Structured Summary of the Opinion — Petition No. 123/2002

Factual and Procedural Background

The petitioner filed a petition seeking approval of tariff for certain transmission assets — specifically the 400 kV D/C Vijayawada–Nellore line, 400 kV D/C Nellore–Sriperumbudur line, a new 400 kV switching station at Nellore, and extensions (bays) at Vijayawada and Sriperumbudur — under the Southern Region system strengthening scheme for the period 1 March 2003 to 31 March 2004. The petitioner relied on the Commission's notification dated 26 March 2001 for the terms and conditions of tariff determination.

The Central Government (Ministry of Power) accorded investment approval on 5 February 2001 for an estimated cost of Rs. 39,628.00 lakh (1st quarter 2000 price level), including IDC of Rs. 2,900.00 lakh. The investment approval required commissioning within 24 months (by February 2003). The assets were put into commercial operation on 1 March 2003, and the Commission recorded that the transmission assets were commissioned without delay.

The petition sought transmission charges for 2002-2003 (pro rata) and 2003-2004 based on a claimed capital cost; the matter is recorded as disposing Petition No. 123/2002.

Legal Issues Presented

  1. Whether the Commission should approve the tariff for the specified transmission assets for the period 1.3.2003 to 31.3.2004 under the notification dated 26.3.2001.
  2. What capital cost (historical gross block as on date of commercial operation) should be adopted for tariff computation, and whether additional capitalisation up to 31.3.2004 should be considered.
  3. What debt–equity ratio should be applied for tariff purposes (whether the petitioner's actual financing mix may be accepted).
  4. How interest on loan, depreciation, Advance Against Depreciation (AAD), return on equity, operation & maintenance (O&M) expenses, and interest on working capital should be computed in accordance with the notification of 26.3.2001.
  5. Whether the petitioner is entitled to other statutory charges such as income tax, incentives, development surcharge, late payment surcharge, levies, cess and filing fee in addition to transmission charges.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

(In the opinion, the Commission applies the methodology and specific clauses of the notification dated 26.3.2001 step-by-step to the petitioner's submissions and supporting documents.)

