Power Grid Corporation Of India Ltd. v. Madhya Pradesh Power Management Company Ltd.

Central Electricity Regulatory Commission
Jan 12, 2016
Smart Summary (Beta)

Structured Summary of the Legal Opinion

Factual and Procedural Background

The petition was filed by Power Grid Corporation of India Ltd. (the petitioner), a transmission licensee, seeking truing up of capital expenditure and tariff for a set of combined transmission assets under Vindhyachal Stage-III transmission system in the Western Region. The assets listed include multiple 400 kV D/C lines, LILOs, associated bays, and 400/220 kV 315 MVA ICT-II equipments at Satna and Raigarh substations. The petitioner sought truing up based on actual expenditure for the period 1.4.2009 to 31.3.2014 under the 2009 Tariff Regulations, and determination of tariff for 1.4.2014 to 31.3.2019 under the 2014 Tariff Regulations.

The respondents are distribution licensees or centralized power procurement companies (mainly beneficiaries of the Western Region). The petition was served on respondents and advertised under Section 64 of the Electricity Act, 2003; no public comments were received and none of the respondents filed a reply. A hearing was held on 21.12.2015. After hearing and perusal of record, the Commission disposed of Petition No. 388/TT/2014 by the present order.

Legal Issues Presented

  1. Whether the capital cost and the annual fixed charges for the transmission assets for the tariff period 2009-14 should be trued up based on the petitioner's submissions and supporting documents in accordance with the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009.
  2. What should be the capital cost, component-wise annual transmission charges and allied normative parameters (depreciation, interest on loan, return on equity, O&M expenses, interest on working capital) for these transmission assets for the tariff period 2014-19 in accordance with the 2014 Tariff Regulations?

Arguments of the Parties

Petitioner's Submissions

  • Claimed admitted opening capital cost of Rs. 63,718.32 lakh as on 31.3.2009 (to be taken as on 1.4.2009) and additional capitalisation of Rs. 1,137.50 lakh during 2009-14 for afforestation, differential entry tax and balance/retention payments (within and after cut-off as applicable).
  • Explained variation in entry tax from projection (Rs. 630.99 lakh) to actual (Rs. 804.86 lakh) by reference to earlier projection being on tower parts only and increase in entry tax rate for conductor from 1% to 5%.
  • Provided details and justification for afforestation cost of Rs. 32.76 lakh (breakdown of supervision charges, deposits and NPV difference).
  • Adopted debt:equity ratio of 70:30 as admitted by the Commission as on 31.3.2009 for opening capital structure and set out debt/equity split for additional capitalization years.
  • Submitted weighted average actual interest rates and actual loan portfolio for computation of Interest on Loan (IOL) and asked for IOL to be calculated per Regulation 16 (2009 Tariff Regulations) and Regulation 26 (2014 Tariff Regulations) as applicable.
  • Requested ROE to be grossed up using actual MAT/effective tax rates for respective years; provided MAT variations for 2009-14 and computed grossed up ROE accordingly.
  • Computed depreciation in accordance with Regulation 17 of the 2009 Tariff Regulations and Regulation 27 of the 2014 Tariff Regulations using useful lives and the admitted capital bases.
  • Computed O&M expenses according to normative rates in Regulation 19(g) (2009 Regulations) for 2009-14 and Regulation 29 (2014 Regulations) for 2014-19; noted normalized basis for 2014-19 and sought the possibility of later revision in case of wage revision impact.
  • Computed Interest on Working Capital (IWC) using components and rates in Regulation 18 (2009) and Regulation 28 (2014) and provided the bases and figures for both tariff periods.
  • For 2014-19 the petitioner claimed opening capital cost as Rs. 64,855.82 lakh as on 31.3.2014 and did not claim any additional capital expenditure for 2014-19.
  • Requested reimbursement of filing fees and publication expenses under Regulation 52 (2014 Tariff Regulations), and reimbursement of licence fee and RLDC fees and charges as per Regulation 52(2).
  • Prayed to be allowed to recover service tax separately if service tax treatment changes in future; sought recovery of deferred tax liability materializing up to 31.3.2009 as per Regulation 49 (2014 Regulations).

Respondents' Position

None of the respondents filed replies to the petition; the opinion records that no respondent submissions were received.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Order dated 8.2.2011 in Petition No. 243/2010 (Central Electricity Regulatory Commission) Determination of transmission tariff for 2009-14 based on admitted capital cost as on 31.3.2009 and approval of additional capital expenditure for 2009-14. The Commission used the admitted capital cost (Rs. 63,718.32 lakh as on 31.3.2009), the admitted debt:equity ratio (70:30 as on 31.3.2009), and the approved additional capitalisation figures in that order as the opening base for truing up and as a comparator to the petitioner's claimed actual additional capitalisation. The order is cited repeatedly as the baseline for admitted figures on 1.4.2009.
Order dated 8.6.2011 in Petition No. 238/2010 (Central Electricity Regulatory Commission) Rule that in case of floating rate of interest, any change in interest rates during the tariff period shall be considered at the time of true up. The Commission relied on this statement to justify accepting and using the petitioner's actual weighted average rate of interest on loan (as per the actual loan portfolio) for calculation of IOL at truing up.
Orders dated 19.6.2009 (Petition No. 48/2009), 17.9.2008 (Petition No. 45/2008), 20.4.2009 (Petition No. 132/2008), and revision dated 18.6.2010 (Petition No. 44/2010) Prior determinations of transmission tariff for the transmission assets up to 31.3.2009 and revision to account for additional capital expenditure up to that date. The Commission referred to these earlier orders as the basis for the transmission tariff outcomes up to 31.3.2009 and as background to the admitted figures used for the 2009-14 truing up exercise.

Court's Reasoning and Analysis

The Commission applied the provisions of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 for truing up the tariff for 2009-14 and the 2014 Tariff Regulations for determining tariff for 2014-19. The analysis proceeded component-wise and is summarised as follows (the Commission followed the petitioner's submitted data where supported and applied the relevant regulatory formulae):

