Kunjumon v. Lissy

Kerala High Court
Jun 27, 2016

K. Harilal, J.:— The petitioner herein is the plaintiff in Original Suit No. 656 of 2015, on the files of the Munsiff's Court, Cherthala as well as the petitioner in Interlocutory Application No. 3687 of 2015 filed therein. The suit is one for an injunction, restraining the respondents from cutting open a new pathway and from committing waste over the plaint schedule property. Along with the suit, the petitioner has filed the Interlocutory Application, seeking a temporary injunction for the same. After considering the objection filed by the respondents, the trial court passed Ext.P7 order, directing both parties to maintain status quo, until the disposal of the suit.

2. Aggrieved by Ext.P7 order, the petitioner had preferred C.M.A No. 39 of 2015, before the Sub Court, Cherthala and after re-appreciating the materials on record, the Sub Court also confirmed Ext.P7 order passed by the trial court and dismissed the C.M.A The legality and propriety of the concurrent findings, whereby the courts below dismissed the applications filed by the petitioner, are under challenge in this Original Petition (Civil)

3. Heard the learned counsel for the petitioner.

4. Going by the impugned order, it is seen that respondents in their objection contended that there is a pathway through the property of Maniyampally family and plaint schedule property towards south, so as to reach Edappangazhy temple-Thaliyaparampu road and thereby, they acquired prescriptive easement right of way over the said pathway, by their long, continuous and uninterrupted usage of the pathway for the egress and ingress to their property. An Advocate Commissioner was appointed to ascertain the nature and lie of the plaint schedule property as well as the alleged pathway and the Commissioner filed Ext.C1 and C1(a) report. The Commissioner has reported that there is a definite pathway, having a width around 1.5 feet through the plaint schedule property in the south-west direction. Further, the Commissioner did not report any sign of damage caused by the respondents or anyone in the plaint schedule property. So also there was no prayer in commission application to ascertain damage caused by respondents in the plaint schedule property, as alleged in the petition. After considering the pleadings of both parties, in the light of the Commission Report, the trial court arrived at a finding that whether defendants/respondents had acquired any right of prescriptive easement or not is an issue to be determined after trial and it is just and proper to direct both parties to maintain status quo, as seen by the Commissioner in Ext.C1 and C1(a) report, until final adjudication of the alleged exclusive possession of the petitioner over the plaint schedule property and prescriptive easement right of way claimed by the respondents, after trial.

5. In the C.M.A the learned Sub Judge also re-appreciated the materials available on record and arrived at a finding that unless evidence is taken to determine the rights and liabilities claimed by both parties, no injunction order can be passed, as prayed for by the petitioner. I do not find any kind of illegality or impropriety in the concurrent findings of the courts below. In the above view, there is no reason to interfere with the orders passed by the courts below.

6. This Original Petition (Civil) is devoid of merits and dismissed accordingly.