  1. Capital Cost and Base for Tariff
    • The notification requires that project cost approved by CEA or an appropriate independent agency (other than the generating company's board) be the basis for tariff; capital cost includes initial spares for first five years and actual expenditure on completion shall generally determine tariff subject to approval for any excesses.
    • The petitioner furnished an auditor's certificate (dated 7.12.2004) showing gross block/expenditure figures. The Commission accepted the gross block of Rs. 33,116.13 lakh as on the date of commercial operation (1.3.2003) for tariff computation.
  2. Additional Capitalisation
    • The notification permits tariff revision within the period if capital expenditure during the tariff period exceeds 20% of the approved cost; otherwise revision is to be considered in the next tariff period.
    • The Commission observed that capital expenditure from the date of commercial operation until 31.3.2004 did not exceed 20% of the approved cost and therefore such expenditure was not considered for the present tariff computation.
  3. Sources of Financing and Debt–Equity Ratio
    • The notification requires financing as per the techno-economic clearance by CEA or an appropriate independent agency. The Central Government's investment approval did not specify a debt–equity ratio.
    • The petitioner claimed an actual debt–equity ratio of 86.79:13.21 (Debt Rs. 28,742.00 lakh; Equity Rs. 4,374.13 lakh); respondents did not oppose this. Accordingly, the Commission used this actual ratio in tariff determination.
  4. Interest on Loan
    • Interest on loan capital is to be computed on outstanding loans taking into account the repayment schedule and the approved financial package. The Commission computed interest by reference to the gross loan amounts, repayment schedules, and interest rates submitted by the petitioner (including floating-rate loans whose prevailing rates as on date of commercial operation were taken).
    • The Commission noted that any subsequent resetting of floating rates would require mutual settlement between parties or an application to the Commission if unresolved.
    • The Commission used the actual loan amount of Rs. 28,742.00 lakh as on the date of commercial operation for its calculations and set out detailed item‑wise loan interest computations in the order.
  5. Depreciation and Weighted Average Rate
    • Depreciation is to be calculated on historical cost by the straight-line method at rates prescribed in the notification, with the total depreciation in the life of the project not exceeding 90% of approved original cost. Depreciation begins from the first year of operation and is pro rata for part years.
    • The petitioner claimed depreciation on capital expenditure figures; the Commission computed depreciation using the gross block of Rs. 33,116.13 lakh (as per the auditor's certificate) and calculated a weighted average rate of depreciation of 2.70%.
    • Depreciation figures allowed by the Commission were: Rs. 74.64 lakh for 2002–2003 (pro rata) and Rs. 895.73 lakh for 2003–2004.
  6. Advance Against Depreciation (AAD)
    • The notification provides that AAD arises when scheduled loan repayment exceeds depreciation; it is computed as the minimum of (scheduled repayment subject to a ceiling of 1/12 of original loan) minus depreciation as per schedule.
    • The petitioner did not claim AAD. The Commission computed the components (1/12th of gross loans, scheduled repayments, depreciation) and concluded the petitioner was not entitled to AAD for the years concerned (AAD = 0.00).
  7. Operation & Maintenance (O&M) Expenses
    • The notification prescribes a methodology (normalisation, five‑year averages, escalation, and per‑unit metrics for line length and bays) for calculating admissible O&M expenses. Where regional normalised values are available, the Commission uses those.
    • The Commission used its previously computed normalized O&M values for the Southern Region, applied the prescribed escalation (6% p.a.), and adjusted for items disallowed in earlier normative computations. The Commission noted that differences between petitioner and Commission NOMLL/NOMBN arose from disallowances explained in other normative calculations.
    • On that basis, the Commission allowed O&M of Rs. 58.88 lakh (2002–2003 pro rata) and Rs. 749.02 lakh (2003–2004).
  8. Return on Equity (RoE)
    • The notification entitles the petitioner to RoE at the rate of 16% per annum. Equity of Rs. 4,374.13 lakh as on 1.3.2003 was considered.
    • RoE allowed: Rs. 58.32 lakh (2002–2003 pro rata) and Rs. 699.86 lakh (2003–2004).
  9. Interest on Working Capital
    • Working capital components per the notification include one month O&M (cash), maintenance spares at a normative rate (1% of capital cost less 1/5th initial spares), and receivables (two months' average billing at 98% availability). The petitioner claimed 11% interest on working capital.
    • The Commission computed working capital on the prescribed basis and allowed interest on working capital at 10.75% (based on annual SBI PLR for 2002–2003, a figure the Commission had allowed in other petitions), resulting in interest of Rs. 11.18 lakh (2002–2003 pro rata) and Rs. 134.43 lakh (2003–2004).
  10. Aggregation and Approval of Transmission Charges
    • Applying the above components (interest on loan, interest on working capital, depreciation, RoE, O&M and AAD), the Commission computed and approved the sanctioned transmission charges for the two periods. The Commission noted the primary reason for the difference between the petitioner's claim and the Commission's allowance: different gross block figures considered for tariff purposes.
    • The Commission also recorded ancillary decisions: the petitioner is entitled to other statutory charges (income tax, incentive, surcharge, cess and taxes) in accordance with the 26.3.2001 notification (subject to directions of superior courts); the petitioner may recover a filing fee of Rs. 2 lakh in five monthly instalments shared by respondents in the same ratio as transmission charges (subject to confirmation that the amount is not already included in O&M); provisional billings already made are to be adjusted against the final approved tariff; and approved charges shall be included in the regional transmission tariff for Southern Region and shared by regional constituents as per the notification.

Holding and Implications

Holding (core ruling): The Commission approved the transmission charges for the specified transmission assets for the periods 2002–2003 (pro rata) and 2003–2004 and disposed of Petition No. 123/2002.

