Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Power Grid Corporation Of India Ltd. v. Madhya Pradesh Power Trading Company Ltd.

Central Electricity Regulatory Commission
Feb 11, 2011
Smart Summary (Beta)

Factual and Procedural Background

The petitioner filed Petition No. 175/2010 seeking approval of transmission tariff for a bundle of transmission assets in the Western Region (referred to in the order as "the transmission assets") for the tariff block 2009-2014 under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 ("the 2009 regulations").

The transmission assets for which tariff approval was sought comprised: (i) extension of 400/220 kV Kolhapur (MSEB) sub-station; (ii) 220 kV D/C Vapi–Magarwada transmission line; and (iii) 220 kV D/C Vapi–Khardpada transmission line together with associated bays in the WRSS-III transmission system.

The petition set out a number of specific reliefs (including approval of capitalisation/additional capital expenditure, relaxation to gross up Return on Equity (ROE) for tax changes, approval to recover depreciation, reimbursement of petition filing and publication expenses, and permission to bill service tax and licence fee separately). Investment approval was shown to have been accorded by the petitioner’s Board on 20.2.2006 at an estimated cost of Rs. 7,565 lakh (including IDC of Rs. 219 lakh at 3rd quarter, 2005 price level).

Transmission charges for the assets up to 31.3.2009 had already been approved by the Commission by its order dated 23.2.2010 in Petition No. 217/2009; the petitioner sought tariff for the 2009–2014 block using the admitted capital cost as on 1.4.2009 and projected additional capitalisation during the block.

The Commission heard the parties, considered responses (including an objection from Madhya Pradesh Power Trading Company Limited (MPPTCL)), and proceeded to dispose of the petition by the order summarized in the provided text.

Legal Issues Presented

  1. Whether approval of transmission tariff for the specified transmission assets for the tariff block 2009–2014 should be granted under the 2009 regulations using the admitted capital cost as on 1.4.2009 and the claimed additional capitalisation.
  2. Whether the Commission should invoke Regulation 44 (power to relax) of the 2009 regulations to relax clause (3) of Regulation 15 so as to allow grossing up the base rate of ROE to reflect revised tax rates (e.g., MAT, surcharge, cesses) and permit year-to-year truing up/settlement with beneficiaries.
  3. Whether the petitioner may recover full depreciation (up to 90% of gross block) of the assets during their useful life.
  4. Whether additional capital expenditure (Add Cap) claimed after the cutoff date—specifically Rs. 781.21 lakh for 2010–2011—should be admitted for tariff purposes.
  5. Whether the petitioner is entitled to reimbursement from beneficiaries for petition filing fees and publication expenses.
  6. Whether the petitioner may bill and recover Service Tax and licence fee separately from respondents if subjected to those charges in future.

Arguments of the Parties

Petitioner

  • Sought approval of transmission tariff for the transmission assets for 2009–2014 based on the 2009 regulations, using admitted capital cost as on 1.4.2009 plus additional capitalisation claimed for 2009–2014.
  • Prayed for invocation of Regulation 44 to relax Regulation 15(3) so that grossing up ROE may reflect revised MAT, surcharge, cesses and other levies, and allow consequential truing up to be billed and settled year-to-year with beneficiaries.
  • Claimed additional capital expenditure, including Rs. 781.21 lakh projected for 2010–2011 on account of balance and retention payments (undischarged liabilities).
  • Requested permission to recover full depreciation (90% of gross block), to recover filing fees and publication expenses from beneficiaries, and to separately bill Service Tax and licence fee if applicable.
  • Clarified (affidavit dated 9.12.2010) that the notional date of commercial operation for the assets is 1.7.2008 and requested that cut-off date be considered in accordance with the definition in the 2009 regulations.

Madya Pradesh Power Trading Company Limited (MPPTCL)

  • Admitted the additional capital expenditure of Rs. 51.49 lakh during 2009–2010 (claimed by the petitioner) as being within the cut-off date and permissible under Regulation 9(1) of the 2009 regulations.
  • Objected to admission of the additional capital expenditure of Rs. 781.21 lakh during 2010–2011, contending it is not in accordance with the 2009 regulations because it represented undischarged liability incurred after the cut-off date (objected under Regulation 9(2)).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Commission order dated 23.2.2010 in Petition No. 217/2009 Admission of capital cost as on 31.3.2009 (used as the admitted capital cost baseline prior to 1.4.2009 under Regulation 7, proviso). The Commission relied on that admitted capital cost of Rs. 3,834.54 lakh as on 31.3.2009 and treated the capital expenditure of Rs. 3,834.54 lakh as on 1.4.2009 for tariff determination for 2009–2014; details in interest-on-loan calculations were also taken from that order.
Commission order dated 8.2.2011 in Petition No. 176/2010 Relaxation of Regulation 9(2) to permit capitalisation of expenditure incurred after the cut-off date for balance and retention payments (explicit regulatory relaxation applied by the Commission). The Commission applied the relaxation announced in that order to admit the petitioner’s projected expenditure of Rs. 781.21 lakh during 2010–2011 in respect of Asset-II and Asset-III for tariff determination.
Commission order dated 3.8.2010 in Petition No. 17/2010 Directed that the generic issue of grossing up the base rate with the applicable tax rate be addressed by amending the 2009 regulations and provided that tax liability settlement between licensee and beneficiaries should be on a year-to-year basis with true-up. The Commission noted this prior direction. Pending any amendment or decision on revision of MAT rate, the Commission computed ROE strictly as per Regulation 15 of the 2009 regulations (i.e., using the base rate and tax rate for 2008–2009) for the present order.
Commission order dated 11.1.2010 in Petition No. 109/2009 Authority for recovery of petition filing fees from beneficiaries. Applied to allow the petitioner to recover filing fees and publication expenses from beneficiaries on a pro rata basis in connection with the present petition.