  1. Capital Cost and Additional Capitalisation:
    • The Commission accepted the admitted capital cost of Rs. 63,718.32 lakh as on 31.3.2009 (per its earlier order dated 8.2.2011) as the opening capital cost on 1.4.2009 in accordance with Regulation 7(2) (last proviso) of the 2009 Tariff Regulations.
    • Additional capital expenditure of Rs. 1,137.50 lakh actually incurred during 2009-14 (for afforestation, differential entry tax and balance/retention payments) was claimed by the petitioner. The Commission required explanations for variances (for example, entry tax increase and afforestation costs) and accepted audited certification. After scrutiny and explanations, actual additional capitalisation of Rs. 1,137.50 lakh was admitted in accordance with Clause (1) and Clause (2) of Regulation 9 (2009 Regulations).
    • For 2014-19 the Commission took the trued up capital cost of Rs. 64,855.82 lakh as on 31.3.2014 as the opening capital cost on 1.4.2014 in accordance with Regulation 9(1) and 9(3) of the 2014 Tariff Regulations; the petitioner did not claim further additions for 2014-19.
  2. Debt:Equity:
    • For the 2009-14 period, the admitted debt:equity ratio of 70:30 as on 31.3.2009 (per the earlier order) was used as the opening ratio (per Regulation 12(2) of the 2009 Regulations).
    • For 2014-19 the admitted ratio as on 31.3.2014 (effectively 70.08:29.92 by amounts shown) was taken as the opening debt:equity ratio in accordance with Regulation 19(3) of the 2014 Regulations.
  3. Interest on Loan (IOL):
    • The weighted average rate of interest was computed using the petitioner's actual loan portfolio and rates. The Commission followed Regulation 16 of the 2009 Regulations for truing up IOL (and Regulation 26 of 2014 Regulations for 2014-19), applying the weighted average rates to normative average loan amounts. The Commission accepted the petitioner's actual rates and approved IOL figures after computation.
    • The Commission relied on its earlier pronouncement (order dated 8.6.2011) that changes in floating interest rates during the tariff period are to be considered at true up, justifying use of actual rates.
  4. Return on Equity (ROE) and Tax Gross-up:
    • The Commission computed ROE by grossing up the base rate (15.50%) with the applicable tax rate (MAT or effective tax) for each year as required by Regulation 15 (2009 Regulations) and Regulations 24/25 (2014 Regulations).
    • For 2009-14 the petitioner provided actual MAT rates for each year, and the Commission used these to gross up ROE; consequently the allowed ROE at truing up was higher than the earlier order because of increase in MAT rates during the period.
    • For 2014-19 the petitioner’s position that MAT applies was accepted and the MAT rate applicable for 2013-14 (20.96%) was used for grossing up ROE for the 2014-19 period, subject to truing up with actual taxes as per Regulation 25(3).
  5. Depreciation:
    • The Commission applied the useful lives and straight-line method as per Regulation 17 (2009 Regulations) for 2009-14 and Regulation 27 (2014 Regulations) for 2014-19. It calculated depreciation based on admitted gross capital cost and additional capitalization, applied the prescribed rates (weighted life where required), and accounted for the proviso relating to spreading remaining depreciable value after 12 years.
    • Depreciation allowed at truing up was slightly higher where additional capitalisation increased the depreciable base.
  6. Operation & Maintenance (O&M) Expenses:
    • The Commission accepted petitioner’s computation of O&M expenses using the normative rates specified in Regulation 19(g) of the 2009 Regulations for 2009-14 (which matched the previously approved figures) and Regulation 29 for 2014-19, applying the line lengths and number of bays as claimed.
    • The petitioner raised a prospective issue of wage revision impact; the Commission noted that any such application will be considered under the 2014 Regulations provisions.
  7. Interest on Working Capital (IWC):
    • The Commission computed IWC in accordance with Regulation 18(1)(c) and Regulation 18(3) (2009 Regulations) for 2009-14 and Regulation 28 and the definition of Bank Rate (SBI base + 350 bps) for 2014-19. It accepted the petitioner's components, applied the specified rates (12.25% for 2009-14 as SBI short-term PLR on 1.4.2009; and 13.50% for 2014-19 as SBI base on 1.4.2014 plus 350 bps), and allowed the resulting IWC figures.
  8. Other operational/directional matters:
    • The Commission allowed reimbursement of filing fees and publication expenses under Regulation 52(2014) to be recovered from beneficiaries on pro-rata basis; allowed recovery of licence fees and RLDC fees and charges under Regulation 52(2)(b) and (2)(a) respectively;
    • It held the petitioner's prayer to recover service tax separately as premature (no relief granted on that ground at present); and directed that deferred tax liability up to 31.3.2009 shall be recoverable if and when it materializes in accordance with Regulation 49 (2014 Regulations).
    • Billing, collection and disbursement of approved transmission charges to be governed by the Sharing Regulations (Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010) as provided in Regulation 43 (2014 Regulations).

Holding and Implications

DISPOSAL: Petition No. 388/TT/2014 is disposed of.

Core rulings and direct effects on the parties:

  • The Commission trued up the annual fixed charges for the tariff period 2009-14 and determined the annual transmission charges for 2014-19 in accordance with the respective Regulations and on the bases stated in the order.
  • Annual fixed charges allowed after truing up for 2009-14 (Rs. in lakh) — totals by year as set out in the order:
    • 2009-10: 12,318.67
    • 2010-11: 12,338.24
    • 2011-12: 12,186.98
    • 2012-13: 12,009.50
    • 2013-14: 11,869.87
  • Annual transmission charges allowed for 2014-19 (Rs. in lakh) — totals by year as set out in the order:
    • 2014-15: 11,422.58
    • 2015-16: 11,185.54
    • 2016-17: 10,950.27
    • 2017-18: 10,717.22
    • 2018-19: 10,486.31
  • The petitioner is entitled to reimbursement of filing fees and publication expenses directly from beneficiaries on pro-rata basis (Regulation 52 of 2014 Regulations).
  • The petitioner may bill and recover licence fee and RLDC fees and charges separately from respondents in accordance with Regulation 52(2).
  • Service tax recovery claim was held to be premature and not granted in the present order.
  • Deferred tax liability up to 31.3.2009 may be recovered by the petitioner if and when it materializes, in accordance with Regulation 49 (2014 Regulations).
  • Billing, collection and disbursement of the approved transmission charges will be governed by the Sharing Regulations (2010) as referenced under Regulation 43 (2014 Regulations).

Broader implications: The order implements regulatory provisions (2009 and 2014 Tariff Regulations) as applied to the specific factual and financial claims of the petitioner. The opinion does not purport to establish a novel legal precedent; it applies existing Commission orders and regulatory rules to the petitioner's case.

This summary is based exclusively on the contents of the provided opinion and does not add or infer facts beyond those expressly stated therein.

Show all summary ...

Prashant Saran, Whole Time Member:— The present petition has been preferred by Power Grid Corporation of India Ltd. (‘the petitioner’), a transmission licensee, for truing up of capital expenditure and tariff for Combined Assets of (i) Ckt-III of 400 kV D/C Vindhyachal-Satna transmission line along with associated bays; (ii) 400/220 kV, 315 MVA ICT-II at Satna Sub-station; (iii) Ckt-IV of 400 kV D/C Vindhyachal-Satna line along with associated bays; (iv) LILO of 400 kV Satna-Bina Ckt-I & II at Bina (Power Grid) Sub-station; (v) Circuit IV of 400 kV D/C Satna-Bina transmission line; (vi) Circuit III of 400 kV D/C Satna-Bina transmission line; (vii) LILO of 400 kV D/C Raipur-Rourkela transmission line along with associated bays; and (viii) 400/220 kV 315 MVA ICT-II along with associated bays equipment at Raigarh Sub-station under Vindhyachal Stage-III transmission system in Western Region (hereinafter collectively referred as “transmission asset”) under Regulation 6 of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 (hereinafter referred to as “the 2009 Tariff Regulations”) based on actual expenditure for the period 1.4.2009 to 31.3.2014 and for determination of tariff under Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as “the 2014 Tariff Regulations”) for the period from 1.4.2014 to 31.3.2019

2. The respondents are distribution licensees or centralised power procurement companies of States, who are procuring transmission service from the petitioner, mainly beneficiaries of Western Region.

3. The petitioner has served the petition to the respondents and notice of this application has been published in the newspaper in accordance with Section 64 of the Electricity Act, 2003 (“the Act”). No comments have been received from the public in response to the notices published by the petitioner under Section 64 of the Act. None of the respondents have filed reply to the petition. The hearing in this matter was held on 21.12.2015 Having heard the representatives of the petitioner and perused the material on record, we proceed to dispose of the petition.

