previous payments and royalty and after charging interest at 1 per cent, per month, lays the total claim at Rs. 1,67,493-4 only.
Several defences to the suit have been taken by the defendant railway company, but we will notice only those around which controversy has centred in the present appeal. Such defences are: (1) that the suit is barred by limitation, as the works, in respect of which the suit has been instituted, were completed more than three years before the institution of the suit; (2) that the schedules of rates for earthwork, bridgework and miscellaneous works form the foundations of the contract between the parties and the defendant relies on the schedule of rates and the terms and conditions appearing therein; (3) that the schedules of rates were not liable to variation as alleged by the plaintiffs; (4) that the plaintiffs pressed for some increases as a matter of favour and pointed out some difficulties in view of which certain increase of rates were sanctioned by the Chief Engineer as a matter of favour and were entered in the schedules (5) that the defendant did not abandon the contractor's schedules, but increased-certain rates, as permitted by condition No. 15 of the schedules; that as the contractor did not agree to or initial the enhanced rates as entered in the schedules, the plaintiffs are bound by the lower rates of the original schedules, that the Assistant Engineer had no authority to make any new proposal with regard to the rates or give any assurance in respect thereof without the prior sanction of the District and Chief Engineers who alone have the right to alter them; (6) that the defendant never admitted its liability to pay any rates other than those entered in the signed schedules; the defendant states that the rates granted by the defendant are fair and reasonable rates; that, without admitting the plaintiff's right to reopen the question of rates, the defendant submits, with regard to clauses (b), (c), (d) and (e) of paragraph 8 of the plaint as follows:—
(b) that the defendant railway company submit that the schedule rates, as voluntarily amended by the defendant together with 25 per cent, jungle allowance, are just and adequate;
(c) that over and above the jungle allowance, a mileage allowance of annas six per 100 cft. as allowed on earthwork on this contractor's length. This was the highest mileage allowance on the district. In the case of bridge work, where special rates have not been allowed, Rs. 2 per cft. special mileage allowance has been included in masonry rate and annas twelve per 100 cft. for concrete. That the plaintiffs are not entitled to get what they claim under this head;
(d) it is submitted that 25 per cent, is a fair allowance and ought not to be increased;
(e) that special rates higher than the amended scheduled rates with mileage and jungle allowance were approved by the Chief Engineer. These rates are on average about twice those originally agreed to in the printed schedules. That special road to the contractor's quarry was constructed by the railway and he was given other advantages. The defendant denies the allegations made in sub-paragraph (e) of the plaint;
(7) that the plaintiffs are not entitled to reopen the question of the said rates and to have fresh rates assessed, that, without giving up this position but strongly relying upon it, the defendant makes the following submission with regard to clauses (a), (b) and (c) of paragraph 9 of the plaint:—
(a) that the principle of the agreed schedule is that the work should be done for an agreed price and not on an expenditure and commission basis. The contractor cannot claim the latter in view of the agreement signed by him;
(b) that the rates paid to this contractor are in no way less than those paid to other contractors working near him;
(c) that the District Engineer is the sole judge of the classifications. The plaintiffs are not entitled to what they call expert and experienced estimate of rates and expenses;
(8) that with regard to the allegations made in paragraph 16 of the plaint, the defendant submits, that it is not true, that there was any oral agreement between the parties in pursuance of which the contractor was supplied by the defendant with explosives free of charges for blasting purposes, and that no account of such supply to a particular contractor was kept by the contractor or the defendant; on the contrary, it was, agreed that the contractor would pay for such explosives and that the cost of explosives would be deducted from the amounts due to the contractor and that in the account bills for this contractor the cost of explosives was as a matter of fact recovered; the defendant denies that the contractors' rates for the cuttings are based on their expenses and do not include the cost of explosives; (9) that the plaintiffs are not entitled to any interest as claimed by them and that in any case the interest claimed is excessive.
On the 10th of January, 1929, the plaintiffs put in an application, supported by an affidavit, for local investigation and, on the 12th February, they supplemented that petition. On the 16th of February, the court allowed the application of the plaintiffs and directed that a commissioner be appointed to assess the fair and reasonable rates for the works done, remarking that such an investigation was necessary, it being the plaintiffs' case, in the pleadings, that the contract known as the schedule of rates was abandoned by the defendant, who agreed to pay at reasonable and fair rates and remarking also that expert opinion was necessary for such investigation. The commissioner submitted a very long report, covering about 250 pages of volume 2 of the paper book. This report was filed on the 15th of August, 1930. On the 8th of January, 1931, both sides filed petitions of objection to the commissioners' report. The learned Subordinate Judge, after taking oral and documentary evidence, has granted a partial decree to the plaintiffs for the sum of Rs. 1,51,846 and it is against this decree that the present appeal has been brought by the Bengal-Nagpur Railway Company, Ltd.
