Power Grid Corporation Of India Limited v. Rajasthan Rajya Vidyut Prasaran Nigam Limited
Structured Summary of the Opinion — Petition by Power Grid Corporation of India Ltd. (Transmission Tariff)
Factual and Procedural Background
Power Grid Corporation of India Ltd. (the petitioner) filed a petition for approval of transmission tariff in respect of specified transmission assets sanctioned under a Common Scheme for 765 kV Pooling Stations and Network for Northern Region and related import networks. Four assets were listed in the petition:
- Asset-I: 400 kV D/C (Quad) LILO of Barh-Balia transmission line at Patna with associated bays;
- Asset-II: 765/415 kV, 3 × 500 MVA ICT-I Ranchi with associated bays;
- Asset-III: Combined assets comprising 400 kV D/C (Quad) Ranchi (New)–Ranchi (Old) lines, associated bays and 765/415 kV, 3 × 500 MVA ICT II at Ranchi;
- Asset-IV: 765/415 kV, 3 × 500 MVA ICT at Sasaram with associated bays.
Anticipated dates of commercial operation (DOCO) were 1.7.2012 for Asset-I and 1.9.2012 for Assets II–IV. The petitioner later filed affidavits reporting actual commissioning dates: Asset-I commissioned on 1.12.2012 and Asset-IV on 1.3.2013. Assets II and III remained under construction with revised anticipated DOCO of 1.1.2014; accordingly the Commission considered transmission charges only for Asset-I and Asset-IV in this petition and granted liberty to the petitioner to file separate petitions for Asset-II and Asset-III.
The petition relied on investment approval dated 29.8.2008 at an estimated consolidated cost for the Common Scheme. Notices under Section 64 of the Electricity Act were published and no comments were received from the general public. BSES Rajdhani Power Ltd. (BRPL) filed a reply to the petition and the petitioner submitted a rejoinder. The Commission heard the parties and proceeded to dispose of the petition in respect of the commissioned assets.
Legal Issues Presented
- Whether transmission charges for Asset-I and Asset-IV should be approved from their actual dates of commercial operation to 31.3.2014 in terms of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 (the 2009 Tariff Regulations).
- Whether time overruns (delay in commissioning) and associated Interest During Construction (IDC) / Interest on Extraordinary Deferred Credit (IEDC) should be condoned or disallowed, and to what extent.
- Whether cost overruns / additional capital expenditure should be admitted, including the proper treatment of capitalisation and restriction where Revised Cost Estimates (RCE) for individual assets are not submitted.
- Appropriate treatment of initial spares under the ceiling norms in Regulation 8 of the 2009 Tariff Regulations.
- Computation and admissibility of debt-equity ratio, Return on Equity (RoE), interest on loan and depreciation in accordance with the 2009 Tariff Regulations.
- Computation and allowance of Operation & Maintenance (O&M) norms and interest on working capital (components and rate).
- Whether reimbursement of filing fee and publication expenses, licence fee and prospective recovery of service tax may be allowed.
- Other consequential billing, collection and disbursement directions (e.g., applicability of CERC sharing regulations).
Arguments of the Parties
Petitioner's (Power Grid Corporation) Arguments
- Petitioner claimed transmission charges for Asset-I and Asset-IV based on the actual DOCOs (1.12.2012 and 1.3.2013 respectively) and submitted revised tariff calculations for the period until 31.3.2014.
- For delays, petitioner explained causes: heavy rains, non-availability of shut-downs at tapping points and dead end towers, change of route alignment (Asset-I); and delayed transportation of ICTs due to non-availability of shut-down at busy railway crossing, prolonged heavy rains, fog affecting testing of HV bushings and civil works, delay in forest permissions for tree-cutting and associated logistics for heavy consignments (Asset-IV). Petitioner asserted that its efforts reduced the total delays.
- Petitioner submitted detailed capital cost, IDC/IEDC, additional capitalisation and working capital computations and claimed initial spares within the capital cost.
- Petitioner sought reimbursement of filing fee and publication expenses in terms of Regulation 42 of the 2009 Tariff Regulations, and sought separate recovery of licence fee under Regulation 42A(1)(b).
- Petitioner requested permission to bill and recover service tax on transmission charges separately from beneficiaries in future, if applicable.
Respondent's (BRPL) Arguments
- BRPL submitted that though element-wise completion report (Form 5C) was filed, an element-wise schedule of completion was not provided, making assessment of time over-run difficult; on this basis BRPL prayed that IDC/IEDC for the period of delay should not be allowed.
- BRPL argued the petitioner should file the tariff petition only after commissioning of all transmission assets (i.e., not asset-wise), although the Commission proceeded to consider the commissioned assets separately.
- BRPL objected to the claim for reimbursement of filing fee and publication expenses, relying on a Commission order dated 11.9.2008 in Petition No. 129 of 2005 to argue that such claims should be rejected.
- BRPL objected to reimbursement of licence fee, contending that licence fee is an eligibility cost for the licensee and should be borne by the petitioner rather than passed on to beneficiaries.
- BRPL objected to recovery of future service tax from beneficiaries, noting that at the time CBEC had exempted service tax on transmission and sought to preclude such recovery.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Order dated 11.9.2008 in Petition No. 129 of 2005 (Central Commission) | Referenced by BRPL to argue that reimbursement of filing fee and publication expenses should be rejected. | The Commission noted BRPL's reliance on this order but applied a later Commission order in resolving the issue (see entry for the 11.1.2010 order). The 11.9.2008 order was not adopted as a bar to reimbursement in this disposition. |
| Order dated 11.1.2010 in Petition No. 109 of 2009 (Central Commission) | Used by the petitioner to support entitlement to recover filing fee directly from beneficiaries on a pro-rata basis. | The Commission applied this prior order to allow the petitioner to recover filing fee directly from beneficiaries on pro-rata basis and to allow reimbursement of publication expenses for the present petition. |
Court's Reasoning and Analysis
The Commission proceeded by reference to the explicit provisions of the 2009 Tariff Regulations, performing a prudence check on the capital cost, time over-run, cost over-run, additional capitalisation, components of working capital, O&M norms and the applicable formulae for RoE, interest on loan and depreciation. The reasoning follows the regulatory framework quoted throughout the opinion (Regulations 7, 8, 9, 12, 15, 16, 17, 18, 19 and others).