4. The brief facts of the case are as follows:

a) The investment approval for the transmission system was accorded by Ministry of Power vide its letter dated 23.7.2004 at an estimated cost of Rs. 59647.00 lakh, which included IDC of Rs. 5289.00 lakh. Subsequently, approval for the revised cost estimate was accorded by Ministry of Power under its letter dated 13.11.2007 at an estimated cost of Rs. 68956.00 lakh, which included IDC of Rs. 1319.00 Lakh. The notional date of commercial operation of the transmission has been taken as 1.2.2008

b) The transmission tariff for the transmission assets up to 31.3.2009 were decided by the Commission in its order dated 19.6.2009 in Petition No. 48/2009, order dated 17.9.2008 in Petition No. 45/2008 and order dated 20.4.2009 in Petition No. 132/2008 and same were revised vide order dated 18.6.2010 in Petition No. 44/2010, after accounting for the additional capital expenditure up to 31.3.2009

c) The Commission, in its order dated 8.2.2011 in Petition No. 243/2010, has determined the tariff for the tariff period 2009-14 based on admitted capital cost of Rs. 63718.32 lakh as on 31.3.2009 and additional capital expenditure of Rs. 1096.84 lakh for the tariff period 2009-14 in accordance with the 2009 Tariff Regulations. The tariff allowed for the tariff period 2009-14 is as under:—

(Rs. in lakh)

Approved in 2009-14 2009-10 2010-11 2011-12 2012-13 2013-14 Depreciation 3342.05 3369.57 3391.60 3391.60 3391.60 Interest on Loan 3452.38 3199.24 2932.49 2637.76 2342.59 Return on Equity 3348.26 3377.02 3399.09 3399.09 3399.09 Interest on WC 292.34 292.87 293.13 292.16 291.46 O&M Expenses 1618.13 1710.83 1808.76 1912.12 2021.26 Total 12053.15 11949.53 11825.07 11632.73 11446.00

d) The MAT rate applicable during 2008-09 was considered to arrive at the rate of return on equity for the tariff period 2009-14, which is required to be adjusted as per the actual MAT rate applicable for the respective year at the time of truing up of the tariff for 2009-14 tariff period.

e) The instant petition was filed on 19.9.2014

TRUING UP OF ANNUAL FIXED CHARGES FOR TARIFF PERIOD 2009-14

5. The truing up of tariff for the tariff period 2009-14 has been determined as discussed below:—

Capital Cost

6. The petitioner has claimed admitted capital cost of Rs. 63718.32 lakh as on 31.3.2009 for the purpose of tariff. In addition to this, the petitioner has claimed additional capitalisation of Rs. 1137.50 lakh on account of afforestation, differential entry tax and balance and retention payments for which works have been executed with in cut-off date for the tariff period 2009-14.

7. Last proviso to Clause (2) of Regulation 7 of the 2009 Tariff Regulations provides that:

“Provided also that in case of the existing projects, the capital cost admitted by the Commission prior to 1.4.2009 duly trued up by excluding un-discharged liability, if any, as on 1.4.2009 and the additional capital expenditure projected to be incurred for the respective year of the tariff period 2009-14, as may be admitted by the Commission, shall form the basis for determination of tariff”.

8. The capital cost admitted as on 31.3.2009, vide order dated 8.2.2011 in Petition No 243/2010, has been considered as the opening capital cost as on 1.4.2009 for determination of tariff in accordance with Regulation 7 of the 2009 Tariff Regulations. The admitted capital cost of Rs. 63718.32 lakh as on 1.4.2009 has been considered to work out the trued up tariff for the tariff period 2009-14.

Additional Capital Expenditure

9. The petitioner has claimed Rs. 1137.50 lakh as additional capital expenditure against the approved additional capital expenditure of Rs. 1096.84 lakh for the tariff period 2009-14 on account of afforestation, differential entry tax and balance and retention payments for which works have been executed with in cut-off date under Clause (1) of Regulation 9 of the 2009 Tariff Regulations and after cut-off date under Clause (2) of Regulation 9 of the 2009 Tariff Regulations.

10. Clause (1) and Clause (2) of Regulation 9 of the 2009 Tariff Regulations provides as follows:—

“(1) The capital expenditure incurred or projected to be incurred, on the following counts within the original scope of work, after the date of commercial operation and up to the cut-off date may be admitted by the Commission, subject to prudence check:

(i) Undischarged liabilities;

(ii) Works deferred for execution;

(iii) Procurement of initial capital spares within the original scope of work, subject to the provisions of regulation 8;

(iv) Liabilities to meet award of arbitration or for compliance of the order or decree of a court; and

(v) Change in law …

(2) The capital expenditure incurred on the following counts after the cut-off date may, in its discretion, be admitted by the Commission, subject to prudence check:

(i) Liabilities to meet award of arbitration or for compliance of the order or decree of a court;

(v) In case of transmission system any additional expenditure on items such as relays, control and instrumentation, computer system, power line carrier communication, DC batteries, replacement of switchyard equipment due to increase of fault level, emergency restoration system, insulators cleaning infrastructure, replacement of damaged equipment not covered by insurance and any other expenditure which has become necessary for successful and efficient operation of transmission system:

Provided that in respect sub-clauses (iv) and (v) above, any expenditure on acquiring the minor items or the assets like tools and tackles, furniture, air-conditioners, voltage stabilizers, refrigerators, coolers, fans, washing machines, heat convectors, mattresses, carpets etc. brought after the cut-off date shall not be considered for additional capitalization for determination of tariff w.e.f 1.4.2009”

11. The total actual additional capitalisation of Rs. 1137.50 lakh claimed during the tariff period 2009-14 is more than the additional capitalisation of Rs. 1096.84 lakh for the tariff period 2009-14 approved by the Commission vide order dated 8.2.2011 in Petition No. 243/2010 on account of afforestation, differential entry tax and balance and retention payments. In this regards, the petitioner wqas directed to submit the reason for variation in entry tax amount from Rs. 630.99 lakh as approved in the order dated 8.2.2011 in Petition No. 243/2010 to Rs. 804.86 lakh. In response, the petitioner submitted that the projection of entry tax was done on tower parts only. Additional amount paid is due increase in rate of entry tax from 1% to 5% for Conductor.

12. The petitioner was directed to confirm whether all the payments are claimed or some payments are still to be claimed. In this regard, the petitioner confirmed that all the balance/retention payments under this petition have been paid and no further balance/retention payments are to be claimed.

13. Further, the Commission directed the petitioner to submit details and justification for the additional capitalisation amount of Rs. 32.76 lakh claimed on account of afforestation. In response, the petitioner submitted details and justification for the additional capitalisation amount of Rs. 32.76 lakh claimed on account of afforestation as given in the table below:—

S. No. Head/Justification Amount (in Rs.) 1 Supervision charges for compensatory afforestation as per guidelines received from Vanmandal Adhikari West Siddhi 2288515 2 Deposit - difference amount for use of forest land for 400kV Vindhyachal-satna ckt.III 87020 3 Difference amount of NPV paid 900140 4 Total 3275675

14. The actual additional capital expenditure of Rs. 1137.50 lakh is certified by the Auditor has been considered to work out the true up tariff for 2009-14 tariff period in accordance with Clause (1) and Clause (2) of Regulation 9 of the 2009 Tariff Regulations. The summary of capital cost including additional capitalization is shown in the table below:—

(Rs. in lakh)

Cost as per Investment Approval is Rs. 68956 lakh Particulars Admitted Capital Cost as on 31.3.2009 Additional Capitalisation Total Additional Capitalisation Total Capital cost including Additional Capitalisation 2009-10 2010-11 2011-12 2012-13 2013-14 Approved in Order dated 8.2.2011 63718.32 255.11 841.73 0.00 0.00 0.00 1096.84 64815.2 Actual 63718.32 627.18 313.99 181.49 14.84 0.00 1137.50 64855.82

Debt: Equity

15. clause 2 of regulation 12 of the 2009 Tariff Regulations provides that:—

“In case of the generating station and the transmission system declared under commercial operation prior to 1.4.2009, debt:equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2009 shall be considered.”

