- Bookmark
- Share
- CaseIQ
M/S. Chebrolu Enterp... v. Andhra Pradesh Backw...
Factual and Procedural Background
The Government of Andhra Pradesh launched the “Adarana” scheme to provide essential tools to rural artisans such as blacksmiths, carpenters, and dhobis. Purchases were to be made through the A.P. Backward Classes Cooperative Finance Corporation Ltd. (“the Corporation”), a State-controlled entity. The appellants (“suppliers”) agreed to supply “Razaka tools” at negotiated rates of Rs 165 per kg in six coastal districts and Rs 189.75 per kg in the remaining districts, exclusive of sales tax. Each supplier executed an undertaking that the quoted prices were the lowest at which they sold comparable tools anywhere in Andhra Pradesh and agreed to refund any excess if lower market prices were discovered.
After delivery, the Corporation concluded that the suppliers’ prices were not the lowest and invoked the contractual arbitration clause. The Arbitral Tribunal determined on 11-3-2002 that the fair price was Rs 115 per kg and awarded that sum plus 6% interest from 26-4-2001. The suppliers’ challenges under Section 34 of the Arbitration and Conciliation Act, 1996 (“the Act”) were dismissed by the XIV Additional Chief Judge, City Civil Court (Fast Track Court), Hyderabad. Their Section 37 appeals met the same fate in the High Court of Andhra Pradesh in Mercury Metal Corpn. v. A.P. Backward Classes Coop. Finance Corpn. Ltd., 2009 SCC OnLine AP 811. The suppliers then filed the present appeals before the Supreme Court.
Legal Issues Presented
- Whether the suppliers committed fraud or fraudulent misrepresentation upon the Corporation.
- Whether either party breached the contract arising out of the “Adarana” scheme.
- Whether the Arbitral Tribunal was competent to determine the price of the tools supplied.
- Whether the price of Rs 115 per kg fixed by the Arbitral Tribunal was reasonable.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Mercury Metal Corpn. v. A.P. Backward Classes Coop. Finance Corpn. Ltd., 2009 SCC OnLine AP 811, (2010) 3 ALD 290 | High Court judgment under Section 37 of the Act affirming the arbitral award. | The Supreme Court reviewed this judgment and concluded that the High Court’s reasoning was “just and proper,” thereby affirming it. |
Court's Reasoning and Analysis
1. The Court emphasized the suppliers’ written undertakings that the quoted prices were the lowest available in the State. Those undertakings formed an integral part of the contracts.
2. The Arbitral Tribunal’s finding that comparable tools were sold by the very suppliers within Andhra Pradesh at prices lower than those quoted to the Corporation was treated as a pure question of fact, supported by evidence.
3. Under Article 136 of the Constitution, the Supreme Court will not disturb concurrent findings of fact unless they are perverse. Both the Section 34 court and the High Court had upheld the Tribunal’s findings; no perversity was shown.
4. The Court rejected the contention that the Tribunal lacked jurisdiction to fix a lower price. In light of the undertakings, determining the correct market-aligned price fell squarely within the arbitral mandate.
5. Allegations of fraud were dismissed as unfounded. Even if the contract price exceeded market price, that discrepancy, in itself, did not amount to fraudulent conduct.
6. Having found the Tribunal’s price determination reasonable and within jurisdiction, the Court held that no ground existed under the Act—or otherwise—to interfere with the award.
Holding and Implications
APPEALS DISMISSED. The Supreme Court affirmed the High Court’s judgment and the arbitral award, leaving the suppliers entitled only to Rs 115 per kg plus the specified interest, and made no order as to costs.
Implications: The decision finalises the price payable to the suppliers under the “Adarana” scheme and reinforces judicial reluctance to interfere with concurrent arbitral and appellate findings of fact. No broader legal precedent was articulated beyond this affirmation.
Anil R. Dave, J.— Leave granted. In all these appeals validity of a common judgment delivered in Mercury Metal Corpn. v. A.P. Backward Classes Coop. Finance Corpn. Ltd. 2009 SCC OnLine AP 811 , (2010) 3 ALD 290 dated 14-12-2009 has been challenged.
2. The aforestated civil miscellaneous appeals had been filed in the High Court of Judicature of Andhra Pradesh at Hyderabad under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) against a common order dated 14-3-2005 passed in different original petitions, by the XIVth Additional Chief Judge, City Civil Court (FTC), Hyderabad, dismissing the original petitions. The High Court vide its common judgment dated 14-12-2009 2009 SCC OnLine AP 811 , (2010) 3 ALD 290 dismissed the aforestated appeals.