Court's Reasoning and Analysis

The Commission proceeded by applying the relevant provisions of the 2009 regulations to the facts and claims made by the petitioner. The key steps in its legal analysis (drawn verbatim from the reasoning in the order) are summarized below:

  1. Capital Cost: The Commission took the admitted capital cost as on 31.3.2009 (Rs. 3,834.54 lakh) from its earlier order in Petition No. 217/2009 and used that as the capital cost as on 1.4.2009 for tariff determination for 2009–2014, consistent with the proviso to clause (2) of Regulation 7 of the 2009 regulations.
  2. Additional Capital Expenditure (Add Cap): The petitioner claimed projected Add Cap for 2009–2014 amounting in part to Rs. 781.21 lakh for 2010–2011 (balance and retention payments). MPPTCL objected that undischarged liabilities after the cut-off date were not permissible under Regulation 9(2). The petitioner argued the notional date of commercial operation was 1.7.2008 and asked for the cut-off date to be considered under the 2009 regulations. The Commission noted that it had already relaxed Regulation 9(2) in its order dated 8.2.2011 in Petition No. 176/2010 to permit capitalisation of expenditure incurred after the cutoff date on account of balance and retention payments; accordingly, the Commission admitted the Rs. 781.21 lakh for tariff calculation.
  3. Debt–Equity Ratio: The Commission applied clause (2) of Regulation 12 of the 2009 regulations which requires that where commercial operation was prior to 1.4.2009, the debt–equity ratio allowed by the Commission for the period ending 31.3.2009 should be considered. The admitted capital as on 31.3.2009 showed a combined debt–equity of 70.01:29.99, which was used for capital cost as on 1.4.2009. For additional capitalisation, the Commission applied the normative debt–equity split (70:30) for the respective years and amounts (e.g., Rs. 51.49 lakh in 2009–10 and Rs. 781.21 lakh in 2010–11 were split on normative percentages).
  4. Return on Equity (ROE): Regulation 15 prescribes ROE computation: base rate of 15.5% pre-tax to be grossed up by the normal tax rate for 2008–2009 (clause (3)), with truing up per year. The petitioner computed ROE grossing up at 11.33% tax (MAT) to claim a pre-tax ROE of 17.481%. The petitioner’s request to invoke Regulation 44 to relax Regulation 15(3) to permit grossing up with revised tax rates was noted; the Commission referred to its earlier direction in Petition No. 17/2010 to prepare amendments to allow grossing up with applicable tax rates per Finance Act and year-to-year settlement with beneficiaries. Pending any decision on revision of the MAT rate or regulatory amendment, the Commission computed ROE strictly under the 2009 regulations using the 11.33% tax figure and therefore adopted the pre-tax ROE of 17.481% for the tariff block.
  5. Interest on Loan: The Commission applied Regulation 16. It used normative loan figures, treated cumulative repayment up to 31.3.2009 as per the earlier order (Petition No. 217/2009), applied normative repayments equal to depreciation, and computed interest on normative average loan applying the weighted average rate of interest (computed from the project’s actual loan portfolio and schedules). The weighted average rates (around 9.339%–9.344%) were applied to compute interest on loan for each year.
  6. Depreciation: The Commission computed depreciation following Regulation 17: depreciable value = 90% of capital cost; depreciation computed on straight line basis at rates specified in Appendix-III. The remaining depreciable value and annual depreciation figures were calculated for each year and used as normative repayment for loans.
  7. Operation & Maintenance (O&M) Expenses: The Commission applied the norms prescribed in clause (g) of Regulation 19 based on the type and length of lines, bay numbers and substation, accepted the petitioner’s calculation in accordance with those norms, and allowed O&M as claimed per year.
  8. Interest on Working Capital: The Commission applied Regulation 18 components: maintenance spares at 15% of O&M, O&M for one month, receivables equivalent to two months' billing at target availability. Rate of interest on working capital was the normative SBI PLR as on 1.4.2009 (12.25%), and the Commission allowed interest on working capital at that rate.
  9. Application Fee & Publication: Relying on its earlier order in Petition No. 109/2009, the Commission held that the petitioner is entitled to recover the filing fee and publication expenses from beneficiaries and ordered direct recovery on a pro rata basis.
  10. Service Tax and Licence Fee: The petitioner’s broad prayer to bill and recover Service Tax on transmission charges and to bill licence fee separately was addressed. The Commission treated the Service Tax prayer as premature and indicated that if the petitioner files a separate application, it will be considered in accordance with law.
  11. Recovery and Sharing: The Commission directed that the transmission charges allowed would be recovered on a monthly basis in accordance with Regulation 23 and shared by respondents according to Regulation 33 of the 2009 regulations.