Time over-run: The Commission compared the scheduled commissioning period (48 months from investment approval dated 29.8.2008, i.e., up to 1.9.2012) with actual commissioning dates. Asset-I was delayed by 3 months and Asset-IV by 6 months. The petitioner’s explanations (heavy rains, fog, non-availability of shut-downs, route change, delays in transportation across busy railway crossing, delays for forest permissions) were examined on the record.
The Commission concluded:
- Seasonal events like heavy rains and fog are normal and foreseeable and the petitioner did not furnish evidence of extraordinary weather events; therefore these grounds did not justify condonation of the entire period of delay.
- For other alleged causes (non-availability of shut-downs, change of route alignment, contractor default for Asset-I; delay in obtaining railway shut-down permissions and tree-cutting permission for Asset-IV), the petitioner did not produce documentary evidence to support that approvals/permissions were unreasonably delayed. The petitioner’s own submissions and documents showed that the petitioner had claimed liquidated damages from the contractor, indicating contractor default.
- Consequently, the Commission did not condone the entire period of delay and disallowed a pro rata portion of IDC and IEDC corresponding to the period of delay: 3 months for Asset-I and 6 months for Asset-IV. The exact IDC and IEDC disallowed were computed on a pro rata basis from the management certificates provided by the petitioner.
Cost over-run and additional capitalisation: The Commission examined the estimated completion costs against apportioned approved costs. Asset-I’s estimated completion cost fell within its apportioned approved cost. Asset-IV’s estimated completion cost exceeded its apportioned approved cost by Rs. 463.46 lakh after adjusting disallowed IDC/IEDC. As the petitioner had not submitted a Revised Cost Estimate (RCE) for individual assets, the Commission restricted capital expenditure for Asset-IV by disallowing additional capital expenditure of Rs. 463.46 lakh for 2013–2014.
Initial spares: The Commission compared the claimed initial spares against ceiling norms in Regulation 8 and found the petitioner’s claims within the specified ceilings. The ceiling for initial spares will however be reviewed at truing up on the basis of actual capital expenditure.
Additional capitalisation (Regulation 9 and cut-off date): The Commission verified that claimed additional capital expenditure fell within the cut-off date definition (cut-off as per Regulation 3(11)) and allowed additional capitalisation except where restricted for Asset-IV due to the cost over-run described above.
Debt-equity ratio and RoE: The Commission applied the normative 70:30 debt-equity ratio for the projects (as per Regulation 12) in absence of equity exceeding or falling short of the normative ratio and computed Return on Equity as per Regulation 15, grossing up the pre-tax base rate of 15.5% by the MAT rate applicable for 2008–09 (11.33%) to arrive at the pre-tax RoE used in calculations.
Interest on loan: Interest on loan was computed on the gross normative loan applying the weighted average rate of interest derived from the petitioner’s loan portfolio. Repayment for the tariff period was deemed equal to the depreciation allowed in accordance with Regulation 16; repayment was considered from the first year of commercial operation notwithstanding any moratorium.
Depreciation: Depreciation was computed on the admitted capital cost using the Straight Line Method at rates prescribed in Appendix-III to the 2009 Tariff Regulations. Because the assets were commissioned during 2012–2013, the Commission applied the relevant provisions regarding depreciable value and remaining useful life.
Operation & Maintenance (O&M) expenses: The Commission applied the normative O&M expense rates prescribed in Regulation 19 for the tariff block 2009–2014. The Commission noted the petitioner’s position on wage revision (50% considered) but held that the 2009 Tariff Regulations had already factored a 50% pay revision, and there was no justification in the present petition to deviate from the established norms; any separate application by the petitioner would be considered by the Commission as per law.
Interest on working capital: The components of working capital (two months' receivables, maintenance spares at 15% of O&M, and one month of O&M) were computed as per Regulation 18. Interest on working capital was computed at 13.5% (base rate as on 1.4.2012 = 10% plus 350 bps) and applied to the working capital components to arrive at the interest on working capital.
Filing fee and publication expenses: BRPL relied on an earlier order (11.9.2008 in Petition No.129/2005) to object to reimbursement. The Commission applied its order dated 11.1.2010 in Petition No.109/2009 to hold that the petitioner is entitled to recover the filing fee directly from beneficiaries on a pro-rata basis and is also entitled to reimbursement of publication expenses from beneficiaries on a pro-rata basis in relation to the present petition.
Licence fee and service tax: On the licence fee, the petitioner’s submission that licence fee had become an incidental component from 2008–09 was accepted and the Commission allowed reimbursement of licence fee in accordance with Regulation 42A(1)(b) of the 2009 Tariff Regulations. On service tax, the petitioner’s prayer to bill service tax separately was rejected as premature because at the time CBEC exempted transmission from service tax; the Commission declined to permit a prospective recovery at this stage and rejected the prayer.
Resulting transmission charges and truing up: After making the adjustments above (disallowance of IDC/IEDC for the disallowed delay periods, restriction of additional capitalisation where RCE not filed, application of normative ratios and regulatory formulae), the Commission computed the allowed transmission charges for the two assets for 2012–13 and 2013–14. The Commission noted that the approved charges are lower than those claimed and are subject to future truing up in accordance with the 2009 Tariff Regulations.
