Power Grid Corporation Of India Limited v. Karnataka Power Transmission Corporation Ltd., Bangalore
Structured Summary of the Opinion — Petition No. 136/2006
Factual and Procedural Background
The petition sought approval of final tariff for the 400 kV D/C Madurai–Thiruvananthapuram Transmission System in the Southern Region for the period 1.8.2005 to 31.3.2009, under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004 ("the 2004 regulations"). The petitioner sought the tariff after accounting for additional capitalization of Rs. 600.21 lakh during 2005–2006 and requested reimbursement of (a) expenditure incurred in publishing statutory notices in newspapers and (b) the petition filing fee.
Investment approval for the transmission system was originally accorded by the petitioner's Board by Memorandum dated 22.11.2000 at an estimated cost of Rs. 19,597 lakh (including IDC Rs. 2,371 lakh). A revised estimate for Rs. 26,003 lakh (including IDC Rs. 3,422 lakh) was approved by Board Memorandum dated 30.1.2006.
Provisional transmission charges had earlier been approved by the Commission by order dated 13.2.2006 in Petition No. 137/2005. The present petition was for final tariff determination from the date of commercial operation (DOCO), which is recorded as 1.8.2005.
The petition included year-wise claims for depreciation, interest on loan, return on equity, advance against depreciation, interest on working capital and O&M expenses for the periods 2005–2006 (pro rata), 2006–2007, 2007–2008 and 2008–2009. Replies to the petition were filed by Karnataka Power Transmission Corporation Ltd. and Tamil Nadu Electricity Board. No public comments were received in response to notices published under section 64 of the Electricity Act, 2003.
Legal Issues Presented
- Whether the final tariff for the 400 kV D/C Madurai–Thiruvananthapuram Transmission System for the period 1.8.2005 to 31.3.2009 should be approved under the 2004 regulations, including allowance for additional capitalization of Rs. 600.21 lakh for 2005–2006.
- Whether the claimed additional capitalization is within the original scope of work and should be admitted after prudence check under Regulation 53 of the 2004 regulations.
- Whether the time overrun (commissioning delay to 1.8.2005 from scheduled October 2003) is attributable to the petitioner or excusable for the purpose of tariff determination.
- How the capital cost should be treated for tariff — including computation of gross block and segregation of debt and equity (debt-equity ratio) for tariff purposes under Regulation 54 and the Note thereto.
- Appropriate computation and allowance of: (a) return on equity, (b) interest on loan (including normative computations and weighted average interest rate), (c) depreciation and advance against depreciation, (d) operation & maintenance expenses as per norms, and (e) interest on working capital — all in accordance with the 2004 regulations.
- Whether the petitioner is entitled to reimbursement of expenses incurred on publication of notices and to the filing fee paid, and the procedure for any such reimbursement.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The court's analysis closely applied the provisions of the 2004 regulations to the factual record presented by the petitioner. The reasoning steps recorded in the opinion are summarized below, following the order in which the analysis appears in the opinion.
Admissibility of Additional Capitalization (Regulations 52 and 53)
- The court applied Regulation 52(1) which makes actual expenditure incurred on completion of the project (subject to prudence check) the basis for final tariff, and sets a ceiling norm for capitalized initial spares at 1.5% of original project cost. The regulation applies where DOCO is on or after 1.4.2004.
- Regulation 53(1) was cited to identify categories of additional capital expenditure admissible after DOCO and up to cutoff date, subject to prudence check (deferred liabilities, works deferred, initial spares within ceiling, liabilities from awards, change in law, etc.).
- The petitioner submitted details of additional capitalization in 2005–2006 amounting to Rs. 600.21 lakh (breakdown: Building & civil works Rs. 169.63 lakh; PLCC Rs. 87.03 lakh; Transmission line Rs. 343.55 lakh).
- The court concluded that the claimed additional capitalization was within the original scope of work and constituted committed liabilities; accordingly it allowed the additional capitalization of Rs. 600.21 lakh.
Time Overrun — Causation and Attribution
- The project was scheduled for commissioning by October 2003 but was declared under commercial operation only on 1.8.2005 (about 21 months delay).
- The court reviewed the factual chronology supplied by the petitioner showing stoppages and obstructions primarily in the Kerala portion arising from local public objections, litigation in the Kerala High Court, multiple administrative steps and interventions by State authorities and Ministers, route diversion considerations and compensation/ROW disputes that lasted from February 2002 to March 2004.
- On this factual basis the court found that the delay (21 months) with reference to investment approval was not attributable to the petitioner because it arose from the prolonged stoppage and resolution process involving third-party public objections and State actions.
Computation of Capital Cost and Means of Finance
- Gross block as on 31.3.2006 for tariff purpose was worked out at Rs. 24,933.68 lakh (which includes the admitted additional capitalization).
- Regulation 54(2) (applicable to projects with investment approval prior to 1.4.2004 and declared commercial during 1.4.2004–31.3.2009) provides a normative debt-equity ratio of 70:30 subject to provisos.
- Note 1 below Regulation 53 was applied to treat committed liabilities within original scope as serviced in the normative 70:30 debt-equity ratio.
- The petitioner had actually deployed a debt-equity ratio of 71.95:28.05 on DOCO and had treated the entire additional capitalization against loan. The Commission accepted the petitioner's DOCO ratio (71.95:28.05) for the date of commercial operation but segregated the Rs. 600.21 lakh additional capitalization into debt and equity on a normative 70:30 basis for tariff purposes (per Note 1). Accordingly, specific equity amounts considered were stated (e.g., Rs. 6,824.47 lakh as equity on 1.8.2005 and Rs. 7,004.53 lakh as equity on 1.4.2006 for tariff calculations).
Return on Equity
- Regulation 56(iii) prescribes that return on equity shall be computed on the equity base determined under Regulation 54 at 14% per annum.