[After dealing with the evidence the judgment proceeded as follows]:—
There being the abandonment of the old rates and no settlement of any new rates, let us consider what the true legal position is, keeping in view the fact that the railway company has got the benefit of the work of the contractor and the further fact that the contractor did not do the work gratuitously. We are of opinion that, in the circumstances, any actual transaction between the parties gave rise to the ordinary legal rights and, in the absence of any settlement of any rates, the plaintiffs are entitled to get reasonable rates or market rates. Section 70 of the Indian Contract Act may be applied to the present case. That section runs as follows:—
Where a person lawfully does anything for another person, or delivers anything to him, not intending to do so gratuitously, and such other person enjoys the benefit thereof, the latter is bound to make compensation to the former in respect of or to restore the thing so done or delivered.
Reference may be made in this connection to Rose and Frank Company v. J.R Crompton and Brothers, Limited , where the facts are stated as follows:— By successive arrangements, made, before 1913, between an American firm and an English company, “the American firm were constituted sole agents for the sale, in the United States and Canada, of tissues for carbonizing paper supplied by the English company. The greater part of these tissues was manufactured for this English company by another English company. By an arrangement, made between the American firm and both English companies in 1913, the English companies expressed their willingness that the existing arrangements with the American firm, which were then for one year only, should be continued on the same lines for three years and so on for further periods of three years, subject to six months' notice. This document, after setting out the understanding between the parties, including several modifications of the previous arrangements, proceeded as follows:—
This arrangement is not entered into, nor is this memorandum written, as a formal or legal agreement, and shall not be subject to legal jurisdiction in the law courts either of the United States or England, but it is only a definite expression and record of the purpose and intention of the three parties concerned, to which they honorably pledge themselves, with the fullest confidence—based on past business with each other—that it will be carried through by each of the three parties with mutual loyalty and friendly co-operation. This is referred to as the “honorable pledge” clause.
Disputes having arisen between the parties, the English companies determined this arrangement without notice. Before the relations between the parties were broken off, the American firm had given and the first mentioned English company had accepted certain orders for goods. In an action by the American firm for breach of contract and for non-delivery of goods—it was held in the above state of facts that the arrangement of 1913 was not a legally binding contract; that, at the date of the arrangement of 1913, all previous agreements were determined by mutual consent, but that the orders given and accepted constituted enforceable contracts of sale. The following passage in the speech of Lord Phillimore is pertinent to the present controversy:—
Any actual transaction between the parties, however, gave rise to the ordinary legal rights; for the fact that it was not of obligation to do the transaction did not divest the transaction when done of its ordinary legal significance. This, my Lords, will, I think, be plain if we begin at the latter end of each transaction. Goods were ordered, shipped and received. Was there no legal liability to pay for them? One stage further back goods were ordered, shipped, and invoiced. Was there no legal liability to take delivery? I apprehend that in each of these cases the American company would be bound.
This case rests on the wide general principle that where one has expressly or impliedly requested another to render him a service without specifying any remuneration, but the circumstances of the request imply that the service is to be paid for, the law will imply a promise to pay quantum meruit, i.e, so much as the party doing the service has deserved, or, as we normally say a reasonable sum. By the letter of the 5th of October, 1920, Exhibit 78, the contractor was asked to carry on the work and assurance was given that it was the policy of the railway company to see that the contractors get a certain amount of profit.
Mr. Bagram has contended that there has been no abandonment of the original scheduled rates, but that there has been merely a variation of the contract in one particular and he has relied on the decision of the House of Lords in the case of Morris v. Baron and Company in support of this proposition. Whether there has been a mere variation of terms or a rescission depends upon the facts of each particular case and is often not easy to determine, but the following test has been suggested by Lord Dunedin:—
In the first case (variation) there are no such executory clauses in the second arrangement as would enable you to sue upon that alone if the first did not exist; in the second (rescission) you could sue on the second arrangement alone, and the first contract is got rid of either by express words to that effect, or because, the second dealing with the same subject-matter as the first but in a different way, it is impossible that the two should be both performed. When I say you could sue on the second alone, that does not exclude cases where the first is used for mere reference, in the same way as you may fix a price by a price list, but where the contractual force is to be found in the second by itself.