Holding and Implications
Primary holding: The Commission approved transmission charges for Asset-I and Asset-IV for the period up to 31.3.2014, subject to the adjustments described in the order (disallowance of IDC/IEDC for specified delay periods, restriction of additional capitalisation for Asset-IV, application of normative debt-equity, RoE, interest on loan, depreciation, O&M and working capital norms) and subject to future truing up.
Key direct effects and orders:
- The Commission allowed transmission charges (summary figures as approved by the Commission):
- Asset-I: Total allowed - 2012–2013: Rs. 361.17 lakh (pro rata), 2013–2014: Rs. 1161.13 lakh.
- Asset-IV: Total allowed - 2012–2013: Rs. 183.26 lakh (pro rata), 2013–2014: Rs. 2382.11 lakh.
- The Commission disallowed IDC and IEDC pro rata for the periods of delay determined (3 months for Asset-I and 6 months for Asset-IV) — amounts disallowed were computed on the basis of management certificates supplied by the petitioner (specified numeric disallowances are set out in the order).
- Additional capital expenditure for Asset-IV up to 31.3.2014 was restricted by disallowing Rs. 463.46 lakh due to absence of an RCE for the asset.
- Initial spares claimed were within regulatory ceilings and allowed; ceiling review to be done at truing up on actual expenditure.
- Filing fee and publication expenses were allowed to be recovered directly from beneficiaries on a pro-rata basis (following the Commission's prior order dated 11.1.2010 in Petition No.109/2009).
- Licence fee reimbursement was allowed in accordance with Regulation 42A(1)(b) of the 2009 Tariff Regulations.
- The petitioner’s prayer to bill and recover service tax separately in the future was rejected as premature.
- The billing, collection and disbursement of the approved transmission charges shall be governed by the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010 (as amended).
- The petition in respect of Asset-II and Asset-III was not adjudicated in this order; petitioner was granted liberty to file a separate petition for those assets.
Implications: The decision directly affects the parties by fixing the allowed transmission charges for Asset-I and Asset-IV (with the numeric amounts and regulatory adjustments stated above) and denying certain claimed costs tied to the period of delay and to unapproved additional capitalisation. The order applies the extant 2009 Tariff Regulations and prior Commission orders to the facts; the opinion does not purport to create new legal precedent beyond application of the existing regulatory framework and prior Commission determinations.
Disposition: This order disposes Petition No. 101.TT/2012 in respect of the assets covered (Asset-I and Asset-IV), and leaves open filing for Asset-II and Asset-III as a separate petition.
Note: This summary is prepared strictly from the information contained in the provided opinion. No additional facts or inferences beyond the opinion text have been introduced.
The petition has been filed by Power Grid Corporation of India Ltd. for approval of transmission tariff in respect of the following transmission assets sanctioned under the Common Scheme for 765 kV Pooling Stations and Network for Northern Region, Import by Northern Region from Eastern Region and from North Eastern Region/Southern Region/Western Region via Eastern Region from the anticipated dates of commercial operation of the respective assets to 31.3.2014 in terms of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 (hereinafter the 2009 Tariff Regulations):
(a) 400 kV D/C (Quad) LILO of Barh-Balia transmission line at Patna along with associated bays at Patna sub-station (Asset-I)
(b) 765/415 kV, 3 × 500 MVA ICT-I Ranchi along with associated bays at 765 kV Ranchi sub-station (Asset-II);
(c) Combined assets of 400 kV D/C (Quad) Ranchi (New) - Ranchi (Old) - I transmission line and associated 400 kV Line bays at Ranchi (New) sub-station and Ranchi (old) sub-station and 400 kV D/C (Quad) Ranchi (New)-Ranchi (Old) - II transmission line and associated 400 kV line bays 400 kV line bays at Ranchi (New) sub-station and Ranchi (Old) sub-station and 765/415 kV, 3 × 500 MVA ICT II at Ranchi along with associated bays at 765 kV Ranchi sub-station (Asset-III) and
(d) 765/415 kV, 3 × 500 MVA ICT at Sasaram along with associated bays (Asset-IV).
2. The anticipated date of commercial operation was 1.7.2012 for Asset-I and 1.9.2012 for Asset-II, Asset-III and Asset-IV. The petitioner subsequently filed affidavits stating that Asset-I and Asset-IV were commissioned respectively on 1.12.2012 and 1.3.2013 and filed revised calculations of tariff in respect of both the transmission assets from the actual dates of commercial operation to 31.3.2014 The petitioner submitted during hearing on 21.11.2013 that the other two transmission assets, namely Asset-II and Asset-III were under construction with revised anticipated dates of commercial as 1.1.2014 Therefore, transmission charges are being approved for Asset-I and Asset-IV only, with liberty to the petitioner to file a separate petition for Asset-II and Asset-III.
3. The investment approval for the Common Scheme for 765 kV Pooling Stations and Network for NR, Import by NR from ER and from NER/SR/WR via ER and Common Scheme for Network for WR and Import by WR from ER and from NER/SR/WR/via ER in Eastern Region was accorded by the Board of Directors of the petitioner company vide letter dated 29.8.2008 at an estimated cost of Rs. 707533 lakh, including Interest During Construction (IDC) of Rs. 71360 lakh (based on 1st Quarter, 2008 price level).