- The Commission applied the equity bases derived above and allowed return on equity accordingly: Rs. 645.35 lakh (pro rata) for 2005–2006 and Rs. 980.63 lakh for each year 2006–2009.
Interest on Loan — Normative Computation and Weighted Average Rate
- Regulation 56(i) was applied: interest on loan is to be computed loan-wise on loans arrived at under Regulation 54; loan outstanding as on 1.4.2004 computed as gross loan less cumulative repayment admitted; repayments for 2004–2009 to be worked out on normative basis; refinancing considerations; moratorium and treatment of depreciation as repayment, etc., were referenced.
- The petitioner’s method (gross loan opening from 2005–2006, adding loan for additional capitalization, working out weighted average interest rate on actual average loan) was described in the opinion.
- The Commission addressed: (i) usage of loan reconciliation and gross loan on DOCO; (ii) adoption of notional loan arising from additional capitalization; (iii) normative loan and normative repayments and formula application; (iv) treatment of moratorium if normative repayment < depreciation; and (v) application of weighted average interest rate — including specific reference to replacement of a floating rate bridge financing (IOB at 5.90%) by Bond XVII (fixed 7.39%) and subjecting any change/resetting to mutual settlement between parties.
- The Commission produced year-wise interest computations applying weighted average rates (e.g., interest allowed: Rs. 945.73 lakh for 2005–2006 (pro rata), Rs. 1,375.41 lakh for 2006–2007, Rs. 1,290.89 lakh for 2007–2008, Rs. 1,183.63 lakh for 2008–2009). Annexure I contains detailed loan-wise weighted interest calculations as relied upon by the Commission.
Depreciation
- The Commission applied Regulation 56(ii) sub-clause (a): historical cost basis, straight-line depreciation using Appendix II rates, residual value 10% (maximum 90% depreciable), land excluded, depreciation from first year pro rata where part-year operation.
- The petitioner claimed depreciation on capital cost of Rs. 24,777.37 lakh. The Commission computed a gross depreciable value equal to 90% of the relevant capital base and applied a depreciation rate of 2.7192% to arrive at depreciation amounts: Rs. 446.29 lakh (pro rata for 1.8.2005–31.3.2006) and Rs. 677.99 lakh in each year 2006–2009.
Advance Against Depreciation (AAD)
- The opinion applied sub-clause (b) of clause (ii) of Regulation 56 which prescribes calculation of AAD as the loan repayment amount subject to a ceiling of one-tenth of loan less depreciation as per schedule, and that AAD is permitted only when cumulative repayment exceeds cumulative depreciation.
- The Commission computed 1/10th of gross loan, normative repayments and compared with depreciation to determine AAD year-by-year. The resulting AAD allowed was: 0.00 (2005–2006 pro rata), Rs. 185.75 lakh (2006–2007), Rs. 329.32 lakh (2007–2008) and Rs. 830.72 lakh (2008–2009), as presented in the opinion's tabulation.
Operation & Maintenance (O&M) Expenses
- The Commission applied Regulation 56(iv) norms prescribing O&M expenses per ckt-km and per bay for the relevant years (tabulated in the opinion).
- The petitioner’s claimed O&M for 432.3 ckt-km and 12 bays was accepted in computation. The resulting O&M allowed was Rs. 302.02 lakh (2005–2006 pro rata), Rs. 471.39 lakh (2006–2007), Rs. 489.80 lakh (2007–2008) and Rs. 509.79 lakh (2008–2009).
- The petitioner raised a point about prospective wage revision effective 1.1.2007 and sought revision/allowance; the Commission recorded the request, noted that it does not arise at this stage and left the petitioner free to approach for relief as appropriate in law.
Interest on Working Capital
- The Commission applied Regulation 56(v) components: maintenance spares @1% of historical cost escalated @6% p.a.; O&M expenses for one month; receivables equivalent to two months' average billing on target availability; and normative rate of interest equal to SBI short-term PLR as on the relevant 1 April.
- Using the historical cost on DOCO Rs. 24,333.47 lakh, maintenance spares as on 1.8.2005 were computed (Rs. 243.33 lakh). Receivables and O&M components were computed as per regulation.
- The petitioner claimed and the Commission allowed interest on working capital at 10.25% (SBI PLR as on 1.4.2005), yielding interest figures of Rs. 60.20 lakh (2005–2006 pro rata), Rs. 94.64 lakh (2006–2007), Rs. 97.73 lakh (2007–2008) and Rs. 106.78 lakh (2008–2009) in the Commission's calculations.
Final Transmission Charges and Related Orders
- The Commission summarized and allowed the transmission charges for each year, aggregating depreciation, interest on loan, return on equity, advance against depreciation, interest on working capital and O&M expenses. The totals allowed were: Rs. 2,399.60 lakh (2005–2006 pro rata), Rs. 3,785.80 lakh (2006–2007), Rs. 3,866.37 lakh (2007–2008) and Rs. 4,289.55 lakh (2008–2009).
- The Commission recorded that, in addition to these transmission charges, the petitioner is entitled to other charges such as income-tax, incentive, surcharge and other cess and taxes in accordance with the 2004 regulations.
- On reimbursement: the petitioner’s expenditure of Rs. 127,224 for publication of statutory notices was accepted for reimbursement and the petitioner was directed to claim reimbursement directly from the respondent in one installment. The petitioner’s claim for reimbursement of the filing fee of Rs. 5 lakh was left open pending a final view by the Commission after stakeholder comments; the view adopted after consideration of comments will apply to the present case.
- The Commission ordered that provisional billing being carried out in accordance with its earlier order dated 13.2.2006 (Petition No. 137/2005) shall be adjusted in the light of the final tariff now approved.
Holding and Implications
Core Ruling: The petition for approval of final tariff for the 400 kV D/C Madurai–Thiruvananthapuram Transmission System for the period 1.8.2005 to 31.3.2009 is allowed in the terms and on the computations recorded in the opinion. This order disposes of Petition No. 136/2006.
