- Bookmark
- Share
- CaseIQ
J.K. Surface Coatings Pvt. Ltd. v. Oil And Natural Gas Corporation
Judgment Summary — High Court of Judicature at Bombay (Per B.P. Colabawalla J.)
Factual and Procedural Background
The petitioner, M/s J.K. Surface Coatings Pvt. Ltd., challenged by way of a writ petition under Article 226 the office order dated 25 April 2014 issued by Respondent No.1 (ONGC) which banned the petitioner from participating in any tenders floated by ONGC for a period of three years ("the banning order"). The banning order followed a Show Cause Notice dated 4 December 2013 issued by an Inquiry Officer alleging certain "irregularities" and "discrepancies" in performance of a contract dated 8 May 2009 for maintenance painting (completed on 31 May 2011).
Procedurally, the petition was heard finally after respondents waived service; the petition sought certiorari (quashing the banning order) and mandamus directing respondents to permit the petitioner to obtain documents and participate in future tenders. The Court reserved judgment on 5 October 2016 and pronounced it on 27 October 2016.
Legal Issues Presented
- Whether the banning order dated 25 April 2014 issued by ONGC (Respondent No.1) can be quashed under Article 226 of the Constitution for procedural infirmities and/or for being arbitrary or disproportionate.
- Whether the Show Cause Notice dated 4 December 2013 was deficient because it did not indicate that blacklisting/banning was a contemplated action (i.e., whether natural justice required the SCN to state the proposed penalty).
- Whether the impugned banning order violated Articles 14 and 19(1)(g) of the Constitution of India as argued by the petitioner.
- Whether the matters raised by the petitioner were essentially contractual disputes and, if so, whether blacklisting was an appropriate remedy in the absence of allegations of fraud or habitual misconduct.
Arguments of the Parties
Petitioner's Arguments
- The SCN dated 4 December 2013 did not indicate that the petitioner was being called upon to show cause why it should not be banned/blacklisted; therefore the banning order is unsustainable.
- The SCN limited the scope to alleged "irregularities" and "discrepancies" during Feb 2009–May 2011 which were contractual in nature and could be resolved by contractual/statutory remedies rather than by blacklisting.
- No inquiry report (if any) was furnished to the petitioner and no opportunity to respond to any inquiry report was provided.
- The banning order was arbitrary, harsh, violative of Articles 14 and 19(1)(g), and smacked of malafides intended to exclude the petitioner from a subsequent tender (for which petitioner was lowest bidder) to favour another agency.
- The petitioner had replied to the SCN (letter dated 16 December 2013) explaining the alleged irregularities, and the alleged discrepancies did not warrant blacklisting; bank guarantees had been wrongly invoked.
Respondents' Arguments (Respondent Nos.1–3 / ONGC)
- The petition involves disputed questions of fact and could not be disposed of in writ jurisdiction; the petition is also barred by delay and laches since the banning order was dated 25 April 2014 but the petition was filed on 25 September 2014 without explanation for delay.
- The impugned order was passed after due procedure, including investigation following a vigilance complaint, constitution of an inquiry committee, a joint inspection/reconciliation process, and correspondence between parties from May 2012 to April 2014.
- An Inquiry Committee and a Joint Inspection Report (e.g., 13 March 2013) recorded discrepancies such as double billing in respect of invoice Nos.34 and 43 and recommended recovery; ONGC invoked bank guarantees to recover alleged overpayments.
- The petitioner was given multiple opportunities between May 2012 and April 2014 to explain discrepancies, and principles of natural justice and fair play were, according to respondents, complied with.
- The banning order was justified and not perverse or vitiated by any error apparent on the face of the record; the writ petition should be dismissed with costs.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Kulja Industries Limited v. Chief Manager, Western Telecom Project, Bharat Sanchar Nigam Limited and Others (cited) | Sets out settled principles on blacklisting/banning by authorities: that power to blacklist is inherent but when exercised by State/instrumentality it is subject to natural justice and proportionality; blacklisting should not be used for mere contractual disputes and requires objective satisfaction. | The Court relied on these principles to evaluate whether the banning order in the present case was justified; having applied the criteria, the Court concluded the ban was not justified in the facts of this case. |
| Gorkha Security Services v. Government (NCT of Delhi) (cited) | Holds that a show-cause notice must indicate the nature of the action proposed (especially blacklisting) so the noticee can understand the precise case to be met; non-mention of proposed blacklisting in SCN can render a blacklisting order bad in law. | The Court applied this principle directly: because the SCN did not indicate blacklisting as the proposed action, the banning order could be set aside on this ground alone. |
| Haryana Financial Corporation v. Kailash Chandra Ahuja (cited) | Discusses natural justice and supply of inquiry officer's report to the delinquent; non-supply is a breach but does not automatically invalidate punishment unless prejudice is shown (the doctrine of prejudice). | The Court referred to this line of authority to consider the petitioner's contention that inquiry material/report was not furnished and to note that lack of supply must be shown to have caused prejudice; the Court observed that no inquiry report was served and considered the factual impact in the present case. |
| ECIL v. B. Karunakar (cited) | Part of the jurisprudence cited concerning supply of inquiry officer's report and natural justice; indicates non-supply does not automatically void punishment absent demonstration of prejudice. | Used within the Court's discussion on natural justice to explain the relevance of prejudice where inquiry reports were not supplied; the Court examined whether non-supply prejudiced the petitioner in the facts of this matter. |
Court's Reasoning and Analysis
The Court first set out the general legal principles on blacklisting/banning as articulated by the Supreme Court: while the power to blacklist is inherent in the contracting authority, when exercised by a State or its instrumentality it is subject to scrutiny under natural justice and the doctrine of proportionality. Blacklisting is a severe disability and requires objective satisfaction and fair play by the authority before imposing it.
