Power Grid Corporation Of India Ltd. v. Kerala State Electricity Board

Central Electricity Regulatory Commission
Feb 14, 2011
Smart Summary (Beta)

Structured Summary of the Opinion — Petition No. 241/2010

Factual and Procedural Background

This petition was filed by the transmission licensee seeking approval of transmission tariff for three grouped assets (referred to as Asset-I, Asset-II and Asset-III) forming the "Transmission System associated with Kaiga-3&4 (2×235 MW) Project" for the tariff period 1.4.2009 to 31.3.2014 under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 (the "2009 regulations"). The petition sought multiple specific reliefs including approval of additional capital expenditure (ACE) during 2009-12, invocation of Regulation 44 to relax the cut-off restrictions, grossing up of the base rate of return with applicable tax rates, certain depreciation and interest adjustments, reimbursement of filing and publication costs, and separate billing of service tax and licence fee.

Investment approval for the transmission system was initially accorded by the Ministry of Power (letter dated 29.3.2005) at an estimated cost of Rs. 58,825 lakh (including IDC). A revised cost estimate was approved by the petitioner's Board on 29.12.2008 at Rs. 100,716 lakh (including IDC). The Commission had earlier, by separate orders in Petition Nos. 5/2009, 180/2009 and 290/2009, admitted a total capital cost of Rs. 33,857.63 lakh as on 31.3.2009 (including ACE up to 31.3.2009), and that admitted cost was used as the opening capital cost as on 1.4.2009 for tariff determination in this petition.

Reply to the petition was filed by respondent No.2, Tamil Nadu Electricity Board (TNEB). No public comments were received in response to the public notice. After hearing the parties and examining the record, the Commission proceeded to dispose of the petition (the order states "This order disposes of Petition No. 241/2010").

Legal Issues Presented

  1. Whether the Commission should approve transmission tariff for the three grouped transmission assets for the period 1.4.2009 to 31.3.2014 in accordance with the 2009 regulations.
  2. Whether the additional capital expenditure (ACE) projected/incurred during 2009-14 (including amounts beyond the cutoff date) should be allowed as part of the capital base for tariff determination, including invocation of Regulation 44 (power to relax) and application of Regulation 9(2).
  3. Whether the base rate of return on equity should be grossed up with the applicable tax rate as per the relevant Finance Act and whether tax liabilities should be settled year-to-year between the licensee and beneficiaries.
  4. Whether, in cases of combined assets, full depreciation should be recoverable during the useful life reckoning from the actual date of commercial operation.
  5. Whether the petitioner may bill and adjust the impact on interest on loan arising from changes in floating interest rates during 2009-14.
  6. Whether the petitioner is entitled to reimbursement by beneficiaries of filing fee and publication expenses under Regulation 42 of the 2009 regulations.
  7. Whether the petitioner may bill and recover Service Tax on transmission charges separately from respondents, if transmission is made a taxable service.
  8. Whether the petitioner may bill and recover licence fee separately from the respondents in addition to O&M charges.

Arguments of the Parties

Petitioner's Arguments

  • Sought approval of transmission tariff for the combined transmission assets for the 2009-14 tariff period under the 2009 regulations.
  • Claimed additional capital expenditure to be allowed for 2009-12 and asked the Commission to invoke Regulation 44 to permit allowance of ACE incurred/ to be incurred beyond the cut-off date on account of undischarged liabilities.
  • Requested grossing up of the base rate of return with the applicable tax rate as per the Finance Act for the relevant year and direct settlement of tax liability between the licensee and beneficiaries on a year-to-year basis.
  • Sought permission to recover full depreciation when assets are combined, reckoning from the actual date of commercial operation.
  • Sought allowance to bill and adjust the impact of changes in interest rate due to floating rate loans during 2009-14.
  • Prayed for reimbursement by beneficiaries of filing fee and publication expenses under Regulation 42.
  • Requested permission to bill and recover Service Tax on transmission charges separately if transmission becomes taxable.
  • Sought permission to bill and recover licence fee separately from respondents.

Respondent's (TNEB) Submissions

  • Contended that the petitioner's claim for estimated ACE of Rs. 80.27 lakh (Kalivandapattu SS during 2010-11) and Rs. 25.00 lakh (Narendra-Devangere line) on account of balance/retention payments beyond the cut-off date is not permissible under Regulation 9(2) of the 2009 regulations and should be disallowed.
  • On the petitioner's prayer for MAT grossing up, submitted that the Commission had issued a draft amendment to the 2009 regulations and that any amended regulation should be applied in the present case.
  • Regarding adjustment for floating rate interest, submitted there is no specific provision in the 2009 regulations; any reimbursement may be allowed only along with truing up of expenditure and without interest liability to the respondent.
  • Argued that transmission of electricity is exempt from Service Tax and therefore the petitioner's claim to recover Service Tax should be rejected.
  • Submitted that O&M expenses for pay revision are fixed on a normative basis for 2009-14 and the 2009 regulations do not provide revisiting normative O&M; thus the petitioner's claim for revision should be rejected.
  • Contended that licence fee is a levy on the petitioner and should not be allowed over and above normative O&M expenses.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Commission's reasoning applies the 2009 regulations to the facts and claims presented. The analysis proceeded by addressing capital cost, additional capitalisation, debt-equity, return on equity, interest on loan, depreciation, O&M expenses, interest on working capital, and contested reimbursement items. The court's step-by-step approach (as reflected in the order) is summarized below, strictly reflecting the content of the opinion:

  1. Capital Cost and Opening Base:

    The Commission took the capital cost admitted by its earlier orders (Petition Nos. 5/2009, 180/2009 and 290/2009) totalling Rs. 33,857.63 lakh as on 31.3.2009 and treated that as the opening capital cost on 1.4.2009, applying the proviso to clause (2) of Regulation 7 of the 2009 regulations for existing projects.

  2. Additional Capital Expenditure (ACE) and Relaxation:

    The petitioner sought allowance of ACE projected/incurred during 2009-14, including payments beyond the cut-off date (1.2.2008 for certain assets). The Commission recognized the petitioner's request and, referencing prior consideration, noted that it had in Petition No. 176/2010 granted a general relaxation of Regulation 9(2) to allow projected ACE on account of balance and retention payments after the cut-off date. Exercising its power of relaxation (Regulation 44), the Commission allowed capitalization of the additional expenditure projected to be incurred during 2010-11 and 2011-12 to discharge undischarged liabilities on account of balance/retention payments. Consequently, the ACE claimed in the petition (as listed in para 13 of the opinion) were allowed.

  3. Debt-Equity Ratio:

    Pursuant to clause (2) of Regulation 12, the Commission used the debt-equity ratios admitted prior to 1.4.2009 for existing projects. The admitted values and 70:30 debt-equity splits for the assets and for ACE were set out and used for calculations. The Commission accepted the debt-equity details as conforming to the 2009 regulations and used them in tariff computations.

  4. Return on Equity (ROE):

    The Commission applied Regulation 15 of the 2009 regulations: ROE is computed in rupee terms on the equity base determined under Regulation 12; ROE is computed on a pre-tax basis at the base rate of 15.5% grossed up as per clause (3). The petitioner sought grossing up of the base rate with tax rates as per the Finance Act. The Commission noted that it has proposed an amendment to Regulation 15(3) to address practical problems and agreed to consider applicable tax rates as per the Finance Act after issuance of that amendment. Detailed ROE calculations for each asset and year were presented in the order, using the admitted equity bases and the tax-related grossing-up approach described in the regulations (including the base rate and gross-up formula).

  5. Interest on Loan:

    The Commission applied Regulation 16: loans determined under Regulation 12 are treated as gross normative loans; normative outstanding loans as on 1.4.2009 are computed by deducting cumulative repayments admitted up to 31.3.2009; repayment in each year of 2009-14 is treated as equal to the depreciation allowed for that year. The rate of interest used is the weighted average rate of interest based on the actual loan portfolio at the beginning of each year. The Commission adopted the petitioner's loan schedules and methodology for weighted average interest, used the rates prevailing as on 01.04.2009 for floating rate loans for the purpose of the present calculation, and stated that any change in interest rates after 1.4.2009 will be considered at truing up.

