National Co-Operative Consumers' Federation Of India Ltd. v. Union Of India

Delhi High Court
Jan 21, 2008
Smart Summary (Beta)

Factual and Procedural Background

The appellant challenged the order dated 06.02.1995 passed by the learned Additional District Judge, Delhi, which allowed objections filed by the Union of India (UOI) to an arbitral award dated 24.08.1993. The award was given by Shri K.D. Singh, the sole arbitrator appointed by the railway authorities. The dispute arose from a contract for the supply of urad whole dal, specifically regarding whether the appellant had agreed to supply the goods as per ASC Specification 192. The arbitrator disallowed UOI's claim for damages on the ground that UOI failed to prove that the appellant had agreed to supply the goods as per the specified ASC standard. The trial court overturned this finding, holding that a valid contract existed and that the arbitrator had erred in rejecting UOI's claim.

Legal Issues Presented

  1. Whether the arbitrator was justified in disallowing the claim of UOI on the basis that UOI failed to prove that the appellant agreed to supply urad whole dal as per ASC Specification 192.
  2. Whether the trial court erred in re-appreciating evidence and setting aside the arbitral award by concluding that a valid contract conforming to ASC Specification 192 was established.
  3. Whether the letter dated 07.06.1988 relied upon by UOI was a genuine document evidencing the appellant's offer to supply urad whole dal as per ASC Specification 192.

Arguments of the Parties

Union of India (Appellant before the trial court)

  • Argued that a valid contract was formed with the appellant agreeing to supply 450 MTs of urad whole dal conforming to ASC Specification 192.
  • Relied on various documents including the invitation to tender dated 07.06.1988, offer dated 07.06.1988 (Annexure D18), acceptance telegram dated 28.06.1988, and acceptance letter dated 29.06.1988 to prove the contract.
  • Asserted that the appellant partially performed the contract by furnishing a security deposit and tendering part supply, which was rejected for non-conformance to ASC Specification, and that the contract was eventually cancelled due to appellant’s failure to supply within the extended delivery period.
  • Contended that the arbitrator erred in relying solely on the appellant's letter dated 04.07.1988 and failed to consider the totality of material evidence showing acceptance of the ASC Specification condition.

Appellant (Respondent before the trial court)

  • Contended that the trial court wrongly re-appreciated evidence and returned a contrary finding to the arbitrator’s award, which was not permissible.
  • Denied that the letter dated 07.06.1988 (D18) was authored by them or constituted an offer to supply urad whole dal.
  • Highlighted the minutes of the meeting dated 08.06.1988 indicating that the tender enquiry was restricted to four types of dals excluding urad whole.
  • Argued that the letter dated 07.06.1988 was a fabricated document because it referenced negotiations held on 10.06.1988, which post-dated the letter.
  • Pointed out that the offer letter dated 27.06.1988 did not mention conformity to ASC Specification 192, and that UOI’s acceptance letter dated 29.06.1988 with the ASC Specification condition was effectively a counter-offer.
  • Emphasized that the parties were not ad idem (not in agreement) as the appellant understood the offer to relate to stock imported from Thailand, which was rejected by UOI for non-conformance.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court undertook a detailed examination of the documentary evidence and the sequence of events. It noted that the arbitrator had relied heavily on the appellant’s letter dated 04.07.1988 to conclude that the claimant failed to prove the appellant’s agreement to supply as per ASC Specification 192. However, the court found this reliance misplaced as the arbitrator ignored other material documents, including the invitation to tender, the offer, the acceptance telegram, and the acceptance letter, which indicated a contract had been formed with the ASC Specification condition.

The court also analyzed the authenticity and timing of the letter dated 07.06.1988 relied upon by UOI, highlighting inconsistencies such as references to negotiations held after the letter’s date, suggesting the letter was fabricated. It further observed that the tender enquiry originally covered only four dals, excluding urad whole, and that the appellant’s offer for urad whole dal was made later and did not include the ASC Specification condition.

Recognizing that the parties were not in mutual agreement (not ad idem) regarding the terms of the contract, the court concluded that the arbitrator’s finding—that the appellant never agreed to supply urad whole dal as per ASC Specification 192—was correct. The court held that the trial court erred in re-appreciating evidence and setting aside the award based on a contrary view.

Holding and Implications

The appeal was allowed, the impugned order dated 06.02.1995 was set aside, and the arbitral award was restored.

Holding: The trial court's order setting aside the arbitral award was overturned, affirming the arbitrator’s conclusion that the appellant did not agree to supply urad whole dal as per ASC Specification 192.

Implications: This decision reinstates the arbitral award and underscores the limited scope of judicial review over arbitral findings, particularly the inadmissibility of re-appreciation of evidence by courts in such matters. No new precedent was established beyond the direct effect of restoring the award in favor of the appellant.

Show all summary ...

