Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

South Delhi Municipal Corporation v. Ravinder Kumar And Another

Supreme Court Of India
Oct 7, 2015
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

South Delhi Municipal Corporation (“the Corporation”) issued Notice Inviting Tender (NIT) No. 21 dated 15-11-2012 for 26 civil works. Five contractors, including the two respondents, submitted bids. When financial bids were opened on 29-11-2012, the respondents emerged as the lowest bidders for 16 works.

On 30-11-2012 the Corporation cancelled NIT 21 through a corrigendum citing “administrative reasons.” The respondents sought clarification, served a legal notice on 13-12-2012, and, on the same day, the Corporation issued a fresh NIT 24 dated 13-12-2012 for the same works.

The respondents filed a writ petition before the Delhi High Court challenging the cancellation. By judgment dated 14-02-2013 (2013 SCC OnLine Del 625) the High Court quashed the cancellation of NIT 21 and the subsequent NIT 24, directing the Corporation to process the respondents’ original bids.

The Corporation appealed to the Supreme Court, leading to the present decision.

Legal Issues Presented

  1. Whether the Corporation’s decision to cancel NIT 21 and issue a fresh NIT 24 was arbitrary, unreasonable or violative of Article 14 of the Constitution of India.
  2. Whether the Delhi High Court erred in setting aside the cancellation and directing the Corporation to process the respondents’ earlier bids.

Arguments of the Parties

Appellant Corporation

  • The cancellation was bona fide, aimed at protecting public funds by securing more reasonable rates in line with other work orders issued in the same financial year.
  • Seventy-two comparable contracts had been awarded at substantially lower rates, indicating the respondents’ bids were excessive.
  • CVC Guidelines and the Corporation’s internal financial checks obligated it to ensure price reasonableness; re-tendering was therefore justified.
  • The High Court wrongly presumed that a “justification of rates” document existed; none was prepared because the offered rates were already deemed unreasonably high.
  • Courts should not sit in appeal over commercial decisions of public bodies absent mala fides or violation of Article 14, neither of which was found.

Respondents (Contractors)

  • The claim that their bids were high is “false and misleading”; rates were quoted below benchmarks derived from Delhi Schedule of Rates (DSR) 2007/2012.
  • The Corporation’s own circulars (30-08-2012 and 02-01-2013) allowed substantial escalation over DSR, and respondents’ rates were below those escalated figures.
  • Prior low-priced contracts cited by the Corporation were abnormally low and could not serve as a valid comparison.
  • The High Court correctly found the cancellation process faulty and restored their entitlement to have bids considered.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Supreme Court noted that the High Court quashed the cancellation despite finding no mala fides on the Corporation’s part. It identified several errors in the High Court’s approach:

  • The Corporation, as custodian of public money, is entitled to reassess tenders to ensure reasonable pricing; this is consistent with CVC Guidelines and internal financial checks.
  • Evidence showed 72 comparable contracts in 2012-2013 were awarded at lower rates, supporting the Corporation’s view that respondents’ bids were excessive.
  • The High Court mistakenly assumed a “justification of rates” had been prepared and ignored the Corporation’s explanation that none was necessary because rates were patently high.
  • Government entities may refuse even the lowest bid provided the action is not arbitrary or discriminatory; Article 14 was not violated as no favoritism was found.
  • Judicial review should not substitute judicial opinion for commercial discretion unless illegality, irrationality or procedural impropriety is shown, which was absent here.

Consequently, the Supreme Court concluded that the High Court had overstepped its limited role in tender matters and failed to give due weight to the Corporation’s fiduciary duty to protect public funds.

Holding and Implications

The civil appeal is allowed. The Supreme Court set aside the Delhi High Court’s judgment, restored the cancellation of NIT 21 and validated NIT 24 dated 13-12-2012. Respondents are permitted to participate in the re-tender, and the Corporation may process all bids in accordance with law.

Implications: The decision reinstates the Corporation’s discretion to cancel and re-issue tenders for bona fide fiscal reasons. The ruling primarily affects the parties; it does not lay down new precedent but re-affirms established principles on judicial deference to administrative decisions in tender matters.

Show all summary ...

V. Gopala Gowda, J.— Leave granted. This civil appeal is directed against the impugned judgment and order dated 14-2-2013 passed by the High Court of Delhi at New Delhi in Ravinder Kumar & Ors…. S v. South Delhi Municipal Corporation 2013 SCC OnLine Del 625 whereby it has set aside the decision of the appellant Corporation dated 30-11-2012 regarding cancellation of the earlier tender notice whereunder both the respondents were declared successful and it has also quashed the appellant Corporation's subsequent e-tender process carried out in pursuance of Tender Notice No. 24 dated 13-12-2012. Further, the High Court has directed the appellant Corporation to process the bids submitted by both the respondents in accordance with law in pursuance of Notice Inviting Tender No. 21 dated 15-11-2012. The correctness of the impugned judgment and order is challenged in this appeal as the appellant Corporation is aggrieved of the said judgment and order of the High Court.