  6. Depreciation:

    The Commission followed Regulation 17: depreciable value is the admitted capital cost less a 10% salvage value, depreciation calculated on a straight-line basis at rates in Appendix-III, and for existing projects the balance depreciable value as on 1.4.2009 is to be determined by deducting cumulative depreciation admitted until 31.3.2009. As the assets were commissioned on or after 1.4.2008, the assets would complete 12 years beyond 2013-14 and depreciation was calculated annually accordingly. Depreciation schedules for each asset and year were included in the order.

  7. Operation & Maintenance (O&M) Expenses:

    The petitioner calculated O&M expenses in accordance with Regulation 19(g) (norms based on sub-station and line type). The Commission allowed O&M expenses as calculated by the petitioner in accordance with those norms.

  8. Interest on Working Capital:

    The components of working capital were determined in accordance with Regulation 18: receivables (two months' average billing), maintenance spares (15% of O&M), and one month O&M. The rate of interest on working capital was set at the short-term Prime Lending Rate of State Bank of India as on 1.4.2009 (12.25%), and the Commission allowed the petitioner's claimed interest on working capital using that rate.

  9. Reimbursement of Filing Fee and Publication Expenses:

    The petitioner sought reimbursement of the petition filing fee and publication expenses. The Commission, relying on its prior decision in Petition No. 109/2009 (order dated 11.1.2010), held that the petitioner is entitled to recover the filing fee and publication expenses from beneficiaries on a pro-rata basis.

  10. Service Tax and Licence Fee:

    The petitioner sought permission to bill and recover Service Tax on transmission charges if exemption is withdrawn. The Commission found this prayer premature and rejected it. Regarding licence fee reimbursement, the Commission stated that a view is yet to be taken in the matter.

  11. Final Numeric Outcome:

    The Commission set out detailed year-wise numeric calculations for depreciation, interest on loan, ROE, interest on working capital, O&M and total transmission charges for each asset for the tariff years 2009-10 through 2013-14, and stated that transmission charges shall be recovered monthly in accordance with Regulation 23 and shared by respondents under Regulation 33.

Holding and Implications

Core Ruling: The petition (Petition No. 241/2010) is disposed of with the transmission charges for Asset-I, Asset-II and Asset-III for the tariff period 2009-2014 allowed as set out in the order.

Direct consequences for the parties (as expressly stated in the opinion):

  • The additional capital expenditures claimed by the petitioner for the years shown in the petition (as extracted in para 13 of the opinion) are allowed, by application of Regulation 9(2) in exercise of the Commission's relaxation power (consistent with the general relaxation granted in Petition No. 176/2010) for balance/retention payments after the cut-off date.
  • Debt-equity ratio, ROE (grossed up in accordance with the regulations and subject to the contemplated amendment to Regulation 15(3)), interest on loan (on weighted average rates as on 01.04.2009, subject to truing up), depreciation, O&M, interest on working capital (at SBI PLR 12.25%) and total transmission charges are allowed and numerically specified year-wise for 2009-14 in the order.
  • The petitioner may recover the petition filing fee and publication expenses from beneficiaries on a pro-rata basis per the Commission's earlier order in Petition No. 109/2009.
  • The petitioner's request to be permitted to bill and recover Service Tax on transmission charges is rejected as premature. The question of licence fee reimbursement remains outstanding (a view is yet to be taken by the Commission).
  • The transmission charges allowed are to be recovered on a monthly basis and shared by respondents as per the 2009 regulations.

Implication regarding precedent or broader legal effect:

The order applies provisions of the 2009 regulations and adopts a previously granted general relaxation (Petition No. 176/2010) to allow ACE beyond the cut-off date in specified circumstances (balance/retention payments). The opinion does not purport to create or state a new judicial precedent beyond the Commission's regulatory determinations; it implements and applies the 2009 regulations and the Commission's prior orders to the facts of this petition. No additional broader legal principles beyond those expressly applied in the order are declared.


This summary is based exclusively on the material contained in the provided opinion and does not add, infer or assume facts or holdings beyond that text.

Show all summary ...

This petition has been filed seeking approval of transmission tariff in respect of Asset-I consisting, (a) 50 MVAR Reactor at Narendra S/S, (b) Narendra-Devangiri 400 kV D/C T/L and 50 MVAR Bus Reactor at Mysore (c) LILO of Kolar-Sriperumbudur 400 kV S/C Line along with one 50 MVAR Reactor at Kalvindapattu; Asset-II consisting of 2nd 315 MVA Auto Transformer at Hiriyur Sub-Station; and Asset-III consisting (a) 1st 315 MVA Auto Transformer at Kalvindapattu Sub-Station and (b) 2nd 315 MVA Auto Transformer at Kalvindapattu Sub-Station along with associated bays and Equipments (hereinafter collectively referred to as “the transmission assets”) under “Transmission System associated with Kaiga-3&4(2×235 MW) Project” (hereinafter referred to as “the transmission system”) in Southern Region, for the period from 1.4.2009 to 31.3.2014, in accordance with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009, (hereinafter referred to as “the 2009 regulations”). The petitioner has also sought the following reliefs:

(a) Approve the additional capital expenditure during 2009-12.

(b) Invoke the provisions of Regulation 44 of the 2009 regulations (Power to relax) so that additional capitalization incurred/to be incurred on account of undischarged liabilities after the cut-off date is allowed and considered for tariff fixation for the tariff period 2009-14.

(c) Allow grossing up of base rate of return with the applicable tax rate as per the Finance Act for the relevant year and direct settlement of tax liability between the generating company/transmission licensee and the beneficiaries/long term customers on year to year basis.

(d) Allow the petitioner to recover, in the case of assets being combined to calculate the transmission charges, full depreciation of the assets during the useful life reckoning from the date of actual date of commercial operation.

(e) Allow the petitioner to bill and adjust impact on interest on loan due to change in interest rate on account of floating rate of interest, if any, during 2009-14.

(f) Approve the reimbursement by the beneficiaries, of expenditure towards petition filing fee, and publishing of notices in newspapers in terms of Regulation 42 of the 2009 regulations, and other expenditure (if any) in relation to the filing of petition.

(g) Allow the petitioner to bill and recover Service Tax on Transmission charges separately from the respondents, if petitioner is subjected to such service tax.

(h) Allow the petitioner to bill and recover licence fee separately from the respondents.

(i) Pass such other relief as the Commission deems fit and appropriate under the circumstances of the case and in the interest of justice.

2. Investment approval for the transmission system was accorded by Ministry of Power vide letter dated 29.3.2005 at an estimated cost of Rs. 58825 lakh including interest during construction (IDC) of Rs. 3072 lakh. Subsequently, the approval of Revised Cost Estimate was accorded by the Board of Directors of the petitioner company vide its memorandum dated 29.12.2008 at an estimated cost of Rs. 100716 lakh including IDC of 9503 lakh.