Holding and Implications

Holding:

The Commission issued an order disposing of Petition No. 175/2010 and, in that order, allowed transmission charges for the transmission assets for the tariff block 2009–2014. The core rulings included:

  • Admitted capital cost as on 1.4.2009: Rs. 3,834.54 lakh (as admitted earlier in Petition No. 217/2009) was taken as the base for tariff determination.
  • Additional capitalisation admitted: Projected capitalisation of Rs. 781.21 lakh during 2010–2011 (balance and retention payments for Asset-II and Asset-III) was admitted for tariff calculation, applying the relaxation previously announced in Petition No. 176/2010.
  • ROE: Pre-tax ROE of 17.481% was adopted for tariff computation (computed by grossing up base 15.5% with the 11.33% tax rate applicable for 2008–2009) pending any regulatory amendment on grossing up methodology.
  • Financial components: Depreciation, interest on loan, O&M, interest on working capital and total allowed transmission charges were computed and allowed as detailed in the order (yearwise totals summarized below).
  • Application fees and publication expenses: Allowed to be recovered from beneficiaries on a pro rata basis (per Petition No. 109/2009).
  • Service tax: Petitioner’s general prayer to bill service tax separately was held to be premature; any such claim must be the subject of a separate application.

The direct financial effect on the parties (as allowed in the order) is summarized by the annual totals the Commission allowed as transmission charges for each year of the block:

Transmission charges allowed (Rs. in lakh):

  • 2009–2010: Total 877.34 (Depreciation 204.09; Interest on Loan 232.80; ROE 202.41; Interest on WC 24.03; O&M 214.01)
  • 2010–2011: Total 942.27 (Depreciation 226.08; Interest on Loan 239.98; ROE 224.24; Interest on WC 25.70; O&M 226.25)
  • 2011–2012: Total 1,001.48 (Depreciation 246.71; Interest on Loan 243.52; ROE 244.73; Interest on WC 27.29; O&M 239.24)
  • 2012–2013: Total 992.27 (Depreciation 246.71; Interest on Loan 220.46; ROE 244.73; Interest on WC 27.49; O&M 252.89)
  • 2013–2014: Total 983.93 (Depreciation 246.71; Interest on Loan 197.42; ROE 244.73; Interest on WC 27.73; O&M 267.34)

Implications:

  • The immediate consequence is that the petitioner may recover the allowed tariff components on a monthly basis from beneficiaries, apportioned as per the applicable regulations (Regulations 23 and 33 of the 2009 regulations).
  • The admitted additional capital expenditure of Rs. 781.21 lakh for 2010–2011 (balance/retention payments) is accepted for tariff purposes by applying a regulatory relaxation previously made by the Commission; this admission affects the capital base and therefore the components of tariff (depreciation, interest, ROE).
  • The Commission did not grant a blanket change to the ROE grossing-up methodology in this order; instead, it applied the 2009 regulations as they stood and awaited a formal amendment (as directed in Petition No. 17/2010) before changing the approach to grossing up ROE with tax rates applicable under subsequent Finance Acts. Therefore, any change in the grossing-up approach remains subject to a separate regulatory amendment and/or final determination, with truing up envisaged.
  • No final decision was made in this order on the separate recovery of Service Tax or licence fee; those matters remain for separate application(s) if the petitioner seeks relief in future.
  • No new legal precedent beyond application of the 2009 regulations and prior Commission orders was established by this order; the decision implements the regulatory provisions and prior Commission directions to the facts of this petition and provides the specific financial determinations summarized above.

Final administrative note from the order: This order disposes of Petition No. 175/2010.

Show all summary ...

This petition has been filed seeking approval of transmission tariff in respect of combined elements of (i) extension of 400/220 kV Kolhapur (MSEB) sub-station; (ii) 220 kV D/C Vapi-Magarwada transmission line; and (iii) 220 kV D/C Vapi-Khardpada transmission line along with associated bays with WRSS-III transmission system in Western Region (hereinafter called “the transmission assets”) for tariff block 2009-2014 period based on the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009, (hereinafter referred to as “the 2009 regulations”). The petitioner has also sought the following reliefs:

(a) Invoke the provisions of Regulation 44(Power to Relax) of the 2009 regulations, for relaxation of clause (3) of regulation 15 thereof so that grossing up the base rate of Return on Equity (ROE) may be allowed considering the revised rate of MAT, surcharge, any other cess, charges, levies etc. as per the relevant Finance Acts and accordingly allow consequential impact of tariff on account of truing up, to be billed and settled directly with the beneficiaries every year in the tariff block.