3. Being aggrieved by the said common judgment, the appellants have approached this Court by way of these appeals.
4. The circumstances which gave rise to the present litigation in a nutshell are as under: the Government of Andhra Pradesh had launched a scheme named “Adarana” under which certain tools of trade necessary for blacksmiths, carpenters, dhobis, etc. were to be supplied to the rural artisans. The Government was to purchase the tools through A.P. Backward Classes Cooperative Financial Corpn. Ltd., a corporation set up for welfare of the persons belonging to downtrodden classes, controlled by the Government and the “State” within the meaning of Article 12 of the Constitution of India. The respondent Corporation had invited quotations for supplying iron boxes, iron ring used for placing the iron; boxes, buckets and bannas required in the process of washing clothes, etc. The present appellants had agreed to supply the “Razaka tools” at a particular rate. We do not go into the details as to how the rates were finalised after several meetings held among the suppliers of the tools and the officers of the respondent Corporation. Suffice it to state at this stage that the suppliers, after several meetings and bargaining on both the sides had agreed to supply the tools @ Rs 165 per kg in six coastal districts of Andhra Pradesh, namely, Srikakulam, Vizianagaram, Visakhapatnam, East Godavari, West Godavari and Krishna, whereas for the other remaining districts, the rate had been fixed at Rs 189.75 per kg and the above rates were exclusive of sales tax.
5. It is pertinent to note that when the agreement had been entered into with regard to supply of the tools by the appellants to the respondent Corporation, it was also agreed among the parties that the rate at which the tools were offered was the lowest rate at which the suppliers were selling the tools of the same specification in the State of Andhra Pradesh.
6. Each appellant (who has been referred to hereinafter as “the supplier”) had also filed an undertaking stating that the prices quoted for supply of the tools were the lowest possible prices and that nowhere in Andhra Pradesh, the supplier was selling those products at prices lower than the price quoted. They had also undertaken to refund the difference of amount arising on account of any price difference in the price quoted by them and lower price offered by them in the open market in Andhra Pradesh in respect of the tools. One such undertaking dated 22-4-1999 given by one of the suppliers is reproduced hereinbelow:
“Undertaking
“… I, Smt Chebrolu Lakshmi Sesha Kumari, proprietor of M/s Chebrolu Enterprises, hereby declare that the prices quoted for the supply of our products under Adarana Project being implemented by Andhra Pradesh Backward Classes Cooperative Finance Corporation are the lowest possible prices and nowhere in Andhra Pradesh, we are selling our products with the same specifications at prices lower than the prices we have quoted under the said project.
I also undertake to refund/authorise Andhra Pradesh Backward Classes Cooperative Finance Corporation to deduct excess amount paid to us on account of any price differential between higher prices quoted by us under Adarana Project and lower prices offered in open markets in Andhra Pradesh….”
7. Ultimately, the tools had been supplied by the suppliers to the respondent Corporation but it was found that the rates which had been charged by the suppliers were neither reasonable nor were the lowest at which the suppliers had sold their products similar to the one which they had supplied to the respondent Corporation and therefore, a dispute had arisen among the parties and the dispute had been referred to an Arbitral Tribunal, as agreed upon by the parties in the agreement dated 22-4-1999. The aforestated facts are not in dispute.
8. The learned Arbitral Tribunal ultimately came to the conclusion that the amount charged by the suppliers was excessive and therefore, made an award dated 11-3-2002 in favour of the respondent Corporation to the effect that the suppliers were entitled to only Rs 115 per kg towards price of the tools supplied by them and the claim exceeding the said amount had been rejected. It was also provided in the award that the amount be paid with interest @ 6% per annum with effect from the date of claim petition i.e. 26-4-2001 till the date of the payment.
9. The suppliers, being aggrieved by the award, challenged the validity of the award by filing original petitions before the Court of XIVth Additional Chief Judge, City Civil Court (Fast Track Court), Hyderabad under the provisions of Section 34 of the Act. After hearing the parties concerned, the said original petitions were dismissed and therefore, the suppliers approached the High Court with the abovereferred civil miscellaneous appeals. The said appeals have also been dismissed and therefore, the present appeals have been filed by the suppliers before this Court.
10. The issues that fall for determination in these appeals are whether the suppliers had committed any fraud or fraudulent misrepresentation upon the respondent Corporation and whether any breach of contract had been committed either by the suppliers or by the respondent Corporation and further, whether the price fixed by the Arbitral Tribunal was reasonable or whether it was open to the Arbitral Tribunal to determine the price of the tools which had been supplied by the suppliers to the respondent Corporation.
11. We have heard the learned counsel appearing for the parties at length. Upon hearing the learned counsel, looking at the facts of the case and upon perusal of the relevant documents, including the agreement entered into between the suppliers and the respondent Corporation and the undertakings given by the suppliers in relation to supply of tools at the lowest price in the State, we are of the view that the impugned judgment delivered by the High Court is just and proper.
