Greater Noida Ind. Dev. Authority v. Savitri Mohan & Ors. S

Supreme Court Of India
Jun 29, 2016
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The State of Uttar Pradesh issued two notifications for acquisition of land in Village Chhapraula, Gautam Budh Nagar District, for the purpose of “planned industrial development” by the Greater Noida Industrial Development Authority (GNIDA):

  • 12-3-2008 – Notification under Sections 4(1) and 17(4) of the Land Acquisition Act, 1894.
  • 3-2-2009 – Declaration under Section 6 read with Section 17(1).

An award was passed on 31-3-2011. Approximately 76 % of the compensation had already been disbursed and substantial physical development (roads, sewer lines, green belts, power and water infrastructure) had taken place.

The landowners (respondents) filed a writ petition in the Allahabad High Court on 3-3-2009, disputing the invocation of the urgency clause and asserting that they were running an agro-based and floriculture industry on the land. A Division Bench of the High Court, by judgment dated 30-5-2012, allowed the writ petition and quashed both notifications.

GNIDA and the State appealed to the Supreme Court, contending that the High Court’s view conflicted with an earlier Full Bench decision of the same High Court in Gajraj v. State of U.P. (2011) 11 ADJ 1, which had been affirmed by the Supreme Court in Savitri Devi v. State of U.P. (2015) 7 SCC 21.

Legal Issues Presented

  1. Whether the Division Bench of the Allahabad High Court was justified in quashing the acquisition despite the Full Bench decision in Gajraj—subsequently upheld in Savitri Devi—which had sustained the same notifications but moulded the relief to higher compensation and allotment of developed plots.
  2. Consequently, what relief should be granted to the respondent landowners: quashing of acquisition or enhanced compensation and allotment of developed land?

Arguments of the Parties

Respondent Landowners

  • The urgency clause under Section 17(4) was invoked mechanically, depriving landowners of their statutory right to object under Section 5-A.
  • Possession was wrongly shown as taken on 9-3-2009 despite an interim High Court order dated 5-3-2009.
  • Relied on Supreme Court authorities—Anand Singh, Dev Sharan, Radhy Shyam, Devender Kumar Tyagi, Devendra Singh, GNIDA v. Devendra Kumar and Darshan Lal Nagpal—to urge that absence of real urgency invalidates the acquisition.
  • Contended that, having approached the Court without delay, they were entitled to complete quashing of the acquisition.

Appellant State/GNIDA

  • Immediate development requirements and the threat of illegal constructions justified invocation of the urgency clause.
  • Article 226 jurisdiction should not be exercised to stall large-scale public-interest infrastructure; relief, if any, should be confined to additional compensation.
  • 82 % of landowners covering 76 % of the land had accepted compensation; major developmental works had already been completed.
  • The Division Bench’s judgment conflicted with the binding Full Bench ruling in Gajraj, which, as affirmed in Savitri Devi, upheld the same notifications for Village Chhapraula while granting enhanced compensation and plot allotment.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Anand Singh v. State of U.P. (2010) 11 SCC 242 Urgency clause under Section 17(4) is exceptional; inquiry under Section 5-A is normal rule. Cited by respondents; Supreme Court did not rely as controlling authority given subsequent Savitri Devi.
Dev Sharan v. State of U.P. (2011) 4 SCC 769 Need for genuine urgency to dispense with Section 5-A. Invoked by respondents; ultimately not determinative of relief.
Radhy Shyam v. State of U.P. (2011) 5 SCC 553 Protection of landowners’ rights; limited scope of urgency powers. Cited by respondents; Court distinguished in light of development already executed.
Devender Kumar Tyagi v. State of U.P. (2011) 9 SCC 164 Similar scrutiny of urgency clause. Referenced by respondents; not decisive in present outcome.
Devendra Singh v. State of U.P. (2011) 9 SCC 551 Same principle on urgency. Same as above.
GNIDA v. Devendra Kumar (2011) 12 SCC 375 Land acquisition for Greater Noida; moulding of relief. Cited by respondents; Court preferred later precedent.
Darshan Lal Nagpal v. Govt. (NCT of Delhi) (2012) 2 SCC 327 Scope of Section 17(4). Cited by respondents; not central to final ruling.
Gajraj v. State of U.P. (2011) 11 ADJ 1 (FB) Upheld same notifications but granted 64.7 % additional compensation and 10 % developed plot. Treated as binding; Division Bench erred in deviating from it.
Savitri Devi v. State of U.P. (2015) 7 SCC 21 Supreme Court affirmation of Gajraj; doctrine of moulding relief where large-scale development exists. Applied as controlling precedent; acquisition sustained, enhanced compensation and plot allotment ordered.