The Court examined the Show Cause Notice dated 4 December 2013 and noted that the SCN alleged three categories of irregularity (insufficient quantity of paint relative to area claimed; incorrect manpower deployment information; failure to maintain/furnish necessary documents). The SCN appointed an Inquiry Officer to investigate these alleged irregularities. Crucially, the Court observed that the SCN contained no indication that blacklisting/ban was a proposed action to be considered.
Applying the Supreme Court authority in Gorkha Security Services, the Court held that omission to indicate proposed blacklisting in the SCN is a material defect: the noticee must be told the nature of the action proposed so as to address it; absence of such indication can render a blacklisting order bad in law. The Court stated that this ground alone justified setting aside the banning order.
The Court then considered the substantive nature of the disputes and the procedural record. It found that the disputes were predominantly contractual, without allegations of fraud or habitual misconduct. The SCN and the banning order related to contractual discrepancies arising after the contract had been completed and after a Completion Certificate had been issued. The banning order was silent as to who gave the "impartial, prudent and careful consideration" said to underlie ONGC's conclusions, and no inquiry report from the Inquiry Officer was served on the petitioner.
Applying the principles from Kulja Industries (and taking into account proportionality), the Court concluded that blacklisting in these circumstances—where the matters were contractual, no fraud was alleged, the SCN did not indicate blacklisting as a contemplated penalty, and no inquiry report was furnished—was not justified. The Court also noted that the petitioner had already suffered more than two years of the three-year ban, which affected the proportionality analysis.
Finally, having found the banning order to be ex facie erroneous and unsustainable in law, and having considered the parties' submissions (including respondents' request for a four-week stay), the Court refused to stay its order and allowed the petition while preserving respondents' contractual remedies.
Holding and Implications
Core Holding: The Writ Petition is allowed and the impugned banning order dated 25 April 2014 is set aside.
Implications and immediate consequences:
- The petitioner is entitled to participate in any future tenders/bids that may be floated by Respondent No.1 (ONGC).
- No order as to costs was made.
- The respondents are not restrained from pursuing contractual remedies: the Court clarified that its order does not prohibit respondents from raising contractual disputes or adopting proceedings permissible in law to recover any sums; all contentions regarding maintainability and merits of such contractual proceedings are kept open.
- The respondents' request for a four-week stay to enable challenge of the order in a higher court was refused by the Court on the basis that the blacklisting order was ex facie erroneous and that the petitioner had already suffered the ban for over two years.
- The Court did not set any new broad precedent beyond applying existing Supreme Court authorities to the facts: the decision is an application of settled principles (natural justice, requirement to indicate proposed penalty in SCN in blacklisting cases, and proportionality) to the specific facts of this case.
wp.2752.2014 (Colabawalla)19.10.2016.doc dik
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION NO. 2752 OF 2014
ALONG WITH
NOTICE OF MOTION 210 OF 2016
IN
WRIT PETITION NO. 2752 OF 2014
AND
NOTICE OF MOTION (L) 117 OF 2015
IN
WRIT PETITION NO. 2752 OF 2014
M/s J.K.Surface Coatings Pvt. Ltd. ] A Pvt. Ltd. Co. incorporated under the ] Companies Act, 1956, having its registered ] office at Neelsiddhi Enclave Commercial ] Complex Plot No.48/9, M.G.Complex, ] Sector 14, Vashi Navi Mumbai - 400 703 ] through its authorized Signatory Sajid ] Ahmed Vice President ( P & A) ]...Petitioner Versus
1 Oil and Natural Gas Corporation, A ] Corporation registered under the ] Companies Act, 1956 through its ] General Manager (MM) M.H.Asset, ] having Office at 501 Vasundhara ] Bhavan, ONGC, Mumbai 400 051 ]
2 The General Manager (Civil) ] ONGC Ltd, having its office at Room No. ] 404, 11 High, Bandra Sion Link Road, ] Sion (West), Mumbai 400 017. ]
3 Executive Director, MH Asset, 801 ] Vasundhara Bhavan, ONGC Mumbai ]
400 051 ]
1
4 Shri Kalraj Mishra, Hon'ble Union ] Cabinet Minister, Minister for Micro, ] Small and Medium Enterprises, Room ] No.168, Udyog Bhawan, Rafi Marg, New ] Delhi 11001 ]
5 M/s Global Corrosion Control Office No. ] No.301, Urmila Complex, 32 Station ] Avenue Road, Chembur East, Mumbai ] 400 071 ]…Respondents
.....
Mr. Raju Z Moray a/w Mr. S.R.Nargolkar i/b Mr Aumkar Vijaykumar Joshi for the Petitioner.
Mr Kevic Setalvad, Sr. Counsel a/w Ms Daisy Dubhash, Mr J.P.Kapadia, Mr. O. Mohandas, Mr Amrit Khare i/b M/s Little & Co. for Respondent Nos.1 to 3.
Mr. Rajiv Singh a/w Ms Astha Tamhankar i/b M/s Chitnis & Co. for Respondent No.5.
…..
CORAM : S. C. DHARMADHIKARI &
B.P.COLABAWALLA, JJ.
RESERVED ON : 5th October, 2016
PRONOUNCED ON : 27th October, 2016.
JUDGMENT: [ Per B. P. Colabawalla J ]
1. Rule. Respondents waive service. By consent of parties, Rule made returnable forthwith and heard finally.
2
2. By this Writ Petition under Article 226 of the Constitution of India, the Petitioner seeks a Writ of Certiorari or any other appropriate writ, order or direction, quashing and setting aside the office order dated 25thApril, 2014 (for short "the impugned order"
or "the banning order") issued by the 1stRespondent Corporation (Exh. "C" to the Petition). A Writ of Mandamus is also sought directing the Respondents to permit the Petitioner Company to obtain the documents and participate in future tenders floated by Respondent No.1.