3. The Commission vide its order dated 20.7.2009 in Petition No. 5/2009, order dated 11.3.2010 in Petition No. 180/2009 and order dated 13.5.2010 in Petition No. 290/2009 have admitted the total Capital Cost of Rs. 33857.63 lakh as on 31.3.2009 including Additional Capital Expenditure upto 31.3.2009

4. The petitioner has claimed the following transmission charges:

(Rs. in lakh)

Asset - I 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Depreciation 1432.21 1448.10 1449.42 1450.08 1450.08 Interest on Loan 1656.39 1543.45 1411.47 1277.39 1142.53 Return on equity 1447.51 1464.22 1465.53 1466.18 1466.18 Interest on Working Capital 124.00 124.02 123.10 122.22 121.40 O & M Expenses 588.96 622.70 658.34 695.98 735.70 Total 5249.07 5202.49 5107.86 5011.85 4915.89 Asset-II 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Depreciation 131.01 133.00 134.20 134.20 134.20 Interest on Loan 148.65 138.87 128.02 115.55 103.07 Return on equity 131.06 133.03 134.23 134.23 134.23 Interest on Working Capital 16.69 17.03 17.35 17.60 17.89 O & M Expenses 162.44 171.74 181.57 191.94 202.92 Total 589.85 593.67 595.37 593.52 592.31 Asset III Depreciation 216.25 219.64 221.76 221.76 221.76 Interest on Loan 249.32 233.00 214.90 194.03 173.17 Return on equity 214.96 218.32 220.43 220.43 220.43 Interest on Working Capital 30.43 31.17 31.86 32.46 33.13 O & M Expenses 324.88 343.48 363.14 383.88 405.84 Total 1035.84 1045.61 1052.09 1052.56 1054.33

5. The details submitted by the petitioner in support of its claim for interest on working capital are given hereunder:

(Rs. in lakh)

Asset - I 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Maintenance Spares 88.34 93.40 98.75 104.40 110.36 O & M expenses 49.08 51.89 54.86 58.00 61.31 Receivables 874.85 867.08 851.31 835.31 819.32 Total 1012.27 1012.37 1004.92 997.71 990.99 Interest 124.00 124.02 123.10 122.22 121.40 Rate of Interest 12.25% 12.25% 12.25% 12.25% 12.25% Asset - II 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Maintenance Spares 24.37 25.76 27.24 28.79 30.44 O & M expenses 13.54 14.31 15.13 16.00 16.91 Receivables 98.31 98.95 99.23 98.92 98.72 Total 136.22 139.02 141.60 143.71 146.07 Interest 16.69 17.03 17.35 17.60 17.89 Rate of Interest 12.25% 12.25% 12.25% 12.25% 12.25% Asset - III Maintenance Spares 48.73 51.52 54.47 57.58 60.88 O & M expenses 27.07 28.62 30.26 31.99 33.82 Receivables 172.64 174.27 175.35 175.43 175.72 Total 248.44 254.41 260.08 265.00 270.42 Interest 30.43 31.17 31.86 32.46 33.13 Rate of Interest 12.25% 12.25% 12.25% 12.25% 12.25%

6. Reply to the petition has been filed only by Tamil Nadu Electricity Board (TNEB), respondent No. 2 herein. No comments/submissions from the general public have been received in response to the public notice in the newspapers. TNEB has made the following submissions in its reply:

(a) The petitioner's claim for estimated additional capital expenditure of Rs. 80.27 lakh in respect of Kalivandapattu SS during 2010-2011 and Rs. 25.00 lakh in respect of 400 kV Narendra-Devangere line on account of balance and retention payment beyond the cut-off date is not permissible under Regulation 9(2) of 2009 regulations and may be disallowed.

(b) As regards the prayer for MAT rate as per the applicable Finance Act, the Commission has come out with draft amendment to the 2009 regulations and such regulations as and when amended may be made applicable in this case.

(c) As regards the petitioner's prayer for adjusting the impact of floating rate of interest, it has been submitted that as there is no specific provision in the 2009 regulations in this regard, reimbursement, if any’ may be allowed alongwith truing up of expenditure without any interest liability to the respondent.

(d) As regards the reimbursement of service tax, it has been submitted that since transmission of electricity has been exempted from the purview of service tax, the petitioner's claim in this regard may be rejected.

(e) As regards the petitioner's prayer for revision of norms for O&M expenditure due to impact of pay revision, it has been submitted that O&M expenses on account of pay revision has been fixed on normative basis during 2009-14 period and 2009 regulations do not provide for revisiting the normative O&M charges. Hence the petitioner's claim may be rejected.

(f) Licence fee being a levy on the petitioner to be in transmission business, it should not be allowed over and above the O&M expenses.

7. The objections of the respondent have been dealt with in relevant paras of this order.

8. Having heard the representatives of the parties and examined the material on record, we proceed to dispose of the petition.

CAPITAL COST

9. As per the last proviso to clause (2) of regulation 7 of the 2009 regulations, in case of the existing projects, capital cost admitted by the Commission prior to 1.4.2009 and the additional capital expenditure projected to be incurred for the respective year of the tariff period 2009-14 as may be admitted by the Commission, shall form the basis for determination of tariff.

10. Details of the capital cost as on 31.3.2009 admitted by the Commission are as under:

Asset Date of commercial operation Admitted Cost as on 31.3.2009 (Rs. in lakh) Relevant order of the Commission Asset-I (Notional Date of commercial operation: 1.6.2008) a) 50 MVAR Reactor at Narendra S/S 1.1.2008 2046.60 Order dated 13.5.2010 in Petition No. 290/2009 b) Narendra-Devangiri 400 kV D/C T/L and 50 MVAR Bus Reactor at Mysore 1.2.2008 17235.02 Order dated 13.5.2010 in Petition No. 290/2009 c) LILO of Kolar-Sriperumbudur 400 kV S/C Line along with one 50 MVAR Reactor at Kalvindapattu 1.6.2008 8016.55 Order dated 11.3.2010 in Petition No. 180/2009 Total 27298.17 Aeet-II (Actual Date of commercial operation: 1.4.2008) a) 2nd 315 MVA Auto Transformer at Hiriyur S/S 1.4.2008 2484.45 Order dated 13.5.2010 in Petition No. 290/2009 Total 2484.45 Asset-III (Notional Date of commercial operation: 1.7.2008) a) 1st 315 MVA Auto Transformer at Kalvindapattu Sub-Station 1.6.2008 2664.53 Order dated 11.3.2010 in Petition No. 180/2009 b) 2nd 315 MVA Auto Transformer at Kalvindapattu Sub-Station 1.7.2008 1410.48 Order dated 11.3.2010 in Petition No. 180/2009 Total 4075.01 Grand Total 33857.63

11. The above admitted capital cost has been considered as the opening capital cost as on 1.4.2009 for the purpose of determination of tariff.

ADDITIONAL CAPITAL EXPENDITURE

12. The petitioner has claimed the additional capital expenditure incurred/projected to be incurred during 2009-14 as under:

13. Details of the projected additional capital expenditure claimepd by the petitioner are as under:

(Rs. in lakh)

Assets Expendiure from 1.4.2009 to 31.3.2010 Expendiure from 1.4.2010 to 31.3.2011 Expendiure from 1.4.2011 to 31.3.2012 Asset-I a) 50 MVAR Reactor at Narendra S/S 0.00 0.00 0.00 b) Narendra-Devangiri 400 kV D/C T/L and 50 MVAR Bus Reactor at Mysore 352.41 25.00 25.00 c) LI LO of Kola r-Sri perumbudur 400 kV S/C line Along with one 50 MVAR Rea ctor at Kal vi ndapattu 259.87 0.00 0.00 Sub-Total 612.28 25.00 25.00 Asset-II a) 2nd 315 MVA Auto Transformer at Hiriyur S/S 29.38 45.66 0.00 Sub-Total 29.38 45.66 0.00 Asset-III a) 1st 315 MVA Auto Transformer at Kalvindapattu Sub Station 47.98 30.00 0.00 b) 2nd 315 MVA Auto Transformer at Kalvindapattu Sub Station 0.15 50.27 0.00 Sub-Total 48.13 80.27 0 Grand Total 689.79 150.93 25.00

14. The petitioner has submitted that a sum of Rs. 25 lakh is to be released during 2011-2012 in respect of Asset - I. Apparently, the proposed payment is beyond the cutoff date which is 1.2.2008, in respect of 400 kV Narendra - Devangere D/C line and 50 MVAR Bus reactor at Mysore S/S. The petitioner has submitted that the above deferment of payment is attributable to contractual exigencies and other reasons beyond its control and has prayed that the Commission may invoke its powers under regulation 44 of the 2009 regulations and allow the above expenditure as part of the additional capital expenditure.

15. We have considered the issue in a number of petitions filed by the petitioner and have decided to allow the additional capital expenditure incurred after the cut-off date under Regulation 9(2) of 2009 regulations in exercise of our power of relaxation. In petition No. 176/2010, the Commission has granted a general relaxation of Regulation 9(2) of 2009 regulations in order to allow the projected additional capital expenditure on account of balance and retention payments made after the cut-off date. Accordingly, capitalization of additional expenditure projected to be incurred during 2010-2011 and 2011-2012 to discharge the undischarged liability on account of balance/retention payment is allowed.