Pradeep Nandrajog, J. (Oral):— The appellant is aggrieved by the order dated 06.02.1995 passed by the learned Additional District Judge, Delhi allowing objections filed by Union of India (UOI) to the award dated 24.08.1993 published by Shri K.D Singh, the learned sole arbitrator appointed by the railway authorities.

2. The learned arbitrator disallowed the claim for damages laid by Union of India by observing as under:

“It has been argued on behalf of the respondent that they had submitted a quotation for supply of urad whole dal to APO against Tender Enquiry No. J-12027/1/88.Pur-III dated 07.06.1988 It was later on that they had agreed to supply 450 MTs of urad whole @ Rs. 570 per quintal net FOR Bombay. Thereupon, the claimant had put a condition unilaterally that the goods will be as per ASC Specification 192. It is evident that no sooner the respondent received aforesaid communication, they had protested vide their letter dated 04.07.1988 I have considered the argumen???ts of both the parties in light of documentary evidence adduced and pleadings filed by both the parties. The claimant did not seem to prove that the respondent had agreed to supply the goods as per ASC Specification 192. In light of the above, the claim of the claimant is disallowed.”

3. Claimant was UOI. Appellant was the respondent before the arbitrator.

4. Upsetting the finding recorded by the learned arbitrator, vide impugned order dated 06.02.1995, learned trial judge has held as under:

“The foremost ground pressed by the Union of India in support of their plea for setting aside the award of the sole arbitrator is that there exists an error of fact and law apparent on the face of the award because the arbitrator rejected the claim of the petitioner mainly on the ground that the petitioner did not prove that the respondents had agreed to supply the goods as per ASC Specification 192. Learned counsel for the petitioner- Union of India emphatically urged before me that on the face of the available material on record, the petitioner had successfully proved that a valid contract had come into existence between the parties by which this respondent had agreed to supply 450 MTs urad whole as per ASC Specification 192 and, therefore, the finding returned by the arbitrator is wholly against the record. In support of this contention, the learned counsel has invited my attention to a number of documents, viz. invitation to tender dated 7th June, 1988 issued by the petitioner. Offer of the respondent no. 1 dated 07.06.1988 Annexure D18 of reply before the arbitrator. A/T Telegram dated 28.06.1988 followed by registered AD, acceptance letter dated 29.06.1988 On going through these documents it cannot be lost sight that the invitation to tender issued by the petitioner-Union of India was for the supply of whole urad as per ASC Specification 192 and the offer made by the respondent was also for the supply of 450 MTs of urad whole as per ASC Specification. The A/T also finds mention of ASC Specification. Not only this, the respondent no. 1 has in part-performance of the said contract and according to the provisions of Clause 4 of the contract furnished the security deposit in the form of bank guarantee dated 27.09.1988 and tendered part supply of 74.33 MTs, of urad whole to the petitioner on 05.09.1988, which was rejected because it was not as per the ASC Specification stipulated in the contract. After that, respondent no. 1 requested for extension of delivery period up to October 1988 vide letter dated 08.08.1988 and the delivery period was extended by 10th December, 1988 with a specific direction that, if the respondent failed to deliver the stores, the contract will be cancelled. It is also not denied that the respondent failed to supply the contracted item within the extended delivery period and consequently the petitioner cancelled the contract at the risk and cost of the respondent vide their letter dated 25.01.1989

On the face of the above factual position emerging from the material placed before the arbitrator it is to be seen as to whether the arbitrator was justified in taking a view that the claimants had not proved that the respondent had agreed to supply the goods as per ASC Specification 192 and rejecting their claim. It seems that the arbitrator has failed to look into the material documents brought on record and had gone wrong in relying upon the letter of the respondent dated 04.07.1988 only in holding that the petitioner failed to prove that the goods were to be supplied subject to ASC Specification 192. It appears that the arbitrator failed to appreciate that on accepting the offer of respondent no. 1 and issuing the A/T to them for the supply, a valid contract had come into existence between the parties and, therefore, any subsequent document produced by the respondent was of no consequence. The contention of the respondent that they had not submitted the quotation of urad whole as against the Tender Enquiry No. J-12027/1/88.Pur-III dated 07.06.1988 or that it was at subsequent date that they had agreed to supply 450 MTs of urad whole @ Rs. 570 per quintal net FOR Bombay; and that the petitioner had put in a condition unilaterally about the supply of goods as per ASC Specification 192 ought to have been repelled, on the face of the facts and circumstances obtaining on record. Even if the letter dated 04.07.1988 was to be taken on its face value, this at best would show that the respondent requested to the petitioner not to insist the supply of the goods as per ASC Specification. This would rather show that they having undertaken to supply the goods as per ASC Specification, subsequently wanted the concession from the side of the petitioner which was not agreed to by them. On the face of this position, the arbitrator was not at all justified in holding that the petitioner had failed to prove that the respondent had agreed to supply of goods as per ASC Specification 192.”