3. The order dated 25thApril, 2014 and which is impugned herein, is nothing but a banning order passed by the 1stRespondent against the Petitioner. This banning order has been passed pursuant to a Show Cause Notice ("SCN") dated 4thDecember, 2013 issued to the Petitioner. The grounds on which the Petitioner is sought to be banned are more particularly set out in the said banning order. In a nutshell, the said order is impugned by the Petitioner on the ground
(i) that it is violative of Articles 14 & 19(1)(g) of the Constitution of India; (ii) that the SCN dated 4thDecember, 2013 issued to the Petitioner did not even indicate that the same was issued with a view to consider banning the Petitioner from future tenders for a particular period; (iii) that this SCN limited the scope of inquiry to
3
the alleged "irregularities" and "discrepancies" which had been committed by the Petitioner during the period of works between February, 2009 and May, 2011 and which were in the realm of contractual disputes which could be resolved by taking recourse to different contractual and statutory provisions; (iv) that in these circumstances there was absolutely no justification in passing the banning order against the Petitioner and in any event was extremely harsh; (iv) no inquiry report, if any, had been furnished to the Petitioner and no opportunity of responding and/or challenging the same had been afforded to it before the banning order was passed; and (v) the entire action of the 1stRespondent smacks of malafides as the Petitioner has been blacklisted / banned only to ensure that a particular bidder is favoured and the Petitioner is ousted from the bidding process.
4. Brief facts give rise to the present controversy are as follows:-
(a) The Petitioner specializes in corrosion resistant coating application in India and is the only Indian Company to offer vessel based blasting and painting services for off- shore industries. The Petitioner also offers under-water
4
painting. It is the case of the Petitioner that it has carried out business of painting works with several leading companies including a company in Saudi Arabia and has been awarded good quality and safety certificate in respect of their work. The Petitioner in the past has been awarded contracts by the 1stRespondent Corporation (ONGC) for off-shore maintenance painting as well as for painting of new off-shore platforms etc. The first Respondent is ONGC and is a "State" within the meaning of Article 12 of the Constitution of India. Respondent Nos.2 and 3, are the officers/employees of ONGC and who have played a role in issuance of the impugned order dated 25thApril, 2014, by virtue of which the Petitioner Company has been banned from participating in any tender floated by Respondent No.1 for a period of three years.
(b) In the year 2008, Respondent No.1 invited bids for maintenance painting of its platforms of Mumbai off- shore (Mumbai High, Neelam, Heera, Bassein and Satellite) for which the Petitioner had put in its bid. The bid of the Petitioner was accepted by Respondent No.1
5
and pursuant to a Notification of Award dated 2nd February, 2009, a contract dated 8thMay, 2009 was executed between the Petitioner and Respondent No.1. The said contract set out scope of work including the total area which was proposed to be painted, as well as different paint coating systems that were to be employed in respect thereof. It is not in dispute that the said contract was for a period of three years and was completed on 31stMay, 2011.
(c) It is the case of the Petitioner that it successfully completed the work under this contract and under clause
18.1 thereof, the contract was successfully terminated on expiry of the contract period. There was no delay in performance of the said contract and the same was completed in time. In fact, a Completion Certificate was also issued by the 1stRespondent on 19thSeptember, 2011. Thereafter, final payments towards performance of the said contract were also received by the Petitioner on 18thOctober, 2011.
(d) It is the case of the Petitioner that after completion of the
6
contract, a survey was carried out in respect thereof and the work completed by the Petitioner was found to be satisfactory. After that a second survey was carried out in terms of the contract and a Joint Survey Report was signed on 6thOctober, 2012 in respect of one of the facilities (Neelam) and on 7thOctober, 2012 in respect of other facility (Heera). Since, there was no dispute about the work completed by the Petitioner, there was no deduction made in the R.A. bill submitted by the Petitioner.
(e) Thereafter, a fresh tender No. Y-15 MC 11001 for maintenance painting for another off-shore platform was issued by Respondent No.1. The Petitioner even participated in this tender. The technical bids for this fresh tender were opened on 11thOctober, 2012 and the price bids were opened on 29thMay, 2013. Out of five bidders that participated in the said bidding process, three bidders qualified in the technical bid including the Petitioner. Accordingly, the price bid of all these bidders were opened and the Petitioner was the lowest bidder (L-
1) and Saraf Hospitality Services Pvt. Ltd. (another
7
bidder) was the second lowest (L-2) and its bid was 63% higher than that of the Petitioner.
(f) In the interregnum, the Petitioner was served with the letter dated 16thMay, 2012, alleging "discrepancies" and
"inconsistencies" in the area painted and the quality of paint used in respect of the earlier contract, that was duly completed on 31stMay, 2011. The said letter claimed a refund of an amount of approx Rs.57 Lacs on account of invoice Nos.34 and 43. Despite the fact that both these invoices were earlier certified by Respondent No.1 as well as a Third Party Inspection Agency ("TPI"), the Petitioner offered its co-operation and requested for resolving of the issue and submitted a clarification/ explanation in the prescribed format on 9thAugust, 2012.
(g) It is the case of the Petitioner that thereafter a Committee was constituted to inquire into whether there was any excess payment in respect of said two invoices (Nos.34 and 43) and whether any claim was maintainable against the Petitioner Company. This Committee, (which comprised of the representatives of Respondent No.1, the
8
Petitioner as well as the TPI), after reconciliation of the said invoices, gave a report dated 13thMarch, 2013 which was in favour of the Petitioner. This report inter alia concluded that the said invoice Nos.34 and 43 were different and some work under these invoices had been carried out by the Petitioner simultaneously. The report, therefore, concluded that the Petitioner was eligible for payment in respect of the work done for both these invoices. It is the Petitioner's case that despite this, the Respondents, unilaterally and without any justification invoked two Bank Guarantees amounting to Rs.29.86 Lacs and Rs.25.56 Lacs (aggregating to Rs.55.42 Lacs) and appropriated the said amount towards their alleged claims. This invocation was done on 30thSeptember, 2013. In view of this wrongful invocation, the Petitioner from time to time issued letters seeking refund of the said amounts, but without any success.