4. The transmission charges claimed by the petitioner based on the actual date of commercial operation are as under:—
(Rs. in lakh)
Asset - I Asset - IV Particulars 2012–2013 2013–2014 2012–2013 2013–2014 Depreciation 83.22 273.66 53.44 716.89 Interest on Loan 102.68 320.94 65.34 841.30 Return on Equity 82.37 270.68 53.08 712.05 Interest on Working Capital 10.91 34.95 4.64 60.93 O & M Expenses 85.79 272.08 12.38 157.10 Total 364.97 1172.31 188.88 2488.27
5. The details submitted by the petitioner in support of its claim for interest on working capital are given hereunder:
(Rs. in lakh)
Asset-I Asset-IV Particulars 2012–2013 2013–2014 2012–2013 2013–2014 Maintenance Spares 38.61 40.81 22.28 23.56 O & M Expenses 21.45 22.67 12.38 13.09 Receivables 182.49 195.39 377.76 414.71 Total 242.55 258.87 412.42 451.36 Rate of Interest 13.50% 13.50% 13.50% 13.50% Interest 10.91 34.95 4.64 60.93
6. No comments or suggestions have been received from the general public in response to the notices published by the petitioner under Section 64 of the Electricity Act. The reply to the petition has been filed by BSES Rajdhani Power Ltd. (BRPL), Respondent No. 12, vide affidavit dated 20.11.2013 The petitioner has filed rejoinder to the reply of BRPL, vide affidavit dated 23.12.2013
7. We have heard the representatives of the parties present at the hearing and have perused the material available on record. We proceed to dispose of the petition. While doing so, the submissions of the respondents shall be duly taken note of.
Capital cost
8. Regulation 7 of the 2009 Tariff Regulations so far as relevant provides as under:—
“(1) Capital cost for a project shall include:—
(a) The expenditure incurred or projected to be incurred, including interest during construction and financing charges, any gain or loss on account of foreign exchange risk variation during construction on the loan - (i) being equal to 70% of the funds deployed, in the event of the actual equity in excess of 30% of the funds deployed, by treating the excess equity as normative loan, or (ii) being equal to the actual amount of loan in the event of the actual equity less than 30% of the fund deployed, - up to the date of commercial operation of the project, as admitted by the Commission, after prudence check.
(b) capitalised initial spares subject to the ceiling rates specified in regulation 8; and
(c) additional capital expenditure determined under regulation 9:
Provided that the assets forming part of the project, but not in use shall be taken out of the capital cost.
(2) The capital cost admitted by the Commission after prudence check shall form the basis for determination of tariff:
Provided that in case of the thermal generating station and the transmission system, prudence check of capital cost may be carried out based on the benchmark norms to be specified by the Commission from time to time:
Provided further that in cases where benchmark norms have not been specified, prudence check may include scrutiny of the reasonableness of the capital expenditure, financing plan, interest during construction, use of efficient technology, cost over-run and time over-run and such other matters as may be considered appropriate by the Commission for determination of tariff.”
9. The details of the apportioned approved capital cost, capital cost as on the dates of commercial operation and estimated additional capital expenditure projected to be incurred for the transmission assets as submitted by the are given overleaf:—
(Rs. in lakh)
Particulars Apportioned approved cost Actual cost on DOCO Projected additional capital expenditure Estimated completion cost 2011–2012 2012–2013 Asset-I 5771.48 4483.91 456.68 441.59 5382.18 Asset-II 14056.58 12054.29 183.24 2680.02 14917.55
Time over-run
10. As per investment approval dated 29.8.2008, the assets were scheduled to be commissioned progressively within 48 months from the date of investment approval, i.e by 1.9.2012 Asset-I and Asset-IV were commissioned on 1.12.2012 and 1.3.2013 respectively. Accordingly, there is a delay of 3 months in case of Asset-I and 6 months in case of Asset-IV. The petitioner has explained the reasons for delay in the commissioning of Asset-I and asset-IV, in its affidavit dated 19.11.2013
11. The petitioner has submitted that the commissioning of Asset-I got delayed by one month (September - October 2012) on account of heavy rains and two months on account of non-availability of shut-down at tapping point and dead end tower of 400 kV Patna - Barh & Patna - Balia transmission lines and yet another 2 months on account of change of route alignment. The petitioner has submitted that the total delay of five months has been reduced to 3 months because of the petitioner's efforts to expedite completion of the critical activities.
12. Regarding the delay in the commissioning of Asset-IV, the petitioner has submitted that transportation of ICTs got delayed by six weeks due to non-availability of shut-down at Railway crossing near sub-station for passing lorry carrying ICT to Sasaram sub-station site as it is a very busy rail route and clearance for passing of an ICT takes two to three weeks. The petitioner has further submitted that there was a delay of 8 weeks because of heavy rains on account of which foundation could not be constructed. The petitioner has attributed delay of another eight weeks to heavy fog conditions during winter season between December, 2011 and January, 2012 (four weeks) and December, 2012 to January, 2013 (four weeks) at site which badly affected 800 kV HV Bushing Tan Delta values/IR Values/Megger values. Further, the civil work for ICT could not be undertaken from June, 2011 till mid-September, 2011 due to pre-monsoon rains which caused water logging in sub-station premises. The commissioning further got delayed by approximately four weeks (14.9.2011 to 11.10.2011) for obtaining permission from forest department for tree-cutting at the sub-station premises. All the huge consignments like reactor and transformers have to cross a very busy Railway crossing to reach Sasaram sub-station. The crossing lies on the busiest Delhi - Howrah Railway track and a complete shut-down of route for few hours is needed for consignment to cross towards sub-station. Permission for shut-down for track took fifteen to thirty days for each reactor. The petitioner has submitted that all the above factors caused thirty week's delay which has been reduced to twenty four weeks (six months) by rigorous follow-up by the petitioner.
13. BRPL in its reply has submitted that though element-wise completion report has been given in Form 5C, element - wise schedule of completion has not been given. In the circumstances it is difficult to assess time over-run. Accordingly, BRPL has prayed that IDC/IEDC for the period of delay may not be allowed. BRPL has further submitted that the petitioner should file the tariff petition after the commissioning of all the transmission assets. Though the petitioner has filed asset-wise schedule of completion as per the Letter of Award, the objection by BRPL has become irrelevant, since approval of transmission charges for assets already commissioned (i.e Asset-I and Asset-IV) is under consideration in this order.