(b) Allow the petitioner to recover full depreciation (90% of the gross block) of the assets during its useful life.

(c) Approve the reimbursement, of expenditure, by the beneficiaries towards petition filing fee, and publishing of notices in newspapers in terms of Regulation 42 of the 2009 regulations, and other expenditure (if any) in relation to the filing of petition.

(d) Allow the petitioner to bill and recover Service Tax on Transmission charges separately from the respondents, if petitioner is subjected to such service tax.

(e) Allow the petitioner to bill and recover licence fee separately from the respondents

(f) Pass such other relief as Hon'ble Commission deems fit and appropriate under the circumstances of the case and in the interest of justice.

2. The investment approval for the transmission system was accorded by Board of Directors of the petitioner company vide memorandum dated 20.2.2006 at an estimated cost of Rs. 7565 lakh which included IDC of Rs. 219 lakh, at 3rd quarter, 2005 price level.

3. Transmission charges for the transmission assets for the period upto 31.3.2009 were approved by the Commission vide order dated 23.2.2010 in Petition No. 217/2009.

4. The petitioner has claimed the following transmission charges:

(Rs. in lakh)

2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Depreciation 204.09 226.08 246.71 246.71 246.71 Interest on Loan 232.80 239.99 243.52 220.46 197.42 Return on equity 202.41 224.24 244.73 244.73 244.73 Interest on Working Capital 24.03 25.70 27.29 27.49 27.73 O & M Expenses 214.01 226.25 239.24 252.89 267.34 Total 877.34 942.26 1001.49 992.28 983.93

5. The details submitted by the petitioner in support of its claim for interest on working capital are given hereunder:

(Rs. in lakh)

2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Maintenance Spares 32.10 33.94 35.89 37.93 40.10 O & M expenses 17.83 18.85 19.94 21.07 22.28 Receivables 146.22 157.04 166.92 165.38 163.99 Total 196.15 209.83 222.75 224.38 226.37 Interest 24.03 25.70 27.29 27.49 27.73 Rate of Interest 12.25% 12.25% 12.25% 12.25% 12.25%

6. No reply has been received from the general public in relation to public notice. Madya Pradesh Power Trading Company Limited (MPPTCL) in its reply affidavit dated 11.1.2011 has submitted that additional capital expenditure of Rs. 51.49 lakh during 2009-2010 claimed by the petitioner on account of undischarged liability can be admitted under Regulation 9(1) of 2009 regulations being within the cut-off date and additional capital expenditure of Rs. 781.21 during 2010-2011 being not in accordance with the 2009 regulations should not be admitted. The objection of MPPTCL has been dealt with in subsequently in this order.

7. Having heard the representatives of the parties and examined the material on record, we proceed to dispose of the petition.

CAPITAL COST

8. Last Proviso to clause (2) of regulation 7 of the 2009 regulations, provides as under:

“Provided also that in case of the existing projects, the capital cost admitted by the Commission prior to 1.4.2009 and the additional capital expenditure projected to be incurred for the respective year of the tariff period 2009-2014, as may be admitted by the Commission, shall form the basis for determination of tariff.”

9. As per the Commission's order dated 23.2.2010 in Petition No. 217/2009, the Commission had admitted the capital cost of Rs. 3834.54 lakh as on 31.3.2009 Accordingly, capital expenditure of Rs. 3834.54 lakh as on 1.4.2009 has been considered for tariff determination for 2009-2014 period.

ADDITIONAL CAPITAL EXPENDITURE

10. Details of the projected additional capital expenditure (hereinafter referred to as “Add Cap”) claimed by the petitioner are as under:

(Rs. in lakh)

1 2 3 4 5 7 Name of the Asset Apportioned approved cost Actual capital cost incurred as on 31.3.2009 Add cap 2009-2010 Add cap 2010-2011 Total Capital. Cost Asset-I 1045.19 478.47 0.00 0.00 478.47 Asset-II 3634.00 1888.27 29.30 380.40 2297.97 Asset-III 2886.00 1467.80 22.19 400.81 1890.80

11. Category-wise breakup of the additional capital expenditure is as under:

Name of Asset Year Nature Amount (Rs. in lakh) Details of Expenditure ASSET-1 No Add-Cap during 2009-14 period TL 8.23 Final/Balance Retention Payments 2009-2010 Sub-Station 20.44 ASSET-2 PLCC 0.63 TL 380.30 Final/Balance Retention Payments 2010-2011 Sub-Station 0.10 TL 4.13 Final/Balance Retention Payments 2009-2010 Sub-Station 17.51 ASSET-3 PLCC 0.55 2010-2011 TL 400.73 Final/Balance Retention Payments Sub-Station 0.08 Total 832.7

12. We find that Rs. 781.21 lakhs has been projected to be incurred during 1011 on account of balance and retention payments. MPPTCL has objected to the claim on the ground that undischarged liability incurred after the cutoff date is not permissible under Regulation 9(2) of the 2009 regulations. The petitioner vide its affidavit dated 9.12.2010 has clarified that the notional date of commercial operation of the assets involved in the petition being 1.7.2008, the tariff block 2004-2009 expired on 31.3.2009, before the expiry of the cut off date as per the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004, (hereinafter referred to as “the 2004 regulations”) and has requested that the cut-off date of the transmission assets be considered in accordance with the definition of the term in the 2009 regulations.