2. The necessary brief facts are stated hereunder to appreciate the rival legal contentions urged on behalf of the parties: the appellant is South Delhi Municipal Corporation and the respondents are registered civil contractors with the appellant authorities and stated to have executed several works of the Corporation in the past. The appellant Corporation in its area invited tenders relating to 26 works to be executed against NIT No. 21/EE(MZ-WZ)-II/TC/2012-2013 dated 15-11-2012. The last date for bid preparation and its submission was 26-11-2012 up to 3.00 p.m. and the opening of the financial bids was scheduled on 28-11-2012, but the date was extended to 29-11-2012 as 28-11-2012 was declared a holiday on account of “Guru Nanak Birthday”.

3. On 29-11-2012, when the financial bids were opened, both the respondents were declared successful being the lowest bidder in respect of 16 works. There were only five bidders who participated in the tender process. Both the respondents being successful bidders approached the appellant Corporation for issuance of work order against the works for which they were declared successful. The Executive Engineer of the appellant Corporation orally informed the respondents about the cancellation of the entire tender due to non-submission of draft by some of the bidders (containing the tender cost and earnest money) required to be filed along with the tender. Dissatisfied with the oral information about the cancellation process the respondents insisted for written intimation regarding the same.

4. On the respondents' insistence the appellant Corporation issued a corrigendum dated 30-11-2012 which stated that the tender was being cancelled due to administrative reasons.

5. The respondents then sent a legal notice dated 13-12-2012 to the appellant Corporation but they did not receive any reply to the same. However, on the same day the appellant Corporation issued a fresh NIT No. 24 EE-(M-WZ)-U/TC/2012-2013 dated 13-12-2012 inviting fresh bids from the eligible persons.

6. Being aggrieved by the cancellation of earlier tender i.e. NIT No. 21 dated 15-11-2012 vide corrigendum dated 30-11-2012, both the respondents filed a writ petition before the High Court of Delhi.

7. The High Court allowed the respondents' writ petition holding that the process adopted by the appellant Corporation in coming to the conclusion that the rates offered were high was faulty. The High Court on that basis set aside and quashed the decision of the appellant Corporation dated 30-11-2012, regarding cancellation of its earlier tender and directed the appellant Corporation to process the bids submitted by both the respondents in accordance with law in pursuance of NIT No. 21 dated 15-11-2012. It also quashed the subsequent tender process pursuant to NIT No. 24 dated 13-12-2012. Hence, this appeal is filed by the appellant Corporation challenging the said order on several grounds.

8. Mr Gaurang Kanth, learned counsel for the appellant Corporation contended that the High Court has erred in quashing the decision of the appellant Corporation regarding cancellation of earlier tender even when it did not find any mala fide intention on the part of the appellant to favour someone. He urged that the High Court has failed to appreciate the fact that the said decision was taken by the appellant Corporation to serve the best interest of the Corporation with a bona fide intention.

9. He further contended that the High Court has erroneously ignored the fact that in the same financial year i.e. 2012-2013, the appellant Corporation issued 72 other work orders for similar works in the adjacent areas of the Corporation and all of them were issued at much lower rates than the rates quoted by both the respondents. He urged that before the issuance of a particular contract, the internal system for financial check by the department concerned of the appellant Corporation has to justify the reasonableness of the rates quoted by the bidders by comparing the same with rates of other similar works awarded in the recent past by the appellant Corporation.

10. He further submitted that CVC Guidelines on the subject ensure that the Corporation gets the best price for execution of works at the same time ensuring transparency in awarding contracts in favour of successful bidders. It was further urged by him that the appellant Corporation had acted bona fide to get the best price for execution of works and to protect the public money, by cancelling the entire tender process and inviting fresh bids by another tender notice dated 13-12-2012.

11. It was further contended by him that the High Court has proceeded on the wrong assumption that the appellant Corporation had prepared a justification of rates in connection with the said tender. As no such justification of rates was prepared by the appellant Corporation reason being the rates received from both the respondents were much higher than the rates at which similar works were awarded in favour of successful bidders by the appellant Corporation in the recent past. The High Court has thus proceeded on a wrong basis to quash the decision of the appellant Corporation regarding the cancellation of its earlier tender and also the subsequent tender dated 13-12-2012 issued afresh for the same works. This decision of the High Court is erroneous in law and is liable to be set aside in this appeal.