16. The petitioner has claimed trued up Annual Fixed Charge based on debt:equity ratio of 70:30 as on 31.3.2009 considered by the Commission in its order dated 8.2.2011 in Petition No. 243/2010. The transmission assets covered in the instant petition were commissioned prior to 1.4.2009 The Commission had admitted debt:equity ratio of 70:30 as on 31.3.2009 vide order dated 8.2.2011 in Petition No. 243/2010. The admitted debt:equity ratio of 70:30 as on 31.3.2009 has been considered as opening debt:equity ratio as on 1.4.2009 for the purpose of truing up of the approved tariff for the tariff period 2009-14, as given under:—

(Rs. in lakh)

Funding Admitted as on 31.3.2009 (%) Debt 44602.89 70.00 Equity 19115.43 30.00 Total 63718.32 100.00

17. The debt:equity ratio claimed by the petitioner for the purpose of additional capital expenditure is given in the table below:—

(Rs. in lakh)

Funding 2009-10 2010-11 2011-12 2012-13 2013-14 Debt 439.03 219.79 176.00 10.39 0.00 Equity 188.15 94.20 5.50 4.45 0.00 Total 627.18 313.99 181.50 14.84 0.00 Debt-Equity Ratio Debt (%) 70.00 70.00 96.97 70.00 70.00 Equity (%) 30.00 30.00 3.03 30.00 30.00 Total(%) 100.00 100.00 100.00 100.00 100.00

18. Debt-equity ratio is allowed in accordance with clause 2 of regulation 12 of the 2009 Tariff Regulations. The overall debt:equity admitted as on 31.03.2014 including additional capitalization is as under:—

(Rs. in lakh)

Funding 2009-10 2010-11 2011-12 2012-13 2013-14 Admitted as on 31.3.2014 Debt 439.03 219.79 176.00 10.39 0.00 45448.10 Equity 188.15 94.20 5.50 4.45 0.00 19407.73 Total 627.18 313.99 181.50 14.84 0.00 64855.83 Debt-Equity Ratio Debt (%) 70.00 70.00 96.97 70.00 70.00 70.08 Equity (%) 30.00 30.00 3.03 30.00 30.00 29.92 Total (%) 100.00 100.00 100.00 100.00 100.00 100.00

Interest on Loan (“IOL’)

19. Regulation 16 of the 2009 Tariff Regulations provides the methodology for working out weighted average rate of interest on loan. The Commission in its earlier order dated 8.6.2011 in Petition No. 238/2010 has held that:—

“…in case of floating rate of interest, any change in the rates of interest during the tariff period will be considered at the time of true up”.

20. The petitioner has submitted the weighted average rate of interest on loan based on its actual loan portfolio and rate of interest.

21. We have considered the submissions of the petitioner and accordingly calculated the IOL based on actual interest rate submitted by the petitioner, in accordance with Regulation 16 of the 2009 Tariff Regulations. The details of weighted average rate of interest are placed at Annexure-I and the IOL has been worked out and approved as follows:—

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 8.2.2011 3452.38 3199.24 2932.49 2637.76 2342.59 As claimed by the petitioner 3463.35 3204.79 2929.86 2643.68 2348.77 Allowed after trued up 3463.35 3204.81 2929.85 2643.70 2348.76

Return on Equity (“ROE”)

22. Clause (3), (4) and (5) of the Regulation 15 of the 2009 Tariff Regulations provide that:—

“(3) The rate of return on equity shall be computed by grossing up the base rate with the Minimum Alternate/Corporate Income Tax Rate for the year 2008-09, as per the Income Tax Act, 1961, as applicable to the concerned generating company or the transmission licensee, as the case may be.

(4) Rate of return on equity shall be rounded off to three decimal points and be computed as per the formula given below:

Rate of pre-tax return on equity = Base rate/(1-t)

Where “t” is the applicable tax rate in accordance with clause (3) of this regulation.

(5) The generating company or the transmission licensee, as the case maybe, shall recover the shortfall or refund the excess Annual Fixed Charge on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax Rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before the Commission:

Provided further that Annual Fixed Charge with respect to the tax rate applicable to the generating company or the transmission licensee, as the case may be, in line with the provisions of the relevant Finance Acts of the respective year during the tariff period shall be trued up in accordance with Regulation 6 of these regulations.”

23. The petitioner has submitted that MAT rate of 11.330% applicable for 2008-09 was considered in the order dated 8.2.2011 However, for truing up purpose, the computation of RoE for the tariff period 2009-14 has been done on the basis of actual MAT rate applicable during 2009-14. The petitioner has submitted the variation in MAT rate during 2009-14 as per the Finance Act of the relevant year for the purpose of grossing up of ROE, as below:—

Particulars MAT Rate (%) Grossed up RoE (Base rate/(1-t)) (%) 2009-10 16.995 18.674 2010-11 19.931 19.358 2011-12 20.008 19.377 2012-13 20.008 19.377 2013-14 20.961 19.611

24. Accordingly, the ROE as trued up is worked out by considering actual MAT rate for grossing up of ROE as shown in the table below:—

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 8.2.2011 3348.26 3377.02 3399.09 3399.09 3399.09 As claimed by the petitioner 3587.19 3745.91 3759.24 3760.21 3805.86 Allowed after trued up 3587.18 3745.91 3759.24 3760.21 3805.86

25. The return on equity allowed in the instant order is more than the ROE allowed vide order dated 8.2.2011 due to increase in the applicable MAT rate for the purpose of grossing up of base rate of return on equity.

Depreciation

26. Clause (42) of Regulation 3 of the 2009 Tariff Regulations defines useful life as follows:—

“useful life’ in relation to a unit of a generating station and transmission system from the COD shall mean the following, namely:—

(c) AC and DC sub-station 25 years

(d) Hydro generating station 35 years

(e) Transmission line 35 years”

27. Further, Clause (4) of Regulation 17 of the 2009 Tariff Regulations provides as follows:—

“17. Depreciation:

(4) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-III to these regulations for the assets of the generating station and transmission system:

Provided that, the remaining depreciable value as on 31st March of the year closing after a period of 12 years from date of commercial operation shall be spread over the balance useful life of the assets.”

28. Regulation 17 of the 2009 Tariff Regulations provides the methodology to workout the depreciation. The Commission, in its order dated 8.2.2011, has worked out the depreciation in accordance with Regulation 17 of the 2009 Tariff Regulations. There is variation in actual capital expenditure incurred during the tariff period 2009-14 with that admitted vide order dated 8.2.2011 in Petition No. 243/2010.

29. As per Regulation 17(4) of the 2009 Tariff Regulations, useful life for transmission line, sub-station and PLCC is 35 years, 25 years, and 15 years, respectively. In the present case, weighted average life of the transmission system works out to 32 years.

30. The depreciation for the tariff period 2009-14 has been worked out in accordance with Regulation 17 of the 2009 Tariff Regulations based on admitted capital expenditure and additional capitalisation as under:—

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 8.2.2011 3342.05 3369.57 3391.60 3391.60 3391.60 As claimed by petitioner 3352.25 3375.89 3388.61 3393.63 3393.88 Allowed after true up 3352.25 3375.89 3388.61 3393.63 3393.88

31. The depreciation allowed in the instant order is more than the depreciation allowed vide order dated 8.2.2011 due to increase in actual additional capitalisation vis-à-vis that of approved vide order dated 8.2.2011

Operation & Maintenance Expenses (“O&M Expenses”)

32. The petitioner has computed O&M Expenses for the transmission assets mentioned in the petition in accordance with the O&M norms specified in Regulation 19(g) of the 2009 Tariff Regulations. Accordingly, the O&M Expenses have been worked out as given below:—

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Norms as per Regulati on 400 kV, D/C twin conductor transmission line (Rs. lakh/km) 0.627 0.663 0.701 0.741 0.783 400 kV bay (Rs. lakh/bay) 52.40 55.40 58.57 61.92 65.46 220 kV bay (Rs. lakh/bay) 36.68 38.78 41.00 43.34 45.82 Actual line length (km) 400 kV, D/C twin conductor transmission line (Rs. lakh) 549.934 549.934 549.934 549.934 549.934 Actual (No. of Sub-stations) 400 kV bay (Rs. lakh) 18 18 18 18 18 220 kV bay (Rs. lakh) 9 9 9 9 9 O&M expense 400 kV, D/C twin conductor transmission line (Rs. lakh) 344.81 364.61 385.50 407.50 430.60 400 kV bay (Rs. lakh) 943.20 997.20 1054.26 1114.56 1178.28 220 kV bay (Rs. lakh) 330.12 349.02 369.00 390.06 412.38 Total 1618.13 1710.83 1808.76 1912.12 2021.26

33. The O&M Expenses claimed by the petitioner for tariff period 2009-14 are same as that approved in the tariff order dated 8.2.2011 in Petition No. 243/2010. Accordingly, the O&M Expenses claimed by the petitioner, allowed and trued up are the same, and are as follows:—

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 8.2.2011 1618.13 1710.83 1808.76 1912.12 2021.26 As claimed by petitioner 1618.13 1710.83 1808.76 1912.12 2021.26 Allowed after true up 1618.13 1710.83 1808.76 1912.12 2021.26

Interest on working capital (“IWC”)

34. Sub-clause (c) of Clause (1) of Regulation 18 of the 2009 Tariff Regulations provides the components of the working capital for the transmission system and Clause (3) of Regulation 18 of the 2009 Tariff Regulations provides for the rate of interest on working capital.

