1. This is an application in the pending writ petition made by the petitioner seeking interim protection on the threat of disconnection.

2. Learned advocate for the petitioner submits that, there subsists an interim order dated January 21, 2016. The petitioner is complying with such order. During the pendency of the writ petition, the petitioner has received a demand for delayed payment surcharge for a sum of about Rs. 18,00,000/-. He contends that, the calculation and the demand are wrong. Such amount is not payable by the petitioner. He draws the attention of the Court to the fact that, subsequent to the pendency of the application, the petitioner has received a notice dated October 13, 2017 requiring the petitioner to pay the delayed payment surcharge within October 28, 2017 or else the electricity supply would be disconnected. He also draws the attention of the Court to the fact that, there are some incorrect statements made in the application with regard to the filing of affidavits.

3. The Electricity Regulatory Commission is represented.

4. None appears for the distribution company. Affidavit of service filed in Court be kept with the record.

5. Apparently, the petitioner is complying with the order dated January 21, 2016, which puts in place a mechanism to pay the arrears to the distribution company. There is a demand for delayed payment surcharge. Without entering into the dispute as to whether such demand is permissible when a writ petition is pending and whether the quantum of demand is correct or not, it would be appropriate in the facts of the present case, to direct the petitioner to pay a sum of Rs. 18,00,000/- by six installments commencing from the month of November, 2017 and payable within the 15th of every month, towards liquidation of the claim for delayed payment surcharge. In the event of the petitioner paying such amount, the distribution company will not disconnect the electricity supply on account of non-payment of the delayed payment surcharge as claimed in the letter dated October 13, 2017. In the event by a solitary default, the distribution company is at liberty to implement the writing dated October 13, 2017. There will be an unconditional stay directing the distribution company not to disconnect the electricity supply of the petitioner till November 15, 2017 on the ground of non-payment of the delayed payment surcharge as demanded by the writing dated October 13, 2017.

6. Let affidavit-in-opposition be filed to this application by the respondents within two weeks from date; reply thereto, if any, be filed a week thereafter.

7. List C.A.N 9359 of 2017 four weeks hence under the same heading. List W.P No. 493 (W) of 2016 along with the application.

8. Parties are requested to come ready for hearing of the main writ petition also on that date.

9. Urgent certified website copies of this order, if applied for, be made available to the parties upon compliance of the requisite formalities.