(h) However, it did not stop here. It is the case of the Petitioner that thereafter a SCN was issued by the Investigation Officer (Respondent No.2) dated 4th December, 2013. This SCN called upon the Petitioner to
9
submit an explanation / clarification no later than 11th December, 2013. This SCN called upon the Petitioner to explain the alleged "irregularities" and "discrepencies"
that were committed by the Petitioner in respect of the contract dated 8thMay, 2009. The SCN alleged basically three irregularities against the Petitioner. The first alleged irregularity was that the required quantity of paint, corresponding to the area of painting claimed for payment, was not supplied by the Petitioner. The second was that the Petitioner Company had submitted documents containing incorrect information with respect to the required manpower deployment. The third alleged irreularity was that the Petitioner had failed to maintain and furnish to the 1stRespondent, the necessary documents / record books / registers pertaining to quality of work and measurement, for payment.
(i) The Petitioner replied to the said SCN and gave its explanations/ clarifications by its letter dated 16th December, 2013. To put it in a nutshell, it was pointed out that the contract was in respect of painting a particular area and hence the total quantity of paint applied was
10
immaterial. It was stated that the total quantity of paint mentioned in the invoices was solely indicative and the total quantity against each group could vary. However, payment was made by the 1stRespondent for the actual quantity of job done and not related to the quantity of paint supplied. This is, according to the Petitioner, was in accordance with what was stipulated in the contract. It was further stated that the contract was for a lump-sum based on the actual application of paint and the quality was verified by the DFT check. In respect of the discrepancies regarding Manpower Deployment, it was stated that the manpower was shifted and painting was done as per the directives of the 1stRespondent and as per their specifications. The 1stRespondent as well as the TPI representatives were also well aware about utilization of the manpower at different locations resulting into observations as regards reporting of manpower test due to clubbing of areas in respect of two platforms (Heera and Neelam) and shifting manpower from one location to the other as per the instructions of the 1stRespondent. It was also pointed out that Respondent No.1 followed the practice of engaging the TPI for inspection of works and
11
that the representatives of the TPI were in fact deputed at platforms for complete supervision of painting jobs who had thereafter certified the same. Based on this certification, cross-checking and monitoring the activities were also supervised by construction manager/OIM nominated by Respondent No.1, and who had certified the measurement accordingly. Thus the reports were verified by TPI and certified by the 1stRespondent before releasing payment. For all the foregoing reasons, the alleged irregularities regarding Manpower Deployment, as claimed in the SCN, according to the Petitioner, was explained appropriately. With regard to the third irregularity, namely, that the Petitioner had failed to maintain and furnish to the 1stRespondent the necessary documents / record books / registers pertaining to quantity of work etc., it was pointed out that in terms of the contract there was no contractual obligation to maintain records indefinitely after successful completion of the contract. Despite this, the appropriate record in terms of the actual measurement of area painted, manpower deployment, daily progress reports and all other relevant certificates and inspection reports were
12
submitted to the 1stRespondent along with the invoices. The Petitioner also offered to submit the work completion certificate, all details of measurement sheets and inspection reports etc.
(j) After this reply was sent by the Petitioner, the 1st Respondent issued the banning order dated 25thApril, 2014 inter alia banning the Petitioner from paticipating in any futute tenders floated by Respondent No.1 (ONGC) for a period of 3 years from the date of the order. The relevant part of the banning order reads thus:
"AND WHEREAS, on inquiry and examination of the case including the reply of the contractor dated 16.12.2013, and having given an impartial, prudent and careful consideration to the facts, ONGC has come to the following conclusion that:
(i) Contractor has failed to provide satisfactory and logical explanation to the issues of incorrect DPR, high productivity of manpower, required quantity of paint against surface area claimed for payment, deficiency in records documents, non availability of required records/ documents for scrutiny.
(ii) Contractor has failed to support their stand by furnishing relevant documents w.r.t. high productivity, mismatch of manpower
deployment, quantity of paint and quality of work etc.
(iii) Contractor tried to bank their clarification and arguments more on those documents, which are
13
not available. At the same time, no explanations have been offered for the issues raised in the document, which are available.
(iv) Contractor has manipulated manpower deployment's details and submitted improper and erroneous documents alongwith their invoices for purpose of inflated measurement/ payment of painting work.
(v) Contractor has compromised the quality of work by not using required quantity of paint for the painting area billed for payment.
(vi) Contractor has failed to maintain contractually required documents and records pertaining to the work. There has been an attempt on the part of Contractor to circumvent the documentation process, required under the contract.
(vii) Contractor has, by and large, taken a plea that ONGC / TPI had checked and scrutinised all the required documents at the time of verification certification of payment and hence, everything was in order. Contractor cannot shed their contractual obligation like this and justify their misdeeds.
(viii) The lapses as brought out above on the part of Contractor are not only gross violation of contractual obligations in terms of
specifications and quality of work but also put a question mark on their intention, in the light of spirit of the contract.
Hence, ONGC has decided to ban all business dealings with the Contractor, i.e., M/s J. K. Surface Coatings Pvt. Ltd., Navi Mumbai, India alongwith its allied concern(s), Partner(s) or Associate(s) or Director(s) or Proprietor involved in any capacity, for participation in future tenders of ONGC, whatsoever, for a period of 3 (three) years from the date of issue of this letter for gross violation of contractual obligations in terms of specifications and quality of work but also put a question mark on their intentions, in the light of spirit
14
of the contract no. MR/MM/MH/SCON/ PAINT- PLAT/88/OT/07-08/ Y 15 KC08002/ 90300003047. Neither any tender enquiry shall be issued nor offer(s) of the Contractor or its allied concern(s), Partner(s) or Associate(s) or Director(s) or Proprietor as aforesaid shall be considered in any of the ongoing tenders during the period the banning order is in force. (Dr.R.V.Marathe)
Executive Director - MH Asset."