13. In our view, the cutoff date under Regulation 3(11) of the 2009 regulations cannot be given retrospective application in case of the generating stations which achieved their commercial operation during 2004-2009. However, we have decided in our order dated 8.2.2011 in Petition No. 176/2010 to relax the provisions of Regulation 9(2) of the 2009 regulations to permit capitalization of expenditure incurred after the cutoff date on account of balance and retention payments. Accordingly, the projected expenditure of Rs. 781.21 lakh during 2010-2011 in respect of Asset-II and III have been considered for determination of tariff.

DEBT-EQUITY RATIO

14. Clause (2) of Regulation 12 of the 2009 regulations inter alia provides that,—

“(2) In case of the generating station and the transmission system declared under commercial operation prior to 1.4.2009, debt-equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2009 shall be considered.”

15. Details of debt-equity considered by the petitioner for the transmission assets with regard to the additional capital expenditure for the year 2009-2010 is as under:—

Asset I Admitted as on 31.03.2009 (Rs. in lakh) % Debt 334.93 70.00% Equity 143.54 30.00% Total 478.47 100.00% Asset II (Rs. in lakh) % Debt 1321.99 70.01% Equity 566.28 29.99% Total 1888.27 100.00% Asset III (Rs. in lakh) % Debt 1027.46 70.00% Equity 440.34 30.00% Total 1467.80 100.00% Combined Admitted as on 31.03.2009 (Rs. in lakh) % Debt 2684.38 70.01% Equity 1150.16 29.99% Total 3834.54 100.00%

16. Based on the above debt-equity ratio of 70.01:29.99 has been considered for the capital cost as on 1.4.2010 As regards the additional capital expenditure. Details of the normative debt-equity ratio as given below is applied:

2009-2010 Normative Amount (Rs. in lakh) % Debt 36.04 69.99% Equity 15.45 30.01% Total 51.49 100.00% 2010-2011 Normative Amount (Rs. in lakh) % Debt 546.85 70.00% Equity 234.36 30.00% Total 781.21 100.00%

RETURN ON EQUITY

17. Regulation 15 of the 2009 regulations provides that,—

“15. (1) Return on equity shall be computed in rupee terms, on the equity base determined in accordance with regulation 12.

(2) Return on equity shall be computed on pre-tax basis at the base rate of 15.5% to be grossed up as per clause (3) of this regulation:

Provided that in case ofprojects commissioned on or after 1st April, 2009, an additional return of 0.5% shall be allowed if such projects are completed within the timeline specified in Appendix-II:

Provided further that the additional return of 0.5% shall not be admissible if the project is not completed within the timeline specified above for reasons whatsoever.

(3) The rate of return on equity shall be computed by grossing up the base rate with the normal tax rate for the year 2008-2009 applicable to the concerned generating company or the transmission licensee, as the case may be:

Provided that return on equity with respect to the actual tax rate applicable to the generating company or the transmission licensee, as the case may be, in line with the provisions of the relevant Finance Acts of the respective year during the tariff period shall be trued up separately for each year of the tariff period along with the tariff petition filed for the next tariff period.

(4) Rate of return on equity shall be rounded off to three decimal points and be computed as per the formula given below:

Rate of pre-tax return on equity = Base rate/(1-t)

Where t is the applicable tax rate in accordance with clause (3) of this regulation.

………………………………………………………………………”

18. The petitioner has computed ROE on pre-tax basis on 11.33% MAT in accordance with the tax rate applicable for 2008-2009 and has claimed return on equity @ 17.481%.

19. Petitioner's prayer to invoke the provisions of Regulation 44 of the 2009 regulations for relaxation of Regulation 15(3) thereof so that grossing up the base rate of ROE may be allowed considering the tax rates viz., MAT, surcharge, any other cess, charges, levies etc., as per the relevant Finance Acts, has already been taken cognizance of in the Commission's order dated 3.8.2010 in Petition No. 17/2010 wherein a decision has been taken to address the issue raised by the petitioner. Relevant portion of the said order is extracted as under:

“We are of the view that this issue of ‘grossing up the base rate with the normal tax rate for the year 2008-2009’ is generic in nature and therefore, it will be appropriate to make suitable provisions in the 2009 regulations to cater to any future changes in the tax rate. Accordingly, we direct the staff of the Commission to prepare and submit draft amendment to the 2009 regulations for allowing grossing up of base rate of return with the applicable tax rate as per the Finance Act for the relevant year and direct settlement of tax liability between the generating company/transmission licensee and the beneficiaries/long term transmission customers on year to year basis. Any under/over recovery on account of direct settlement of tax liability shall be subject to the final adjustment at the time of true up exercise.”