14. We now examine the reasons for delay explained by the petitioner. Main reasons for delay in the commissioning are heavy rains, fog and non-availability of shut-down for transportation of ICT at Sasaram sub-station which hampered the movement of huge consignments like reactors and transformers through a very busy railway route/crossing. Heavy rains and fog are normal seasonal variations. There is nothing abnormal in these events and must have been foreseen at the planning stage. The petitioner has not submitted any evidence to suggest that there was any extraordinary rain or fog causing disruption in construction activities. In case of Asset-I, two additional reasons, which are said to have contributed to the delay in commissioning, have been given. These are unavailability of shut down at tapping point and dead end tower of 400 kV Patna - Barh and Patna - Balia transmission line and change of route alignment. No documentary evidence has been provided by the petitioner. Whatever documents the petitioner has submitted only reveal that the petitioner has claimed liquidated damages amounting to Rs. 12.83 lakh from the vendor for delay in commissioning of the asset by five months. Thus delay is on account of the contractor hired by the petitioner. The beneficiaries cannot be saddled with cost as result of the default of the contractor. Similarly, the petitioner has not placed on record a shred of evidence that there was any delay in obtaining shut-down on railway crossing/route needed for transportation of ICT at the sub-station site or abnormally long time was taken in getting the permission for tree-cutting in case of Asset-IV. Therefore, delay of three months in case of Asset-I and of six months in case of Asset-IV is not being condoned. Details of IDC and IEDC disallowed are as follows:—
(Rs. in lakh)
Asset-I Details of IDC and IEDC as per Management Certificate dated 18.11.2013 IDC IEDC Up to March 2012 220.71 57.66 April 2012 to Nov 2012 141.54 79.68 Total IDC and IEDC claimed 362.25 137.34 Details of IDC and IEDC disallowed for 3 months September 2012 to November 2012 (computed on pro rata basis from IDC and IEDC of April 2012 to November 2012) 35.39 29.88 Total IDC and IEDC disallowed 35.39 29.88
(Rs. in lakh)
Asset-IV Details of IDC and IEDC as per Management Certificate IDC IEDC Up to March 2012 701.66 180.19 April 2012 to February 2013 544.14 168.13 Total IDC and IEDC claimed 1245.80 348.32 Details of IDC and IEDC disallowed for 6 months September 2012 to February 2013 (computed on pro rata basis from IDC and IEDC of September 2012 to February 2013) 296.80 91.71 Total IDC and IEDC disallowed 296.80 91.71
Cost over-run
15. The total estimated completion cost for Asset-I falls within the apportioned approved cost whereas in the case of Asset-IV, the estimated completion cost exceeds the apportioned approved cost by Rs. 463.46 lakh (after adjusting disallowed IDC and IEDC of Rs. 388.51 lakh). Since the petitioner has not submitted RCE for individual assets, capital expenditure for Asset-IV up to 31.3.2014 has been restricted by disallowing additional capital expenditure of Rs. 463.46 lakh for the year 2013–2014.
Treatment of initial spares
16. The actual cost on the date of commercial operation claimed by the petitioner is inclusive of the cost of initial spares of Rs. 27.36 lakh (for sub-station) and 20.96 lakh (for transmission line) in case of Asset-I and Rs. 355 lakh (for sub-station) in case of Asset-IV.
17. Regulation 8 of the 2009 Tariff Regulations provide for ceiling norms for capitalization of initial spares in respect of transmission system as under:
“8. Initial Spares. Initial spares shall be capitalised as a percentage of the original project cost, subject to following ceiling norms:
(iv) Transmission system
(a) Transmission line - 0.75%
(b) Transmission Sub-station - 2.5%
(c) Series Compensation devices and HVDC Station - 3.5%
Provided that where the benchmark norms for initial spares have been published as part of the benchmark norms for capital cost under first proviso to clause (2) of regulation 7, such norms shall apply to the exclusion of the norms specified herein.
18. Initial spares claimed by the petitioner are within the ceiling limits specified under Regulation 8 of the 2009 Tariff Regulations. The ceiling limit of the initial spare will be reviewed at the time of truing up, on the basis of actual capital expenditure incurred.
Projected additional capital expenditure
19. Clause (1) of Regulation 9 of the 2009 Tariff Regulations provides as under:—
“Additional Capitalisation: (1) The capital expenditure incurred or projected to be incurred, on the following counts within the original scope of work, after the date of commercial operation and up to the cut-off date may be admitted by the Commission, subject to prudence check:
(i) Undischarged liabilities;
(ii) Works deferred for execution;
(iii) Procurement of initial capital Spares within the original scope of work, subject to the provisions of Regulation 8;
(iv) Liabilities to meet award of arbitration or for compliance of the order or decree of a court; and
(v) Change in Law:”
20. Clause (11) of Regulation 3 of the 2009 Tariff Regulations defines “cut-off” date as under:—
“Cut-off date” means 31 March of the year closing after 2 years of the year of commercial operation of the project and in case the project is declared under commercial operation in the last quarter of the year, the cut-off date shall be 31 March of the year closing after 3 years of the year of commercial operation”.
21. The additional capital expenditure claimed by the petitioner is within the cut-off date and is mainly on account of balance and retention payments. Therefore, additional capital expenditure has been allowed after restricting capital cost in case of Asset-IV due to cost over-run, as per details given hereunder:—
(Rs. in lakh)
Particulars Apportioned Approved Cost Cost on Date of Commercial Operation after deducting IDC/IEDC Additional Capital Expenditure Allowed Capital Cost on 31.3.2014 2012–2013 2013–2014 Asset-I 5771.48 4418.65 456.68 441.59 5316.92 Asset-IV 14056.58 11665.78 183.24 2216.56 14065.58
Debt - equity ratio
22. Regulation 12 of the Tariff Regulations provides as under:—
“12. Debt-Equity Ratio (1) For a project declared under commercial operation on or after 1.4.2009, if the equity actually deployed is more than 30% of the capital cost, equity in excess of 30% shall be treated as normative loan:
Provided that where equity actually deployed is less than 30% of the capital cost, the actual equity shall be considered for determination of tariff:
Provided further that the equity invested in foreign currency shall be designated in Indian rupees on the date of each investment.