35. The petitioner has submitted that the rate of interest on working capital has been considered as 12.25% as per Clause (3) of Regulation 18 of the 2009 Tariff Regulations and the components of working capital are also considered in accordance with Sub-clause (c) of Clause (1) of Regulation 18 of the 2009 Tariff Regulations.

36. The Commission in its order dated 8.2.2011 in Petition No. 243/2010 approved rate of interest on working capital as 12.25% as applicable for 2008-09. In accordance with Clause (3) of Regulation 18 of the 2009 Tariff Regulations, rate of interest on working capital shall be on normative basis and in case of transmission assets declared under commercial operation prior to 1.4.2009, shall be equal to short-term Prime Lending Rate as applicable as on 1.4.2009 State Bank of India short-term Prime Lending Rate on 1.4.2009 was 12.25%. Therefore, interest rate of 12.25% has been considered to work-out the interest on working capital in the instant case.

37. The IWC trued up is as under:—

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Maintenance Spares 242.72 256.62 271.31 286.82 303.19 O & M expenses 134.84 142.57 150.73 159.34 168.44 Receivables 2053.11 2056.37 2031.16 2001.58 1978.31 Total 2430.68 2455.57 2453.21 2447.75 2449.94 Rate of Interest (%) 12.25 12.25 12.25 12.25 12.25 Interest 297.76 300.81 300.52 299.85 300.12

38. The IWC claimed by the petitioner, allowed and trued up are as shown in the table below:—

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Approved vide order dated 8.2.2011 292.34 292.87 293.13 292.16 291.46 As claimed by petitioner 297.76 300.81 300.52 299.85 300.12 Allowed after true up 297.76 300.81 300.52 299.85 300.12

39. The IWC has increased on account of increase in receivables due to variation in ROE on account of applicable MAT rate during the tariff period 2009-14.

ANNUAL FIXED CHARGES FOR 2009-14 TARIFF PERIOD

40. The detailed computation of the various components of the trued up annual fixed charges for the transmission asset for the tariff period 2009-14 is summarised below:—

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Gross Block Opening Gross block 63718.32 64345.50 64659.49 64840.99 64855.83 Addition during 2014-19 due to Additional Capitalization 627.18 313.99 181.50 14.84 0.00 Closing Gross block 64345.50 64659.49 64840.99 64855.83 64855.83 Average Gross block 64031.91 64502.50 64750.24 64848.41 64855.83 Depreciation Rate of Depreciation (%) 5.235% 5.234% 5.233% 5.233% 5.233% Depreciable Value 57594.47 58017.99 58240.96 58329.32 58335.99 Elapsed Life (Beginning of the year) 1 2 3 4 5 Weighted Balance Useful life of the assets (yrs) 31 30 29 28 27 Remaining Depreciable Value 54204 51275 48122 44822 41435 Depreciation 3352.25 3375.89 3388.61 3393.63 3393.88 Cumulative Depreciation 6742.91 10118.81 13507.42 16901.05 20294.93 Interest on Loan Gross Normative Loan 44602.89 45041.92 45261.71 45437.71 45448.10 Cumulative Repayment upto COD/Previous Year 3390.66 6742.91 10118.81 13507.42 16901.05 Net Loan-Opening 41212.23 38299.00 35142.90 31930.29 28547.05 Addition due to Additional Capitalisation 439.03 219.79 176.00 10.39 0.00 Repayment during the year 3352.25 3375.89 3388.61 3393.63 3393.88 Net Loan-Closing 38299.00 35142.90 31930.29 28547.05 25153.17 Average Loan 39755.62 36720.95 33536.60 30238.67 26850.11 Weighted Average Rate of Interest on Loan (%) 8.71 8.73 8.74 8.74 8.75 Interest 3463.35 3204.81 2929.85 2643.70 2348.76 Return on Equity Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Opening Equity 19115.43 19303.58 19397.78 19403.28 19407.73 Additional Capitalisation 188.15 94.20 5.50 4.45 0.00 Closing Equity 19303.58 19397.78 19403.28 19407.73 19407.73 Average Equity 19209.51 19350.68 19400.53 19405.51 19407.73 Return on Equity (Base Rate) (%) 15.50 15.50 15.50 15.50 15.50 MAT rate for respective year (%) 17.00 19.93 20.01 20.01 20.96 Rate of Return on Equity (Pre Tax)(%) 18.674 19.358 19.377 19.377 19.610 Return on Equity (Pre Tax) 3587.18 3745.91 3759.24 3760.21 3805.86 Interest on Working Capital Maintenance Spares 242.72 256.62 271.31 286.82 303.19 O & M expenses 134.84 142.57 150.73 159.34 168.44 Receivables 2053.11 2056.37 2031.16 2001.58 1978.31 Total 2430.68 2455.57 2453.21 2447.75 2449.94 Interest 297.76 300.81 300.52 299.85 300.12 Annual Transmission Charges Depreciation 3352.25 3375.89 3388.61 3393.63 3393.88 Interest on Loan 3463.35 3204.81 2929.85 2643.70 2348.76 Return on Equity 3587.18 3745.91 3759.24 3760.21 3805.86 Interest on Working Capital 297.76 300.81 300.52 299.85 300.12 O & M Expenses 1618.13 1710.83 1808.76 1912.12 2021.26 Total 12318.67 12338.24 12186.98 12009.50 11869.87

DETERMINATION OF ANNUAL TRANSMISSION CHARGES FOR 2014-19

41. The petitioner has claimed the transmission charges as under:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Depreciation 3393.88 3393.88 3393.88 3393.88 3393.88 Interest on Loan 2053.34 1757.90 1462.41 1166.85 871.15 Return on Equity 3805.86 3805.86 3805.86 3805.86 3805.86 Interest on Working Capital 315.41 312.03 308.73 305.56 302.50 O&M Expenses 1854.09 1915.89 1979.40 2045.08 2112.93 Total 11422.58 11185.56 10950.28 10717.23 10486.32

42. The details submitted by the petitioner in support of its claim for interest on working capital are given hereunder:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Maintenance Spares 278.11 287.38 296.91 306.76 316.94 O&M Expenses 154.51 159.66 164.95 170.42 176.08 Receivables 1903.76 1864.26 1825.05 1786.21 1747.72 Total 2336.38 2311.30 2286.91 2263.39 2240.74 Rate of Interest (%) 13.50 13.50 13.50 13.50 13.50 Interest 315.41 312.03 308.73 305.56 302.50

Capital Cost

43. Clause (1) and (3) of Regulation 9 of the 2014 Tariff Regulations provide as follows:—

“(1) The Capital cost as determined by the Commission after prudence check in accordance with this regulation shall form the basis of determination of tariff for existing and new projects.