Direct effect on the parties

  • The Commission approved the following transmission charges (Rs. in lakh):
    Component 2002–2003 (Pro rata) 2003–2004
    Interest on Loan230.742,709.51
    Interest on Working Capital11.18134.43
    Depreciation74.64895.73
    Advance Against Depreciation0.000.00
    Return on Equity58.32699.86
    O & M Expenses58.88749.02
    Total433.765,188.55
  • The petitioner is entitled to other charges (income tax, incentive, surcharge, cess and taxes) as per the notification, subject to directions of superior courts.
  • Filing fee recovery: the petitioner may recover Rs. 2 lakh in five monthly instalments of Rs. 40,000 each from respondents, shared in the same ratio as other transmission charges, subject to confirmation that it is not already included in O&M charges.
  • Provisional billings already made by the petitioner are to be adjusted against the final tariff now approved.
  • The approved transmission charges shall be included in the regional transmission tariff for the Southern Region and shared by regional constituents in accordance with the notification dated 26.3.2001.

Broader implications

The order applies and implements the methodology and numeric parameters contained in the Commission's notification dated 26.3.2001 to the petitioner's factual matrix. The opinion does not purport to establish a new legal precedent; it applies the notification's prescribed rules to the specific project data submitted by the petitioner and records administrative directions (e.g., treatment of floating interest resets, recovery of filing fee, and adjustment of provisional billings).

This summary is drawn exclusively from the provided opinion and does not add or infer information beyond the text of that opinion.

Show all summary ...

The petitioner has filed the present petition for approval of tariff for 400 kV D/C Vijayavada - Nellore line, 400 kV D/C Nellore-Sriperumbudur line, New 400 kV switching station at Nellore, and extension of Vijaywada and Sriperumbudur substation with associated bays under the system strengthening scheme in Southern Region (hereinafter referred to as “the transmission assets”) for the period 1.3.2003 to 31.3.2004 based on the terms and conditions for determination of tariff contained in the Commission's notification dated 26.3.2001 (hereinafter referred to as “the notification dated 26.3.2001”).

2. The investment approval for construction of the transmission assets was accorded by the Central Government in Ministry of Power as per letter dated 5.2.2001 at an estimated cost of Rs. 39628.00 lakh (1st quarter 2000 price level), including IDC of Rs. 2900.00 lakh.

3. As per the investment approval, the transmission assets were to be commissioned within a period of 24 months from the date of investment approval by the Central Government, that is, by February 2003. The assets have been put under commercial operation on 1.3.2003 Thus, the transmission assets have been commissioned without any delay.

4. The petitioner, in the present petition, has sought approval for transmission charges for the years 2002-2003 and 2003-2004 based on the notification dated 26.3.2001 based on capital cost of Rs. 34500.39 lakh as under:

(Rs. in lakh)

2002-2003 (Pro rata) 2003-2004 Interest on Loan 230.74 2709.54 Interest on Working Capital 11.70 145.23 Depreciation 75.62 936.96 Advance Against Depreciation 0.00 0.00 Return on Equity 63.12 909.15 O & M Expenses 62.98 801.14 Total 444.18 5502.02

5. In support of its claim for interest on working capital the petitioner has submitted the following details:

(Rs. in lakh)

2002-2003 2003-2004 Spares 325.33 336.48 O & M expenses 62.98 66.76 Receivables 888.35 917.00 Total 1276.66 1320.25 Rate of Interest 11.00% 11.00% Interest 140.43 145.23 Interest (Pro rata) 11.70

6. In addition, the petitioner has prayed for approval of other charges like Income Tax, incentive, Development Surcharge, late payment surcharge, other statutory taxes, levies, cess, filing fee, etc. in terms of the notification.