20. Pending decision on revision of MAT rate, ROE has been computed as per Regulation 15 of the 2009 regulations, and pre-tax ROE of 17.481% has been considered.

21. Detailed calculation of the ROE in respect the transmission assets is as under:

(Rs. in lakh)

2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Gross Notional Equity 1150.16 Addition due to Additional Capitalisation 0.00 Opening Equity 1150.16 1150.16 1165.61 1399.97 1399.97 1399.97 Addition due to Additional Capitalisation 15.45 234.36 0.00 0.00 0.00 Closing Equity 1165.61 1399.97 1399.97 1399.97 1399.97 Average Equity 1157.88 1282.79 1399.97 1399.97 1399.97 Return on Equity (Base Rate) 15.50% 15.50% 15.50% 15.50% 15.50% Tax rate for the year 2008-2009 11.330% 11.330% 11.330% 11.330% 11.330% Rate of Return on Equity (Pre Tax) 17.481% 17.481% 17.481% 17.481% 17.481% Return on Equity (Pre Tax) 202.41 224.24 244.73 244.73 244.73

INTEREST ON LOAN

22. Regulation 16 of the 2009 regulations provides that,—

“16. (1) The loans arrived at in the manner indicated in regulation 12 shall be considered as gross normative loan for calculation of interest on loan.

(2) The normative loan outstanding as on 1.4.2009 shall be worked out by deducting the cumulative repayment as admitted by the Commission up to 31.3.2009 from the gross normative loan.

(3) The repayment for the year of the tariff period 2009-2014 shall be deemed to be equal to the depreciation allowed for that year:

(4) Notwithstanding any moratorium period availed by the generating company or the transmission licensee, as the case may be the repayment of loan shall be considered from the first year of commercial operation of the project and shall be equal to the annual depreciation allowed,.

(5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio at the beginning of each year applicable to the project:

Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered:

Provided further that if the generating station or the transmission system, as the case may be, does not have actual loan, then the weighted average rate of interest of the generating company or the transmission licensee as a whole shall be considered.

(6) The interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest.

(7) The generating company or the transmission licensee, as the case may be, shall make every effort to re-finance the loan as long as it results in net savings on interest and in that event the costs associated with such re-financing shall be borne by the beneficiaries and the net savings shall be shared between the beneficiaries and the generating company or the transmission licensee, as the case may be, in the ratio of 2:1.

(8) The changes to the terms and conditions of the loans shall be reflected from the date of such re-financing.

(9) In case of dispute, any of the parties may make an application in accordance with the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999, as amended from time to time, including statutory re-enactment thereof for settlement of the dispute:

Provided that the beneficiary or the transmission customers shall not withhold any payment on account of the interest claimed by the generating company or the transmission licensee during the pendency of any dispute arising out of re-financing of loan.”

23. In these calculations, interest on loan has been worked out as detailed below:

(a) Details of net outstanding loan as on 31.3.2009, cumulative repayment up to 31.3.2009, repayment schedule for the loans, rate of interest etc. have been taken from the order dated 23.02.2010 in petition no. 217/2009 for working out weighted average rate of interest.

(b) Tariff is worked out considering normative loan and normative repayments. Depreciation allowed has been taken as normative repayment for the tariff period 2009-2014.

(c) Weighted average rate of interest on actual loan worked out as above has been applied on the notional average loan during the year to arrive at the interest on loan.

24. Details of the calculation of Interest on Loan are as under:

(Rs. in lakh)

2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Gross Notional Loan 2684.38 Addition due to Additional Capitalisation 0.00 Gross Normative Loan 2684.38 2684.38 2720.42 3267.27 3267.27 3267.27 Cumulative Repayment upto Previous Year 107.53 311.62 537.71 784.41 1031.12 Net Loan-Opening 2576.85 2408.80 2729.56 2482.86 2236.15 Addition due to Additional Capitalisation 36.04 546.85 0.00 0.00 0.00 Repayment during the year 204.09 226.08 246.71 246.71 246.71 Net Loan-Closing 2408.80 2729.56 2482.86 2236.15 1989.44 Average Loan 2492.82 2569.18 2606.21 2359.50 2112.79 Weighted Average Rate of Interest on Loan 9.3389% 9.3409% 9.3437% 9.3436% 9.3441% Interest 232.80 239.98 243.52 220.46 197.42

DEPRECIATION

25. Regulation 17 of the 2009 regulations provides for computation of depreciation in the following manner, namely:

“17. (1) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission.

(2) The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the capital cost of the asset.

Provided that………………….

Provided further that…………….

(3) Land other than the land held under lease and the land for reservoir in case of hydro generating station shall not be a depreciable asset and its cost shall be excluded from the capital cost while computing depreciable value of the asset.