(3) The Capital cost of an existing project shall include the following:

(a) the capital cost admitted by the Commission prior to 1.4.2014 duly trued up by excluding liability, if any, as on 1.4.2014;

(b) additional capitalization and de-capitalization for the respective year of tariff as determined in accordance with Regulation 14; and

(c) expenditure on account of renovation and modernisation as admitted by this Commission in accordance with Regulation 15.”

44. The petitioner has claimed capital cost of Rs. 64855.82 lakh as on 31.3.2014 including additional capitalisation during the tariff period 2009-14. Further, the petitioner has not projected any additional capital expenditure during the tariff period 2014-19.

45. The trued up capital cost of Rs. 64855.82 lakh as on 31.3.2014 has been considered as opening capital cost as on 1.4.2014 to work out the tariff for tariff period 2014-19.

Additional Capital Expenditure

46. The petitioner has not claimed any additional capital expenditure for the tariff period 2014-19, and accordingly, no additional capital expenditure has been considered for the tariff period 2014-19.

Debt:Equity Ratio

47. Clause 3 of Regulation 19 of the 2014 Tariff Regulations specifies as follows:—

“(3) In case of the generating station and the transmission system declared under commercial operation prior to 1.4.2014, debt:equity ratio allowed by the Commission for determination of tariff for the period ending 31.3.2014 shall be considered.”

48. The admitted debt:equity ratio of 78.55:21.45 for the tariff period ending 31.3.2014 has been considered as opening debt:equity ratio as on 1.4.2014 for determination of tariff for the period 2014-19. The admitted debt:equity ratio as on 1.4.2014 for the purpose of determination of tariff is as follows:—

(Rs. in lakh)

Funding Admitted as on 31.3.2014 (%) Debt 45448.10 70.08 Equity 19407.73 29.92 Total 64855.83 100.00

Interest on Loan (“IOL”)

49. Clause (5) & (6) of Regulation 26 of the 2014 Tariff Regulations are reproduced as under:—

“(5) The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual loan portfolio after providing appropriate accounting adjustment for interest capitalized:

Provided that if there is no actual loan for a particular year but normative loan is still outstanding, the last available weighted average rate of interest shall be considered:

Provided further that if the generating station or the transmission system, as the case may be, does not have actual loan, then the weighted average rate of interest of the generating company or the transmission licensee as a whole shall be considered.

(6) The interest on loan shall be calculated on the normative average loan of the year by applying the weighted average rate of interest.”

50. The weighted average rate of IOL has been considered based on the actual loan portfolio, interest of actual loan prevailing as on 1.4.2014 and average loan amount by considering repayment and additions. The details of interest rate of individual loan and weighted average rate of interest are placed at Annexure-II. The weighted average rate of interest is given in following table:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Average Loan 23456.23 20062.35 16668.48 13274.60 9880.72 Interest 2053.34 1757.89 1462.41 1166.85 871.15 Rate of Interest(%) 8.7539 8.7621 8.7735 8.7901 8.8166

51. The IOL has been worked out by considering normative loan and weighted average rate of interest in accordance with Regulation 26 of the 2014 Tariff Regulations as follows:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Gross loan opening 45448.10 45448.10 45448.10 45448.10 45448.10 Cumulative Repayment upto COD/previous year 20294.93 23688.80 27082.68 30476.56 33870.44 Net Loan-Opening 25153.17 21759.29 18365.42 14971.54 11577.66 Additions during the year 0.00 0.00 0.00 0.00 0.00 Repayment during the year 3393.88 3393.88 3393.88 3393.88 3393.88 Net Loan-Closing 21759.29 18365.42 14971.54 11577.66 8183.78 Average Loan 23456.23 20062.35 16668.48 13274.60 9880.72 Rate of Interest (%) 8.75 8.76 8.77 8.79 8.82 Interest on Loan 2053.34 1757.89 1462.41 1166.85 871.15

Return on Equity (“ROE”)

52. Clause (1) and (2) of Regulation 24 and Clause (2) of Regulation 25 of the 2014 Tariff Regulations specify as under:—

“24. Return on Equity: (1) Return on equity shall be computed inrupee terms, on the equity base determined in accordance with regulation 19.

(2) Return on equity shall be computed at the base rate of 15.50% for thermal generating stations, transmission system including communication system….

25. Tax on Return on Equity:

“..(2) Rate of return on equity shall be rounded off to three decimal places and shall be computed as per the formula given below:

Rate of pre-tax return on equity = Base rate/(1-t)

Where “t” is the effective tax rate in accordance with Clause (1) of this regulation and shall be calculated at the beginning of every financial year based on the estimated profit and tax to be paid estimated in line with the provisions of the relevant Finance Act applicable for that financial year to the company on pro-rata basis by excluding the income of non-generation or non-transmission business, as the case may be, and the corresponding tax thereon. In case of generating company or transmission licensee paying Minimum Alternate Tax (MAT), “t” shall be considered as MAT rate including surcharge and cess.”

53. The petitioner has computed ROE at the rate of 19.610% after grossing up the ROE with MAT rate for 2013-14 as per the above Regulation. The petitioner has further submitted that the grossed up ROE is subject to truing up based on the actual tax paid along with any additional tax or interest, duly adjusted for any refund of tax including the interest received from IT authorities, pertaining to the tariff period 2014-19 on actual gross income of any financial year. Any under-recovery or over-recovery of grossed up ROE after truing up shall be recovered or refunded to the beneficiaries on year to year basis.

54. The petitioner has further submitted that adjustment due to any additional tax demand including interest duly adjusted for any refund of the tax including interest received from IT authorities shall be recoverable/adjustable after completion of income tax assessment of the financial year.

55. We have considered the submissions made by the petitioner. Regulation 24 read with Regulation 25 of the 2014 Tariff Regulations provides for grossing up of return on equity with the effective tax rate for the purpose of return on equity. It further provides that in case the generating company or transmission licensee is paying Minimum Alternative Tax (MAT), the MAT rate including surcharge and cess will be considered for the grossing up of return on equity. The petitioner has submitted that MAT rate is applicable to the petitioner's company. Accordingly, MAT rate applicable during 2013-14 has been considered for the purpose of allowing return on equity, which shall be trued up with actual tax rate in accordance with Regulation 25(3) of the 2014 Tariff Regulations. Accordingly, the ROE is worked out as given below:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Opening Equity 19407.73 19407.73 19407.73 19407.73 19407.73 Addition due to additional capitalization 0.00 0.00 0.00 0.00 0.00 Closing Equity 19407.73 19407.73 19407.73 19407.73 19407.73 Average Equity 19407.73 19407.73 19407.73 19407.73 19407.73 Return on Equity (Base Rate) (%) 15.50 15.50 15.50 15.50 15.50 MAT Rate for the year (%) 20.96 20.96 20.96 20.96 20.96 Rate of Return on Equity (Pre Tax) (%) 19.61 19.61 19.61 19.61 19.61 Return on Equity (Pre Tax) 3805.86 3805.86 3805.86 3805.86 3805.86

Depreciation

56. Clause (2), (5) and (6) of Regulation 27 of the 2014 Tariff Regulations provide as follows:—

“27. Depreciation:

…(2) The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission. In case of multiple units of a generating station or multiple elements of transmission system, weighted average life for the generating station of the transmission system shall be applied. Depreciation shall be chargeable from the first year of commercial operation. In case of commercial operation of the asset for part of the year, depreciation shall be charged on pro rata basis

(5) Depreciation shall be calculated annually based on Straight Line Method and at rates specified in Appendix-II to these regulations for the assets of the generating station and transmission system:

Provided that the remaining depreciable value as on 31 March of the year closing after a period of 12 years from the effective date of commercial operation of the station shall be spread over the balance useful life of the assets.

(6) In case of the existing projects, the balance depreciable value as on 1.4.2014 shall be worked out by deducting the cumulative depreciation as admitted by the Commission upto 31.3.2014 from the gross depreciable value of the assets.”