CAPITAL COST

7. As laid down in the notification dated 26.3.2001, the project cost as approved by CEA or an appropriate independent agency, other than Board of Directors of the generating company, as the case may be, shall be the basis for computation of tariff. The capital cost shall include capitalised initial spares for the first 5 years of operation. The notification dated 26.3.2001 further provides that the actual capital expenditure incurred on completion of the project shall be the criterion for fixation of tariff. Where the actual expenditure exceeds the approved project cost, the excesses as approved by the Authority or an appropriate independent agency, as the case may be, shall be deemed to be the actual capital expenditure for the purpose of determining the tariff, provided that excess expenditure is not attributable to the petitioner or its suppliers or contractors. This is subject to the condition that where a transmission services agreement entered into between the Transmission Utility and the beneficiary provides a ceiling on capital expenditure; the capital expenditure shall not exceed such ceiling.

8. As per the auditor's certificate furnished by the petitioner on 7.12.2004, the estimated completion cost of the transmission assets is Rs. 34,726.52 lakh, including IDC of Rs. 2870.17 lakh, worked out as under:

Expenditure up to date of commercial operation (1.3.2003) :Rs. 33,116.13 lakh Gross block on date of commercial operation :Rs. 33,116.13 lakh Expenditure from date of commercial operation to 31.3.2003 :Rs. 720.23 lakh Gross block as on 31.3.2003 :Rs. 33,836.36 lakh Expenditure from 1.4.2003 to 31.3.2004 :Rs. 664.03 lakh Gross block as on 31.3.2004 :Rs. 34,500.39 lakh Balance anticipated expenditure :Rs. 226.13 lakh Total completion cost :Rs. 34,726.52 lakh Value of mandatory spares included in the above cost is Rs. 47.17 lakh.

9. For the purpose of computation of tariff, the Gross Block of Rs. 33,116.13 lakh as on the date of commercial operation as per the auditor's certificate submitted by the petitioner has been considered.

ADDITIONAL CAPITALISATION

10. The notification dated 26.3.2001 provides that tariff revisions during the tariff period on account of capital expenditure within the approved project cost incurred during the tariff period may be entertained by the Commission if such expenditure exceeds 20% of the approved cost. In all cases, where such expenditure is less than 20%, tariff revision shall be considered in the next tariff period.

11. The capital expenditure from the date of commercial operation till 31.3.2004 has not been considered for the purpose of tariff, as this expenditure does not exceed 20% of the approved capital cost.

SOURCES OF FINANCING. DEBT - EQUITY RATIO

12. As per clause 4.3 of the notification dated 26.3.2001, capital expenditure of the transmission system shall be financed as per approved financial package set out in the techno-economic clearance of CEA or as approved by an appropriate independent agency, as the case may be. The Central Government while according the investment approval has not specified the debt-equity ratio for financing the project. The petitioner has claimed tariff by taking actual debt and equity ratio of 86.79:13.21 This is not opposed by the respondents. Therefore, The same debt-equity ratio has been considered for determination of tariff in the present petition. Necessary details in this regard are extracted below:

Debt: Rs. 28,742.00 lakh Equity: Rs. 4,374.13 lakh Total Rs. 33,116.13 lakh

INTEREST ON LOAN

13. As per clause 4.4(a) of the notification dated 26.3.2001, Interest on loan capital shall be computed on the outstanding loans, duly taking into account the schedule of repayment, as per the financial package approved by CEA or any independent agency.

14. In the calculation, the interest on loan has been worked by considering the gross amount of loan, repayment for the year 2002-2003 and 2003-2004 and rate of interest etc. as per the loan details for the assets commissioned after 31.3.2002 as submitted by the petitioner vide affidavit dated 16.2.2005

15. OBC and PNB II loans carry floating rate of interest and the interest rates as submitted by the petitioner stated to be prevailing as on the date of commercial operation have been taken in the calculation. Any change/resetting of the interest rates of the above loans during the tariff period covered in this petition would require settlement of the same mutually between the parties. In case they are unable to settle the question mutually, any one of them is at liberty to approach the Commission for appropriate decision.