Explanation The premium, if any, raised by the generating company or the transmission licensee, as the case may be, while issuing share capital and investment of internal resources created out of its free reserve, for the funding of the project, shall be reckoned as paid up capital for the purpose of computing return on equity, provided such premium amount and internal resources are actually utilised for meeting the capital expenditure of the generating station or the transmission system.
(2) In case of the generating station and the transmission system declared under commercial operation prior to 1.4.2009, debt-equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2009 shall be considered.
(3) Any expenditure incurred or projected to be incurred on or after 1.4.2009 as may be admitted by the Commission as additional capital expenditure for determination of tariff and renovation and modernisation expenditure for life extension shall be serviced in the manner specified in clause (1) of this regulation.”
23. Details of debt-equity ratio in respect of Asset-I and Asset-IV are given hereunder:—
(Rs. in lakh)
Capital cost as on DOCO Asset-I Particulars Amount % Debt 3093.05 70.00 Equity 1325.59 30.00 Total 4418.65 100.00 Asset-IV Debt 8166.05 70.00 Equity 3499.73 30.00 Total 11665.78 100.00
24. Details of debt-equity ratio in respect of Asset-I and Asset-IV are given hereunder:—
(Rs. in lakh)
Capital cost as on 31.3.2014 Asset-I Particulars Amount % Debt 3721.84 70.00 Equity 1595.07 30.00 Total 5316.92 100.00 Asset-IV Debt 9845.91 70.00 Equity 4219.67 30.00 Total 14065.58 100.00
Return on equity
25. Regulation 15 of the 2009 Tariff Regulations provides as under:—
“15.(1) Return on equity shall be computed in rupee terms, on the equity base determined in accordance with regulation 12.
(2) Return on equity shall be computed on pre-tax basis at the base rate of 15.5% for thermal generating stations, transmission system and run of the river generating station and 16.5% for the storage type generating stations including pumped storage hydro generating stations and run of river generating station with pondage and shall be grossed up as per clause (3) of this regulation.
Provided that in case of projects commissioned on or after 1st April, 2009, an additional return of 0.5% shall be allowed if such projects are completed within the timeline specified in Appendix-II.
Provided further that the additional return of 0.5% shall not be admissible if the project is not completed within the timeline specified above for reasons whatsoever.
(3) The rate of return on equity shall be computed by grossing up the base rate with the Minimum Alternate/Corporate Income Tax Rate for the year 2008–2009, as per the Income Tax Act, 1961, as applicable to the concerned generating company or the transmission licensee, as the case may be.
(4) Rate of return on equity shall be rounded off to three decimal points and be computed as per the formula given below:
Rate of pre-tax return on equity = Base rate/(1-t)
Where it is the applicable tax rate in accordance with clause (3) of this regulation.
(5) The generating company or the transmission licensee as the case may be, shall recover the shortfall or refund the excess Annual Fixed charge on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax Rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before the Commission;
Provided further that Annual Fixed charge with respect to the tax rate applicable to the generating company or the transmission licensee, as the case may be, in line with the provisions of the relevant Finance Acts of the respective financial year during the tariff period shall be trued up in accordance with Regulation 6 of these regulations”.
26. RoE allowed for the years 2012–2013 and 2013–2014 is given below:—
(Rs. in lakh)
Asset-I Asset-IV Particulars 2012–2013 2013–2014 2012–2013 2013–2014 Opening Equity 1325.59 1462.59 3499.73 3554.71 Addition due to Additional Capitalisation 137.00 132.48 54.97 664.97 Closing Equity 1462.59 1595.07 3554.71 4219.67 Average Equity 1394.09 1528.83 3527.22 3887.19 Return on Equity (Base Rate) 15.50% 15.50% 15.50% 15.50% Tax rate for the year 2008–2009 (MAT) 11.330% 11.330% 11.330% 11.330% Rate of Return on Equity (Pre Tax) 17.481% 17.481% 17.481% 17.481% Return on Equity (Pre Tax) 81.23 267.26 51.38 679.52
Interest on loan
27. Regulation 16 of the 2009 Tariff Regulations provides as under:—
“16. Interest on loan capital (1) The loans arrived at in the manner indicated in regulation 12 shall be considered as gross normative loan for calculation of interest on loan.
(2) The normative loan outstanding as on 1.4.2009 shall be worked out by deducting the cumulative repayment as admitted by the Commission up to 31.3.2009 from the gross normative loan.
(3) The repayment for the year of the tariff period 2009–2014 shall be deemed to be equal to the depreciation allowed for that year:
(4) Notwithstanding any moratorium period availed by the generating company or the transmission licensee, as the case may be the repayment of loan shall be considered from the first year of commercial operation of the project and shall be equal to the annual depreciation allowed.
(5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio at the beginning of each year applicable to the project:
Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered:
Provided further that if the generating station or the transmission system, as the case may be, does not have actual loan, then the weighted average rate of interest of the generating company or the transmission licensee as a whole shall be considered.
(6) The interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest.
(7) The generating company or the transmission licensee, as the case may be, shall make every effort to re-finance the loan as long as it results in net savings on interest and in that event the costs associated with such re-financing shall be borne by the beneficiaries and the net savings shall be shared between the beneficiaries and the generating company or the transmission licensee, as the case may be, in the ratio of 2:1.