12. It was further argued by him that the High Court while passing the judgment and order has erroneously ignored the fact that the State Government is the guardian of public finance and the right to refuse the lowest or any other tender submitted to it is vested with the State Government, provided Article 14 of the Constitution of India is not violated in that process. He urged that the appellant Corporation had not violated the said provision of the Constitution of India by cancelling its earlier tender vide corrigendum dated 30-11-2012 and issuing tender notice dated 13-12-2012 for the same works in the public interest. The appellant Corporation had taken the decision regarding cancellation of the tender in the best interest of the Corporation to get the best price and also to save public money. Therefore, the same could not be termed as an arbitrary decision of the appellant Corporation.

13. It was further contended by the learned counsel that the High Court has failed to appreciate the fact that the courts do not sit in appeal over the commercial decisions taken by the statutory local self government in the best interest of public.

14. On the other hand, Ms Anusuya Salwan, learned counsel appearing on behalf of both the respondents contended that the appellant Corporation's stand that the earlier tender was cancelled as the rates received by them pursuant to the said tender were found to be higher than the rates at which similar works were awarded by the appellant Corporation in the Corporation area in the recent past is absolutely false and misleading. In this regard, she submitted that bids were invited by the appellant Corporation on the basis of tender rates fixed and the contractors are required to quote their rates below or above on percentage basis. After a bid is made by the contractor, the tender accepting authority satisfies itself about the reasonableness of the rates offered by the contractor in his bid before acceptance of the tender in his name. At this stage the reasonableness of the rates is assessed on the basis of justified rates. Justification of rates offered by the bidders is prepared by the appellant Corporation on the basis of the Delhi Schedule of Rates, 2007 and the Delhi Schedule of Rates, 2012. In connection with the above she pointed out that the Delhi Schedule of Rates, for each item of work prepared on the basis of CPWD rates on the basis of which works can be executed by the contractor and in case the rates on which works are allotted are very much below the said Delhi Schedule of Rates, there are chances of the quality of the work to be executed by the contractor getting compromised.

15. She further submitted that the appellant Corporation itself has issued two Circulars dated 30-8-2012 and 2-1-2013. The first Circular dated 30-8-2012 provides for adoption of an escalation @ 61% qua 2007 rates and 8% qua 2012 rates, whereas the second Circular dated 2-1-2013 provides for the adoption of escalation @ 70% qua 2007 rates and 14% qua 2012 rates. She further urged that the rates quoted by both the respondents were much below the rates in the said circulars and therefore, the contention of the appellant Corporation that they cancelled the said tender on the ground of rates offered by both the respondents being high is absolutely misconceived and liable to be outrightly rejected.

16. She further contended that the plea of the appellant Corporation that the rates quoted by the respondents were much higher than the rates at which similar works were awarded in favour of successful bidders in the recent past is also not tenable in law as the tenders issued for similar works were issued at abnormally low rates and the same could not be a benchmark for comparison with the rates offered by both the respondents in relation to the tender for the works which have been cancelled by the appellant Corporation. She urged that the High Court was right in passing the judgment in favour of the respondents for reasons that were valid and cogent. Hence, this Court need not exercise its appellate jurisdiction to annul the impugned order as there is no miscarriage of justice in the case on hand. She therefore, prayed for the dismissal of this appeal.

17. With reference to the above rival legal contentions urged on behalf of the parties, this Court has carefully examined the correctness of the findings and reasons recorded in the impugned judgment and order 2013 SCC OnLine Del 625 passed by the High Court. The High Court has quashed the decision of the appellant Corporation dated 30-11-2012, regarding cancellation of its earlier tender without there being any finding to the effect of any mala fide intention on the part of the appellant in taking decision to cancel its earlier tender notice with a view to favour someone.

18. By a careful examination of the impugned judgment and order 2013 SCC OnLine Del 625 of the High Court and the facts of the case on hand, the following aspects would emerge:

18.1. The High Court has failed to appreciate that the appellant Corporation's decision of cancelling its earlier tender notice vide corrigendum dated 30-11-2012 was taken with a bona fide intention to serve the best interest of the Corporation ensuring that only a reasonable price is paid to the successful contractors for the works executed in the area as the money which it spends on getting such works done is public money.

18.2. The High Court has not appreciated the fact that for the same financial year i.e. 2012-2013 the department concerned of the appellant Corporation has issued 72 other work orders for similar works in the adjacent areas of the Corporation and all of them were issued for much lower rates than the rates offered by both the respondents.