16. Accordingly, the additional capital expenditures claimed by the petitioner which has been extracted in para 13 above are allowed.

DEBT-EQUITY RATIO

17. Clause (2) of Regulation 12 of the 2009 regulations inter alia provides that,—

“(2) In case of the generating station and the transmission system declared under commercial operation prior to 1.4.2009, debt-equity ratio allowed by the Comission for determination of tariff for the period ending 31.3.2009 shall be considered.”

18. Details of debt-equity of the transmission assets as on 1.4.2009 as admitted by the Commission are given as under:

Approved Admitted as on 31.03.2009 Asset-I Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 20728.40 0.00% 19109.56 70.00% Equity 8883.60 0.00% 8188.61 30.00% Total 29612.00 0.00% 27298.17 100.00% Asset-II Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 2045.40 0.00% 1739.12 70.00% Equity 876.60 0.00% 745.34 30.00% Total 2922.00 0.00% 2484.46 100.00% Asset-III Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 3419.50 0.00% 2852.56 70.00% Equity 1465.50 0.00% 1222.45 30.00% Total 4885.00 0.00% 4075.01 100.00%

19. Debt-equity details in respect of the additional capital expenditure are as follows:

Approved Admitted as on 31.3.2009 Asset-I 2009-2010 Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 0.00 0.00% 428.60 70.00% Equity 0.00 0.00% 183.68 30.00% Total 0.00 0.00% 612.28 100.00% 2010-2011 Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 0.00 0.00% 17.50 70.00% Equity 0.00 0.00% 7.50 30.00% Total 0.00 0.00% 25.00 100.00% 2011-2012 Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 0.00 0.00% 17.50 70.00% Equity 0.00 0.00% 7.50 30.00% Total 0.00 0.00% 25.00 100.00% Asset-II 2009-2010 Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 0.00 0.00% 20.57 70.01% Equity 0.00 0.00% 8.81 29.99% Total 0.00 0.00% 29.38 100.00% 2010-2011 Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 0.00 0.00% 31.96 70.00% Equity 0.00 0.00% 13.70 30.00% Total 0.00 0.00% 45.66 100.00% Asset-III 2009-2010 Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 0.00 0.00% 33.69 70.00% Equity 0.00 0.00% 14.44 30.00% Total 0.00 0.00% 48.13 100.00% 2010-2011 Amount (Rs. Lakh) % Amount (Rs. Lakh) % Debt 0.00 0.00% 56.19 70.00% Equity 0.00 0.00% 24.08 30.00% Total 0.00 0.00% 80.27 100.00%

20. As the above details are in conformity with the provisions of the 2009 regulations, the same are accordingly being used in these calculations. The equity base for the purpose of computation of tariff in respect of the transmission assets is under:

(Rs. in lakh)

Description Equity on 1.4.2009 Notional equity due to ACE for the period 2009-2010 Total equity considered for tariff calculations for the period 2009-2010* Notional equity due to ACE for the period 2010-2011 Total equity considered for tariff calculations for the period 2010-2011* Notional equity due to ACE for the period 2011-2012 Total equity considered for tariff calculations for the period 2011-2012* Notional equity due to ACE for the period 2012-2013 Total equity considered for tariff calculations for the period 2012-14* Asset-I 8188.61 183.68 8280.45 7.50 8376.05 7.50 8383.55 0.00 8387.30 Asset-II 745.34 8.81 749.74 13.70 761.00 0.00 767.85 0.00 767.85 Asset-III 1222.45 14.44 1229.67 24.08 1248.93 0.00 1260.97 0.00 1260.97

RETURN ON EQUITY

21. Regulation 15 of the 2009 regulations provides that,—

“15. (1) Return on equity shall be computed in rupee terms, on the equity base determined in accordance with regulation 12.

(2) Return on equity shall be computed on pre-tax basis at the base rate of 15.5% to be grossed up as per clause (3) of this regulation:

Provided that in case of projects commissioned on or after 1st April, 2009, an additional return of 0.5% shall be allowed if such projects are completed within the timeline specified in Appendix-II:

Provided further that the additional return of 0.5% shall not be admissible if the project is not completed within the timeline specified above for reasons whatsoever.

(3) The rate of return on equity shall be computed by grossing up the base rate with the normal tax rate for the year 2008-2009 applicable to the concerned generating company or the transmission licensee, as the case may be:

Provided that return on equity with respect to the actual tax rate applicable to the generating company or the transmission licensee, as the case may be, in line with the provisions of the relevant Finance Acts of the respective year during the tariff period shall be trued up separately for each year of the tariff period along with the tariff petition filed for the next tariff period.

(4) Rate of return on equity shall be rounded off to three decimal points and be computed as per the formula given below:

Rate of pre-tax return on equity = Base rate/(1-t)

Where t is the applicable tax rate in accordance with clause (3) of this regulation.

……………………………………………………………………………….”

22. The petitioner has also prayed that it may be allowed the grossing up of base rate of return with the applicable tax rate as per the Finance Act for the relevant year and direct settlement of tax liability with long term customers on year to year basis. TNEB has submitted that the Commission has come out with a draft amendment to 2009 regulations and the regulation as and when amended may be made applicable in this case. We are in agreement with the submissions of TNEB. The Commission after taking note of the problem being faced by the petitioner has proposed amendment to Regulation 15(3) of 2009 regulations and after issue of the amendment, the applicable tax rates as per the relevant Finance Act will be considered for grossing up of the base rate of return.

23. Detailed calculation of the ROE in respect the transmission assets is as under:

(Rs. in lakh)

Asset - I 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Gross Notional Equity 8188.61 Addition due to Additional Capitalisation 0.00 Opening Equity 8188.61 8188.61 8372.30 8379.80 8387.30 8387.30 Addition due to Additional Capitalisation 183.68 7.50 7.50 0.00 0.00 Closing Equity 8372.30 8379.80 8387.30 8387.30 8387.30 Average Equity 8280.45 8376.05 8383.55 8387.30 8387.30 Return on Equity (Base Rate) 15.50% 15.50% 15.50% 15.50% 15.50% Tax rate for the year 2008-2009 (MAT) 11.330% 11.330% 11.330% 11.330% 11.330% Rate of Return on Equity (Pre Tax) 11.33% 17.481% 17.481% 17.481% 17.481% 17.481% Return on Equity (Pre Tax) 1447.51 1464.22 1465.53 1466.18 1466.18

(Rs. in lakh)

Asset - II 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Gross Notional Equity 745.34 Addition due to Additional Capitalisation 0.00 Opening Equity 745.34 745.34 754.15 767.85 767.85 767.85 Addition due to Additional Capitalisation 8.81 13.70 0.00 0.00 0.00 Closing Equity 754.15 767.85 767.85 767.85 767.85 Average Equity 749.74 761.00 767.85 767.85 767.85 Return on Equity (Base Rate) 15.50% 15.50% 15.50% 15.50% 15.50% Tax rate for the year 2008-2009 (MAT) 11.33% 11.33% 11.33% 11.33% 11.33% Rate of Return on Equity (Pre Tax) 17.481% 17.481% 17.481% 17.481% 17.481% Return on Equity (Pre Tax) 131.06 133.03 134.23 134.23 134.23 Asset - III Gross Notional Equity 1222.45 Addition due to Additional Capitalisation 0.00 Opening Equity 1222.45 1222.45 1236.89 1260.97 1260.97 1260.97 Addition due to Additional Capitalisation 14.44 24.08 0.00 0.00 0.00 Closing Equity 1236.89 1260.97 1260.97 1260.97 1260.97 Average Equity 1229.67 1248.93 1260.97 1260.97 1260.97 Return on Equity (Base Rate) 15.50% 15.50% 15.50% 15.50% 15.50% Tax rate for the year 2008-2009 (MAT) 11.330% 11.330% 11.330% 11.330% 11.330% Rate of Return on Equity (Pre Tax) 11.33% 17.481% 17.481% 17.481% 17.481% 17.481% Return on Equity (Pre Tax) 214.96 218.32 220.43 220.43 220.43

INTEREST ON LOAN

24. Regulation 16 of the 2009 regulations provides that,—

“16. (1) The loans arrived at in the manner indicated in regulation 12 shall be considered as gross normative loan for calculation of interest on loan.