Looking to the correspondence * * one cannot but come to the conclusion that, on the one side, the contractor was pointing to the difficulties of the work, to the heavy loss he would suffer if the scheduled rates are adhered to and asking for a settlement of final rates and, on the other, the railway company was increasing the scheduled rates by 25 per cent, and giving the contractor the assurance that he would have rates which will be reasonable and will leave sufficient margin of profit to the contractor. From this correspondence, it is manifest that both parties abandoned the original contract as in the printed schedule, to which were attached general and special conditions (see Ex. P., pages 210-212, Vol. III) and, although the railway were increasing the rates, the contractor still asked for a further increase as he was not satisfied with the last increase and asking for the settlement of final rates. On one point, both the railway company and the contractor were agreed, viz., the rates as in the printed schedule must go and some larger rate must form the basis of the contract.
Mr. Bagram has strenuously argued that the original contract remained, except that there was some variation in the schedule of rates, but the other conditions remained intact; and reference is made to paragraph 15 of the conditions (page 210, Vol. III) that any alteration in rates after the work has commenced must be noted in the schedule and initialled by the engineer in charge and the contractor. Any increased rate claimed and not entered in the schedule as above will not be admitted as agreed to.
Applying the test laid down by Lord Dunedin in Morris's case in the passage already quoted, it appears that the original contract was gone and, as the contractor completed his work, he is entitled to reasonable rates. The argument, as I understand it, is that, under clause 15 of the general conditions, it was permissible to the railway company to vary the rates and the railway company altered it under the condition No. 15 and there was merely variation of a part of the contract and no rescission of the, contract. But clause 15 was altogether disregarded in the correspondence for increase was given in some of the letters without corresponding alteration in the schedule.
In this connection, reference is made to a decision of the House of Lords in Earl of Darnley v. Proprietors, etc., of London, Chatham, and Dover Railway , and reference is made to the following passage occurring in the speech of the Lord Chancellor:—
When parties, who have bound themselves by a written agreement, depart from what has been so agreed on in writing, and adopt some other line of conduct, it is incumbent on the party insisting on, and endeavouring to enforce, a substituted verbal agreement, to shew, not merely what he understood to be the new terms on which the parties were proceeding, but also that the other party had the same understanding—that both parties were proceeding on a new agreement, the terms of which they both understood.
There can be no doubt in this case that both parties understood that the old rates as embodied in the printed schedule must be abandoned. Ex. 78, page 47, Vol. III, which is described by counsel for appellant as the sheet anchor of the respondents' case supports this view. The letter of the District Engineer, dated the 20th April, 1921 (page 47, Vol. III), supports the same view. He says:—
Your paragraph 6. You can see and sign the schedule in the Assistant Engineer's office. Above these rates, you will be paid 25 per cent, extra on all item involving labour, provided you in return make reasonable arrangement to look after your coolies and make them so contented that they do not bolt.
The learned counsel for the appellants has raised a very important question with reference to the interest on the amount claimed. He contends, in the first place, that no decree for interest should have been allowed, as there was no contract, express or implied, to pay interest and he argues further that, in any event, interest, at the rate of 12 per cent, per annum, is excessive and his further extreme contention is that interest pendente lite should never be allowed. The amount of interest claimed and due, if interest is payable, is considerable and the case becomes of importance to the parties in consequence of the amount. In support of the contention that no interest should have been allowed up to the date of the suit, reliance has been placed on the decision of the Patna High Court in the case of J.H Pattinson v. Srimati Bindhya Debi* . That decision, it is to be noticed, is contrary to the view which has been taken consistently in this Court in the cases of Mohamaya Prosad Singh v. Ram Khelawan Singh Thâkur and the case of Khetra Mohan Poddar v. Nishi Kumar Saha . The Patna decision seems to be opposed to the decision of their Lordships of the Judicial Committee in the case of Chajmal Das v. Brij Bhukan Lal , which laid down that, even though the claim of the plaintiffs be or is limited to interest which is not recoverable either under a contract or under the provisions of the Interest Act (XXXII of 1839), it is open to the court to make a decree for damages for wrongful detention of their money. In the case before the Judicial Committee where the bonds stipulated for payment of principal in two years from its date with interest at 15 per cent, and half-yearly rests, but omitted to provide for interest after the expiration of the two years, it was held that interest for the post diem period was nevertheless recoverable as damages for the non-payment at due date, and that, prima facie the rate would be the same as that provided in the bond during the two years, in this case, simple interest was ordered at 15 per cent. Mr. Justice Wort of