Direct Consequences for the Parties
- The Commission allowed additional capitalization of Rs. 600.21 lakh for 2005–2006 as within original scope and on account of committed liability.
- The Commission adopted the specific capital cost, debt-equity treatment, and year-wise components (depreciation, interest on loan, return on equity, advance against depreciation, interest on working capital and O&M) as set out in the opinion and summarized in the year-wise totals: Rs. 2,399.60 lakh (2005–2006 pro rata), Rs. 3,785.80 lakh (2006–2007), Rs. 3,866.37 lakh (2007–2008) and Rs. 4,289.55 lakh (2008–2009).
- The petitioner may claim reimbursement of the publication cost (Rs. 127,224) directly from the respondent in one installment; the filing fee reimbursement (Rs. 5 lakh) remains subject to the Commission's final policy position after stakeholder comments.
- Provisional bills already issued shall be adjusted against the final tariff allowed by this order.
- The petitioner remains entitled to additional statutory items (income-tax, incentive, surcharge, cess and other taxes) as per the 2004 regulations.
Broader Implications
The opinion applies and interprets the 2004 regulations to the facts of this project but does not announce a novel legal precedent beyond its application of the regulations to the factual matrix. No separate case-law precedents were cited. The decision primarily resolves the concrete tariff components, allocative treatment of additional capitalization, debt-equity treatment for admitted additional capitalization, and the procedural outcome on reimbursement claims.
Administrative closure: The order closes Petition No. 136/2006 and records computations in annexures (loan-wise weighted interest calculations and summary sheet) forming part of the tariff determination.
The petition has been filed for approval of tariff for 400 kV D/C Madurai-Thiruvananthapuram Transmission System (the transmission system) in Southern Region for the period from 1.8.2005 to 31.3.2009, based on the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004, (hereinafter referred to as “the 2004 regulations”) after accounting for additional capitalization of Rs. 600.21 lakh during 2005–2006. The petitioner has also prayed for the reimbursement of expenditure from the beneficiaries incurred towards publishing notices in newspapers and the petition filing fee.
2. The investment approval for the transmission system was accorded by the Board of Directors of the petitioner company under Memo dated 22.11.2000 at an estimated cost of Rs. 19597 lakh, which included IDC of Rs. 2371 lakh. Subsequently, the revised cost estimates were approved by the Board of Directors of the petitioner company as per Memorandum dated 30.1.2006 for Rs. 26003 lakh, including IDC of Rs. 3422 lakh.
3. The provisional transmission charges for the transmission system were approved by the Commission in its order dated 13.2.2006 in Petition No. 137/2005. The present petition is for approval of final tariff from the date of commercial operation.
4. The petitioner has claimed the transmission charges as under:
(Rs. in lakh)
2005-2006 (Pro rata) 2006-2007 2007-2008 2008-2009 Depreciation 446.29 677.99 677.99 677.99 Interest on Loan 955.70 1378.65 1294.15 1188.07 Return on Equity 645.35 980.63 980.63 980.63 Advance against Depreciation 0.00 185.75 328.97 801.89 Interest on Working Capital 60.37 94.70 97.78 106.36 O & M Expenses 302.02 471.39 489.80 509.79 Total 2409.73 3789.10 3869.32 4264.73
5. The details submitted by the petitioner in support of its claim for interest on working capital are given hereunder:
(Rs. in lakh)
2005-2006 (Pro rata) 2006-2007 2007-2008 2008-2009 Maintenance Spares 243.33 253.07 268.25 284.35 O & M expenses 37.75 39.28 40.82 42.48 Receivables 602.43 631.52 644.89 710.79 Total 883.52 923.87 953.96 1037.62 Rate of Interest 10.25% 10.25% 10.25% 10.25% Interest 60.37 94.70 97.78 106.36
6. The reply to the petition has been filed by Karnataka Power Transmission Corporation Ltd. and Tamil Nadu Electricity Board. No comments or suggestions have been received from the general public in response to the notices published by the petitioner under section 64 of the Electricity Act, 2003.
CAPITAL COST
7. As per clause (1) of Regulation 52 of the 2004 regulations, subject to prudence check, the actual expenditure incurred on completion of the project shall form the basis for determination of final tariff. The final tariff shall be determined based on the admitted capital expenditure actually incurred up to the date of commercial operation of the transmission system and shall include capitalised initial spares subject to a ceiling norm as 1.5% of original project cost. The regulation is applicable in case of the transmission system declared under commercial operation on or after 1.4.2004
8. The petitioner has claimed additional capitalization of Rs. 600.21 lakh on works for the period from 1.8.2005 to 31.3.2006 over the capital expenditure of Rs. 24333.47 lakh as on the date of commercial operation.
Additional capitalization -2005-2006
9. Clause (1) of Regulation 53 of the 2004 regulations provides—
“(1) The following capital expenditure within the original scope of work actually incurred after the date of commercial operation and up to the cut off date may be admitted by the Commission, subject to prudence check:
(i) Deferred liabilities;
(ii) Works deferred for execution;
(iii) Procurement of initial capital spares in the original scope of works subject to the ceiling norm specified in regulation 52;
(iv) Liabilities to meet award of arbitration or compliance of the order or decree of a court; and
(v) On account of change in law:
Provided that original scope of work along with estimates of expenditure shall be submitted along with the application for provisional tariff:
Provided further that a list of the deferred liabilities and works deferred for execution shall be submitted along with the application for final tariff after the date of commercial operation of the transmission system.”
10. The details submitted by the petitioner in support of its claim for additional capital expenditure are given hereunder:
Year Nature of expenditure 2005-2006 Building and other Civil works = Rs. 169.63 lakh PLCC = Rs. 87.03 lakh Transmission line = Rs. 343.55 lakh Total = Rs. 600.21 lakh
11. The additional capital expenditure claimed is within the original scope of work and is found to be in order as it was against the committed liability. Accordingly, the additional capital expenditure of Rs. 600.21 lakh has been allowed.
