The opinion, authored by R.V. Raveendran, J., concerns the Supreme Court’s consideration of an interim report (dated 17-8-2011) and additional information (submitted 12-9-2011) from an Expert Committee overseeing the security and preservation of a temple and its treasures. After reviewing the materials and the parties’ submissions, the Court issued a series of interim directions dealing with (i) implementation of an integrated, multi-layered security system, (ii) digitisation and archiving of temple antiques through the “Digital Archiving of Temple Antiques” (DATA) project, (iii) funding and budgeting for the above measures, and (iv) future procedural steps. The State Government, Temple Administration, Expert Committee, and an Overseeing Committee are the primary stakeholders referenced in the order.

Legal Issues Presented

The opinion addresses a procedural matter and does not frame distinct legal issues.

Arguments of the Parties

State Government

Temple Administration

Expert Committee

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court accepted the State Government’s assurance of competence and willingness to fund and implement the security measures, finding no necessity to requisition Central security forces. It further directed the State Government to incorporate the Expert Committee’s sixteen suggested security measures while respecting temple traditions and accommodating the Temple Administration’s views.

Regarding the DATA project, the Court approved execution by Keltron, emphasising that costs appeared excessive and should be renegotiated with State involvement. A Nodal Officer was to be appointed for price negotiation and payment scheduling. Although the Expert Committee proposed a one-year timeline, the Court urged acceleration without sacrificing quality and called for continuous supervision.

The Court addressed funding by directing the State Government to consider and sanction the requested interim budget while ensuring economical and transparent expenditure, supplemented by an annual contribution from the Temple Administration. It authorised steps for preservation, conservation, secure storage construction, and administrative logistics such as office space for committees. Continuity of coordination was encouraged through possible re-engagement of the outgoing Coordinator, Dr. Anand Bose.

Holding and Implications

INTERIM DIRECTIONS ISSUED

Direct effects include: (1) mandatory implementation of an integrated, multi-layered security system by the State Government; (2) authorisation and funding framework for the DATA digital archiving project with cost negotiations; (3) allocation of financial responsibilities between the State Government and Temple Administration; (4) steps toward secure storage construction and conservation of temple treasures; and (5) listing of the matter after three months for the Expert Committee’s next interim report and eventual final disposal. The order establishes procedural guidance but does not set new precedent beyond this case.

Show all summary ...

R.V Raveendran, J.— We have examined the interim report dated 17-8-2011 of the Expert Committee and the additional information submitted on 12-9-2011. Having considered the said report and the submissions of the parties, the following interim directions are issued:

Security measures

2. The Expert Committee has identified thirteen security issues and suggested sixteen security measures to be put in place. A copy thereof has already been made available to the State Government and the Temple Administration. The State Government has submitted the Security Technical Committee's Report putting forth an integrated and multi-layered security system for the Temple, for our perusal. In view of security concerns, we do not propose to extract either the security issues raised or the security measures suggested by the Expert Committee or the security measures proposed by the State Government.

3. The State Government has submitted that it has the expertise and capability to provide the necessary security measures; and it is ready and willing to provide the same at its cost. The State Government has assured that it would spare no effort or cost to provide the best security cover and has stated that there is no need to indent the service of any Central security force like CRPF as suggested by the Expert Committee, for strengthening the security. Having examined the Security Technical Committee's Report furnished by the State Government and its assurance to put in place an integrated multi-layered security system for the Temple in a time-bound manner, we are satisfied that the State Government would be in a position to execute the security plan. There is no need for the State Government to requisition the services of any Central security agency.

4. The State Government shall take note of the sixteen security measures that have been suggested by the Expert Committee in its interim report dated 17-8-2011 and promptly implement the integrated multi-layered security system explained and suggested in its Security Technical Committee's Report. In implementing the security system, the State Government will take note of the Temple traditions, customs and practices, and accommodate the views of the Temple Administration as far as possible and feasible.

