M/S Reliance Communications Ltd v. Bharat Sanchar Nigam Ltd .
Notice. Mr. Maninder Singh accepts notice on behalf of the respondent and requests for time to file reply. I have heard the counsel for the parties on question of grant of interim relief. The POIs have already been disconnected by the respondent. The Learned counsel for the petitioner prays that a direction be issued for restoration of POIs and he has offered to pay 50% of the amount claimed by the respondent, which is in challenge in this petition, as a condition for restoration of POIs.
Mr. Maninder Singh, appearing for respondent opposes this prayer. According to him petitioner should be directed to deposit full amount claimed by the respondent. He further argues that in any case the Petitioner should be directed to pay a reasonable amount over and above 50% before respondent can be asked to restore the POIs. After hearing the learned counsel for the respondent and in view of certain facts from the documents produced by him, I am of the view that the petitioner should deposit an amount worked out on the basis of 65% of the demand which is under challenge in this petition with the respondent within one week from today and on this amount being deposited, the respondent will restore the POIs within 48 hours thereafter. This order is being passed without prejudice to the rights and contentions of the parties and will be subject to further orders to be passed by this Tribunal in this connection.
Reply to the main petition be filed within 4 weeks from today and rejoinder, if any, be filed within two weeks thereafter.
To be listed on 4 March 2008.
……………………J
(Arun Kumar)
Chairperson