Court's Reasoning and Analysis

The Supreme Court confined its inquiry to whether the present dispute is governed by Savitri Devi and the underlying Full Bench decision in Gajraj:

  1. Extent of development and compensation already paid: 76 % compensation disbursed and substantial infrastructure erected on the land weighed heavily against setting aside the acquisition.
  2. Binding nature of Gajraj: The Full Bench had upheld the same notifications for Village Chhapraula, granting only enhanced compensation and developed plot allotment. This view was affirmed by the Supreme Court in Savitri Devi.
  3. Irrelevance of prompt filing alone: The Court rejected the respondents’ argument that their timely writ petition entitled them to complete relief, noting that Gajraj distinguished cases on the basis of the degree of development, not individual delay.
  4. Equitable balancing: Following Savitri Devi, the Court held that, although the urgency clause was wrongly invoked, quashing the acquisition would upset significant public-interest development. Equity demanded monetary and rehabilitation benefits instead.

Holding and Implications

APPEAL ALLOWED; the Division Bench judgment quashing the acquisition is set aside. The writ petitions are to be disposed of in conformity with Savitri Devi (2015) 7 SCC 21, entitling the respondents to:

  • Enhanced compensation increased by 64.7 %.
  • Allotment of developed abadi land equivalent to 10 % of the acquired land, subject to a ceiling of 2500 m2.
  • Immediate payment of the enhanced compensation, without prejudice to any further claims under the Land Acquisition Act.

Implications: The judgment reinforces the principle that large-scale development and substantial compensation disbursement may justify moulding relief instead of nullifying acquisitions, thereby providing certainty to infrastructure projects while safeguarding landowners through monetary and rehabilitative measures. No new legal doctrine is created; rather, the Court reiterates the approach adopted in Savitri Devi.

Show all summary ...

Adarsh Kumar Goel, J.— Leave granted. This appeal has been preferred against the judgment and order dated 30-5-2012 of the High Court of Judicature at Allahabad in Savitri Mohan v. State of U.P. 2012 SCC OnLine All 4225 whereby the High Court allowed the writ petition and set aside the Notification dated 12-3-2008 under Section 4(1) and Section 17(4) of the Land Acquisition Act, 1894 (the Act) and the Notification dated 3-2-2009 under Section 6 read with Section 17(1) of the 1894 Act.

2. The notified purpose for acquisition of land is “planned industrial development” of Greater Noida Industrial Development Authority (Gnida). The land of the respondents is in Village Chhapraula and is part of larger area of land acquired falling in many adjoining villages. The award was declared on 31-3-2011.

3. The original petitioners did not receive the compensation as they had already filed a petition in the High Court on 3-3-2009 mainly on the ground that the urgency clause could not have been invoked so as to deprive the landowners of their right to file objections. On coming to know of the proposed acquisition, the respondents made representation dated 11-4-2008 stating that they were running an agro-based industry and floriculture for producing hybrid seeds of flowers. The case of the writ petitioners was that possession was wrongly shown to have been taken on 9-3-2009 as interim order was already passed on 5-3-2009.

4. The writ petitioners relied upon the decisions of this Court inter alia in Anand Singh v. State of U.P. (2010) 11 SCC 242, Dev Sharan v. State of U.P. (2011) 4 SCC 769, Radhy Shyam v. State of U.P. (2011) 5 SCC 553, Devender Kumar Tyagi v. State of U.P. (2011) 9 SCC 164, Devendra Singh v. State of U.P. (2011) 9 SCC 551, Greater Noida Industrial Development Authority v. Devendra Kumar (2011) 12 SCC 375 and Darshan Lal Nagpal v. Govt. (NCT of Delhi) (2012) 2 SCC 327 in support of their case.