Time Over run
12. The transmission system was scheduled to be commissioned by October 2003. However, it was declared under commercial operation on 1.8.2005 Thus, there is delay of about 21 months in the commissioning. The petitioner has explained that transmission line passes through the States of Tamil Nadu and Kerala, with approximate length of 142 kms in the State of Tamil Nadu and approximate length of 74 kms in the State of Kerala. All major activities in the Tamil Nadu portion was completed. As regards the Kerala portion, 86 foundations and 46 towers were erected out of total number of 221 by February 2002, when survey work was stopped in two villages, Kulathupuzha and Chithara, affecting about 30 Kms of transmission line (around 100 locations). The villagers were demanding diversion of the transmission line from the non-forest land to the forest land. The matter was taken up by the petitioner with District Magistrate, Kollam. In May 2002. The villagers filed case in Kerala High Court. The District Magistrate and the High Court issued separate orders in July 2002 and December 2002 respectively allowing the petitioner to commence work. However, land owners of these villages formed an action council and again stopped the work. The petitioner took up the matter with Secretary, Power, Chief Secretary and Power Minister, Govt. of Kerala. Thereafter, the concerned Minister, Govt. of Kerala convened a meeting with MLAs, Village Panchayat leaders on 2 May, 2003 to resolve the problem amicably. After detailed deliberations, a Govt. order dated 16.5.2003 was issued constituting a Committee to go into the questions. Upon submission of report by the Committee, Govt. of Kerala issued order dated 23.8.2003 advising the petitioner to divert the route. The petitioner is said to have lodged its protest vide letter dated 27.8.2003 and finally Govt. of Kerala issued an order dated 22.9.2003 grating approval to the route originally proposed by the petitioner, after which the work in these areas was resumed on 26.9.2003 The local public raised objections again and thereafter Deputy Collector, Kollam, convened a meeting on 6.11.2003 and the matter was resolved to mark the corridor before taking up work. However, the work was stopped again on 9.12.2003 by the public demanding compensation amount to be finalized first and distributed before resuming the work. The Minister for Power, Govt. of Kerala is stated to have convened a fresh meeting on 27.12.2003 and gave direction to District Collector, Thiruvanananthapuram to finalize the rate for compensation for cash crops like rubber, coconut spices etc. in consultation with Rubber Board, Agriculture Department and Spices Board as demanded by the public. During the meeting, the Minister also concluded to pay user fee for the tower location area in line with the procedures followed by KSEB and in line with order of High Court of Kerala. It was also decided that the compensation needed to be finalized and trees were to be removed within three weeks from the date of preparation of Tree Enumeration. Subsequently, the villagers with the support of Action Council members of the affected villages stopped all the construction activities on 29.1.2004 The matter was again taken by the CMD, Powergrid with the Chief Minister, Kerala on 3.2.2004 and intimation was also sent to Secretary (Power), Government of India. Subsequently, a meeting was held on 23.2.2004 with Minister of Energy, Kerala. In the meeting the guidelines for fixing the compensation were approved so as to complete the work on urgent basis. The Action Council members were informed by the Minister that the construction work should be resumed immediately, all cooperation must be extended to complete the transmission line in a time bound manner in May 2004 itself and work should not be disrupted at any cost. Even after the above resolution, the work was not allowed to be resumed by the Action Council members who were demanding compensation amount before commencement of work. The officials of the petitioner reportedly met the Principal Secretary Power on 12.4.2004 and apprised him of the persisting ROW problems, hindering the progress of work. A request to deploy additional revenue staff for early assessment of the compensation amount was also made by the petitioner. The copies of communication exchanged between petition and authorities concerned have been placed on records by the petition.
13. The above factual background shows that the whole process of stoppage of work in February 2002 to the finalization of modalities for fixation of compensation in March 2004 has consumed more that two years time, due to which commissioning of the transmission system got delayed. Therefore, the overall impact of the delay of 21 months with reference to investment approval is not attributable to the petitioner.
TOTAL CAPITAL COST
14. Against the above background, gross block of Rs. 24933.68 lakh as on 31.3.2006 has been worked out for the purpose of tariff over the gross block of Rs. 24333.47 lakh as on the date of commercial operation.
DEBT-EQUITY RATIO
15. Clause (2) of Regulation 54 of the 2004 regulations inter alia provides that,—
“(2) In case of the transmission system for which investment approval was accorded prior to 1.4.2004 and which are likely to be declared under commercial operation during the period 1.4.2004 to 31.3.2009, debt and equity in the ratio of 70:30 shall be considered:
Provided that where equity actually employed to finance the project is less then 30%, the actual debt and equity shall be considered for determination of tariff:
Provided further that the Commission may in appropriate cases consider equity higher than 30% for determination of tariff, where the transmission licensee is able to establish to the satisfaction of the Commission that deployment of equity higher than 30% was in the interest of general public.”
16. The Note 1 below Regulation 53 lays own that any expenditure on account of committed liabilities within the original scope of work is to be serviced in the normative debt-equity ratio specified in Regulation 54.
17. The petitioner has considered debt-equity ratio of 71.95:28.05 as actually deployed on the date of commercial operation. The petitioner has further considered entire amount of additional capitalization against loan. We have considered the debt-equity ratio of 71.95:28.05 on the date of commercial operation. The additional capitalisation on works of Rs. 600.21 lakh has been segregated into debt and equity in the normative debt-equity ratio of 70:30 in view of Note 1 below Regulation 53. Accordingly, for the purpose of tariff, an amount of Rs. 6824.47 lakh has been considered as equity as on 1.8.2005 and Rs. 7004.53 lakh as on 1.4.2006
RETURN ON EQUITY
18. As per clause (iii) of Regulation 56 of the 2004 regulations, return on equity shall be computed on the equity base determined in accordance with regulation 54 @ 14% per annum. Equity invested in foreign currency is to be allowed a return in the same currency and the payment on this account is made in Indian Rupees based on the exchange rate prevailing on the due date of billing.