57. The petitioner has computed depreciation considering capital expenditure of Rs. 64855.83 lakh as on 31.3.2014 We have considered the submission made by the petitioner with reference to depreciation. Depreciation is allowed as provided under Regulation 27 of the 2014 Tariff Regulations. The details of the depreciation allowed are given hereunder:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Opening Gross block 64855.83 64855.83 64855.83 64855.83 64855.83 Addition during the year due to projected additional capitalization 0.00 0.00 0.00 0.00 0.00 Closing Gross block 64855.83 64855.83 64855.83 64855.83 64855.83 Rate of Depreciation (%) 5.23 5.23 5.23 5.23 5.23 Depreciable Value 58335.99 58335.99 58335.99 58335.99 58335.99 Elapsed Life (Beginning of the year) 6 7 8 9 10 Weighted Balance Useful life of the assets 26 25 24 23 22 Remaining Depreciable Value 38041.07 34647.19 31253.31 27859.43 24465.55 Depreciation 3393.88 3393.88 3393.88 3393.88 3393.88

Operation &Maintenance Expenses (“O&M Expenses”)

58. The petitioner has computed normative O&M Expenses as per sub clause (a) of clause (3) of regulation 29 of the 2014 Tariff Regulations. Accordingly, the petitioner's entitlement to O&M Expenses has been worked out as given hereunder:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Norms as per Regulati on 400 kV, D/C twin conductor transmission line (Rs. lakh/km) 0.707 0.731 0.755 0.780 0.806 400 kV bay (Rs. lakh/bay) 60.30 62.30 64.37 66.51 68.71 220 kV bay (Rs. lakh/bay) 42.21 43.61 45.06 46.55 48.10 Actual line length (km) 400 kV, D/C twin conductor transmission line (Rs. lakh) 549.934 549.934 549.934 549.934 549.934 Actual (No. of Sub-stations) 400 kV bay (Rs. lakh) 18 18 18 18 18 220 kV bay (Rs. lakh) 9 9 9 9 9 O&M Expenses 400 kV, D/C twin conductor transmission line (Rs. lakh) 388.80 402.00 415.20 428.95 443.25 400 kV bay (Rs. lakh) 1085.40 1121.40 1158.66 1197.18 1236.78 220 kV bay (Rs. lakh) 379.89 392.49 405.54 418.95 432.90 Total 1854.09 1915.89 1979.40 2045.08 2112.93

59. The petitioner has submitted that O&M Expenses for the tariff period 2014-19 have been arrived on the basis of normalized actual O&M Expenses during the period 2008-13. The petitioner has further submitted that the wage revision of the employees of the petitioner Company is due during 2014-19 and actual impact of wage hike, which will be effective at a future date, has not been factored in fixation of the normative O&M rate specified for the tariff period 2014-19. The petitioner has prayed to be allowed to approach the Commission for suitable revision in the norms of O&M Expenses for claiming the impact of such increase.

60. The O&M Expenses have been worked out as per the norms of O&M Expenses specified in the 2014 Tariff Regulations. As regards impact of wage revision, we would like to clarify that any application filed by the petitioner in this regard will be dealt with in accordance with the appropriate provisions of the 2014 Tariff Regulations.

61. The details of O&M Expenses allowed are given hereunder:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 O&M Expenses allowed 1854.09 1915.89 1979.40 2045.08 2112.93

Interest on Working Capital (“IWC”)

62. Clause 1 (c) of Regulation 28 and Clause 5 of Regulation 3 of the 2014 Tariff Regulations specify as follows:—

“28. Interest on Working Capital

(c)(i) Receivables equivalent to two months of fixed cost;

(ii) Maintenance spares @ 15% of operation and maintenance expenses specified in regulation 29; and

(iii) Operation and maintenance expenses for one month”

“(5) ‘Bank Rate’ means the base rate of interest as specified by the State Bank of India from time to time or any replacement thereof for the time being in effect plus 350 basis points;”

63. The petitioner has submitted that it has computed IWC for the tariff period 2014-19 considering the SBI Base Rate as on 1.4.2014 plus 350 basis points. The rate of interest on working capital considered for the purpose of computation of tariff is 13.50%.

64. The interest on working capital is worked out in accordance with Regulation 28 of the 2014 Tariff Regulations. The rate of interest on working capital considered is 13.50% (SBI Base Rate of 10% plus 350 basis points). The interest on working capital as determined is shown in the table below:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Maintenance Spares 278.11 287.38 296.91 306.76 316.94 O&M Expenses 154.51 159.66 164.95 170.42 176.08 Receivables 1903.76 1864.26 1825.05 1786.20 1747.72 Total 2,336.39 2,311.30 2,286.91 2,263.39 2,240.73 Rate of Interest (%) 13.50 13.50 13.50 13.50 13.50 Interest on working Capital 315.41 312.03 308.73 305.56 302.50

Annual Transmission Charges

65. The Annual Transmission Charges allowed for the transmission asset is given hereunder:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Depreciation 3393.88 3393.88 3393.88 3393.88 3393.88 Interest on Loan 2053.34 1757.89 1462.41 1166.85 871.15 Return on Equity 3805.86 3805.86 3805.86 3805.86 3805.86 Interest on WC 315.41 312.03 308.73 305.56 302.50 O&M Expenses 1854.09 1915.89 1979.40 2045.08 2112.93 Total 11422.58 11185.54 10950.27 10717.22 10486.31

66. The detailed computation of various components of annual fixed charges for the tariff period 2014-19 is summarized below:—

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Gross Block Opening Gross block 64855.83 64855.83 64855.83 64855.83 64855.83 Additional Capitalization during 2014-19 0.00 0.00 0.00 0.00 0.00 Closing Gross block 64855.83 64855.83 64855.83 64855.83 64855.83 Average Gross block 64855.83 64855.83 64855.83 64855.83 64855.83 Depreciation Rate of Depreciation (%) 5.23 5.23 5.23 5.23 5.23 Depreciable Value 58335.99 58335.99 58335.99 58335.99 58335.99 Elapsed Life (Beginning of the year) 6 7 8 9 10 Weighted Balance Useful life of the assets 26 25 24 23 22 Remaining Depreciable Value 38041.07 34647.19 31253.31 27859.43 24465.55 Depreciation 3393.88 3393.88 3393.88 3393.88 3393.88 Cumulative Depreciation 23688.80 27082.68 30476.56 33870.44 37264.32 Interest on Loan Net Loan-Opening 25153.17 21759.29 18365.42 14971.54 11577.66 Addition due to Additional Capitalization 0.00 0.00 0.00 0.00 0.00 Repayment during the year 3393.88 3393.88 3393.88 3393.88 3393.88 Net Loan-Closing 21759.29 18365.42 14971.54 11577.66 8183.78 Average Loan 23456.23 20062.35 16668.48 13274.60 9880.72 Weighted Average Rate of Interest on Loan (%) 8.75 8.76 8.77 8.79 8.82 Interest 2053.34 1757.89 1462.41 1166.85 871.15 Return on Equity Opening Equity 19407.73 19407.73 19407.73 19407.73 19407.73 Additions 0.00 0.00 0.00 0.00 0.00 Closing Equity 19407.73 19407.73 19407.73 19407.73 19407.73 Average Equity 19407.73 19407.73 19407.73 19407.73 19407.73 Return on Equity (Base Rate)(%) 15.50 15.50 15.50 15.50 15.50 MAT rate for the respective year (%) 20.96 20.96 20.96 20.96 20.96 Rate of Return on Equity 19.61 19.61 19.61 19.61 19.61 (Pre Tax)(%) Return on Equity (Pre Tax) 3805.86 3805.86 3805.86 3805.86 3805.86 Interest on Working Capital Maintenance Spares 278.11 287.38 296.91 306.76 316.94 O&M expenses 154.51 159.66 164.95 170.42 176.08 Receivables 1903.76 1864.26 1825.05 1786.20 1747.72 Total 2,336.39 2,311.30 2,286.91 2,263.39 2,240.73 Rate of Interest 13.50% 13.50% 13.50% 13.50% 13.50% Interest 315.41 312.03 308.73 305.56 302.50 Annual Transmission Charges Depreciation 3393.88 3393.88 3393.88 3393.88 3393.88 Interest on Loan 2053.34 1757.89 1462.41 1166.85 871.15 Return on Equity 3805.86 3805.86 3805.86 3805.86 3805.86 Interest on Working Capital 315.41 312.03 308.73 305.56 302.50 O&M Expenses 1854.09 1915.89 1979.40 2045.08 2112.93 Total 11422.58 11185.54 10950.27 10717.22 10486.31