the Patna High Court seems to think that this decision of the Judicial Committee cannot be reconciled with a later decision of their Lordships in the case of Kalyan Das v. Maqhul Ahmad , but if the facts of that case are examined it will be seen that there is no conflict between Chajmal Das's case and Kalyan Das's case . The facts are:—In 1878, the mortgagees under the mortgage of 1863 got Rs. 6,988 on account of a redemption, which is only now taking places therefore, they received it over thirty years too soon, therefore, they should not only allow it in account, which they have done, but should allow over thirty years' interest on it too. Alternatively, since 1878 the principle mortgage moneys under the mortgage of 1863 must be deemed to have been paid off in the proportion of Rs. 6,988 to Rs. 15,944 and as the enjoyment of the usufruct by the mortgagees was conceded only in consideration of the continuance of the mortgage loan, the enjoyment should be reduced pro tanto from that date; in strictness, on redemption, a part of the rents and profits collected should be returned or credited in account to the mortgagors in the above proportion, but for simplicity's sake interest at a sufficient rate will do as well. One cannot, however, help remembering here that the persons, who are asked to repay these profits are the respondents, whose predecessors never collected them or had anything to do with them, and that the persons to whom they are to be repaid are the successors of Debi Das, who collected and enjoyed them and probably bequeathed them to the appellants, but this inconvenient reminiscence is for present purposes outside the hypothesis. In this state of facts their Lordships of the Judicial Committee said this:—
To the first way of putting the matter their Lordships reply, as the High Court replied, that interest depends on contract, express or implied, or on some rule of law allowing it. Here there is no express contract for interest and none can be implied, and no circumstances less capable of justifying the allowance of interest as matter of law can be imagined. The mortgage of 1863 is the answer to the second view. It treats the usufruct as a whole, as a remuneration for the loan or any part of it so long as it remains outstanding.
The facts of this case are somewhat peculiar and all that was laid down was that a man cannot claim interest for money practically in his own pocket. After the abandonment of the original schedule rates, the law implied a promise to pay at market rate and if there is a breach the court is entitled to assess damages under section 73 of the Indian Contract Act. It appears that the work was completed in December, 1924, and, on the 23rd of September, 1925, the plaintiff contractor wrote a letter to the Assistant Engineer in charge that he would charge interest on Rs. 65,714 at 15 per cent, per annum, as the amount, though admittedly due, was being unlawfully withheld from him. The interest before suit was claimed from the 26th of July, 1925 to 29th November, 1927. In this case, the interest is really in the nature of damages for detention of the debt. In the case of Cook v. Fowler , Lord Cairn refers to the well-known principle that any claim, in the nature of a claim for interest after the day up to which interest was stipulated for, would be a claim really, not for a stipulated sum and interest, but for damages, and then it would be for the tribunal before which that claim was asserted to consider the position of the claimant and the sum which properly and under all the circumstances should be awarded for damages. No doubt prima facie the rate of interest stipulated for up to the time certain might be taken and generally would be taken, as the measure of interest but that would not be conclusive. It would be for the tribunal to look at all the circumstances of the case, and to decide what was the proper sum to be awarded by way of damages. And this is what was said by Lord Morris in Chajmal's case above referred to. The appellant has also referred to a decision of this Court in the case of Prosonnomoyi Ghoshani v. Gopal Lal Sinha where Mr. Justice Walmsley held that interest by way of damages is not recoverable for the mere wrongful detention of an ordinary debt. Mr. Justice Huda did not agree with him. He held that the plaintiff in that case was clearly not entitled to any interest under the Interest Act. But, observed the learned Judge:—
That in my opinion does not debar him from claiming interest by way of damages under section 73 of the Contract Act.
Mr. Justice Walmsley's view no doubt supports the appellant, but we are not prepared to agree with him in view of the decision of the Judicial Committee and of this Court to which reference has already been made.
The ground, therefore, that no interest should be allowed before suit should fail. The next point taken is that interest pendente lite should not be allowed. There is no authority for this proposition. On the other hand there is authority for the proposition that, for the period between the filing of the plaint and the determination of the suit, the plaintiffs are entitled to interest [see Kandappa Mudaliar v. Mutuswami Ayyar ]. On the point of interest another ground is taken and it is said that 12 per cent, per annum is excessive. Considering all the circumstances of the case, regard being had to the fact that there is no evidence that the contractor sustained actual damage or that he paid 12 per cent, on his borrowings, we think that 9 per cent, per annum is the fair rate of interest that the plaintiffs can claim. We, accordingly, reduce the rate of interest from 12 per cent, to 9 per cent, and the decree of the Subordinate Judge must be varied in this respect.
Patterson, J.:— I agree.
Appeal allowed in part.