(k) It is in these circumstances that the Petitioner is before us challenging the validity and legality of the banning order dated 25thApril, 2014.
5. In this factual background Mr Moray, learned counsel appearing on behalf of the Petitioner, submitted that the issuance of SCN as well as banning order, was calculated to eliminating the Petitioner from the bidding process in order to favour a particular agency of choice. Mr. Moray submitted this entire exercise of issuing the SCN and that had culminated in the banning order, was done to ensure that another tender bearing No.Y 16 MC 12003 would not be awarded to the Petitioner despite the fact that it is price bid was the lowest and could not have been awarded to anyone else but the Petitioner, without proper justification. Therefore, to oust the Petitioner from any bidding process as well as to ensure that this subsequent tender is not awarded to the Petitioner, but to a tenderer
15
of their choice, that this entire exercise of issuing the SCN and which culminated in the banning order, has been undertaken by the 1st Respondent and its representatives. In this regard, Mr Moray brought to our attention the averments at paragraphs 11 to 13 of the Petition.
6. Mr. Moray additionally submitted that the entire tenor of the SCN would indicate that the same was based on some alleged
"irregularities" and which at best, could have resulted in a money claim against the Petitioner company. In fact in furtherance thereof, the 1stRespondent had also unilaterally invoked the bank guarantees and appropriated the amounts towards their alleged claim. It was, therefore, not at all necessary to issue the banning order and particularly when the alleged irregularities were was satisfactorily explained.
7. Apart from this, Mr Moray submitted that the SCN did not even indicate, let alone mention, that the same was issued with a view to consider whether to ban/blacklist the Petitioner company. In other words, Mr Moray submitted that the Petitioner was not called upon to show cause as to why they should not be blacklisted and/or banned from dealing with the 1stRespondent. He submitted that on
16
this count alone the banning order could not be sustained and ought to be set aside.
8. Mr Moray further submitted that the Inquiry Officer appointed to conduct the proceedings in the investigation, had issued the SCN limiting the scope of the inquiry only to alleged
"irregularities" which had been committed by the Petitioner during the period February, 2009 to May, 2011. He submitted that even though the inquiry was conducted by the General Manager, the banning order has been issued by the Executive Director. Further, no inquiry report, if any, submitted by the General Manager, has been furnished to the Petitioner Company and no opportunity of responding/challenging the same has been afforded to them. He submitted that even the banning order records that "impartial, prudent and careful consideration of the facts" had led the 1st Respondent to come to the conclusions which have been enumerated in the banning order (and reproduced earlier). As to which Officer had given this so called "impartial, prudent and careful consideration" is not mentioned in the banning order and the same is totally silent on this aspect. What is important to note, according to Mr Moray, was that there were no allegations of fraud or improper business practice even alleged against the Petitioner company to lead
17
to such an drastic step of banning the Petitioner Company from dealing with the 1stRespondent for the period of three years. He submitted that it now becomes clear from the affidavit in reply filed on behalf of Respondent Nos.1 to 3 that the action against the Petitioner was initiated on the basis of some complaint received from Respondent No.4 (who was an Ex-Rajyasabha Member at the relevant time) and it was as a result of this interference that the decision to award a fresh tender was to be on hold, and on which the Petitioner emerged as the lowest bidder. Mr Moray submitted that distancing himself from the present controversy, Respondent No.4 has now addressed a letter dated 19thFebruary, 2015 to the 1st Respondent stating therein that he has never complained about the Petitioner or asking that it be banned. He, therefore, stated that no cognizance of such complaint / letter ought to be taken.
9. Looking to all these facts, Mr Moray submitted that the banning order was one that smacks of malafides, was wholly unreasonable, arbitrary and violative of the Petitioner's fundamental rights enshrined under Articles 14 and 19(1)(g) of the Constitution of India. He submitted that the facts of this case would clearly indicate that the banning order is calculated to oust the Petitioner company from any future tender process and to ensure that a
18
particular bidder is favoured. For all the aforesaid reasons, he submitted that the banning order dated 25thApril, 2014, is wholly unsustainable in law and ought to be set aside by us in our equitable, extraordinary and discretionary jurisdiction under Article 226 of the Constitution of India.
10. On the other hand, Mr Setalvad, learned Senior Counsel appearing on behalf of the 1stRespondent, submitted that the present Writ Petition involves disputed questions of fact which ought not to be gone into by this Court in its writ jurisdiction. Further, Mr Setalvad submitted that the order impugned in the present Writ Petition was passed on 25thApril, 2014. Thereafter a fresh tender was issued on 1stAugust, 2014 and was at an advance stage. The challenge to the order dated 25thApril, 2014 was filed only on 25th September, 2014 and no explanation for this delay has been given in the Petition. He therefore submitted that the Petition suffers from delay and laches and is liable to be dismissed in limine on this ground alone.