16. For the purpose of tariff we have considered the actual loan of Rs. 28742.00 lakh as on the date of commercial operation.

17. The detailed calculations in support of interest on loan are appended below:

(Rs. in lakh)

Details of Loan 2002-2003 2003-2004 No. of days in the Year 365 366 Bond-X Gross Loan -Opening 5680.00 5680.00 Cumulative Repayment up to Previous Year 0.00 0.00 Net Loan-Opening 5680.00 5680.00 Repayment during the year 0.00 0.00 Net Loan-Closing 5680.00 5680.00 Rate of Interest 10.90% 10.90% Interest 52.58 619.12 Repayment Schedule 12 Annual Instalments from 21.06.2004 Bond XIII (Option-I) Gross Loan -Opening 11000.00 11000.00 Cumulative Repayment up to Previous Year 0.00 0.00 Net Loan-Opening 11000.00 11000.00 Repayment during the year 0.00 0.00 Net Loan-Closing 11000.00 11000.00 Rate of Interest - Bond XIII -Option-II 8.63% 8.63% Interest 80.63 949.30 Repayment Schedule 12 Annual Instalments from 31.07.2006 Bond-IX Gross Loan -Opening 980.00 980.00 Cumulative Repayment up to Previous Year 0.00 0.00 Net Loan-Opening 980.00 980.00 Repayment during the year 0.00 98.00 Net Loan-Closing 980.00 882.00 Rate of Interest 12.25% 12.25% Interest 10.20 112.74 Repayment Schedule 10 Annual Instalments from 22.08.2003 Bond-XI Option I Gross Loan -Opening 5320.00 5320.00 Cumulative Repayment up to Previous Year 0.00 0.00 Net Loan-Opening 5320.00 5320.00 Repayment during the year 0.00 0.00 Net Loan-Closing 5320.00 5320.00 Rate of Interest 9.80% 9.80% Interest 44.28 521.36 Repayment Schedule 12 Annual Instalments from 07.12.2005 Oriental Bank of Commerce Gross Loan -Opening 2449.00 2449.00 Cumulative Repayment up to Previous Year 0.00 0.00 Net Loan-Opening 2449.00 2449.00 Repayment during the year 0.00 0.00 Net Loan-Closing 2449.00 2449.00 Rate of Interest 8.60% 8.60% Interest 17.89 210.61 Repayment Schedule 12 Annual Instalments from 22.03.2005 PNB-II Gross Loan -Opening 2939.00 2939.00 Cumulative Repayment up to Previous Year 0.00 0.00 Net Loan-Opening 2939.00 2939.00 Repayment during the year 0.00 0.00 Net Loan-Closing 2939.00 2939.00 Rate of Interest 8.85% 8.85% Interest 22.09 260.10 Repayment Schedule 12 Annual Instalments from 08.03.2005 Bond-XII Gross Loan -Opening 374.00 374.00 Cumulative Repayment up to Previous Year 0.00 0.00 Net Loan-Opening 374.00 374.00 Repayment during the year 0.00 0.00 Net Loan-Closing 374.00 374.00 Rate of Interest 9.70% 9.70% Interest 3.08 36.28 Repayment Schedule 12 Annual Instalments from 28.03.2006 Total Loan Gross Loan -Opening 28742.00 28742.00 Cumulative Repayment up to Previous Year 0.00 0.00 Net Loan-Opening 28742.00 28742.00 Repayment during the year 0.00 98.00 Net Loan-Closing 28742.00 28644.00 Interest 230.74 2709.51

DEPRECIATION

18. With regard to depreciation, para 4(b) of the notification dated 26.3.2001 provides:

(i) The value base for the purpose of depreciation shall be the historical cost of the asset.

(ii) Depreciation shall be calculated annually as per straight-line method at the rate of depreciation as prescribed in the Schedule attached to the notification.

Provided that the total depreciation during the life of the project shall not exceed 90% of the approved Original Cost. The approved original cost shall include additional capitalisation on account of foreign exchange rate variation also.