Work Plan

5. The Expert Committee has suggested “Digital Archiving of Temple Antiques” (for short “DATA”) to achieve the following: (i) Recording of detailed information after examination and assigning an Antique Identification Number/Code; (ii) to store the information in a computerised database; (iii) recording of a 3D image of the object and link it to the database. The Expert Committee is permitted to implement the said “DATA” procedure.

6. The Expert Committee has recommended appointment of Kerala State Electronic Corporation (Keltron), a State Government undertaking with technical expertise from Vikram Sarabhai Space Centre (VSSC), a unit of the Department of Space, for implementing the work plan. Having regard to the security concerns and approval of the said agency by the State Government, we accept the suggestion that the “DATA” work should be executed by the said government undertaking instead of inviting tenders from private agencies.

7. Keltron has estimated the cost of executing the work to be Rs 3,16,35,000 made up of Rs 1,65,35,000 for hardware, Rs 40,00,000 for software, and Rs 1,11,00,000 for services and miscellaneous items. The cost appears to be very high and far exceeds the figures shown in the interim report. The feasibility of borrowing/hiring the equipment can be considered. The software cost and servicing cost requires drastic reduction. However, Keltron being a State Government undertaking and VSSC, the technical expert being a unit of the Department of Space, the Expert Committee may proceed to entrust the work to Keltron after involving the State Government in the process of negotiations relating to cost and the schedule of payment. We do not propose to approve the said price. As the State Government has to bear the expenditure involved, it will take the final decision on the pricing after negotiations, in consultation with the Expert Committee. The State Government shall nominate a Nodal Officer for this purpose, failing which the Secretary, Devaswom Department shall be the Nodal Officer.

Time-frame

8. The Committee has suggested time framework of one year to complete the entire work. Efforts shall be made to shorten the time schedule without sacrificing the quality of work. To ensure that the time schedule is maintained, we request the State Government to take appropriate decisions and release the required funds without any delay. The Expert Committee shall maintain constant supervision and follow-up, to avoid delay.

Kallara B

9. The issue relating to opening of Kallara ‘B’ shall be considered after substantial progress is made in regard to documentation, categorisation, security, preservation, conservation, maintenance and storage relating to the contents in the other kallaras.

Funding

10. The Committee has requested for sanction of an interim budget outlay of Rs 2,98,82,000. This will be considered by the State Government and appropriate amounts shall be sanctioned and released. The Expert Committee shall ensure that the expenditure is kept to be the minimum and avoid any kind of wasteful expenditure. Having regard to the huge expenditure that is contemplated, the State Government shall provide for appropriate accounting/audit assistance so that the fund utilisation is economical, efficient and transparent.

11. The Temple Administration has expressed its inability to make any significant contribution towards the expenditure involved, having regard to its limited resources. However, having regard to its participatory status, the Temple Administration shall contribute Rs 25,00,000 per year towards the funds required for completing the work plan and for security arrangements. The balance shall be contributed by the State Government.

Miscellaneous

12. The Expert Committee may take all necessary steps for preservation and conservation of the contents of kallaras.

13. The Temple Administration shall identify a suitable space (keeping in view the security concerns and the Temple traditions) for construction of a safety vault/storage space as per Reserve Bank of India norms in consultation with the Expert Committee and commence construction without delay.

14. To maintain confidentiality and avoid logistic problems, the Temple Administration shall make available an independent office space with proper security in the Temple premises for the Overseeing Committee and the Expert Committee, for the duration of the project.

15. The Expert Committee has reported that the term of office of the Coordinator Dr Anand Bose, under the Central Government has come to an end on 20-9-2011. If his services are not extended by the Central Government, we request the State Government to consider engaging his services as a Coordinator of the Expert Committee for a period of one year so that there will be continuity and coordination in the functioning of the Expert Committee.

16. The State Government and the Temple Administration shall extend their full cooperation to the Overseeing Committee and the Expert Committee for execution of the DATA project and security measures.

17. The Expert Committee will take the approval of the Overseeing Committee before taking final decisions on matters of policy and execution.

18. List after three months for the next interim report of the Expert Committee and for final disposal.