11. Mr Setalvad submitted that Respondent No.1's offshore operations pertain to oil and gas production and are carried out inter alia in the Arabian Sea off the coast of the city of Mumbai. The
19
offshore platforms require protection from corrosion in the marine environment, and therefore, maintenance painting to prevent corrosion, is one of the important and essential non-core activities carried out on offshore platforms to prevent marine corrosion. For this purpose, maintenance painting of offshore platforms is outsourced by Respondent No.1 to painting contractors. Since this activity is a non-core activity, Respondent No.1 does not have the manpower resources to continuously check the quality and quantity of the painting work being carried out. For this purpose, therefore, Respondent No.1 engages an independent TPI for verifying the quality and quantity of painting work carried out and for the purposes of certifying documents for the work done by the successful contractor/s. He submitted that one such contract that was entered into for carrying out maintenance painting was dated 8thMay, 2009 executed between the Petitioner and Respondent No.1. This contract was valid till approximately 15thMay, 2011. International Certification Services Pvt. Ltd. was engaged by Respondent No.1 as the TPI. This contract was completed by the Petitioner on or about 25thMay, 2011. Mr Setalvad submitted that after completion of the work under the said contract dated 8thMay, 2009, Respondent No.1 received a vigilance complaint with regard to the work carried out by the Petitioner and payments made in respect thereof. The Vigilance
20
Section of Respondent No.1, by an inter office memo dated 2ndApril, 2012, called upon the Executive Director - Asset Manager, N & H Asset to provide various office records pertaining to the paintaining work carried out at Heera platform. Thereafter, by office order dated 24thApril, 2012, it was communicated that certain discrepancies had occurred in the execution of said contract with the Petitioner. Therefore, an Inquiry Committee was constituted by the Competent Authority to re-examine the documents, payment of invoices and all other relevant records in respect of the work carried out on Heera Platform under the contract dated 8thMay, 2009. This Inquiry Committee, by its report dated 8thMay, 2012, observed that in respect of the work carried out by the Petitioner, the area painted during 1stMarch, 2011 to 18thApril, 2011 was billed twice vide bill Nos.34 and 43 which was needed to be recovered from the Petitioner in the first instance. Thereafter, the said Committee also recommended steps for ascertaining the measurement discrepancies, duplication of measurement, on the basis of the additional documents / information set out in the said Inquiry Report. This Inquiry Report was thereafter considered by the 1stRespondent and it was inter alia decided to call upon the Petitioner to refund the excess amount paid under the said contract dated 8thMay, 2009. It is, in these circumstances, that the Petitioner was called upon to refund a sum of
21
approximately Rs.57.41 Lacs, which according to the 1stRespondent, was overpaid and that is how Respondent No.1 has invoked the two Bank Guarantees and recovered the said amount.
12. Mr Setalvad has referred to voluminous correspondence that has been annexed to the affidavit-in-reply to justify passing of the impugned order dated 25thApril, 2014. He submitted that as there were discrepancies, a meeting was held between the representatives of the Petitioner, the TPI and Respondent No.1, and it was decided that a team comprising of these people would visit the Heera Platform inter alia for re-measurement of areas covering invoice Nos.34 and 43. This team visited the spot and submitted its Joint Inspection Report dated 13thMarch, 2013. When this inspection was carried out, several discrepancies were noticed as more particularly set out in paragraph 33 of the affidavit in reply. He thereafter took us through the affidavit-in-reply filed by the 1st Respondent to show the alleged glaring laches on the part of the Petitioner in carry out its contractual obligations in relation to the contract dated 8thMay, 2009.
13. Looking to all these facts, Mr Setalvad submitted that the Petitioner was given enough time and several opportunities between
22
May 2012 till April 2014 to represent its case and explain the discrepancies, but the Petitioner failed to do so. This being the position, and the principles of natural justice and fair play being duly complied with, Respondent No.1 after following due procedure has issued the order dated 25thApril, 2014 banning further business dealings with the Petitioner for the period of three years. He, therefore, submitted that the banning order passed against the Petitioner was fully justified and in any event could not be termed as perverse or suffering from any error apparent on the face of the record requiring our interference under Article 226 of the Constitution of India. Consequently, he submitted that the Writ Petition is devoid of any merit and ought to be dismissed with costs.
14. We have heard the learned counsel at length and perused the papers and proceedings in the Writ Petition along with the annexures thereto as well as affidavit-in-reply filed on behalf of all the Respondents. Before we deal with the rival contentions, we would like to set out some settled principles that have been laid down by the Supreme Court on blacklisting and/or banning a party from dealing and/or participating in contracts/tenders floated by the Government and or its undertakings. The power to blacklist a contractor, whether the contract be for supply of material or
23
equipment or for the execution of any other work whatsoever, is inherent in the party allotting the contract. There is, therefore, no need for any such power being specifically conferred by the statute or reserved by the party awarding the contract. This is because blacklisting/banning simply signifies a business decision by which the party affected by the breach decides not to enter into any contractual relationship with the party committing the breach. In the normal course, between two private parties, the right to take any such decision is absolute and untrammelled by any constraints whatsoever. The freedom to contract or not to contract is unqualified in the case of private parties. However, when such a decision is taken by the State or any of its instrumentalities, the same would be open to scrutiny not only on the touchstone of the principles of natural justice but also on the doctrine of proportionality. In other words, the Court would have the power to examine whether the punishment meeted out is commensurate with the crime. Therefore, a fair hearing to the party becomes an essential pre-condition for a proper exercise of the power and to uphold the blacklisting order. Blacklisting has the effect of preventing a person from the privilege of entering into any contract or relationship with the Government for the purposes of gain. The fact that a disability is created by the order of blacklisting indicates that the relevant authority is to have an
24
objective satisfaction before such an order is passed. Hence, objective satisfaction and fair-play on the part of the authority issuing the blacklisting order is of paramount importance. To put it in a nutshell, merely due to some contractual disputes, a banning order passed by the concerned authority would be too harsh. Only on the basis of some contractual violations which have an equally effacious remedy available for redressal of those violations, cannot be the only ground for passing the banning order. Considering that a blacklisting/banning order virtually leads to a civil death of the person/party blacklisted, there has to be definitely something more than just contractual disputes, such as frequency of incidents and/or duration of wrong doing; whether there is a pattern or prior history of wrong doing; whether the contractor has accepted the responsibility for the wrong doing and recognised the seriousness of the misconduct; etc. Suffice it to state that blacklisting/banning is recognized and often used as an effective method for disciplining deviant contractors who may have committed acts of fraud, misrepresentations, falsification of records and other breaches of regulations under which such contracts are awarded. What is important is that blacklisting is never permanent and the period of blacklisting would invariably depend upon the nature of the offence committed by the Contractor. These principles are very well settled
25
and have been succinctly set out by the Supreme Court in the case of
Kulja Industries Limited Vs. Chief Manager, Western Telecom Project Bharat Sanchar Nigam Limited and Others.1
15. Having set out the general principles, we shall now turn our attention to the facts at hand. The first thing that we noticed in the facts of the present case is the contents of the Show Cause Notice (SCN) dated 4thDecember, 2013. This SCN states that some irregularities and discrepancies have been reported during the execution of the contract between the period February, 2009 to May, 2011. To inquire into these alleged irregularities and discrepancies, the signatory of the said SCN (A. K. Srivastava) has been appointed as the Inquiry Officer to conduct an investigation regarding the irregularities / discrepancies set out in the said SCN. The alleged irregularities mentioned in the said SCN were as follows:
(i) The Petitioner had not supplied the required quantity of paint corresponding to the area of painting claimed for payment in their invoices;
(ii) The Petitioner had submitted documents containing incorrect and unrealistic information with respect to the
1 (201 4) 1 4 SCC 731
26
required manpower deployment; and
(iii) The Petitioner had failed to maintain and furnish necessary documents/ records/ registers pertaining to the quality of work and measurement, for payment.