5. The stand of the State is that having regard to immediate need for development and likelihood of illegal and unauthorised constructions, invocation of urgency clause was justified. It was submitted that the power under Article 226 should not be exercised so as to obstruct development of infrastructure which will serve larger public interest. Instead, the relief could be moulded so as to compensate the writ petitioners. It was submitted that the land was part and parcel of larger area. In view of substantial development having taken place, the plea of the writ petitioners should not be considered in isolation.

6. Reliance was placed on a Full Bench judgment of the High Court in Gajraj v. State of U.P. (2011) 11 ADJ 1, 2011 SCC OnLine All 1711 whereby 461 petitions were decided. Acquisition was upheld but additional compensation of 64.70% was awarded with further direction to allot developed plots to the extent of 10% of the acquired land subject to maximum of 2500 sq m as against allotment of abadi plots to the extent of 6%. This order was passed having regard to the extent of development, which had already taken place after the acquisition. The said judgment also covered land of Village Chhapraula as a part of Group 18 (out of 65 groups). While discussing the writ petitions of Village Chhapraula, the Full Bench judgment noted that compensation had already been disbursed to the extent of 76%.

7. The Division Bench of the High Court, following the decisions of this Court referred to above, held that power of dispensing inquiry under Section 5-A could be exercised in exceptional situations and not without real urgency. In the present case, invocation of urgency was not justified. The judgment of the Full Bench in Gajraj (2011) 11 ADJ 1, 2011 SCC OnLine All 1711 was distinguished on the ground that therein the writ petition was filed with delay of two years and in some cases where there was no delay, the acquisition had been quashed.

8. Gnida has challenged the view of the High Court mainly on the ground that the Division Bench has taken a view contrary to the view taken by the Full Bench which by now stands affirmed by this Court in Savitri Devi v. State of U.P. (2015) 7 SCC 21 Subject to the moulding of relief as above, the Full Bench had upheld the acquisition relating to Village Chhapraula covered by the very same notification as in the present case. It was submitted that large-scale development work had already been executed on the acquired land. 82% landowners had accepted compensation which covered 76% of the land in terms of the area, Gnida had constructed roads, laid down sewer lines, electric transmission lines, developed green belts, provided drinking water facility and other infrastructure. In these circumstances, the impugned judgment could not be sustained. The learned counsel for the respondents supports the impugned judgment.

9. We have heard the learned counsel for the parties at length and perused the record including the layout plan showing Sectors 13 and 16 (Ind.) in Greater Noida (West).

10. The only question for consideration is whether the matter is covered by the judgment of this Court in Savitri Devi (2015) 7 SCC 21, as claimed by the appellant in which case the respondents will be entitled to relief of higher compensation and allotment of land instead of quashing of acquisition proceedings.

11. Our attention has been drawn to the relevant part of the Full Bench judgment of the High Court in Gajraj (2011) 11 ADJ 1, 2011 SCC OnLine All 1711 as follows: (SCC OnLine All)