Filing Fee and Publication Expenses

67. The petitioner has sought reimbursement of fee paid by it for filing the petition and publication expenses, in terms of Regulation 52 of the 2014 Tariff Regulations. The petitioner shall be entitled for reimbursement of the filing fees and publication expenses in connection with the present petition, directly from the beneficiaries on pro-rata basis in accordance with clause (1) of regulation 52 of the 2014 Tariff Regulations.

Licence Fee and RLDC Fees and Charges

68. The petitioner has requested to allow the petitioner to bill and recover Licence fee and RLDC fees and charges, separately from the respondents. The petitioner shall be entitled for reimbursement of licence fee and RLDC fees and charges in accordance with Clause (2)(b) and (2)(a), respectively, of Regulation 52 of the 2014 Tariff Regulations.

Service Tax

69. The petitioner has sought to recover service tax on transmission charges separately from the respondents, if at any time service tax on transmission is withdrawn from negative list in future. We are of the view that the petitioner's prayer is premature.

Deferred Tax Liability

70. The petitioner has sought recovery of deferred tax liability before 1.4.2009 from the beneficiaries or long term consumers/DICs as and when materialized under Regulation 49 of the 2014 Tariff Regulations. The deferred tax liability shall be dealt as per Regulation 49 of the 2014 Tariff Regulations, as amended. Accordingly, the petitioner is entitled to recover the deferred tax liability upto 31.3.2009 whenever the same materializes, directly from the beneficiaries or long term transmission customers/DICs.

Sharing of Transmission Charges

71. The billing, collection and disbursement of the transmission charges approved shall be governed by the provisions of Central Electricity Regulatory Commission (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2010, as amended from time to time, as provided in Regulation 43 of the 2014 Tariff Regulations.

72. This order disposes of Petition No. 388.TT/2014.

Annexure-I

DETAILS OF LOAN BASED ON ACTUAL LOAN PORTFOLIO

(Rs. in lakh)

Interest Rate (%) Loan deployed as on 1.4.2009 Additions during the tariff period Particulars Total BOND XVIII 8.15 19117.00 0.00 19117.00 BOND XX 8.93 12039.00 0.00 12039.00 BOND XXI 8.73 520.00 0.00 520.00 BOND XXII 8.68 1204.00 0.00 1204.00 BOND XXIII 9.25 1617.00 0.00 1617.00 BOND XXIV 9.95 2675.00 0.00 2675.00 BOND XXVI 9.30 3953.00 0.00 3953.00 BOND XXVIII-Add Cap 2008-09 Loan 1 9.33 1124.00 0.00 1124.00 BOND XXIX-Add Cap 2009-10 9.20 0.00 52.00 52.00 BOND XXIX-Add Cap 2008-09 Loan 2 9.20 932.00 0.00 932.00 BOND XXX-Add Cap 2009-10 8.80 0.00 85.00 85.00 BOND XXXI-Add Cap 2009-10 8.90 0.00 127.00 127.00 BOND XXXVIII-Add Cap 2011-12 Loan 1 9.25 0.00 48.96 48.96 BOND XXXIII-Add Cap 2010-11 Loan 2 8.64 0.00 44.00 44.00 BOND XXXVIII-Add Cap 2011-12 Loan 1 9.25 0.00 127.04 127.04 Total Loan 43181.00 484.00 43665.00

WEIGHTED AVERAGE RATE OF INTEREST ON LOAN DURING 2009-14 TARIFF PERIOD

(Rs. in lakh)

Particulars 2009-10 2010-11 2011-12 2012-13 2013-14 Gross Opening Loan 43,181.00 43,445.00 43,489.00 43,665.00 43,665.00 Cumulative Repayments of Loans upto Previous Year 0.00 1,593.08 4,690.74 8,117.82 11,720.57 Net Loans Opening 43,181.00 41,851.92 38,798.26 35,547.18 31,944.43 Add: Drawl(s) during year 264.00 44.00 176.00 0.00 0.00 Less: Repayment(s) of Loan during the year 1,593.08 3,097.66 3,427.08 3,602.75 3,620.41 Net Closing Loan 41,851.92 38,798.26 35,547.18 31,944.43 28,324.02 Average Net Loan 42,516.46 40,325.09 37,172.72 33,745.81 30,134.23 Rate of Interest on Loan (%) 8.7116 8.7275 8.7363 8.7428 8.7477 Interest on Loan 3,703.86 3,519.36 3,247.51 2,950.32 2,636.04

Annexure-II

DETAILS OF LOAN BASED ON ACTUAL LOAN PORTFOLIO

(Rs. in lakh)

Particulars Interest Rate (%) Loan deployed as on 1.4.2014 Additions during the tariff period Total BOND XVIII 8.15 19117.00 0.00 19117.00 BOND XX 8.93 12039.00 0.00 12039.00 BOND XXI 8.73 520.00 0.00 520.00 BOND XXII 8.68 1204.00 0.00 1204.00 BOND XXIII 9.25 1617.00 0.00 1617.00 BOND XXIV 9.95 2675.00 0.00 2675.00 BOND XXVI 9.30 3953.00 0.00 3953.00 BOND XXVIII-Add Cap 2008-09 Loan 1 9.33 1124.00 0.00 1124.00 BOND XXIX-Add Cap 2009-10 9.20 52.00 0.00 52.00 BOND XXIX-Add Cap 2008-09 Loan 2 9.20 932.00 0.00 932.00 BOND XXX-Add Cap 2009-10 8.80 85.00 0.00 85.00 BOND XXXI-Add Cap 2009-10 8.90 127.00 0.00 127.00 BOND XXXVIII-Add Cap 2011-12 Loan 1 9.25 48.96 0.00 48.96 BOND XXXIII-Add Cap 2010-11 Loan 2 8.64 44.00 0.00 44.00 BOND XXXVIII-Add Cap 2011-12 Loan 1 9.25 127.04 0.00 127.04 Total Loan 43665.00 0.00 43665.00

WEIGHTED AVERAGE RATE OF INTEREST ON LOAN DURING 2014-19 TARIFF PERIOD

(Rs. in lakh)

Particulars 2014-15 2015-16 2016-17 2017-18 2018-19 Gross Opening Loan 43,665.00 43,665.00 43,665.00 43,665.00 43,665.00 Cumulative Repayments of Loans upto Previous Year 15,340.98 18,961.39 22,585.47 26,209.55 29,833.63 Net Loans Opening 28,324.02 24,703.61 21,079.53 17,455.45 13,831.37 Add: Drawl(s) during year 0.00 0.00 0.00 0.00 0.00 Less: Repayment(s) of Loan during the year 3,620.41 3,624.08 3,624.08 3,624.08 3,624.08 Net Closing Loan 24,703.61 21,079.53 17,455.45 13,831.37 10,207.29 Average Net Loan 26,513.82 22,891.57 19,267.49 15,643.41 12,019.33 Rate of Interest on Loan (%) 8.7539 8.7621 8.7735 8.7901 8.8166 Interest on Loan 2,321.00 2,005.79 1,690.43 1,375.07 1,059.70