16. In this regard, the Petitioner was advised to furnish its clarification / explanation, if any. There is not a whisper in the said SCN that any action is going to be taken against the Petitioner, let- alone the fact that the Petitioner was being considered for being blacklisted from dealing with the 1stRespondent Corporation. As mentioned earlier, this SCN was replied to by the Petitioner by its letter dated 16thDecember, 2013 and sought to explain all the above alleged irregularities / discrepancies. It is in this light that, we are surprised that the impugned order dated 25thApril, 2014, bans / blacklists the Petitioner from doing any business with the 1st Respondent Corporation for a period of three years from the date of the blacklisting order. We find considerable force in the argument of Mr Moray that the SCN did not even indicate, let-alone mention, that the same was issued with a view to consider whether to ban / blacklist the Petitioner Company. In other words, the Petitioner was not even called upon to show cause as to why they should not be
27
blacklisted and/or banned from dealing with the 1stRespondent.
17. In this regard, it would be apposite to refer to a decision of the Supreme Court in the case of Gorkha Security Services Vs Govt. (NCT of Delhi).2 Paragraphs 21, 32 and 33 of the aforesaid decision are very instructive and clearly lay down that mentioning or even indicating the proposed action of blacklisting in the SCN is imperative so as to make the noticee understand the proposed case set up against him which he has to meet. In the absence of this, the blacklisting/banning order would be bad in law. The relevant portion of this Supreme Court decision reads thus:-
21. The central issue, however, pertains to the requirement of stating the action which is proposed to be taken. The fundamental purpose behind the serving of show-cause notice is to make the noticee understand the precise case set up against him which he has to meet. This would require the statement of imputations detailing out the alleged breaches and defaults he has committed, so that he gets an opportunity to rebut the same. Another requirement, according to us, is the nature of action which is proposed to be taken for such a breach. That should also be stated so that the noticee is able to point out that proposed action is not warranted in the given case, even if the defaults/breaches complained of are not satisfactorily explained. When it comes to blacklisting, this requirement becomes all the more imperative, having regard to the fact that it is harshest possible action.
******
32. It was sought to be argued by Mr Maninder Singh, learned Additional Solicitor General appearing for the respondent, that even if it is accepted that the show-cause notice should have contained the proposed action of blacklisting, no prejudice was caused to the
2 (2 014) 9 SCC 105.
28
appellant inasmuch as all necessary details mentioning defaults/prejudices committed by the appellant were given in the show-cause notice and the appellant had even given its reply thereto. According to him, even if the action of blacklisting was not proposed in the show-cause notice, the reply of the appellant would have remained the same. On this premise, the learned Additional Solicitor General has argued that there is no prejudice caused to the appellant by non-mentioning of the proposed action of blacklisting. He argued that unless the appellant was able to show that non- mentioning of blacklisting as the proposed penalty has caused prejudice and has resulted in miscarriage of justice, the impugned action cannot be nullified. For this proposition he referred to the judgment of this Court in Haryana Financial Corpn. v. Kailash Chandra Ahuja [(2008) 9 SCC 31 : (2008) 2 SCC (L&S) 789] :
(SCC pp. 38, 40-41 & 44, paras 21, 31, 36 & 44)
"21. From the ratio laid down in B. Karunakar [ECIL v. B. Karunakar, (1993) 4 SCC 727 : 1993 SCC (L&S) 1184 : (1993) 25 ATC 704] it is explicitly clear that the doctrine of natural justice requires supply of a copy of the inquiry officer's report to the delinquent if such inquiry officer is other than the disciplinary authority. It is also clear that non-supply of report of the inquiry officer is in the breach of natural justice. But it is equally clear that failure to supply a report of the inquiry officer to the delinquent employee would not ipso facto result in the proceedings being declared null and void and the order of punishment non est and ineffective. It is for the delinquent employee to plead and prove that non-supply of such report had caused prejudice and resulted in miscarriage of justice. If he is unable to satisfy the court on that point, the order of punishment cannot automatically be set aside. ***
31. At the same time, however, effect of violation of the rule of audi alteram partem has to be considered. Even if hearing is not afforded to the person who is sought to be affected or penalised, can it not be argued that 'notice would have served no purpose' or 'hearing could not have made difference' or 'the person could not have offered any defence whatsoever'. In this connection, it is interesting to note that under the English law, it was held few years before that non-compliance with principles of natural justice would make the order null and void and no further inquiry was necessary. ***
36. The recent trend, however, is of 'prejudice'. Even in those cases where procedural requirements have not been complied with, the action has not been held ipso facto illegal, unlawful or void unless it is shown that non-observance had prejudicially affected the applicant.