19. The petitioner has claimed return on equity of Rs. 6824.47 lakh. For the reasons recorded in para 17 above equity of Rs. 6824.47 lakh has been considered as on 1.8.2005 and from 1.4.2006 onwards, equity of Rs. 7004.53 lakh has been considered each year. However, tariff for the period 1.8.2005 to 31.3.2006 has been allowed on average equity of Rs. 6914.50 lakh. Accordingly, the petitioner shall be entitled to return on equity of Rs. 645.35 lakh during 200506 on pro rata basis and Rs. 980.63 lakh each year during 2006–2009.
INTEREST ON LOAN
20. Clause (i) of regulation 56 of the 2004 regulations inter alia provides that,—
“(a) Interest on loan capital shall be computed loan wise on the loans arrived at in the manner indicated in regulation 54.
(b) The loan outstanding as on 1.4.2004 shall be worked out as the gross loan in accordance with Regulation 54 minus cumulative repayment as admitted by the Commission or any other authority having power to do so, up to 31.3.2004 The repayment for the period 2004–2009 shall be worked out on a normative basis.
(c) The transmission licensee shall make every effort to re-finance the loan as long as it results in net benefit to the beneficiaries. The costs associated with such re-financing shall be borne by the beneficiaries.
(d) The changes to the loan terms and conditions shall be reflected from the date of such re-financing and benefit passed on to the beneficiaries.
(e) In case of dispute, any of the parties may approach the Commission with proper application. However, the beneficiaries shall not withhold any payment ordered by the Commission to the transmission licensee during pendency of any dispute relating to re-financing of loan;
(f) In case any moratorium period is availed of by the transmission licensee, depreciation provided for in the tariff during the years of moratorium shall be treated as repayment during those years and interest on loan capital shall be calculated accordingly.
(g) The transmission licensee shall not make any profit on account of re-financing of loan and interest on loan;
(h) The transmission licensee may, at its discretion, swap loans having floating rate of interest with loans having fixed rate of interest, or vice versa, at its own cost and gains or losses as a result of such swapping shall accrue to the transmission licensee:
Provided that the beneficiaries shall be liable to pay interest for the loans initially contracted, whether on floating or fixed rate of interest.”
21. The petitioner has claimed interest on loan in the following manner:
(i) Gross loan opening has been considered from 2005–2006.
(ii) Gross loans drawn for additional capital expenditure during 2005–2006 has been added to the gross loan up to date of commercial operation.
(iii) On the basis of actual rate of interest on actual average loan, the weighted average rate of interest on loan is worked out for various years.
(iv) Weighted average rate of interest on loan for respective years as per above has been has been multiplied to arrive at interest on loan.
22. In our calculation, the interest on loan has been worked out as detailed below:
(i) Gross amount of loan, repayment of instalments as per the loan allocation statement for 2005–2006 has been prepared on the basis of loan allocation details submitted by the petitioner and rate of interest as given in the petition. The same is used to work out weighted average rate of interest on actual loan. The gross loan as per loan reconciliation has been considered as gross loan as on date of commercial operation.
(ii) Notional loan arising out of additional capitalization during the year 2005–2006 has been considered.
(iii) Tariff has been worked out considering normative loan and normative repayments. Once the normative loan has been arrived at, it has been considered for all purposes in the tariff. Normative repayment has been worked out by the following formula:
(iv) Moratorium in repayment of loan has been considered with reference to normative loan and if the normative repayment of loan during the year is less than the depreciation during the year, it has been considered as moratorium and depreciation during the year has been deemed as normative repayment of loan during the year.
(v) Weighted average rate of interest on actual loan worked out as per (i) above has been applied on the average loan during the year to arrive at the interest on loan.
(vi) Bridge financing of loan from IOB having a floating rate of interest 5.90% was replaced with Bond XVII having a fixed rate of interest of 7.39%. Therefore, weighted average rate of interest has been arrived at before calculating the interest pertaining to this loan, subject to mutual settlement between the parties in case of any change/resetting of the interest rate during the tariff period.
23. Based on the above, the year-wise details of interest worked out are given hereunder:
(Rs. in lakh)
Details of loan 2005-2006 (Pro rata) 2006-2007 2007-2008 2008-2009 Interest on Loan Opening Gross Loan 17509.00 17929.15 17929.15 17929.15 Cumulative Repayment 288.82 735.11 1598.84 2606.15 Net Loan-Opening 17220.18 17194.04 16330.31 15323.00 Additions due to Additional Capitalisation 420.15 Repayment during the year 446.29 863.73 1007.31 1508.71 Net Loan-Closing 17194.04 16330.31 15323.00 13814.28 Average Loan 17207.11 16762.17 15826.65 14568.64 Weighted Average Rate of Interest on Loan 8.24% 8.21% 8.16% 8.12% Interest 945.73 1375.41 1290.89 1183.63
24. The detailed calculations in support of the weighted average rate of interest are contained in Annexure I attached.
DEPRECIATION
25. Sub-clause (a) of clause (ii) of Regulation 56 of the 2004 regulations provides for computation of depreciation in the following manner, namely:
(i) The value base for the purpose of depreciation shall be the historical cost of the asset.
(ii) Depreciation shall be calculated annually based on straight line method over the useful life of the asset and at the rates prescribed in Appendix II to these regulations. The residual value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the historical capital cost of the asset. Land is not a depreciable asset and its cost shall be excluded from the capital cost while computing 90% of the historical cost of the asset. The historical capital cost of the asset shall include additional capitalisation on account of Foreign Exchange Rate Variation up to 31.3.2004 already allowed by the Central Government/Commission.
(iii) On repayment of entire loan, the remaining depreciable value shall be spread over the balance useful life of the asset.
(iv) Depreciation shall be chargeable from the first year of operation. In case of operation of the asset for part of the year, depreciation shall be charged on pro rata basis.