(8) The changes to the terms and conditions of the loans shall be reflected from the date of such re-financing.
(9) In case of dispute, any of the parties may make an application in accordance with the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999, as amended from time to time, including statutory re-enactment thereof for settlement of the dispute:
Provided that the beneficiary or the transmission customers shall not withhold any payment on account of the interest claimed by the generating company or the transmission licensee during the pendency of any dispute arising out of re-financing of loan.”
28. In keeping with the provisions of Regulation 16, the petitioner's entitlement to interest on loan has been calculated on the following basis:—
(a) Gross amount of loan, repayment of instalments and rate of interest and weighted average rate of interest on actual average loan have been considered as per the petition.
(b) The repayment for the tariff period 2009–2014 shall be deemed to be equal to the depreciation allowed for that period.
(c) Notwithstanding moratorium period availed by the transmission licensee, the repayment of the loan shall be considered from the first year of commercial operation of the project and shall be equal to the annual depreciation allowed.
(d) Weighted average rate of interest on actual average loan worked out as per (a) above is applied on the notional average loan during the year to arrive at the interest on loan.
29. Detailed calculations in support of the weighted average rate of interest have been given in Annexure I (for Asset-I) and Annexure II (for Asset-IV) to this order.
30. Based on the above, interest on loan has been calculated as per details given overleaf:—
(Rs. in lakh)
Asset - I Asset - IV Particulars 2012–2013 2013–2014 2012–2013 2013–2014 Gross Normative Loan 3093.05 3412.73 8166.05 8294.31 Cumulative Repayment upto previous year 0.00 82.07 0.00 51.73 Net Loan-Opening 3093.05 3330.66 8166.05 8242.58 Addition due to additional capital expenditure 319.68 309.11 128.27 1551.59 Repayment during the year 82.07 270.20 51.73 684.15 Net Loan-Closing 3330.66 3369.57 8242.58 9110.03 Average Loan 3211.86 3350.12 8204.31 8676.30 Weighted Average Rate of Interest on Loan 9.4578% 9.4591% 9.2517% 9.2528% Interest 101.26 316.89 63.25 802.80
Depreciation
31. Regulation 17 of the 2009 Tariff Regulations provides as under:—
“17. Depreciation (1) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission.
(2) The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the capital cost of the asset.
Provided that in case of hydro generating stations, the salvage value shall be as provided in the agreement signed by the developers with the State Government for creation of the site;
Provided further that the capital cost of the assets of the hydro generating station for the purpose of computation of depreciable value shall correspond to the percentage of sale of electricity under long-term power purchase agreement at regulated tariff.
(3) Land other than the land held under lease and the land for reservoir in case of hydro generating station shall not be a depreciable asset and its cost shall be excluded from the capital cost while computing depreciable value of the asset.
(4) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-III to these regulations for the assets of the generating station and transmission system:
Provided that, the remaining depreciable value as on 31 March of the year closing after a period of 12 years from date of commercial operation shall be spread over the balance useful life of the assets.
(5) In case of the existing projects, the balance depreciable value as on 1.4.2009 shall be worked out by deducting the cumulative depreciation as admitted by the Commission up to 31.3.2009 from the gross depreciable value of the assets.
(6) Depreciation shall be chargeable from the first year of commercial operation. In case of commercial operation of the asset for part of the year, depreciation shall be charged on pro rata basis.”
32. The petitioner has claimed actual depreciation. In our calculations, depreciation has been calculated in accordance with clause (4) of regulation 17 extracted above.
33. Both the assets were put under commercial operation during 2012–2013. Accordingly, these assets will complete 12 years beyond 2013–2014 and hence depreciation has been calculated annually based on Straight Line Method at the rates specified in Appendix-III to the 2009 Tariff Regulations, as per details given hereunder:—
(Rs. in lakh)
Asset - I Asset - IV Particulars 2012–2013 2013–2014 2012–2013 2013–2014 Opening Gross Block 4418.65 4875.33 11665.78 11849.02 Addition due to Projected Additional Capitalisation 456.68 441.59 183.24 2216.56 Closing Gross Block 4875.33 5316.92 11849.02 14065.58 Average Gross Block 4646.99 5096.12 11757.40 12957.30 Rate of Depreciation 5.2980% 5.3022% 5.2800% 5.2800% Depreciable Value 4182.29 4586.51 10581.66 11661.57 Remaining Depreciable Value 4182.29 4504.44 10581.66 11609.84 Depreciation 82.07 270.20 51.73 684.15 Cumulative Depreciation 82.07 352.27 51.73 735.88
Operation & maintenance expenses
34. Clause (g) of Regulation 19 of the Tariff Regulations prescribes the norms for operation and maintenance expenses for the transmission system based on the type of sub-station and the transmission line. Norms prescribed in respect of the elements covered in the instant petition are as under:—
Element 2009–2010 2010–2011 2011–2012 2012–2013 2013–2014 D/C four or more conductor transmission line (Rs. lakh per km.) 0.940 0.994 1.051 1.111 1.174 400 kV bay (Rs. lakh per bay) 52.40 55.40 58.57 61.97 65.46 765 kV bay (Rs. lakh per bay) 73.36 77.56 81.99 86.68 91.64
35. The allowable O&M expenses for the assets are as under:—
(Rs. in lakh)
Element 2009–2010 2010–2011 2011–2012 2012–2013 (Pro-rata for 4 months) 2013–2014 Asset-I 8.72 Km. 400 kV D/C four conductor T/L - - - 3.23 10.24 400 kV Patna sub-station (4 Nos. 400 kV bays) - - - 82.56 261.84 Total - - - 85.79 272.08 Asset-IV 765/400 kV Sub-station at Sasaram 2009–2010 2010–2011 2011–2012 2012–2013 (Pro-rata for 1 month) 2013–2014 1 No. 765 kV bay - - - 7.22 91.64 1 No. 400 kV bay - - - 5.16 65.46 Total - - - 12.38 157.10
36. The petitioner has stated that O&M expenditure for 2009–2014 tariff block had been arrived on the basis of normalized actual O&M expenses of the petitioner during the year 2003–2004 to 2007–2008. The wage hike of 50% on account of pay revision of the employees of public sector undertaking was also considered while calculating the O&M charges for tariff period 2009–2014. The petitioner has submitted that it would approach the Commission for suitable revision in the norms for O&M expenditure in case the impact of wage hike w.e.f 1.1.2007 is more than 50%.