(iii) On repayment of entire loan, the remaining depreciable value shall be spread over the balance useful life of the asset.

(iv) Depreciation shall be chargeable from the first year of operation. In case of operation of the asset for part of the year, depreciation shall be charged on pro-rata basis.

(v) Depreciation against assets relating to environmental protection shall be allowed on case-to-case basis at the time of fixation of tariff subject to the condition that the environmental standards as prescribed have been complied with during the previous tariff period.

19. The petitioner has claimed the depreciation based on the capital expenditure of Rs. 34500.39 lakh as on 31.3.2004 in accordance with above principles. In the calculation of depreciation the capital cost of Rs. 33,116.13 lakh has been considered.

20. Based on the provisions of the notification dated 26.3.2001, the depreciation for individual items of capital expenditure has been calculated on the capital cost for each of the assets at the rates as prescribed in the notification. While approving depreciation component of tariff, the weighted average depreciation rate has been worked out. The break up of the capital cost has been considered as per the details furnished by the petitioner. The necessary calculations in support of weighted average depreciation rate are given hereunder:

Particulars Capital cost as on date of commercial operation as per C.A certificate dated 7.12.2004 Approved capital cost Rate of Depreciation as per the notification Dated 26.3.2001 Depreciation Date of commercial operation 1.3.2003 Capital Expenditure as on 1.3.2003 Land 12.72 0% 0.00 Building & Other Civil Works 371.06 1.80% 6.68 Sub-Station Equipments 4070.09 3.60% 146.52 Transmission Line 28490.17 2.57% 732.20 PLCC 172.09 6.00% 10.33 Total 33116.13 39628.00 895.73 Weighted Average Rate of Depreciation 2.70%

21. The calculations in support of depreciation allowed are appended herein below:

(Rs. in lakh)

2002-2003 (Pro rata) 2003-2004 Rate of Depreciation 2.70% Depreciable Value (90% of Gross Block) 29804.52 Remaining Depreciable Value 29804.52 29729.87 Depreciation 74.64 895.73

ADVANCE AGAINST DEPRECIATION

22. In addition to allowable depreciation, the petitioner becomes entitled to Advance Against Depreciation when originally scheduled loan repayment exceeds the depreciation allowable as per schedule to the notification dated 26.3.2001 Advance Against Depreciation is computed in accordance with the following formula:

AAD = Originally scheduled loan repayment amount subject to a ceiling of 1/12 of original loan amount minus depreciation as per schedule.

23. The petitioner has not claimed Advance Against Depreciation.

24. For working out Advance Against Depreciation, 1/12 of the notional loan has been considered while repayment of loan as worked out above has been taken as repayment of the loan during the year. Similarly, depreciation allowed as per para 23 above has been considered. The petitioner is not entitled to Advance Against Depreciation as calculated below:

(Rs. in lakh)

2002-2003 2003-2004 1/12th of Gross Loan(s) 2395.17 2395.17 Scheduled Repayment of the Loan(s) 0.00 98.00 Minimum of the above 0.00 98.00 Depreciation during the year 74.64 895.73 Advance Against Depreciation 0.00 0.00

OPERATION & MAINTENANCE EXPENSES

25. In accordance with the notification dated 26.3.2001, Operation and Maintenance expenses, including expenses on insurance, if any, are to be calculated as under:

(i) Where O & M expenses, excluding abnormal O & M expenses, if any, on sub-station (OMS) and line (OML) are separately available for each region, these shall be normalised by dividing them by number of bays and line length respectively. Where data as aforesaid is not available, O & M expenses in the region are to be apportioned to the sub-station and lines on the basis of 30:70 ratio and these are to be normalised as below:

O & M expenses per Unit of the line length in Kms (OMLL) = Expenses for lines (OML)/Average line length in Kms (LL) O & M expenses for sub-stations (OMBN) = O & M expenses for substations (OMB)/Average number of bays (BN)]

(ii) The five years average of the normalised O & M expenses for lines and for bays for the period 1995-1996 to 1999-2000 is to be escalated at 10% per annum for two years (1998-1999 and 1999-2000) to arrive at normative O & M expenses per unit of line length and per bay for 1999-2000.