(2) The normative loan outstanding as on 1.4.2009 shall be worked out by deducting the cumulative repayment as admitted by the Commission up to 31.3.2009 from the gross normative loan.

(3) The repayment for the year of the tariff period 2009-14 shall be deemed to be equal to the depreciation allowed for that year:

(4) Notwithstanding any moratorium period availed by the generating company or the transmission licensee, as the case may be the repayment of loan shall be considered from the first year of commercial operation of the project and shall be equal to the annual depreciation allowed.

(5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio at the beginning of each year applicable to the project:

Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered: Provided further that if the generating station or the transmission system, as the case may be, does not have actual loan, then the weighted average rate of interest of the generating company or the transmission licensee as a whole shall be considered.

(6) The interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest.

(7) The generating company or the transmission licensee, as the case may be, shall make every effort to re-finance the loan as long as it results in net savings on interest and in that event the costs associated with such re-financing shall be borne by the beneficiaries and the net savings shall be shared between the beneficiaries and the generating company or the transmission licensee, as the case may be, in the ratio of 2:1.

(8) The changes to the terms and conditions of the loans shall be reflected from the date of such re-financing.

(9) In case of dispute, any of the parties may make an application in accordance with the Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999, as amended from time to time, including statutory re-enactment thereof for settlement of the dispute:

Provided that the beneficiary or the transmission customers shall not withhold any payment on account of the interest claimed by the generating company or the transmission licensee during the pendency of any dispute arising out of re-financing of loan.”

25. In these calculations, interest on loan has been worked out as detailed below:

(a) Gross amount of loan, repayment of instalments and rate of interest and weighted average rate of interest on actual average loan have been considered as per the petition.

(b) The repayment for the tariff period 2009-14 shall be deemed to be equal to the depreciation allowed for that period.

(c) Moratorium period availed by the transmission licensee, the repayment of the loan shall be considered from the first year of commercial operation of the project and shall be equal to the annual depreciation allowed.

(d) Weighted average rate of interest on actual average loan worked out as per (a) above is applied on the notional average loan during the year to arrive at the interest on loan.

(e) The methodology followed for the calculation of weighted average Rate of Interest in case of floating interest loans in Petition 132/2010, the same has been adopted in the instant petition. Accordingly, the interest on Loan has been calculated on the basis of rate prevailing as on 01.04.2009 Any change in rate of Interest subsequent to 1.4.2009 will be considered at the time of truing up.

26. Details of the calculation of Interest on Loan are as under:

(Rs. in lakh)

Asset - I 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Gross Notional Loan 19109.56 Addition due to Additional Capitalisation 0.00 Gross Normative Loan 19109.56 19109.56 19538.15 19555.65 19573.15 19573.15 Cumulative Repayment upto Previous Year 795.82 2228.04 3676.14 5125.56 6575.65 Net Loan-Opening 18313.73 17310.12 15879.51 14447.59 12997.51 Addition due to Additional Capitalisation 428.60 17.50 17.50 0.00 0.00 Repayment during the year 1432.21 1448.10 1449.42 1450.08 1450.08 Net Loan-Closing 17310.12 15879.51 14447.59 12997.51 11547.42 Average Loan 17811.93 16594.82 15163.55 13722.55 12272.47 Weighted Average Rate of Interest on Loan 9.2993% 9.3008% 9.3083% 9.3087% 9.3097% Interest 1656.39 1543.45 1411.46 1277.39 1142.53 Asset - II 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Gross Notional Loan 1739.12 Addition due to Additional Capitalisation 0.00 Gross Normative Loan 1739.12 1739.12 1759.68 1791.64 1791.64 1791.64 Cumulative Repayment upto Previous Year 84.52 215.54 348.54 482.74 616.94 Net Loan-Opening 1654.59 1544.14 1443.11 1308.91 1174.71 Addition due to Additional Capitalisation 20.57 31.96 0.00 0.00 0.00 Repayment during the year 131.01 133.00 134.20 134.20 134.20 Net Loan-Closing 1544.14 1443.11 1308.91 1174.71 1040.50 Average Loan 1599.37 1493.62 1376.01 1241.81 1107.60 Weighted Average Rate of Interest on Loan 9.2945% 9.2975% 9.3040% 9.3047% 9.3058% Interest 148.65 138.87 128.02 115.55 103.07 Asset - III 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Gross Notional Loan 2852.56 Addition due to Additional Capitalisation 0.00 Gross Normative Loan 2852.56 2852.56 2886.25 2942.44 2942.44 2942.44 Cumulative Repayment upto Previous Year 109.90 326.15 545.79 767.56 989.32 Net Loan-Opening 2742.67 2560.10 2396.65 2174.89 1953.12 Addition due to Additional Capitalisation 33.69 56.19 0.00 0.00 0.00 Repayment during the year 216.25 219.64 221.76 221.76 221.76 Net Loan-Closing 2560.10 2396.65 2174.89 1953.12 1731.36 Average Loan 2651.38 2478.38 2285.77 2064.00 1842.24 Weighted Average Rate of Interest on Loan 9.4035% 9.4013% 9.4015% 9.4004% 9.4001% Interest 249.32 233.00 214.90 194.02 173.17

DEPRECIATION

27. Regulation 17 of the 2009 regulations provides for computation of depreciation in the following manner, namely:

“17. (1) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission.

(2) The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the capital cost of the asset.

Provided that…………………..

Provided further that…………….t

(3) Land other than the land held under lease and the land for reservoir in case of hydro generating station shall not be a depreciable asset and its cost shall be excluded from the capital cost while computing depreciable value of the asset.

(4) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-III to these regulations for the assets of the generating station and transmission system:

Provided that, the remaining depreciable value as on 31st March of the year closing after a period of 12 years from date of commercial operation shall be spread over the balance useful life of the assets.

(5) In case of the existing projects, the balance depreciable value as on 1.4.2009 shall be worked out by deducting the cumulative depreciation as admitted by the Commission up to 31.3.2009 from the gross depreciable value of the assets.

(6) Depreciation shall be chargeable from the first year of commercial operation. In case of commercial operation of the asset for part of the year, depreciation shall be charged on pro rata basis.”

28. The transmission assets were put on commercial operation on or after 1.4.2008 only. Accordingly, they will complete 12 years beyond 2013-2014 and thus depreciation has been calculated annually based on Straight Line Method and at rates specified in Appendix-III.

29. For the period 1.4.2009 to 31.3.2014 the depreciation worked out are as under:

(Rs. in lakh)

Asset - I 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Rate of Depreciation 5.1884% 5.1861% 5.1862% 5.1862% 5.1862% Depreciable Value of Combined Assets 90% 24519.03 24805.81 24828.31 24839.56 24839.56 Remaining Depreciable Value 23723.21 22577.77 21152.17 19714.00 18263.91 Depreciation 1432.21 1448.10 1449.42 1450.08 1450.08 Asset - II 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Rate of Depreciation 5.2424% 5.2430% 5.2433% 5.2433% 5.2433% Depreciable Value of Combined Assets 90% 2249.23 2282.99 2303.54 2303.54 2303.54 Remaining Depreciable Value 2164.70 2067.45 1955.01 1820.80 1686.60 Depreciation 131.01 133.00 134.20 134.20 134.20 Asset - III 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Rate of Depreciation 5.2757% 5.2757% 5.2758% 5.2758% 5.2758% Depreciable Value of Combined Assets 90% 3689.17 3746.95 3783.07 3783.07 3783.07 Remaining Depreciable Value 3579.27 3420.80 3237.27 3015.51 2793.75 Depreciation 216.25 219.64 221.76 221.76 221.76

OPERATION&MAINTENANCE EXPENSES

30. Clause (g) of Regulation 19 the 2009 regulations specifies the norms for operation and maintenance expenses based on the type of sub-station and line. The petitioner has calculated the operation and maintenance expenses in accordance with the above norms and the same are allowed as such.