(4) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-III to these regulations for the assets of the generating station and transmission system:

Provided that, the remaining depreciable value as on 31st March of the year closing after a period of 12 years from date of commercial operation shall be spread over the balance useful life of the assets.

(5) In case of the existing projects, the balance depreciable value as on 1.4.2009 shall be worked out by deducting the cumulative depreciation as admitted by the Commission up to 31.3.2009 from the gross depreciable value of the assets.

(6) Depreciation shall be chargeable from the first year of commercial operation. In case of commercial operation of the asset for part of the year, depreciation shall be charged on pro rata basis.”

26. Depreciation has been worked out on the admitted capital expenditure as on 1.4.2009 and projected additional capitalization thereafter.

27. For the period 1.4.2009 to 31.3.2014 the depreciation worked out are as under:

(Rs. in lakh)

2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Rate of Depreciation 5.2870% 5.2865% 5.2859% 5.2859% 5.2859% Depreciable Value 90% 3474.26 3848.97 4200.52 4200.52 4200.52 Remaining Depreciable Value 3366.73 3537.35 3662.81 3416.10 3169.40 Depreciation 204.09 226.08 246.71 246.71 246.71

OPERATION&MAINTENANCE EXPENSES

28. Clause (g) of Regulation 19 of the 2009 regulations prescribes the norms for operation and maintenance expenses based on the type of substation and line. The petitioner has calculated the operation and maintenance expenses in accordance with the above norms and the same are allowed as such. The O&M expenditure allowed for the transmission assets are as under:

(Rs. in lakh)

Elements 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 55.37 Km., 220 kV D/C, Single Conductor Transmission Lines 14.89 15.73 16.67 17.61 18.60 One No. 400 kV Bay 52.40 55.40 58.57 61.92 65.46 4 Nos. 220 kV Bays 146.72 155.12 164.00 173.36 183.28 Total O&M for the Assets 214.01 226.25 239.24 252.89 267.34

INTEREST ON WORKING CAPITAL

29. As per the 2009 regulations the components of the working capital and the interest thereon are discussed hereunder:

(i) Receivables: As per Regulation 18(1)(c)(i) of the 2009 regulations, receivables will be equivalent to two months' average billing calculated on target availability level. The petitioner has claimed the receivables on the basis of 2 months' transmission charges claimed in the petition. In the tariff being allowed, receivables have been worked out on the basis of 2 months' transmission charges.

(ii) Maintenance spares: Regulation 18(1)(c)(ii) of the 2009 regulations provides for maintenance spares @ 15% per annum of the O&M expenses from 1.4.2009 The value of maintenance spares has accordingly been worked out.

(iii) O&M expenses: Regulation 18(1)(c)(iii) of the 2009 regulations provides for operation and maintenance expenses for one month as a component of working capital. The petitioner has claimed O&M expenses for 1 month of the respective year as claimed in the petition. This has been considered in the working capital.

(iv) Rate of interest on working capital: As per Regulation 18(3) of the 2009 regulations, rate of interest on working capital shall be on normative basis and shall be equal to the short-term Prime Lending Rate of State Bank of India as on 1.4.2009 or on 1st April of the year in which the project or part thereof (as the case may be) is declared under commercial operation, whichever is later. The interest on working capital is payable on normative basis notwithstanding that the transmission licensee has not taken working capital loan from any outside agency. The petitioner has claimed interest on working capital @ 12.25% based on SBI PLR as on 1.4.2009, which is in accordance with the 2009 regulations and has been allowed.

30. Necessary computations in support of interest on working capital are appended hereinbelow:

(Rs. in lakh)

2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Maintenance Spares 32.10 33.94 35.89 37.93 40.10 O & M expenses 17.83 18.85 19.94 21.07 22.28 Receivables 146.22 157.04 166.91 165.38 163.99 Total 196.16 209.84 222.74 224.39 226.37 Rate of Interest 12.25% 12.25% 12.25% 12.25% 12.25% Interest 24.03 25.70 27.29 27.49 27.73

TRANSMISSION CHARGES

31. The transmission charges being allowed for the transmission lines are summarized below:

(Rs. in lakh)

2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Depreciation 204.09 226.08 246.71 246.71 246.71 Interest on Loan 232.80 239.98 243.52 220.46 197.42 Return on equity 202.41 224.24 244.73 244.73 244.73 Interest on Working Capital 24.03 25.70 27.29 27.49 27.73 O & M Expenses 214.01 226.25 239.24 252.89 267.34 Total 877.34 942.27 1001.48 992.27 983.93

APPLICATION FEE AND THE PUBLICATION EXPENSES

32. The petitioner has sought approval for the reimbursement of fee paid by it for filing the petition. In accordance with our decision in order dated 11.1.2010 in Petition No. 109/2009, the petitioner shall be entitled to recover the filing fee from the beneficiaries.

33. Accordingly, expenses incurred by the petitioner on application filing fees and publication of notices in connection with the present petition shall be directly recovered from the beneficiaries on pro rata basis.