(iii) The normative O & M per unit length and normative O & M per bay for the year 1999-2000 for the region derived in the preceding paragraph is to be escalated @ 6% per annum to obtain normative values of O & M expenses per unit per line length and per bay in the relevant year. These normative values are to be multiplied by line length and number of bays (as the case may be) in a given system in that year to compute permissible O & M expenses for the system.

(iv) The escalation factor of 6% per annum is to be used to revise normative base figure of O & M expenses. Any deviation of the escalation factor computed from the actual inflation data that lies within 20% of the notified escalation factor of 6% shall be absorbed by utilities/beneficiaries.

26. Based on the methodology for computation of O & M expenses specified in the notification dated 26.3.2001, the Commission has computed O & M charges per ckt km (NOMLL) and per bay (NOMB) for Southern Region in other petitions. These are extracted below:

NORMALIZED O & M EXPENSES FOR SOUTHERN REGION

(All Figures in Rs. lakhs)

S. No. Items 1995-1996 1996-1997 1997-1998 1998-1999 1999-2000 Total for five years 95-96 to 99-00 99-00 2000-2001 2001-2002 2002-2003 2003-2004 1 Total O & M expenses (Rs. lakhs) 2129.83 2220.25 3330.40 3724.36 4701.71 2 Abnormal O & M expenses 0.00 0.00 0.00 0.00 0.00 3 Normal O & M expenses (S. No. 1 -S. No. 2) 2129.83 2220.25 3330.40 3724.36 4701.71 4 OML (O & M for lines) = 0.7 × S. No. 3 1490.88 1554.17 2331.28 2607.05 3291.20 11274.58 5 OMS (O & M for substation) = 0.3×S. No. 3 638.95 666.07 999.12 1117.31 1410.51 4831.96 6 Line length at beginning of the year in Kms. 5578.74 5839.71 5839.71 6034.71 6190.71 7 Line length added in the year in Kms. 260.97 0.00 195.00 156.00 656.33 8 Line length at end of the year in Kms. 5839.71 5839.71 6034.71 6190.71 6847.04 9 LL (Average line length in the Region) 5709.23 5839.71 5937.21 6112.71 6518.88 30117.74 10 No. of bays at beginning of the year 66 71 74 76 80 11 No. of bays added in the year 5 3 2 4 26 12 No. of bays at the end of the year 71 74 76 80 106 13 BN (Average number of bays in the Region) 68.5 72.5 75.0 78.0 93.0 387.00 14 AVOMLL (OML/LL) 0.26 0.27 0.39 0.43 0.50 1.851 15 AVOMBN (OMS/BN) 9.33 9.19 13.32 14.32 15.17 61.328 16 NOMLL (allowable O & M per unit of line length) 0.3703 0.4073 0.4480 0.4480 0.4749 0.5034 0.5336 0.5656 17 NOMBN (Allowable O & M per bay) 12.2656 13.4921 14.8413 14.8413 15.7318 16.6757 17.6763 18.7368 NOMLL (as calculated by petitioner) 0.4200 0.5100 0.5400 0.5700 0.6000 0.6400 NOMBN (as calculated by petitioner) 13.9100 16.8300 17.8400 18.9100 20.0400 21.2400

27. The differences in NOMLL and NOMBN as calculated by the petitioner and as allowed are mainly on account of certain expenses disallowed by us as explained in the respective orders for computation of normative values.

28. In our calculations the escalation factor of 6% per annum has been used. In accordance with the notification dated 26.3.2001, if the escalation factor computed from the observed data lies in the range of 4.8% to 7.2%, this variation shall be absorbed by the petitioner. In case of deviation beyond this limit, adjustment shall be made on by applying actual escalation factor arrived at on the basis of weighted price index of CPI for industrial workers (CPI_IW) and index of selected component of WPI

(WPI_TR).