26. The petitioner has claimed the depreciation on the capital cost of Rs. 24777.37 lakh.
27. The gross depreciable value of the transmission system is 0.9 × (Rs. 24777.37 lakh-) = Rs. 22299.63 lakh.
28. Depreciation works out to Rs. 446.29 lakh for the period 1.8.2005 to 31.3.2006 on average gross block of Rs. 24633.58 and Rs. 677.99 lakh each year for the period 1.4.2006 to 31.3.2009 on gross block of Rs. 24777.37 lakh by applying rate of depreciation of 2.7192% as shown below:
(Rs. in lakh)
Details of Depreciation 2005-2006 (Pro rata) 2006-2007 2007-2008 2008-2009 Gross block at the beginning of the period 24333.47 24933.68 24933.68 24933.68 Additional Capitalisation during the period 600.21 24933.68 24933.68 24933.68 24933.68 Gross Block at the end of the period 24333.47 24933.68 24933.68 24933.68 Rate of Depreciation 2.7192% 2.7192% 2.7192% 2.7192% Depreciable Value (90%) 21772.90 22043.00 22043.00 22043.00 Balance Useful life of the asset — — — — Remaining Depreciable Value 21772.90 21596.71 20732.97 19725.66 Depreciation 446.29 677.99 677.99 677.99
ADVANCE AGAINST DEPRECIATION
29. As per sub-clause (b) of clause (ii) of Regulation 56 of the 2004 regulations, in addition to allowable depreciation, the transmission licensee is entitled to Advance Against Depreciation, computed in the manner given hereunder:
AAD = Loan repayment amount as per regulation 56(i) subject to a ceiling of 1/10th of loan amount as per regulation 54 minus depreciation as per schedule
30. It is provided that Advance Against Depreciation shall be permitted only if the cumulative repayment up to a particular year exceeds the cumulative depreciation up to that year. It is further provided that Advance Against Depreciation in a year shall be restricted to the extent of difference between cumulative repayment and cumulative depreciation up to that year.
31. The petitioner has claimed Advance Against Depreciation in the following manner:
(i) 1/10th of gross loan considered for tariff computation.
(ii) Cumulative loan as well as repayment of notional loan considered during the year.
(iii) Depreciation as claimed in the petition.
32. In our calculation, Advance Against Depreciation has been worked as under:
(i) 1/10th of gross loan has been worked out from the gross notional loan as per para 23 above.
(ii) Repayment of notional loan during the year has been considered as per para 23 above.
(iii) Depreciation as worked out as per para 28 has been taken into account.
33. The details of Advance Against Depreciation allowed for the transmission scheme is given hereunder:
(Rs. in lakh)
Details of Advance Against Depreciation 2005-2006 2006-2007 2007-2008 2008-2009 1/10th of Gross Loan(s) 1750.90 1792.91 1792.91 1792.91 Repayment of Loan 446.29 863.73 1007.31 1508.71 Minimum of the above 446.29 863.73 1007.31 1508.71 Depreciation during the year 446.29 677.99 677.99 677.99 (A) Difference 0.00 185.75 329.32 830.72 Cumulative Repayment of the Loan 735.11 1598.84 2606.15 4114.86 Cumulative Depreciation/Advance against Depreciation 446.29 1124.28 1988.01 2995.32 (B) Difference 288.82 474.56 618.14 1119.54 Advance Against Depreciation Minimum of (A) and (B) 0.00 185.75 329.32 830.72
OPERATION & MAINTENANCE EXPENSES
34. In accordance with clause (iv) of Regulation 56 the 2004 regulations, the following norms are prescribed for O & M expenses
Year 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 O&M expenses (Rs. in lakh per ckt-km) 0.227 0.236 0.246 0.255 0.266 O&M expenses (Rs in lakh per bay) 28.12 29.25 30.42 31.63 32.90
35. The petitioner has claimed O & M expenses for 432.3 ckt km and 12 bays, which have been allowed. Accordingly, the petitioner's entitlement to O & M expenses has been worked out as given hereunder:
Year 2005-2006 (Pro rata) 2006-2007 2007-2008 2008-2009 O&M expenses for 432.3 ckt kms line length 68.02 106.35 110.24 114.99 O&M expenses for 12 bays 234.00 365.04 379.56 394.80 Total 302.02 471.39 489.80 509.79
36. The petitioner has submitted that the wage revision of its employees is due with effect from 1.1.2007 Therefore, O & M expenses should be subject to revision on account of revision of employee cost from that date. In the alternative, it has been prayed that the increase in employee cost due to wage revision be allowed as per actuals for extra cost to be incurred consequent to wage revision. We are not expressing any view, as this issue does not arise for consideration at this stage. The petitioner may approach for a relief in this regard at an appropriate stage in accordance with law.
INTEREST ON WORKING CAPITAL
37. The components of the working capital and the interest thereon are discussed hereunder:
(i) Maintenance spares
Regulation 56(v)(1)(b) of the 2004 regulations provides for maintenance spares @ 1% of the historical cost escalated @ 6% per annum from the date of commercial operation. In the present case, the capital expenditure on the date of commercial operation is Rs. 24333.47 lakh, which has been considered as the historical cost for the purpose of the present petition and maintenance spares have been worked out accordingly by escalating 1% of the historical cost @ 6% per annum. In this manner, the value of maintenance spares works out to Rs. 243.33 lakh as on 1.8.2005
(ii) O & M expenses
Regulation 56(v)(1)(a) of the 2004 regulations provides for operation and maintenance expenses for one month as a component of working capital. The petitioner has claimed O & M expenses for 1 month of O & M expenses of the respective year as claimed in the petition. This has been considered in the working capital.
(iii) Receivables
As per Regulation 56(v)(1)(c) of the 2004 regulations, receivables will be equivalent to two months average billing calculated on target availability level. The petitioner has claimed the receivables on the basis 2 months' transmission charges claimed in the petition. In the tariff being allowed, receivables have been worked out on the basis 2 months' transmission charges.