INTEREST ON WORKING CAPITAL

31. As per the 2009 regulations the components of the working capital and the interest thereon are discussed hereunder:

(i) Receivables: As per Regulation 18(1)(c)(i) of the 2009 regulations, receivables will be equivalent to two months' average billing calculated on target availability level. The petitioner has claimed the receivables on the basis of 2 months' transmission charges claimed in the petition. In the tariff being allowed, receivables have been worked out on the basis of 2 months' transmission charges.

(ii) Maintenance spares: Regulation 18(1)(c)(ii) of the 2009 regulations provides for maintenance spares @ 15% per annum of the O&M expenses from 1.4.2009 The value of maintenance spares has accordingly been worked out.

(iii) O& M expenses: Regulation 18(1)(c)(iii) of the 2009 regulations provides for operation and maintenance expenses for one month as a component of working capital. The petitioner has claimed O&M expenses for 1 month of the respective year as claimed in the petition. This has been considered in the working capital.

(iv) Rate of interest on working capital: As per Regulation 18(3) of the 2009 regulations, rate of interest on working capital shall be on normative basis and shall be equal to the short-term Prime Lending Rate of State Bank of India as on 1.4.2009 or on 1st April of the year in which the project or part thereof (as the case may be) is declared under commercial operation, whichever is later. The interest on working capital is payable on normative basis notwithstanding that the transmission licensee has not taken working capital loan from any outside agency. The petitioner has claimed interest on working capital @ 12.25% based on SBI PLR as on 1.4.2009, which is in accordance with the 2009 regulations and has been allowed.

32. Necessary computations in support of interest on working capital are as under:

(Rs. in lakh)

Asset - 1 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Maintenance Spares 88.34 93.41 98.75 104.40 110.36 O & M expenses 49.08 51.89 54.86 58.00 61.31 Receivables 874.85 867.08 851.31 835.31 819.32 Total 1,012.27 1,012.38 1,004.92 997.70 990.98 Rate of Interest 12.25% 12.25% 12.25% 12.25% 12.25% Interest 124.00 124.02 123.10 122.22 121.39 Asset-II 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Maintenance Spares 24.37 25.76 27.24 28.79 30.44 O & M expenses 13.54 14.31 15.13 16.00 16.91 Receivables 98.31 98.94 99.23 98.92 98.72 Total 136.21 139.02 141.59 143.71 146.07 Rate of Interest 12.25% 12.25% 12.25% 12.25% 12.25% Interest 16.69 17.03 17.35 17.60 17.89 Asset-III 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Maintenance Spares 48.73 51.52 54.47 57.58 60.88 O & M expenses 27.07 28.62 30.26 31.99 33.82 Receivables 172.64 174.27 175.35 175.43 175.72 Total 248.45 254.41 260.08 265.00 270.42 Rate of Interest 12.25% 12.25% 12.25% 12.25% 12.25% Interest 30.43 31.17 31.86 32.46 33.13

TRANSMISSION CHARGES

33. The transmission charges being allowed for the transmission assets are summarized below:

(Rs. in lakh)

Asset-I 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Depreciation 1432.21 1448.10 1449.42 1450.08 1450.08 Interest on Loan 1656.39 1543.45 1411.46 1277.39 1142.53 Return on equity 1447.51 1464.22 1465.53 1466.18 1466.18 Interest on Working Capital 124.00 124.02 123.10 122.22 121.39 O & M Expenses 588.96 622.70 658.34 695.98 735.70 Total 5249.08 5202.49 5107.86 5011.85 4915.89 Asset - II 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Depreciation 131.01 133.00 134.20 134.20 134.20 Interest on Loan 148.65 138.87 128.02 115.55 103.07 Return on equity 131.06 133.03 134.23 134.23 134.23 Interest on Working Capital 16.69 17.03 17.35 17.60 17.89 O & M Expenses 162.44 171.74 181.57 191.94 202.92 Total 589.86 593.67 595.37 593.52 592.31 Asset - II 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 Depreciation 216.25 219.64 221.76 221.76 221.76 Interest on Loan 249.32 233.00 214.90 194.02 173.17 Return on equity 214.96 218.32 220.43 220.43 220.43 Interest on Working Capital 30.43 31.17 31.86 32.46 33.13 O & M Expenses 324.88 343.48 363.14 383.88 405.84 Total 1035.85 1045.61 1052.09 1052.56 1054.33

Application fee and the publication expenses

34. The petitioner has sought approval for the reimbursement of fee paid by it for filing the petition. In accordance with our decision in order dated 11.1.2010 in Petition No. 109/2009, the petitioner shall be entitled to recover the filing fee from the beneficiaries on pro-rata basis. The petitioner shall also be eligible for reimbursement of expenses on account of publication of notices in newspapers by the beneficiaries on pro-rata basis.

Service Tax

35. The petitioner has made a specific prayer to be allowed to bill and recover the Service tax on Transmission charges from the respondents if at any time exemption from service tax is withdrawn and transmission is notified as a taxable service. The prayer of the petitioner is premature and is accordingly rejected.

Licence Fees

36. As regards the reimbursement of licence fee, a view is yet to be taken by the Commission in the matter.

37. The transmission charges allowed in this order shall be recovered on monthly basis in accordance with Regulation 23 and shall be shared by the respondents in accordance with Regulation 33 of the 2009 regulations.