29. The details of O & M expenses allowed are given hereunder:

2002-2003 2003-2004 Line length in Ckm No. of bays O & M expenses (Rs. in lakh) Line length in Ckm No. of bays O & M expenses (Rs. in lakh) 1059.28 8 58.88 1059.28 8 749.02

RETURN ON EQUITY

30. In accordance with the notification dated 26.3.2001, the petitioner is entitled to return on equity at the rate of 16% per annum. For the purpose of tariff, equity of Rs. 4374.13 as on 1.3.2003 has been considered. On the above basis, the petitioner shall be entitled to return on equity each year during the tariff period as under:

Year Amount 2002-2003 (Pro rata) Rs. 58.32 lakh 2003-2004 Rs. 699.86 lakh

INTEREST ON WORKING CAPITAL

31. As provided in the notification dated 26.3.2001, the interest on working capital shall cover:

(a) Operation and maintenance expenses (cash) for one month;

(b) Maintenance spares at a normative rate of 1% of the capital cost less 1/5 of the initial capitalised spares. Cost of maintenance spares for each subsequent year shall be revised at the rate applicable for revision of expenditure on O & M of the transmission system; and

(c) Receivables equivalent to two months' average billing calculated on normative availability level, which is 98%.

32. In keeping with the methodology prescribed in the notification dated 26.3.2001, working capital has been worked out. In the calculation, maintenance spares for the years 2002-2003 and 2003-2004 have been worked out on the basis of capital expenditure up to 28.2.2003, and after deduction of 1/5 of the initial capitalised spares therefrom. This has been escalated @ 6% per annum for the years 2002-2003 and 2003-2004. The petitioner has claimed interest on working capital at the rate of 11%. However, interest on working capital has been allowed @ 10.75% based on annual SBI PLR for the year 2002-2003, which has been allowed separately by the Commission in certain other petitions. The detailed calculations in support of interest on Working Capital are as under:

Interest on Working Capital

(Rs. In lakh)

Rate of Escalation for maintenance spares 6% 6% Maintenance Spares 1% 331.16 Less: Capitalised Initial spares 9.43 321.73 323.34 O & M expenses 58.88 62.42 Receivables 867.54 864.76 Total 1,248.15 1,250.51 Rate of Interest 10.75% 10.75% Interest 11.18 134.43

TRANSMISSION CHARGES

33. In the light of above discussion, we approve the transmission charges as given in the Table below:

(Rs. in lakh)

2002-2003 (Pro rata) 2003-2004 Interest on Loan 230.74 2709.51 Interest on Working Capital 11.18 134.43 Depreciation 74.64 895.73 Advance Against Depreciation 0.00 0.00 Return on Equity 58.32 699.86 O & M Expenses 58.88 749.02 Total 433.76 5188.55

34. The difference between the petitioner's claim on account of transmission charges and that allowed by us is primarily on account of difference in gross block considered for the purposes of tariff.

35. In addition to the transmission charges, the petitioner shall be entitled to other charges like income tax, incentive, surcharge and other cess and taxes in accordance with the notification dated 26.3.2001, subject to directions, if any, of the superior courts. The petitioner shall also be entitled to recovery of filing fee of Rs. 2 lakh, which shall be recovered from the respondents in five monthly installments of Rupees forty thousand each and shall be shared by the respondents in the same ratio as other transmission charges. This is subject to confirmation that the amount is not already included in the O & M charges.

36. The petitioner has already billed the respondents on provisional basis in accordance with the Commission's interim orders. The provisional billing of tariff shall be adjusted in the light of final tariff now approved by us.

37. The transmission charges approved by us shall be included in the regional transmission tariff for Southern Region and shall be shared by the regional constituents in accordance with the notification dated 26.3.2001

38. This order disposes of Petition No. 123/2002.