18.3. Further, the High Court has conveniently ignored the very relevant aspect of the case, namely, that the appellant Corporation, before issuance of a particular tender notice, is required to satisfy itself about the reasonableness of the rates quoted by the bidders keeping in view the prevalent market rates in the Corporation area. The internal system for financial check by the department concerned of the appellant Corporation justifies the reasonableness of the rates offered by the bidders by comparing them with the rates at which other similar works were awarded by the appellant Corporation in the recent past in favour of successful bidders. For the aforesaid valid reason, the appellant Corporation being the custodian of public money, with bona fide intention to get the best price, has cancelled its earlier tender notice referred to supra and invited fresh bids by issuing another tender notice dated 13-12-2012.

18.4. Further, the High Court has not noticed another important aspect of the case, namely, that there are CVC Guidelines to ensure that the Corporation gets the best price for the execution of the works as per the said guidelines and to ensure the transparency in awarding the contracts in favour of successful bidders in the tender process the appellant Corporation decided to cancel its earlier tender notice and a subsequent tender notice dated 13-12-2012 was issued afresh by it for getting the same works done through successful contractors.

18.5. The High Court has erroneously quashed the Corporation's decision of cancelling its earlier tender notice vide corrigendum dated 30-11-2012 on the wrong assumption that the department concerned of the appellant Corporation has prepared the justification of rates but in reality the same were never prepared by the department concerned of the appellant Corporation as the rates received from both the respondents were much higher than the rates at which similar works were awarded in favour of the successful bidders by it in the recent past.

18.6. Further, the High Court has failed to consider another important fact that the Government being guardian of public finance it has the right to refuse the lowest or any other tender bid or bids submitted by the bidders to it provided its decision is neither arbitrary nor unreasonable as it amounts to violation of Article 14 of the Constitution of India. The appellant Corporation's decision in cancelling its earlier tender is not in violation of Article 14 of the Constitution of India, as the High Court did not find any mala fide intention on the part of the appellant Corporation to favour someone in taking such decision. The appellant Corporation's decision in cancelling the earlier tender notice vide corrigendum dated 30-11-2012 and then issuing a subsequent tender notice dated 13-12-2012 inviting fresh bids from eligible persons for the same works was with a bona fide intention to get better and reasonable rates from the bidders for the execution of the works and not to show favouritism in favour of any bidder.

18.7. The High Court has also failed to appreciate the relevant fact that the officials of the appellant Corporation made proper analysis about the rates quoted by both the respondents as the same were higher than the usual market tendency and accordingly, they decided to cancel the entire tender process.

19. A careful reading of the impugned judgment and order would show that none of the aforesaid aspects have been borne in mind by the High Court and it has failed to appreciate the same in a proper perspective while exercising its judicial review power. The High Court has erred in quashing the decision of the appellant Corporation regarding the cancellation of its earlier tender notice and also the subsequent tender notice issued afresh by it on 13-12-2012 for the same works.

20. For the reasons stated above, the High Court has failed to see that the appellant Corporation adopted a fair and transparent method by inviting the bids for the re-tender notice issued by it. The High Court has not found any mala fide intention on the part of the appellant Corporation in inviting the fresh bids after taking the decision to cancel its earlier tender notice. The appellant Corporation, being the custodian of public finance, took its decision objectively with a bona fide intention to serve the best interest of the public in general. Thus, for the foregoing reasons, the appellant Corporation has not committed any wrong in cancelling its earlier tender notice and issuing subsequent tender notice afresh inviting bids from the eligible contractors.

21. The decision of the High Court in quashing the appellant Corporation's decision of cancelling the earlier tender vide corrigendum dated 30-11-2012 and also the subsequent e-tender process carried out by it pursuant to Notice No. 24 dated 13-12-2012 is vitiated in law and therefore, the same is liable to be set aside.

22. For the reasons stated supra, the submissions made on behalf of the appellant Corporation are well founded and the same must be accepted by this Court. This civil appeal of the appellant Corporation must succeed and deserves to be allowed. Accordingly, we pass the following order:

22.1. The civil appeal is allowed.

22.2. We set aside the impugned judgment and order of the High Court passed in Ravinder Kumar & Ors…. S v. South Delhi Municipal Corporation 2013 SCC OnLine Del 625 quashing the decision of the Corporation to cancel its earlier tender notice vide corrigendum dated 30-11-2012 and re-tender Notification dated 13-12-2012 issued by the appellant Corporation inviting bids afresh for the works notified therein. We restore the above re-tender notice and opportunity is given to both the respondents to submit their tender and the tender inviting authority of the Corporation can proceed further in processing the bids after proper evaluation of the same without any further delay. No order as to costs.