38. This order disposes of Petition No. 241/2010.

ANNEXURE

Name of the Tr. System: Asset-1: Combined assets if (a) Reactor at Narendra, (b) Narendra-Davengiri Line, (c) LILO of Kolar-Sripurmbudur Notional DOCO: 01.06.2008 Petition No.: 241/2010 Tarrif setting Period: 2009-14 CALCULATION OF WEIGHTED AVERAGE RATE OF INTEREST ON LOAN (Rs. in Lacs) Details of Loan 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 1 Bond XXI Gross loan opening 2000.00 2000.00 2000.00 2000.00 2000.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 166.67 333.33 500.00 Net Loan-Opening 2000.00 2000.00 1833.33 1666.67 1500.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 166.67 166.67 166.67 166.67 Net Loan-Closing 2000.00 1833.33 1666.67 1500.00 1333.33 Average Loan 2000.00 1916.67 1750.00 1583.33 1416.67 Rate of Interest 8.73% 8.73% 8.73% 8.73% 8.73% Interest 174.60 167.33 152.78 138.23 123.68 Rep Schedule 12 Annual instalments from 11-10-2010 2 Bond XXII Gross loan opening 5760.00 5760.00 5760.00 5760.00 5760.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 480.00 960.00 1440.00 Net Loan-Opening 5760.00 5760.00 5280.00 4800.00 4320.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 480.00 480.00 480.00 480.00 Net Loan-Closing 5760.00 5280.00 4800.00 4320.00 3840.00 Average Loan 5760.00 5520.00 5040.00 4560.00 4080.00 Rate of Interest 8.68% 8.68% 8.68% 8.68% 8.68% Interest 499.97 479.14 437.47 395.81 354.14 Rep Schedule 12 Annual instalments from 07-12-2010 3 Bond XIX Gross loan opening 400.00 400.00 400.00 400.00 400.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 33.33 66.67 100.00 Net Loan-Opening 400.00 400.00 366.67 333.33 300.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 33.33 33.33 33.33 33.33 Net Loan-Closing 400.00 366.67 333.33 300.00 266.67 Average Loan 400.00 383.33 350.00 316.67 283.33 Rate of Interest 9.25% 9.25% 9.25% 9.25% 9.25% Interest 37.00 35.46 32.38 29.29 26.21 Rep Schedule 12 Annual instalments from 24.07.2010 4 Bond XX Gross loan opening 1260.00 1260.00 1260.00 1260.00 1260.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 105.00 210.00 315.00 Net Loan-Opening 1260.00 1260.00 1155.00 1050.00 945.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 105.00 105.00 105.00 105.00 Net Loan-Closing 1260.00 1155.00 1050.00 945.00 840.00 Average Loan 1260.00 1207.50 1102.50 997.50 892.50 Rate of Interest 8.93% 8.93% 8.93% 8.93% 8.93% Interest 112.52 107.83 98.45 89.08 79.70 Rep Schedule 12 Annual instalments from 07.09.2010 5 Bond XXIV Gross loan opening 2990.00 2990.00 2990.00 2990.00 2990.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 249.17 498.33 747.50 Net Loan-Opening 2990.00 2990.00 2740.83 2491.67 2242.50 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 249.17 249.17 249.17 249.17 Net Loan-Closing 2990.00 2740.83 2491.67 2242.50 1993.33 Average Loan 2990.00 2865.42 2616.25 2367.08 2117.92 Rate of Interest 9.95% 9.95% 9.95% 9.95% 9.95% Interest 297.51 285.11 260.32 235.52 210.73 Rep Schedule 12 Annual instalments from 26-03-2011 6 Bond XXV Gross loan opening 4127.00 4127.00 4127.00 4127.00 4127.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 343.92 687.83 Net Loan-Opening 4127.00 4127.00 4127.00 3783.08 3439.17 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 343.92 343.92 343.92 Net Loan-Closing 4127.00 4127.00 3783.08 3439.17 3095.25 Average Loan 4127.00 4127.00 3955.04 3611.13 3267.21 Rate of Interest 10.10% 10.10% 10.10% 10.10% 10.10% Interest 416.83 416.83 399.46 364.72 329.99 Rep Schedule 12 Annual instalments from 12-6-2011 7 Bond XXVI Gross loan opening 1303.00 1303.00 1303.00 1303.00 1303.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 108.58 217.17 Net Loan-Opening 1303.00 1303.00 1303.00 1194.42 1085.83 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 108.58 108.58 108.58 Net Loan-Closing 1303.00 1303.00 1194.42 1085.83 977.25 Average Loan 1303.00 1303.00 1248.71 1140.13 1031.54 Rate of Interest 9.30% 9.30% 9.30% 9.30% 9.30% Interest 121.18 121.18 116.13 106.03 95.93 Rep Schedule 12 Annual instalments from 07.03.2012 8 Bond XXVIII Gross loan opening 1554.88 1554.88 1554.88 1554.88 1554.88 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 129.57 Net Loan-Opening 1554.88 1554.88 1554.88 1554.88 1425.31 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 129.57 129.57 Net Loan-Closing 1554.88 1554.88 1554.88 1425.31 1295.73 Average Loan 1554.88 1554.88 1554.88 1490.09 1360.52 Rate of Interest 9.33% 9.33% 9.33% 9.33% 9.33% Interest 145.07 145.07 145.07 139.03 126.94 Rep Schedule 12 Annual instalments from 15.12.2012 9 Bond XXX (Add Cap for 2009-2010 Drawl 31.03.2010) Gross loan opening 0.00 428.60 428.60 428.60 428.60 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 0.00 Net Loan-Opening 0.00 428.60 428.60 428.60 428.60 Additions during the year 428.60 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 0.00 35.72 Net Loan-Closing 428.60 428.60 428.60 428.60 392.88 Average Loan 214.30 428.60 428.60 428.60 410.74 Rate of Interest 8.80% 8.80% 8.80% 8.80% 8.80% Interest 18.86 37.72 37.72 37.72 36.15 Rep Schedule 12 Annual instalments from 29.09.2013 Total Loan Gross loan opening 19394.88 19823.48 19823.48 19823.48 19823.48 Cumulative Repayment upto 0.00 0.00 1034.17 2520.83 4137.07 DOCO/previous year Net Loan-Opening 19394.88 19823.48 18789.31 17302.65 15686.41 Additions during the year 428.60 0.00 0.00 0.00 0.00 Repayment during the year 0.00 1034.17 1486.67 1616.24 1651.96 Net Loan-Closing 19823.48 18789.31 17302.65 15686.41 14034.45 Average Loan 19609.18 19306.40 18045.98 16494.53 14860.43 Weighted Average Rate of Interest 9.2993% 9.3008% 9.3083% 9.3087% 9.3097% Interest 1823.53 1795.65 1679.77 1535.42 1383.46
Name of the Tr. System: Asset-2: 2nd 315 MVA Auto Transformer at Hiriyur Sub-Station Actual DOCO: 01.04.2008 Petition No.: 241/2010 Tarrif setting Period: 2009-14 CALCULATION OF WEIGHTED AVERAGE RATE OF INTEREST ON LOAN (Rs. in Lacs) Details of Loan 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 1 Bond-XIX Gross loan opening 50.00 50.00 50.00 50.00 50.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 4.17 8.33 12.50 Net Loan-Opening 50.00 50.00 45.83 41.67 37.50 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 4.17 4.17 4.17 4.17 Net Loan-Closing 50.00 45.83 41.67 37.50 33.33 Average Loan 50.00 47.92 43.75 39.58 35.42 Rate of Interest 9.25% 9.25% 9.25% 9.25% 9.25% Interest 4.63 4.43 4.05 3.66 3.28 Rep Schedule 12 Annual instalments from 24.07.2010 2 Bond-XX Gross loan opening 200.00 200.00 200.00 200.00 200.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 16.67 33.33 50.00 Net Loan-Opening 200.00 200.00 183.33 166.67 150.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 16.67 16.67 16.67 16.67 Net Loan-Closing 200.00 183.33 166.67 150.00 133.33 Average Loan 200.00 191.67 175.00 158.33 141.67 Rate of Interest 8.93% 8.93% 8.93% 8.93% 8.93% Interest 17.86 17.12 15.63 14.14 12.65 Rep Schedule 12 Annual instalments from 07.09.2010 3 Bond-XXI Gross loan opening 200.00 200.00 200.00 200.00 200.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 16.67 33.33 50.00 Net Loan-Opening 200.00 200.00 183.33 166.67 150.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 16.67 16.67 16.67 16.67 Net Loan-Closing 200.00 183.33 166.67 150.00 133.33 Average Loan 200.00 191.67 175.00 158.33 141.67 Rate of Interest 8.73% 8.73% 8.73% 8.73% 8.73% Interest 17.46 16.73 15.28 13.82 12.37 Rep Schedule 12 Annual instalments from 11.10.2010 4 Bond-XXII Gross loan opening 200.00 200.00 200.00 200.00 200.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 16.67 33.33 50.00 Net Loan-Opening 200.00 200.00 183.33 166.67 150.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 16.67 16.67 16.67 16.67 Net Loan-Closing 200.00 183.33 166.67 150.00 133.33 Average Loan 200.00 191.67 175.00 158.33 141.67 Rate of Interest 8.68% 8.68% 8.68% 8.68% 8.68% Interest 17.36 16.64 15.19 13.74 12.30 Rep Schedule 12 Annual instalments from 07.12.2010 5 Bond-XXIV Gross loan opening 100.00 100.00 100.00 100.00 100.