12. The price at which the tools had to be supplied had been fixed after negotiations and efforts were made to bargain on the subject of price by both the sides. Ultimately, a particular price had been determined as a result of the negotiations and the agreements with different parties had been entered into by the respondent Corporation for purchase of the tools.
13. The most important factor to be considered is the undertaking executed by each supplier to the effect that the tools which the said supplier had agreed to supply to the respondent Corporation was to be charged at the lowest rate at which the said supplier had sold his tools in the State of Andhra Pradesh. In other words, the supplier had not sold tools to anybody at a price lower than the price offered by the supplier to the respondent Corporation.
14. A copy of the undertaking executed by each supplier has been reproduced hereinabove. By virtue of the said undertaking, the suppliers had assured the respondent Corporation that the prices quoted for supply of the tools under Adarana project were the lowest prices and that nowhere in Andhra Pradesh, they had sold their tools with the same specifications at prices lower than the prices which had been quoted by them for supply of the tools to the respondent Corporation for Adarana project. The effect of the undertaking was that if the rate which had been quoted by the suppliers in their agreement was more than the rate at which the said tools were sold by them in the State of Andhra Pradesh, the suppliers would refund the excess of price charged by them to the respondent Corporation.
15. The contract entered into by the suppliers on one hand and the respondent Corporation on the other was subject to the aforestated undertaking given by the suppliers. So, if the price quoted in the agreement is ‘X’ per kg for the tools supplied by the suppliers but if the tools of the same specifications were being sold by the suppliers in the State of Andhra Pradesh for a price lower than ‘X’, say at price ‘Y’, the respondent Corporation was supposed to pay rate ‘Y’ and not ‘X’, which had been agreed upon in the contract.
16. As there was a dispute with regard to the price and as the respondent Corporation had found out that rate quoted in the contract was higher than the rate at which the tools of the same specifications had been supplied by the suppliers in the State of Andhra Pradesh, the respondent Corporation had withheld the payment and in the circumstances the dispute had been raised and the suppliers had made their claim before the Arbitral Tribunal for payment of the remaining amount of price.
17. The learned Arbitral Tribunal considered all factors and the evidence which was adduced before it and came to the conclusion that the price which had been quoted by the suppliers and which had been agreed upon in the contract was higher than the price at which tools of the same specifications were sold by the suppliers in the State of Andhra Pradesh. In the circumstances, the learned Arbitral Tribunal came to the conclusion that the suppliers were entitled to the price of tools lesser than the one which had been agreed upon in the contract because the same quality of tools, which had been manufactured by the suppliers, were sold by them in the State of Andhra Pradesh at a lower price.
18. Determination of price in the aforestated manner is a question of fact. This Court or even the appellate court would not look into the finding of facts unless they are perverse. In the instant case, neither the City Civil Court in the proceedings filed before it under Section 34 of the Act nor the High Court in the proceedings under Section 37 of the Act could find anything wrong with the finding of facts arrived at by the Arbitral Tribunal. This Court under Article 136 of the Constitution of India would not like to interfere with the concurrent finding of facts, save in exceptional circumstances or unless the finding is perverse.
19. For the aforestated reasons, in our opinion, the determination of price by the Arbitral Tribunal cannot be faulted with.
20. The submission that the Arbitral Tribunal was not competent to determine the price is also not well founded. It is a finding of fact by the learned Arbitral Tribunal that the price quoted was more than the price at which the same products/tools were supplied by the same supplier in Andhra Pradesh and therefore, after considering the relevant evidence, the Arbitral Tribunal determined a particular price i.e. Rs 115 per kg. It cannot be said that determination of said price by the Tribunal in the aforestated circumstances was improper. The suppliers were bound as per the undertakings executed by them and as they had not acted as per their undertaking, it was open to the learned Tribunal to find out the correct lower price at which the tools of the same specifications, which were manufactured by the suppliers were available in the State of Andhra Pradesh and if in the aforestated circumstances, the Arbitral Tribunal determines the price, in our opinion, it cannot be said that the Arbitral Tribunal had exceeded its jurisdiction.
21. In our considered opinion, no fraud had been committed as alleged. If higher price had been charged by the suppliers in the contract than the price at which their products were sold in the State of Andhra Pradesh, it cannot be said that the suppliers had committed any fraud while entering into the contract. The parties may determine the price in the manner agreed upon by them. In the instant case, there was an undertaking in the nature of a proviso that if the price fixed in the contract is more than the price at which tools of same specifications manufactured by the same supplier were available in the State, the supplier would be entitled to the lesser rate.
22. In our opinion, the manner of price determination by the Arbitral Tribunal, in the light of the undertakings executed by the suppliers, cannot be said to be irrelevant, incorrect or beyond jurisdiction.
23. For the aforestated reasons, we do not find any substance in these appeals and the same are dismissed with no order as to costs.
Alert