“50. The writ petitions of Group-18 relate to Village Chhapraula. In Writ Petition No. 46775 of 2011 (Jai Pal v. State of U.P.) pleadings are complete which is treated as leading writ petition of Village Chhapraula. This writ petition has been filed by 48 tenure-holders challenging the Notification dated 12-3-2008 issued under Section 4 read with Sections 17(1) and 17(4) of the Act proposing acquisition of 68.129 ha land of Village Chhapraula. The declaration under Section 6 of the Act was issued on 3-2-2009. The State Government by Government Orders dated 8-9-1997 and 9-2-2005 has issued specific directions to the acquiring bodies not to include the land covered by abadi in the acquisition and in case it is utmost necessary for acquisition displaced person be given comparable land. The petitioners claim to be in actual possession of the land. It has been pleaded that it has become fashionable to discriminatingly apply the provisions of Section 17(4) of the Act in every case of acquisition. The land has been allotted to private builders whereas the purpose of acquisition was planned industrial development. In the counter-affidavit filed by the State it has been stated that possession of the land was taken on 9-3-2009 and award was declared on 21-3-2011. Copies of the possession memo and award have been brought on the record. According to Para 24 of the counter-affidavit, the land use of part of Sector Tech Zone was changed from institutional to residential and similarly land use of part of Sector Echotech-13 was changed from industrial to institutional which changes were approved by the Board on 11-2-2010 and also the same were approved by the Government on 30-3-2010. The compensation has been disbursed to the extent of 76%. An application for intervention has been filed on behalf of M/s Marion Biotech (P) Ltd. which claim allotment of land by allotment letter dated 31-3-2011 of an area of 10,000 sq m as an industrial plot in Echotech-16. The applicant claims that 200-300 persons shall be employed in the project.”

12. The operative part of the order in Gajraj case (2011) 11 ADJ 1, 2011 SCC OnLine All 1711 is as follows: (SCC OnLine All)

“21. In view of the foregoing conclusions we order as follows:
(1) Writ Petitions Nos. 45933 and 47545 of 2011 relating to Village Nithari, Writ Petition No. 47522 of 2011 relating to Village Sadarpur, Writ Petitions Nos. 45196, 45208, 45211, 45213, 45216, 45223-24, 45226, 45229-30, 45235, 45238 and 45283 of 2011 relating to Village Khoda, Writ Petitions Nos. 46764 and 46785 of 2011 relating to Village Sultanpur, Writ Petition No. 46407 of 2011 relating to Village Chaura Sadatpur and Writ Petition No. 46470 of 2011 relating to Village Alaverdipur which have been filed with inordinate delay and laches are dismissed.
(2)(i) The writ petitions of Group-40 (Village Devla) being Writ Petition No. 31126 of 2011, Writ Petition No. 59131 of 2009, Writ Petition No. 22800 of 2010, Writ Petition No. 37118 of 2011, Writ Petition No. 42812 of 2009, Writ Petitions Nos. 50417, 54424, 54652, 55650, 57032 and 58318 of 2009, Writ Petitions Nos. 22798, 37784 and 37787 of 2010, Writ Petitions Nos. 31124-25, 32234, 32987, 35648, 38059, 41339, 47427 and 47412 of 2011 are allowed and the Notifications dated 26-5-2009 and 22-6-2009 and all consequential actions are quashed. The petitioners shall be entitled for restoration of their land subject to deposit of compensation which they had received under agreement/award before the Authority/Collector.
(ii) Writ Petition No. 17725 of 2010 Omveer v. State of U.P. (Group-38) relating to Village Yusufpur Chak Sahberi is allowed. Notifications dated 10-4-2006 and 6-9-2007 and all consequential actions are quashed. The petitioners shall be entitled for restoration of their land subject to return of compensation received by them under agreement/award to the Collector.
(iii) Writ Petition No. 47486 of 2011 (Rajee v. State of U.P.) of Group-42 relating to Village Asdullapur is allowed. The Notifications dated 27-1-2010 and 4-2-2010 as well as all subsequent proceedings are quashed. The petitioners shall be entitled to restoration of their land.
(3) All other writ petitions except as mentioned above at (1) and (2) are disposed of with following directions:
(a) The petitioners shall be entitled for payment of additional compensation to the extent of same ratio (i.e. 64.70%) as paid for Village Patwari in addition to the compensation received by them under the 1997 Rules/Award which payment shall be ensured by the Authority at an early date. It may be open for Authority to take a decision as to what proportion of additional compensation be asked to be paid by allottees. Those petitioners who have not yet been paid compensation may be paid the compensation as well as additional compensation as ordered above. The payment of additional compensation shall be without any prejudice to rights of landowners under Section 18 of the Act, if any.
(b) All the petitioners shall be entitled for allotment of developed abadi plot to the extent of 10% of their acquired land subject to maximum of 2500 sq m. We however, leave it open to the Authority in cases where allotment of abadi plot to the extent of 6% or 8% have already been made either to make allotment of the balance of the area or may compensate the landowners by payment of the amount equivalent to balance area as per average rate of allotment made of developed residential plots.
(4) The Authority may also take a decision as to whether benefit of additional compensation and allotment of abadi plot to the extent of 10% be also given to;
(a) those landholders whose earlier writ petitions challenging the notifications have been dismissed upholding the notifications; and
(b) those landholders who have not come to the Court, relating to the notifications which are subject-matter of challenge in writ petitions mentioned at Direction (3).
(5) Greater Noida and its allottees are directed not to carry on development and not to implement the Master Plan 2021 till the observations and directions of the National Capital Regional Planning Board are incorporated in Master Plan 2021 to the satisfaction of the National Capital Regional Planning Board. We make it clear that this direction shall not be applicable in those cases where the development is being carried on in accordance with the earlier Master Plan of Greater Noida duly approved by the National Capital Regional Planning Board.
(6) We direct the Chief Secretary of the State to appoint officers not below the level of Principal Secretary (except the officers of Industrial Development Department who have dealt with the relevant files) to conduct a thorough inquiry regarding the acts of Greater Noida (a) in proceeding to implement the Master Plan 2021 without approval of NCRP Board, (b) decisions taken to change the land use, (c) allotment made to the builders and (d) indiscriminate proposals for acquisition of land, and thereafter the State Government shall take appropriate action in the matter.”