(iv) Rate of interest on working capital
As per Regulation 56(v)(2) of the 2004 regulations, rate of interest on working capital shall be on normative basis and shall be equal to the short-term Prime Lending Rate of State Bank of India as on 1.4.2004 or on 1st April of the year in which the project or part thereof (as the case may be) is declared under commercial operation, whichever is later. The interest on working capital is payable on normative basis notwithstanding that the transmission licensee has not taken working capital loan from any outside agency. The petitioner has claimed interest on working capital @ 10.25% based on SBI PLR as on 1.4.2005, which is in accordance with the 2004 regulations and has been allowed.
38. The necessary computations in support of interest on working capital are appended hereinbelow:
(Rs. in lakh)
2005-2006 (Pro rata) 2006-2007 2007-2008 2008-2009 Maintenance Spares 243.33 253.07 268.25 284.35 O & M expenses 37.75 39.28 40.82 42.48 Receivables 599.90 630.97 644.39 714.92 Total 880.99 923.32 953.46 1041.75 Rate of Interest 10.25% 10.25% 10.25% 10.25% Interest 60.20 94.64 97.73 106.78
TRANSMISSION CHARGES
39. The capital cost and other relevant details are contained in the summary sheet attached as Annexure II. The transmission charges being allowed for the transmission system are summarised below:
(Rs. in lakh)
2005-2006 (Pro rata) 2006-2007 2007-2008 2008-2009 Depreciation 446.29 677.99 677.99 677.99 Interest on Loan 945.73 1375.41 1290.89 1183.63 Return on Equity 645.35 980.63 980.63 980.63 Advance against Depreciation 0.00 185.75 329.32 830.72 Interest on Working Capital 60.20 94.64 97.73 106.78 O & M Expenses 302.02 471.39 489.80 509.79 Total 2399.60 3785.80 3866.37 4289.55
40. In addition to the transmission charges, the petitioner shall be entitled to other charges like income-tax, incentive, surcharge and other cess and taxes in accordance with the 2004 regulations.
41. The petitioner has sought approval for the reimbursement of expenditure of Rs. 1,27,224/- incurred on publication of notices in the newspapers. The petitioner shall claim reimbursement of the said expenditure directly from the respondent in one installment. The petitioner has also sought reimbursement of filing fee of Rs. 5 lakh paid. A final view on reimbursement of filing fee is yet to be taken by the Commission for which views of the stakeholder have been called for. The view taken on consideration of the comments received shall apply in the present case as regards reimbursement of filing fee.
42. The petitioner is already billing the respondents on provisional basis in accordance with the Commission's order dated 13.2.2006 in Petition No. 137/2005. The provisional billing of tariff shall be adjusted in the light of final tariff now approved by us.
43. This order disposes of Petition No. 136/2006.
Annexure I
Calculation of Weighted Average Rate of Interest on Loan
Details of Loan 2005-2006 2006-2007 2007-2008 2008-2009 1 Bond-IX Gross Loan opening 112.00 112.00 112.00 112.00 Cumulative Repayment upto DOCO/previous year 22.40 33.60 44.80 56.00 Net Loan-Opening 89.60 78.40 67.20 56.00 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 11.20 11.20 11.20 11.20 Net Loan-Closing 78.40 67.20 56.00 44.80 Average Loan 84.00 72.80 61.60 50.40 Rate of Interest 12.25% Interest 10.29 8.92 7.55 6.17 Repayment Schedule 10 Annual instalments from 22.8.2003 2 Bond-X Gross Loan opening 1066.00 1066.00 1066.00 1066.00 Cumulative Repayment up to DOCO/previous year 177.67 177.67 266.50 355.33 Net Loan-Opening 888.33 888.33 799.50 710.67 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 0.00 88.83 88.83 88.83 Net Loan-Closing 888.33 799.50 710.67 621.83 Average Loan 888.33 843.92 755.08 666.25 Rate of Interest 10.90% Interest 96.83 91.99 82.30 72.62 Repayment Schedule 12 Annual instalments from 21.6.2004 3 Bond-XI Option-I Gross Loan opening 1052.00 1052.00 1052.00 1052.00 Cumulative Repayment up to DOCO/previous year 0.00 87.67 175.33 263.00 Net Loan-Opening 1052.00 964.33 876.67 789.00 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 87.67 87.67 87.67 87.67 Net Loan-Closing 964.33 876.67 789.00 701.33 Average Loan 1008.17 920.50 832.83 745.17 Rate of Interest 9.80% Interest 98.80 90.21 81.62 73.03 Repayment Schedule 12 Annual instalments from 7.12.2005 4 Bond-XII Gross Loan opening 1874.00 1874.00 1874.00 1874.00 Cumulative Repayment up to DOCO/previous year 0.00 156.17 312.34 468.50 Net Loan-Opening 1874.00 1717.83 1561.66 1405.50 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 156.17 156.17 156.17 156.17 Net Loan-Closing 1717.83 1561.66 1405.50 1249.33 Average Loan 1795.92 1639.75 1483.58 1327.41 Rate of Interest 9.70% Interest 174.20 159.06 143.91 128.76 Repayment Schedule 12 Annual instalments from 28.3.2006 5 Bond-XIII Option-I Gross Loan opening 5000.00 5000.00 5000.00 5000.00 Cumulative Repayment up to DOCO/previous year 0.00 0.00 416.67 833.33 