- Bookmark
- Share
- CaseIQ
Uttar Pradesh Power Corporation Limited And Others v. Vimla Devi And Another
Factual and Procedural Background
The appellant—an electricity distribution corporation—issued a demand notice dated 23-3-2010 to the first respondent, Ms. Vimla Tiwari, seeking Rs 1,97,815 in “escaped billing” for the period between 5-11-2008 (when the old meter was replaced) and 31-1-2010. The notice was based on an inspection conducted on 25/28-11-2009 by the Corporation’s Junior Engineer.
The respondent challenged the notice by filing Writ-C No. 20459 of 2010 before the Allahabad High Court. By order dated 18-5-2010, the High Court permitted her to file objections and directed the Executive Engineer to pass a speaking order. On 8-6-2010 the Executive Engineer revised the demand to Rs 50,891.
Dissatisfied, the respondent again approached the High Court in Vimla Tiwari v. State of U.P., AIR 2012 All 142. The High Court quashed the demand, imposed Rs 10,000 costs on the Corporation, and directed that displeasure be recorded in the annual confidential reports of the assessing and appellate officers. The Corporation and its officials appealed to the Supreme Court, leading to the present judgment.
Legal Issues Presented
- What is the proper basis for revising electricity bills when a consumer’s meter is found non-functional and a short assessment must be made, particularly regarding the permissible period and method of calculation?
- Whether the High Court was justified in recording adverse remarks against the assessing officer and the appellate authority and in imposing personal liability and costs.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Supreme Court noted that the core dispute was narrow: determining an equitable method to calculate the short-assessed energy charges for the period when the respondent’s previous meter was allegedly faulty. The Court accepted the Corporation’s concession that, under applicable regulations, any revised assessment must be limited to twelve months.
Observing that the new meter installed on 23-1-2010 functioned correctly and showed a “marked difference” in consumption patterns, the Court considered it fair to derive the assessment from actual data. It therefore directed that:
- The respondent’s energy bills for the twelve months ending 31-1-2010 be recalculated on the basis of the average consumption for the twelve-month period beginning 1-2-2010.
- A fresh demand be issued within two months, after which the respondent must pay any balance within one month, failing which lawful coercive measures may be taken.
Regarding the High Court’s adverse observations against the officers, the Supreme Court found no evidence of mala fide or illegal conduct—only possible procedural irregularities. Because even the High Court contemplated an inquiry before fixing liability, recording immediate adverse remarks was unwarranted. Consequently, the Supreme Court expunged those remarks and vacated the directions related to officers’ annual confidential reports and costs.
Holding and Implications
APPEAL ALLOWED. The Supreme Court ordered a fresh, limited reassessment of electricity charges as outlined above; expunged adverse remarks against the officers; and vacated the High Court’s cost order.
Implications: The decision resolves the billing dispute between the parties and removes personal and disciplinary consequences for the officers involved. No new legal precedent was articulated beyond reaffirming that reassessments for faulty meters are restricted to a twelve-month period based on reasonable consumption averages.
Kurian Joseph, J.— Leave granted. The short dispute in this case pertains to the steps taken by the appellant Corporation for levying the energy charges on the first respondent for the period of the alleged meter fault. On the basis of the inspection conducted on 25-11-2009/28-11-2009 by the Junior Engineer of the appellant Corporation, the first respondent was served with a notice dated 23-3-2010 demanding an amount of Rs 1,97,815 towards energy charges which escaped billing.
2. The first respondent filed a writ petition before the High Court which was disposed of by the judgment dated 18-5-2010 Writ-C No. 20459 of 2010, order dated 18-5-2010 (All) permitting her to file objections and directing the Executive Engineer to consider the objections and pass a speaking order. The Executive Engineer, by order dated 8-6-2010, passed the revised order limiting the demand to Rs 50,891. The said order was challenged before the High Court in Vimla Tiwari v. State of U.P. 2012 SCC OnLine All 741 , AIR 2012 All 142 leading to the impugned judgment.
3. The High Court, having conducted an elaborate inquiry into the matter, found that there was no justification for the demand. It was held that the proper procedure prescribed under law was not followed in inspection and preparation of the report. Still further, it was held that even the appellate authority did not discharge its functions as expected of them. The displeasure on the conduct of the assessing officer and the appellate authority was directed to be recorded in their annual character roll (annual confidential report) for the relevant period. The writ petition was thus allowed with costs of Rs 10,000 to be paid by the appellant Corporation with liberty to recover the same from the officials concerned after conducting an appropriate inquiry. There was also a direction to communicate the order to the Chief Secretary for ensuring compliance with the directions by the High Court. And thus aggrieved, the Corporation and its officials have come up in appeal.
4. Heard the learned counsel appearing for the appellants and the respondents.
5. Though several contentions are raised by the counsel on both sides, the dispute essentially is in a very narrow compass. According to the appellants, for whatever reason, there was short assessment of energy charged at the premises of the first respondent during the period between 5-11-2008, when the old meter was replaced, and 31-1-2010. It is not in dispute that a new meter was installed at the premises of the first respondent on 23-1-2010. It is fairly conceded that when the meter at the premises of a consumer is reported to be non-functional, and if consequently, there is short assessment for a long period, the bills can be revised for that period but limiting to twelve months. What should be the basis of the assessment, is the simple question.
6. There is no case for the appellants that the meter installed on 23-1-2010 had any fault thereafter, in any case, for quite some time. Therefore, having regard to the entire facts and circumstances of the case, we are of the view that interest of justice will be served if the energy bills of the first respondent are revised for a period of twelve months ending with 31-1-2010, taking the average of twelve months from 1-2-2010. In other words, based on the average consumption for a period of twelve months beginning from 1-2-2010, the energy bills of the first respondent for a period of twelve months ending with 31-1-2010 shall be revised. A fresh demand on that basis shall be issued to the first respondent within two months from today. After adjusting the amounts already paid for the said period, the first respondent shall pay the balance amount within another one month failing which it will be open to the appellants to take appropriate coercive action permitted under law. It is made clear that this order has thus given a quietus to the entire dispute raised in the writ petition regarding the short assessment.
7. Having said that we have also to address the grievances raised by the appellants with regard to the adverse observations against the conduct of the officers and a direction by the High Court to record displeasure in the annual confidential report of the assessing officer and the appellate authority. Going through the materials available on record as produced by both sides, we find that there is no justification for any such direction by the High Court. Apparently, the authorities have only discharged their functions under law. It appears that there has been some procedural irregularity. But that does not mean that there is any mala fide or illegal conduct on the part of the officers. It may be noted that even according to the High Court, an inquiry is to be conducted for fastening the liability. If that be so, there is no justification for the remarks against the assessing officer and the appellate authority. It is seen from the records that there is a marked difference in the pattern of consumption after the new meter was installed in January 2010. In such circumstances, it is difficult to digest any allegation of motivated conduct on the part of the two officers.
8. Accordingly, the appeal is allowed with directions as above on reassessment. The adverse remarks on the conduct of the officers are expunged and the directions contained in paras 48, 49 and 51 of the impugned judgment are vacated. The order on costs is also vacated. There shall be no order as to costs.
Alert