Kss Kssiipl Consortium Through Its Constituted Attorney Devendra Kumar v. Gail (India) Limited .

Supreme Court Of India
Feb 12, 2015
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The petitioner is a consortium comprising M/s JSC OGCC KazStroyService (incorporated in Kazakhstan) and KazStroyService Infrastructure India (P) Ltd. (incorporated under the Companies Act, 1956). The consortium was formed on 1 July 2010 to execute Pipeline Laying and Terminal Works for the Dabhol-Bangalore Pipeline Project floated by the respondent. The overall project was divided into ten “Spreads” (A–J). Arbitration Petition (Civil) No. 36 of 2014 concerns Spread “J”, while Arbitration Petition (Civil) No. 38 of 2014 concerns Spread “D”.

After detailed letters of acceptance were issued on 13 December 2010, the petitioner mobilised resources. It later alleged that delays occurred because the respondent failed to provide construction rights, engineering inputs, consistent drawings, and timely free-issue materials. Claiming entitlement to (i) extended stay compensation and (ii) payment for additional works, the petitioner lodged monetary claims on 4 January 2013 and 5 July 2013. The respondent rejected the claims. Conciliation under Clause 40.2 of the General Conditions of Contract (GCC) was also refused, prompting the petitioner to invoke the arbitration clause (Clause 59). When the respondent remained unresponsive, the petitioner filed the present applications under Section 11(6) of the Arbitration and Conciliation Act, 1996 for appointment of a sole arbitrator.

Legal Issues Presented

  1. Whether the petitioner’s claim for “extended stay compensation” is arbitrable in light of Clauses 42.1.2 and 42.1.4 of the Special Conditions of Contract (SCC) and Clause 12 of the detailed letters of acceptance, given that the petitioner had quoted “Nil” for that compensation.
  2. Whether the petitioner’s claim for payment for additional works is barred from arbitration by Clauses 91.1 and 91.2 of the GCC, which declare the Engineer-in-Charge’s decision “final and binding.”
  3. Consequent to the above, whether the Court should exercise its power under Section 11(6) of the Arbitration and Conciliation Act, 1996 to appoint a sole arbitrator.

Arguments of the Parties

Petitioner’s Arguments

  • The respondent’s failure to provide construction rights, work fronts, engineering inputs, and timely materials caused delays attributable solely to the respondent.
  • Under Clause 42 of the SCC (read with Clause 12 of the letters of acceptance) the petitioner is entitled to extended stay compensation caused by these delays.
  • Additional works were undertaken during contract execution, entitling the petitioner to further payment.
  • The respondent’s rejection of conciliation and failure to appoint an arbitrator justify recourse to the Court under Section 11(6).

Respondent’s Arguments

  • Extended stay compensation is not payable because the petitioner quoted “Nil” for that head in the priced bid. Clauses 42.1.2 and 42.1.4 of the SCC, reinforced by Clause 12 of the letters of acceptance, therefore exclude any such claim from arbitration.
  • Claims for additional works are non-arbitrable under Clauses 91.1 and 91.2 of the GCC; the Engineer-in-Charge has already rejected the claims and his decision is contractually “final and binding.”

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court noted that, under Section 11(6) of the Arbitration and Conciliation Act, it must first determine whether an arbitrable dispute exists.

Extended stay compensation: The petitioner admittedly entered “Nil” against the relevant item in its bid. Clauses 42.1.2 and 42.1.4 of the SCC expressly provide that if no rate is indicated, it will be presumed that no compensation is payable. Clause 12 of the letters of acceptance reiterated this position. By voluntarily quoting “Nil,” the petitioner had consciously waived any future entitlement. Consequently, no arbitrable dispute arises on this head.

Payment for additional works: While Clauses 91.1 and 91.2 of the GCC state that the Engineer-in-Charge’s decision is final, the Court held that contractual finality cannot oust the arbitration clause altogether. The justifiability of such a decision must remain subject to independent adjudication. Therefore, a live arbitrable dispute exists regarding payment for additional works.

Holding and Implications

ORDER: The Court appointed Shri Justice M. M. Kumar, Chief Justice (Retd.), Jammu & Kashmir High Court, as the sole arbitrator to adjudicate the petitioner’s claims for payment of additional works under both contracts. The petitions were ALLOWED IN PART; the claim for extended stay compensation was excluded from arbitration.

Implications: The decision compels the parties to arbitrate the dispute concerning additional works while conclusively barring the extended stay compensation claim at the threshold. It clarifies that contractual clauses declaring decisions “final” do not automatically preclude arbitration when an arbitration clause exists, but a party’s express waiver (as in the “Nil” quotation) can render a claim non-arbitrable.

Show all summary ...

Judgment

1. Both these applications under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Arbitration Act”) have been filed seeking appointment of a sole arbitrator to go into the disputes and differences that the petitioner claims to have arisen out of two separate contract agreements entered into by and between the parties.

2. The facts in brief may be noted at the outset. The petitioner is a consortium of two companies i.e M/s JSC OGCC KazStroyService, a company incorporated under the laws of the Republic of Kazakhstan and KazStroyService Infrastructure India (P) Ltd. incorporated under the Companies Act, 1956. The said consortium has been formed by an agreement dated 1-7-2010 for the purposes of executing a contract that was to be awarded by the respondent for Pipeline Laying and Terminal Works for Dabhol-Bangalore Pipeline Project.

3. According to the petitioner, the respondent had floated a tender for the said project in the year 2010 and the entire work was divided in 10 Spreads (A, B, C, D, E, F, G, H, I, J). While Arbitration Petition (Civil) No. 36 of 2014 pertains to the award of work for Spread ‘J’, Arbitration Petition (Civil) No. 38 of 2014 relates to the work awarded for Spread ‘D’.