Net Loan-Opening 5000.00 5000.00 4583.33 4166.67 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 0.00 416.67 416.67 416.67 Net Loan-Closing 5000.00 4583.33 4166.67 3750.00 Average Loan 5000.00 4791.67 4375.00 3958.33 Rate of Interest 8.63% Interest 431.50 413.52 377.56 341.60 Repayment Schedule 12 Annual instalments from 31.7.2006 6 Bond-XV Gross Loan opening 1690.00 1690.00 1690.00 1690.00 Cumulative Repayment up to DOCO/previous year 0.00 0.00 0.00 140.83 Net Loan-Opening 1690.00 1690.00 1690.00 1549.17 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 140.83 140.83 Net Loan-Closing 1690.00 1690.00 1549.17 1408.33 Average Loan 1690.00 1690.00 1619.58 1478.75 Rate of Interest 6.68% Interest 112.89 112.89 108.19 98.78 Repayment Schedule 12 Annual instalments from 23-2-2008 7 Bond-XVI Gross Loan opening 4650.00 4650.00 4650.00 4650.00 Cumulative Repayment up to DOCO/previous year 0.00 0.00 0.00 0.00 Net Loan-Opening 4650.00 4650.00 4650.00 4650.00 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 465.00 Net Loan-Closing 4650.00 4650.00 4650.00 4185.00 Average Loan 4650.00 4650.00 4650.00 4417.50 Rate of Interest 7.10% Interest 330.15 330.15 330.15 313.64 Repayment Schedule 10 Annual instalments from 18-2-2009 8 Bond-XVII Gross Loan opening 1000.00 1000.00 1000.00 1000.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 Net Loan-Opening 1000.00 1000.00 1000.00 1000.00 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 0.00 Net Loan-Closing 1000.00 1000.00 1000.00 1000.00 Average Loan 1000.00 1000.00 1000.00 1000.00 Rate of Interest 7.07% Interest 70.71 70.71 70.71 70.71 Repayment Schedule 10 Annual Instalments from 22.9.2009 10 Bond-XVIII (For ACE) (Date of Drawal 09.03.2006) Gross Loan opening 0.00 30.00 30.00 30.00 Cumulative Repayment up to DOCO/previous year 0.00 0.00 0.00 0.00 Net Loan-Opening 0.00 30.00 30.00 30.00 Additions during the year 30.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 0.00 Net Loan-Closing 30.00 30.00 30.00 30.00 Average Loan 15.00 30.00 30.00 30.00 Rate of Interest 8.15% Interest 1.22 2.45 2.45 2.45 Repayment Schedule 12 annual inatalments from 9.3.2010 11 PNB-II Gross Loan opening 581.00 581.00 581.00 581.00 Cumulative Repayment up to DOCO/previous year 48.42 96.83 145.25 193.67 Net Loan-Opening 532.58 484.17 435.75 387.33 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 48.42 48.42 48.42 48.42 Net Loan-Closing 484.17 435.75 387.33 338.92 Average Loan 508.38 459.96 411.54 363.13 Rate of Interest 8.60% Interest 43.72 39.56 35.39 31.23 Repayment Schedule 12 Annual Instalments from 8.3.2005 12 OBC Gross Loan opening 484.00 484.00 484.00 484.00 Cumulative Repayment up to DOCO/previous year 40.33 80.67 121.00 161.33 Net Loan-Opening 443.67 403.33 363.00 322.67 Additions during the year 0.00 0.00 0.00 0.00 Repayment during the year 40.33 40.33 40.33 40.33 Net Loan-Closing 403.33 363.00 322.67 282.33 Average Loan 423.50 383.17 342.83 302.50 Rate of Interest 8.60% Interest 36.42 32.95 29.48 26.02 Repayment Schedule 12 Annual Instalments from 22.3.2005 Total Loan Gross Loan opening 17509.00 17539.00 17539.00 17539.00 Cumulative Repayment up to DOCO/previous year 288.82 632.60 1481.89 2472.00 Net Loan-Opening 17220.18 16906.40 16057.11 15067.00 Additions during the year 30.00 0.00 0.00 0.00 Repayment during the year 343.79 849.28 990.12 1455.12 Net Loan-Closing 16906.40 16057.11 15067.00 13611.88 Average Loan 17063.29 16481.76 15562.06 14339.44 Rate of Interest 8.24% 8.21% 8.16% 8.12% Interest 1406.74 1352.40 1269.31 1165.01
Summary Sheet Name of the Company: PGCIL Name of the Element: 400 KV Sub-Station at Thiruvananthapuram and 400 KV D/C Madurai-Thiruvananthapuram Transmission Line Actual DOCO: 1.8.2005 Petition No.: 136/2006 Tariff setting Period: 2004-09 (Rs. in lakh) 1 Capital Cost of the Project as on DOCO 24333.47 24333.47 2 Additional Capitalization 600.21 For the year 2005–2006 600.21 Total 600.21 3 Total Capital Cost as on 1.4.2006 (1+2) 24933.68 4 Means of Finance: As on DOCO As on 1.4.2006 Debt 71.95% 17509.00 71.95% 17929.15 Equity 28.05% 6824.47 28.09% 7004.53 Total 100.00% 24333.47 100.00% 24933.68 5 Gross Loan: As on DOCO As on DOCO Notional Loan corresponding to ACE during 2005–2006 As on 1.4.2006 17509.00 420.15 Up to DOCO 3826.04674 17929.15 From DOCO to 31.3.2009 Total 0.00 6 Cumulative Repayment up to 31.3.2009: Dep 3826.05 3826.05 2480.25 3826.05 3826.04674 From DOCO to 31.3.2009 7 Balance Loan to be repaid beyond 31.3.2009: Total AAD Total 14103.10 8 Depreciation recovered up to 31.3.2009: 1345.79 3826.05 3826.05 Capital cost for the purpose of Depreciation 3826.05 ACE during 2005–2006 24333.47 9 Balance Depreciation to be recovered beyond 31.3.2009: Capital cost as 1.4.2006 18216.95 Less: Land Cost 600.21 24933.68 90% of Capital Cost as above 441.46 Cum. Depreciation to be recovered up to 31.32.2009 24492.22 Balance Depreciation to be recovered beyond 31.3.2009 22043.00 3826.05 18216.95
Alert