13. A perusal of the above shows that compensation had already been disbursed to the extent of 76%. Thereafter, for the entire land of Village Chhapraula falling in Group 18, the relief granted is payment of additional compensation and allotment of land. As already noted, the part of the order where relief of quashing of notification has been given is not of the category of the present case. In these circumstances, we find merit in the contention raised on behalf of the appellant that the Division Bench was in error in distinguishing the present case from the judgment in Gajraj (2011) 11 ADJ 1, 2011 SCC OnLine All 1711.

14. As observed by this Court in Savitri Devi (2015) 7 SCC 21, in spite of the finding that invocation of urgency clause was uncalled for, the relief of setting aside the acquisition was not granted having regard to the development that had already been undertaken on substantial part of the land. However, to balance the equities higher compensation and allotment of land was ordered to meet the ends of justice. (2015) 7 SCC 21

15. The learned counsel for the respondents vehemently submitted that the present case calls for the relief of quashing the acquisition as in the present case, the writ petitioners have approached the Court without any delay.

16. This argument cannot be accepted in view of the fact that the Full Bench judgment as upheld by this Court is not based on the extent of delay in individual cases. Consideration for not granting the relief of quashing the acquisition is overall development on substantial part of the acquired land as noted in para 50 of the Full Bench judgment already quoted hereinabove. Filing of prompt petitions by an individual is not the only consideration for grant of relief of quashing acquisition when almost entire land has already been developed. The Full Bench has quashed acquisition only where substantial part of the land had not been developed. The category of the judgment where acquisition has not been quashed covers the entire village where land of the respondents is located.

17. The respondents are, thus, entitled to be treated on a par with other similarly placed persons. They are entitled to the following relief as per paras 48.1 to 48.3 of the judgment of this Court in Savitri Devi (2015) 7 SCC 21:

“48.1. Increasing the compensation by 64.7%;
48.2. Directing allotment of developed abadi land to the extent of 10% of the land acquired of each of the landowners;
48.3. Compensation which is increased @ 64.7% is payable immediately without taking away the rights of the landowners to claim higher compensation under the machinery provided in the Land Acquisition Act wherein the matter would be examined on the basis of the evidence produced to arrive at just and fair market value.”

18. As earlier noted in para 12 earlier, allotment of 10% of the acquired land to the landowners concerned is subject to maximum of 2500 sq m.

19. In view of the above, we allow this appeal, set aside the impugned judgment and direct disposal of the writ petitions of the respondents in terms of the judgment of this Court in Savitri Devi (2015) 7 SCC 21. There will be no order as to costs.