5. It is urged by learned counsel for the appellant that it was not within the province of the learned court to have re-appreciated the evidence and return a contra-finding. It is further urged that even appreciation of the evidence by the court concerned is with material irregularity and the issue has not been discussed in the correct perspective. It is further urged that the letter dated 07.06.1988 (D18) has been incorrectly treated as a letter of the appellant pertaining to supply of urad whole dal.

6. It is further urged that minutes of a meeting dated 08.06.1988 (Annexure C) have been totally ignored by the court concerned.

7. To appreciate the contention urged by learned counsel for the appellant the minutes of the meeting dated 08.06.1988 become material and can be treated as the take off point for the purposes of the present adjudication.

8. The minutes record that pertaining to offers made by five parties to supply dal arhar, chana, moong chilka and moong whole negotiations were held. Therefrom, it is apparent that the tender enquiry was restricted to only aforesaid four dals and not to urad whole. Counsel submitted that pursuant to the notice inviting tender, appellant submitted offer for supplying arhar dal, chana dal, moong chilka and moong whole and no other dal.

9. Learned trial judge has noted that vide NIT dated 07.06.1988 UOI had invited offer for supply of urad dal and that vide offer dated 07.06.1988 appellant had offered to supply urad dal.

10. The letter of offer stated to have been submitted by the appellant and in respect whereof the respondent claimed reliance before the learned arbitrator is a letter allegedly sent by the appellant on 07.06.1988 recording that its offer to supply 450 MTs of urad whole conformed the ASC Specification 192.

11. Needless to state appellant denied the said letter. The respondent had to prove that the said letter of offer was that of the appellant.

12. The letter in question makes interesting reading. It reads as under:

With reference to our offers against subject tender enquiry and negotiations held on 10.06.1988, we hereby make the following offer….”

13. Indeed, argument of learned counsel for the appellant merits consideration and acceptance that how could the letter dated 07.06.1988 incorporate a reference to negotiations held on 10.06.1988

14. It is further interesting to note that while captioning the subject of the letter, it refers to an offer dated 07.06.1988 allegedly opened on 08.06.1988

15. Surprisingly, the learned court concerned failed to appreciate that the element of creation in the letter in question was self-evident.

16. Submission of the appellant that the tender enquiry relating to four dals resulted in tenders being opened and negotiations held on 08.06.1988 resulting in department informing whether the offerers could even make an offer for urad whole and pursuant thereto an offer was made by the appellant has been totally ignored by the learned trial judge.

17. The record of the arbitration shows that on 27.06.1988 appellant offered, apart from the dals in respect whereof offers were made pursuant to the NIT, to supply 450 MTs of urad dal whole from Bombay. The said letter (Ex. D-25) being the letter dated 27.06.1988 nowhere records that the dal would conform to ASC Specification.

18. In response thereto, UOI sent a letter of acceptance dated 29.06.1988 recording accepting the offer but by stipulating that the offer as accepted could relate to urad whole conforming to ASC Specification 192. On receipt of the letter of acceptance appellant wrote back on 04.07.1988 informing that the dal in respect whereof offer was made was the one imported from Thailand and offer related to said stock and none else.

19. UOI did not respond to the letter dated 04.07.1988 Thinking that its offer has been accepted pertaining to the stock of urad dal lying with the appellant as imported from Thailand and lying stored at Bombay, appellant dispatched 74.33 MTs of urad whole dal which was rejected by UOI on the ground that it did not conform to ASC Specification.

20. The conclusion drawn by the learned judge that the delivery of the consignment evidences a concluded contract belying the knowledge of the basic fact in dispute, namely what was the offer which was accepted.

21. The learned arbitrator has correctly come to the conclusion that the offer made by the appellant pertained to urad whole dal lying in its stock and no document was shown that the appellant ever offered or accepted to supply urad dal conforming to ASC Specification 192.

22. It is apparent that the parties were not ad idem. It is apparent that the appellant thought that offer made by it was accepted and, therefore, appellant proceeded to dispatch 74.33 MTs of urad whole which was imported by the appellant from Thailand.

23. In any case, what stands out is that the original offer pertained to only four types of dal. The tender enquiry restricted itself to four categories of dal. Evidenced by the minutes of the meeting dated 08.06.1988, when tenders were opened, UOI evidenced a desire to purchase even urad whole dal in respect whereof appellant made an offer vide its letter dated 27.06.1988 UOI's acceptance dated 29.06.1988 put a condition of acceptance. Thus, the said conditional acceptance has to be treated as a counter-offer. On 04.07.1988, appellant wrote back that it would be prepared to supply urad dal imported by the appellant from Thailand. There is no document on record to show that UOI refuted aforesaid letter dated 04.07.1988

24. The learned court below has totally failed to appreciate that the alleged offer letter dated 07.06.1988 propounded by UOI was a created document on account of the inherent deficiencies noted hereinabove in paras 12 to 14 above pertaining to the said document.

25. The appeal succeeds. Impugned order dated 06.02.1995 is set aside.

26. The award is restored.

27. No costs.

28. TCR be returned.