***
44. From the aforesaid decisions, it is clear that though supply of report of the inquiry officer is part and parcel of natural justice and must be furnished to the delinquent employee, failure to do so would not automatically result in quashing or setting aside of the
29
order or the order being declared null and void. For that, the delinquent employee has to show 'prejudice'. Unless he is able to show that non-supply of report of the inquiry officer has resulted in prejudice or miscarriage of justice, an order of punishment cannot be held to be vitiated. And whether prejudice had been caused to the delinquent employee depends upon the facts and circumstances of each case and no rule of universal application can be laid down."
(emphasis in original)
33. When we apply the ratio of the aforesaid judgment to the facts of the present case, it becomes difficult to accept the argument of the learned Additional Solicitor General. In the first instance, we may point out that no such case was set up by the respondents that by omitting to state the proposed action of blacklisting the appellant in the show-cause notice, has not caused any prejudice to the appellant. Moreover, had the action of blacklisting being specifically proposed in the show-cause notice, the appellant could have mentioned as to why such extreme penalty is not justified. It could have come out with extenuating circumstances defending such an action even if the defaults were there and the Department was not satisfied with the explanation qua the defaults. It could have even pleaded with the Department not to blacklist the appellant or do it for a lesser period in case the Department still wanted to blacklist the appellant. Therefore, it is not at all acceptable that non-mentioning of proposed blacklisting in the show-cause notice has not caused any prejudice to the appellant. This apart, the extreme nature of such a harsh penalty like blacklisting with severe consequences, would itself amount to causing prejudice to the appellant."
18. In view of this authoritative pronouncement of the Supreme Court in the case of Gorkha Security Services2, we would be justified in setting aside the impugned banning order dated 25th April, 2014 on this ground alone.
19. Even otherwise, on carefully going through the facts of
2 (2 014) 9 SCC 105.
30
the present case and more particularly the SCN and the banning order passed pursuant thereto, what we find is that the disputes in the present case are predominantly of a contractual nature. The SCN does not even allege that there is any fraud or misrepresentation done by the Petitioner or that he is a habitual offender. Furthermore, this SCN has been issued almost 2 đ years after completion of the contract and even though a completion certificate was issued to the Petitioner by Respondent No.1. Even the operative part of the banning order (and which is reproduced by us earlier), also clearly indicates that the disputes between the parties was of a contractual nature and there were no serious allegations against the Petitioner. The only allegation made against the Petitioner was that the Petitioner had manipulated manpower deployment details and submitted improper and erroneous documents for the purpose of inflating payment of the painting work. On what basis this finding has been arrived at is completely silent in the banning order. Further, though the banning order states that the 1stRespondent
"having given an impartial and prudent consideration to the facts", is coming to the conclusions that it did, is completely silent as to who was the Officer who had given this impartial, prudent and careful consideration. It is also an admitted fact that no inquiry report was ever served upon the Petitioner pursuant to the investigation carried
31
out by the Inquiry Officer (A. K. Srivastava). What can be gathered from the facts is that there appears to be a dispute with reference to two invoices, namely, invoice Nos. 34 and 43. It was the case of the 1stRespondent that double payment / over payment had been made with reference to these invoices and these monies were to be recovered from the Petitioner. This was in fact done by the 1st Respondent by invoking the two bank guarantees referred to earlier. Looking to all these facts, and applying the principles on which a blacklisting/banning order can be passed and succinctly set out by the Supreme Court in the case of Kulja Industries Limited1, we do not think that in the facts and circumstances of the present case, the order of blacklisting (dated 25thApril, 2014) was at all justified. In fact, we find considerable force in the argument of Mr Moray that the aforesaid action is taken only with a view to ensure that the Petitioner is kept out of the bidding process and could not be awarded the subsequent tender No. Y-15 MC 11001 for which the Petitioner had qaulified and was the lowest tenderer (L-1).
20. Even on the principle of proportionality, we find that the banning order cannot be continued any further. The impugned banning order was passed on 25thApril, 2014 and has continued till
1 (201 4) 1 4 SCC 731
32
date which is for a period of more than 2 đ years. Even if we were to assume that the allegations in the blacklisting order (dated 25th April, 2014 ) as the gospel truth, the Petitioner, having suffered the banning order for a period of 2 đ years (out of the total period of three years) has to go.
21. In view of the foregoing discussion, we have no hesitation in setting aside the impugned banning order dated 25thApril, 2014. Rule is made absolute in the aforesaid terms and the Writ Petition is allowed in terms of prayer clause (a). It is clarified that the Petitioner shall be entitled to participate in any future tenders / bids that may be floated by the 1stRespondent. The Writ Petition is disposed of in the aforesaid terms. No order as to costs.
22. In view of our detailed judgement, nothing survives in the Notices of Motion and the same are disposed of accordingly.
( B.P.COLABAWALLA J. ) ( S.C.DHARMADHIKARI J )
23. At this stage, after the judgement was pronounced, the learned advocate appearing for the ONGC/Respondent nos. 1 to 3 seeks a stay of this order for a period of four weeks from today to
33
enable the respondents to challenge this order in a higher court or adopt appropriate proceedings. This request is opposed by Mr. Moray, learned counsel appearing for the petitioner.
24. Having heard both sides on this point and finding that the order of blacklisting was ex-facie erroneous and unsustainable in law and negating the mandate of Articles 14 and 19(1)(g) of the Constitution of India, the request is refused. This is more so in the facts of the present case as the Petitioner has already suffered the blacklisting order for a period of 2 đ years (out of a total of 3 years). However, we clarify that our order and direction does not restrain the Respondents or prohibit them in any manner from raising a contractual dispute and adopt such proceedings as are permissible in law to recover any sums. All contentions with regard to maintainability of these proceedings as also the merits thereof, are kept open.
( B.P.COLABAWALLA J. ) ( S.C.DHARMADHIKARI J )
34
Alert