SERVICE TAX

34. The petitioner has made a specific prayer to be allowed to bill and recover the Service tax on Transmission charges separately from the respondents, if it is subjected to service tax in future. The prayer of the petitioner is premature. If the petitioner approaches the Commission by a separate application the same shall be considered in accordance with law.

35. The transmission charges allowed in this order shall be recovered on monthly basis in accordance with Regulation 23 and shall be shared by the respondents in accordance with Regulation 33 of the 2009 regulations.

36. This order disposes of Petition No. 175/2010.

Annexure

CALCULATION OF WEIGHTED AVERAGE RATE OF INTEREST ON LOAN

Details of Loan 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 1 Bond XXI Gross loan opening 270.00 270.00 270.00 270.00 270.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 22.50 45.00 67.50 Net Loan-Opening 270.00 270.00 247.50 225.00 202.50 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 22.50 22.50 22.50 22.50 Net Loan-Closing 270.00 247.50 225.00 202.50 180.00 Average Loan 270.00 258.75 236.25 213.75 191.25 Rate of Interest 8.73% 8.73% 8.73% 8.73% 8.73% Interest 23.57 22.59 20.62 18.66 16.70 Rep Schedule 12 Annual Instalments from 11.10.2010 2 Bond XXII Gross loan opening 78.00 78.00 78.00 78.00 78.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 6.50 13.00 19.50 Net Loan-Opening 78.00 78.00 71.50 65.00 58.50 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 6.50 6.50 6.50 6.50 Net Loan-Closing 78.00 71.50 65.00 58.50 52.00 Average Loan 78.00 74.75 68.25 61.75 55.25 Rate of Interest 8.68% 8.68% 8.68% 8.68% 8.68% Interest 6.77 6.49 5.92 5.36 4.80 Rep Schedule 12 Annual instalments from 07.12.2010 3 Bond XXVII Gross loan opening 1902.05 1902.05 1902.05 1902.05 1902.05 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 158.50 317.01 Net Loan-Opening 1902.05 1902.05 1902.05 1743.55 1585.04 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 158.50 158.50 158.50 Net Loan-Closing 1902.05 1902.05 1743.55 1585.04 1426.54 Average Loan 1902.05 1902.05 1822.80 1664.29 1505.79 Rate of Interest 9.47% 9.47% 9.47% 9.47% 9.47% Interest 180.12 180.12 172.62 157.61 142.60 Rep Schedule 12 Annual Instalments from 31.03.2012 4 Bond XXIX Gross loan opening 191.01 224.00 224.00 224.00 224.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 18.67 Net Loan-Opening 191.011 224.00 1224.00 1224.00 205.33 Additions during the year 32.99 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 18.67 18.67 Net Loan-Closing 224.00 224.00 224.00 205.33 186.67 Average Loan 207.51 224.00 224.00 214.67 196.00 Rate of Interest 9.20% 9.20% 9.20% 9.20% 9.20% Interest 19.09 20.61 20.61 19.75 18.03 Rep Schedule 10 Annual Instalments from 12.03.2013 5 Bond XXVIII Gross loan opening 450.00 450.00 450.00 450.00 450.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 37.50 Net Loan-Opening 450.00 450.00 450.00 450.00 412.50 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 37.50 37.50 Net Loan-Closing 450.00 450.00 450.00 412.50 375.00 Average Loan 450.00 450.00 450.00 431.25 393.75 Rate of Interest 9.33% 9.33% 9.33% 9.33% 9.33% Interest 41.99 41.99 41.99 40.24 36.74 Rep Schedule 12 annual Instalments from 15.12.2012 6 Bond XXX (Add Cap 2009-2010 on 29.09.2009) Gross loan opening 0.00 3.05 3.05 3.05 3.05 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 0.00 Net Loan-Opening 0.00 3.05 3.05 3.05 3.05 Additions during the year 3.05 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 0.00 0.25 Net Loan-Closing 3.05 3.05 3.05 3.05 2.80 Average Loan 1.53 3.05 3.05 3.05 2.92 Rate of Interest 8.80% 8.80% 8.80% 8.80% 8.80% Interest 0.13 0.27 0.27 0.27 0.26 Rep Schedule 12 annual Instalments from 29.09.2013 Total Loan Gross loan opening 2891.06 2927.10 2927.10 2927.10 2927.10 Cumulative Repayment upto DOCO/previous year 0.00 0.00 29.00 216.50 460.18 Net Loan-Opening 2891.06 2927.10 2898.10 2710.60 2466.93 Additions during the year 36.04 0.00 0.00 0.00 0.00 Repayment during the year 0.00 29.00 187.50 243.67 243.93 Net Loan-Closing 2927.10 2898.10 2710.60 2466.93 2223.00 Average Loan 2909.08 2912.60 2804.35 2588.76 2344.96 Weighted Average Rate of Interest 9.3389% 9.3409% 9.3437% 9.3436% 9.3441% Interest 271.68 272.06 262.03 241.88 219.12