37. While specifying the norms for Operation and Maintenance Expenses, the Commission has in the 2009 Tariff Regulations already factored 50% on account of pay revision of the employees of PSUs after extensive consultation with the stakeholders. At this stage there does not seem to be any justification for deviating from the norms. However, in case the petitioner separately approaches the Commission by making an appropriate application, the same shall be dealt with in accordance with law.
Interest on working capital
38. The petitioner is entitled to claim interest on working capital as per the 2009 Tariff Regulations. The components of the working capital and the petitioner's entitlement to interest thereon are discussed hereunder:—
(i) Receivables
As per Regulation 18(1)(c)(i) of the 2009 Tariff Regulations, receivables as a component of working capital will be equivalent to two months' fixed cost. The petitioner has claimed the receivables on the basis of 2 months' annual transmission charges claimed in the petition. In the tariff being allowed, receivables have been worked out on the basis of 2 months' transmission charges.
(ii) Maintenance spares
Regulation 18(1)(c)(ii) of the Tariff Regulations provides for maintenance spares @ 15% per annum of the O. & M. expenses as part of the working capital from 1.4.2009 The value of maintenance spares has accordingly been worked out.
(iii) O. & M. expenses
Regulation 18(1)(c)(iii) of the Tariff Regulations provides for operation and maintenance expenses for one month to be included in the working capital. The petitioner has claimed O&M expenses for 1 month of the respective year. This has been considered in the working capital.
(iv) Rate of interest on working capital
Interest on working capital has been worked out considering interest rate @ 13.5% (Base rate as on 1.4.2012, i.e 10% and 350 basis points) for the assets. The interest on working capital for the assets covered in the petition has been worked out accordingly.
39. Necessary computations in support of interest on working capital are appended hereunder:—
(Rs. in lakh)
Asset - I Asset - IV Particulars 2012–2013 2013–2014 2012–2013 2013–2014 Maintenance Spares 38.61 40.81 22.28 23.57 O & M Expenses 21.45 22.67 12.38 13.09 Receivables 180.59 193.52 366.52 397.02 Total 240.64 257.01 401.19 433.68 Rate of Interest 13.50% 13.50% 13.50% 13.50% Interest 10.83 34.70 4.51 58.55
Transmission charges
40. The transmission charges being allowed for the transmission assets are summarized hereunder:—
(Rs. in lakh)
Asset - I Asset - IV Particulars 2012–2013 2013–2014 2012–2013 2013–2014 Depreciation 82.07 270.20 51.73 684.15 Interest on Loan 101.26 316.89 63.25 802.80 Return on Equity 81.23 267.26 51.38 679.52 Interest on Working Capital 10.83 34.70 4.51 58.55 O & M Expenses 85.79 272.08 12.38 157.10 Total 361.17 1161.13 183.26 2382.11
41. The transmission charges approved for the year 2012–2013 are on pro rata basis. The transmission charges allowed are lower than those claimed by the petitioner. This is for the reason of reduction in capital cost on account of time and cost over-run.
42. The transmission charges allowed are subject to truing up in accordance with the 2009 Tariff Regulations.
Filing fee and the publication expenses
43. The petitioner has sought reimbursement of fee paid by it for filing the petition and publication expenses. BRPL has submitted that the claim of the petitioner for filing fee and publication expenses is liable to be rejected in view of the order of the Commission dated 11.9.2008 in Petition No. 129 of 2005. The petitioner has clarified that reimbursement of expenditure has been claimed in terms of Regulation 42 of the 2009 Tariff Regulations. In accordance with the Commission's order dated 11.1.2010 in Petition No. 109/2009, the petitioner shall be entitled to recover the filing fee directly from the beneficiaries on pro-rata basis. The petitioner shall also be entitled for reimbursement of the publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis.
Licence fee
44. The petitioner has submitted that in O&M norms for tariff block 2009–2014 the cost associated with license fees had not been captured and the license fee may be allowed to be recovered separately from the respondents. BRPL has submitted that the petitioner's request for reimbursement for licence fee should be rejected as license fee is the eligibility fee of a licence holder and it is the onus of the petitioner. The petitioner has clarified that the licence fee has been a new component of cost to the transmission licence under O&M stage of the project and has become incidental to the petitioner only from 2008–2009.
45. The petitioner shall be entitled for reimbursement of licence fee in accordance with Regulation 42A(1)(b) of the 2009 Tariff Regulations.
Service tax
46. The petitioner has made a prayer to be allowed to bill and recover the service tax on transmission charges separately from the respondents, if it is subjected to such service tax in future. The BRPL has objected to recovery of service tax from the beneficiaries in future as CBEC has exempted service tax on transmission. The petitioner has clarified that if notifications regarding granting of exemption to transmission service are withdrawn at a later date, the beneficiaries shall have to share the service tax paid by the petitioner. We consider petitioner's prayer pre-mature and accordingly this prayer is rejected.
Sharing of Transmission Charges
47. The billing, collection and disbursement of the transmission charges approved shall be governed by the provisions of Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, as amended from time to time.
48. This order disposes of Petition Nos. 101.TT/2012.
Alert