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 8.33 16.67 25.00 Net Loan-Opening 100.00 100.00 91.67 83.33 75.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 8.33 8.33 8.33 8.33 Net Loan-Closing 100.00 91.67 83.33 75.00 66.67 Average Loan 100.00 95.83 87.50 79.17 70.83 Rate of Interest 9.95% 9.95% 9.95% 9.95% 9.950% Interest 9.95 9.54 8.71 7.88 7.05 Rep Schedule 12 Annual instalments from26-03-2011 6 Bond-XXV Gross loan opening 300.00 300.00 300.00 300.00 300.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 25.00 50.00 Net Loan-Opening 300.00 300.00 300.00 275.00 250.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 25.00 25.00 25.00 Net Loan-Closing 300.00 300.00 275.00 250.00 225.00 Average Loan 300.00 300.00 287.50 262.50 237.50 Rate of Interest 10.10% 10.10% 10.10% 10.10% 10.10% Interest 30.30 30.30 29.04 26.51 23.99 Rep Schedule 12 Annual instalments from 12-06-2011 7 Bond-XXVI Gross loan opening 519.00 519.00 519.00 519.00 519.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 43.25 86.50 Net Loan-Opening 519.00 519.00 519.00 475.75 432.50 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 43.25 43.25 43.25 Net Loan-Closing 519.00 519.00 475.75 432.50 389.25 Average Loan 519.00 519.00 497.38 454.13 410.88 Rate of Interest 9.30% 9.30% 9.30% 9.30% 9.30% Interest 48.27 48.27 46.26 42.23 38.21 Rep Schedule 12 Annual instalments from 07-03-2012 8 Bond-XXVIII Gross loan opening 169.95 169.95 169.95 169.95 169.95 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 14.16 Net Loan-Opening 169.95 169.95 169.95 169.95 155.79 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 14.16 14.16 Net Loan-Closing 169.95 169.95 169.95 155.79 141.63 Average Loan 169.95 169.95 169.95 162.87 148.71 Rate of Interest 9.33% 9.33% 9.33% 9.33% 9.33% Interest 15.86 15.86 15.86 15.20 13.87 Rep Schedule 12 Annual instalments from 15.12.2012 9 Bond XXX (Add Cap for 2009-2010 Drawl on 31.03.2010) Gross loan opening 0.00 20.57 20.57 20.57 20.57 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 0.00 Net Loan-Opening 0.00 20.57 20.57 20.57 20.57 Additions during the year 20.57 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 0.00 1.71 Net Loan-Closing 20.57 20.57 20.57 20.57 18.86 Average Loan 10.29 20.57 20.57 20.57 19.71 Rate of Interest 8.80% 8.80% 8.80% 8.80% 8.80% Interest 0.91 1.81 1.81 1.81 1.73 Rep Schedule 12 Annual instalments from 29.09.2013 Total Loan Gross loan opening 1738.95 1759.52 1759.52 1759.52 1759.52 Cumulative Repayment upto DOCO/previous year 0.00 0.00 62.50 193.25 338.16 Net Loan-Opening 1738.95 1759.52 1697.02 1566.27 1421.36 Additions during the year 20.57 0.00 0.00 0.00 0.00 Repayment during the year 0.00 62.50 130.75 144.91 146.63 Net Loan-Closing 1759.52 1697.02 1566.27 1421.36 1274.73 Average Loan 1749.24 1728.27 1631.65 1493.81 1348.04 Rate of Interest 9.2945% 9.2975% 9.3040% 9.3047% 9.3058% Interest 162.58 160.69 151.81 139.00 125.45
Name of the Company: PGCIL PGCIL Name of the Tr. System: Asset-3: Combined asset of ICT-I & ICT-II Auto Transformer at Kalvindapattu Notional DOCO: 01.07.2008 Petition No.: 241/2010 Tarrif setting Period: 2009-14 CALCULATION OF WEIGHTED AVERAGE RATE OF INTEREST ON LOAN (Rs. in Lacs) Details of Loan 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 1 Bond XXI Gross loan opening 50.00 50.00 50.00 50.00 50.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 4.17 8.33 12.50 Net Loan-Opening 50.00 50.00 45.83 41.67 37.50 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 4.17 4.17 4.17 4.17 Net Loan-Closing 50.00 45.83 41.67 37.50 33.33 Average Loan 50.00 47.92 43.75 39.58 35.42 Rate of Interest 8.73% 8.73% 8.73% 8.73% 8.73% Interest 4.37 4.18 3.82 3.46 3.09 Rep Schedule 12 Annual instalments from 11-10-2010 2 Bond XXII Gross loan opening 200.00 200.00 200.00 200.00 200.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 16.67 33.33 50.00 Net Loan-Opening 200.00 200.00 183.33 166.67 150.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 16.67 16.67 16.67 16.67 Net Loan-Closing 200.00 183.33 166.67 150.00 133.33 Average Loan 200.00 191.67 175.00 158.33 141.67 Rate of Interest 8.68% 8.68% 8.68% 8.68% 8.68% Interest 17.36 16.64 15.19 13.74 12.30 Rep Schedule 12 Annual instalments from 07-12-2010 3 Bond XX Gross loan opening 20.00 20.00 20.00 20.00 20.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 1.67 3.33 5.00 Net Loan-Opening 20.00 20.00 18.33 16.67 15.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 1.67 1.67 1.67 1.67 Net Loan-Closing 20.00 18.33 16.67 15.00 13.33 Average Loan 20.00 19.17 17.50 15.83 14.17 Rate of Interest 8.93% 8.93% 8.93% 8.93% 8.93% Interest 1.79 1.71 1.56 1.41 1.27 Rep Schedule 12 Annual instalments from 07.09.2010 4 Bond XXIV Gross loan opening 200.00 200.00 200.00 200.00 200.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 16.67 33.33 50.00 Net Loan-Opening 200.00 200.00 183.33 166.67 150.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 16.67 16.67 16.67 16.67 Net Loan-Closing 200.00 183.33 166.67 150.00 133.33 Average Loan 200.00 191.67 175.00 158.33 141.67 Rate of Interest 9.95% 9.95% 9.95% 9.95% 9.95% Interest 19.90 19.07 17.41 15.75 14.10 Rep Schedule 12 Annual instalments from 26-03-2011 5 Bond XXV Gross loan opening 420.00 420.00 420.00 420.00 420.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 35.00 70.00 Net Loan-Opening 420.00 420.00 420.00 385.00 350.00 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 35.00 35.00 35.00 Net Loan-Closing 420.00 420.00 385.00 350.00 315.00 Average Loan 420.00 420.00 402.50 367.50 332.50 Rate of Interest 10.10% 10.10% 10.10% 10.10% 10.10% Interest 42.42 42.42 40.65 37.12 33.58 Rep Schedule 12 Annual instalments from 12-6-2011 6 Bond XXVI Gross loan opening 1555.00 1555.00 1555.00 1555.00 1555.00 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 129.58 259.17 Net Loan-Opening 1555.00 1555.00 1555.00 1425.42 1295.83 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 129.58 129.58 129.58 Net Loan-Closing 1555.00 1555.00 1425.42 1295.83 1166.25 Average Loan 1555.00 1555.00 1490.21 1360.63 1231.04 Rate of Interest 9.30% 9.30% 9.30% 9.30% 9.30% Interest 144.62 144.62 138.59 126.54 114.49 Rep Schedule 12 Annual instalments from 07.03.2012 7 Bond XXVIII Gross loan opening 582.05 582.05 582.05 582.05 582.05 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 48.50 Net Loan-Opening 582.05 582.05 582.05 582.05 533.55 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 48.50 48.50 Net Loan-Closing 582.05 582.05 582.05 533.55 485.04 Average Loan 582.05 582.05 582.05 557.80 509.29 Rate of Interest 9.33% 9.33% 9.33% 9.33% 9.33% Interest 54.31 54.31 54.31 52.04 47.52 Rep Schedule 12 Annual instalments from 15.12.2012 8 Bond XXX (Add Cap for 2009-2010 Drawl 31.03.2010) Gross loan opening 0.00 33.69 33.69 33.69 33.69 Cumulative Repayment upto DOCO/previous year 0.00 0.00 0.00 0.00 0.00 Net Loan-Opening 0.00 33.69 33.69 33.69 33.69 Additions during the year 33.69 0.00 0.00 0.00 0.00 Repayment during the year 0.00 0.00 0.00 0.00 2.81 Net Loan-Closing 33.69 33.69 33.69 33.69 30.88 Average Loan 16.85 33.69 33.69 33.69 32.29 Rate of Interest 8.80% 8.80% 8.80% 8.80% 8.80% Interest 1.48 2.96 2.96 2.96 2.84 Rep Schedule 12 Annual instalments from 29.09.2013 Total Loan Gross loan opening 3027.05 3060.74 3060.74 3060.74 3060.74 Cumulative Repayment upto DOCO/previous year 0.00 0.00 39.17 242.92 495.17 Net Loan-Opening 3027.05 3060.74 3021.57 2817.82 2565.57 Additions during the year 33.69 0.00 0.00 0.00 0.00 Repayment during the year 0.00 39.17 203.75 252.25 255.06 Net Loan-Closing 3060.74 3021.57 2817.82 2565.57 2310.51 Average Loan 3043.90 3041.16 2919.70 2691.70 2438.04 Weighted Average Rate of Interest 9.4035% 9.4013% 9.4015% 9.4004% 9.4001% Interest 286.23 285.91 274.50 253.03 229.18