4. Pursuant to the bid(s) made by the petitioner, detailed letter(s) of acceptance was issued by the respondent on 13-12-2010. According to the petitioner though in terms of the contracts it had mobilised its men and machinery, the work got jeopardised/frustrated as the respondent did not make available to the petitioner the construction right of use and permits in terms of Clause 28 of the Special Conditions of Contract (hereinafter referred to as “SCC”). According to the petitioner, the respondent did not have the necessary work fronts with respect to SV Station work. Furthermore, the petitioner has alleged that the respondent failed to provide necessary engineering inputs. Besides, there were frequent modifications with respect to drawings, extra work and delays in providing free issue materials. All these led to substantial delays in the execution of the works, such delay being attributable solely to the respondent.

5. According to the petitioner, on account of the delays due to the aforesaid reasons, the petitioner became entitled for extended stay compensation in terms of Clause 42 of SCC read with Clause 12 of the detailed letter of acceptance. Apart from extended stay compensation, the petitioner claims to be entitled for payment for additional works undertaken during the course of execution of the contracts. On 4-1-2013 and 5-7-2013, the petitioner submitted its claim to the respondent for Rs 34,70,11,907 (Rupees thirty-four crore seventy lakhs eleven thousand nine hundred and seven only) [in Arbitration Petition (Civil) No. 36 of 2014] and for Rs 1,79,23,83,208 (Rupees one arab seventy-nine crore twenty-three lakhs eighty-three thousand two hundred and eight only) [in Arbitration Petition (Civil) No. 38 of 2014], respectively. The petitioner alleges that the respondent rejected the said claims which was not acceptable to the petitioner. The petitioner, thereafter, invoked Clause 40.2 of the General Conditions of Contract which provides for conciliation. As the petitioner's proposal for conciliation was rejected by the respondent, the petitioner had no option but to invoke the arbitration clause (Clause 59) and seek appointment of a sole arbitrator in respect of the disputes arising from each of the two agreements. The said demand was repeated in several communications which were not responded to. The petitioner, therefore, has lodged the present applications under Section 11(6) of the Arbitration Act for the reliefs earlier noticed.

6. The claims made by the petitioner have been resisted by the respondent by filing separate counter-affidavits in both the cases. A reading of the affidavits filed by the respondent indicate that insofar as the claim for extended stay compensation is concerned, the respondent contend that the said claim does not give rise to any arbitrable issue inasmuch as under Clause 42.1.1 the bidder is required to mention the rate for extended stay compensation per month in the “Priced Part”. Under Clause 42.1.2 in case the bidder did not indicate such rate it is to be presumed that no extended stay compensation is required to be paid. Under Clause 42.1.4 it was expressly mentioned that “Bidder to note that in case they don't indicate the rate for extended stay compensation as per pro forma, provisions of Clause 42.0 will not be applicable to them”. According to the respondent in the relevant pro forma relating to “Compensation for extended stay”, the petitioner had mentioned/quoted “Nil”. Thus, according to Clauses 42.1.2 and 42.1.4, no extended stay compensation is required to be paid to the petitioner. The above position was also expressly stated in Clause 12 of the detailed letter of acceptance dated 13-12-2010, which is in the following terms:

“12.0 Compensation for extended stay.—Extended stay compensation is not applicable and shall not be payable to the contractor as per Clause 42.0 of the Special Conditions of Contract.”

7. According to the respondent, the aforesaid Clause 12.0 was further amplified in Annexure 1 to the said detailed letter of acceptance which was not placed before the Court though the detailed letter of acceptance dated 13-12-2010 formed a part of the petitions filed by the petitioner.

8. Insofar as the claim of payments for additional works is concerned, according to the respondent, Clause 91.0 of GCC deals with such claims. Clauses 91.1 and 91.2 contemplate that such claims will be verified by the Engineer-in-charge whose decision will be final. The respondent further states that the claims made by the petitioner for additional costs had been rejected by the Engineer-in-charge and in terms of Clause 91.2 of GCC such a decision(s) must be construed to be final and binding between the parties and therefore would stand excluded from arbitration.

9. There can be no manner of doubt that before exercising the power under Section 11(6) of the Arbitration Act to make appointment of an arbitrator the Court will have to decide on the existence of an arbitrable dispute/enforceable claim by and between the parties to the contract. The existence of a claim and denial thereof giving rise to a dispute is required to be determined on the basis of what the parties had agreed upon as embodied in the terms of the contract and only for the purpose of a decision on the question of arbitrability and nothing beyond. It is from the aforesaid standpoint that the issues raised in the present proceedings will have to be considered.

10. Clause 42.0 deals with “Compensation for extended stay”. Under Clause 42.1.1 the contractor is required to mention the rate for extended stay of compensation in the event the contract is to be prolonged/extended beyond the contemplated date of completion. Clauses 42.1.2 and 42.1.4 of SCC contemplate that in the event the contractor/bidder does not indicate the rate of extended stay, it will be presumed that no extended stay compensation is required to be paid.

11. In the present case, admittedly, the petitioner had quoted “Nil” against compensation for extended stay in its bid. If that is so, it must be understood that the petitioner had agreed to forego its claim to extended stay compensation in the event the period of performance of the contract is to be extended as had happened in the present case. This position was conveyed to the petitioner by the letter of acceptance dated 13-12-2010. The petitioner did not raise any objection on the aforesaid score. If the petitioner had voluntarily and consciously agreed to the above situation, it will be difficult to accept the contrary position that has sought to be now adopted by seeking to claim extended stay compensation which was earlier agreed to be foregone. It must therefore be held that the claim against the aforesaid head i.e “extended stay compensation” does not give rise to an arbitrable dispute so as to permit/require reference to arbitration under Clause 59.

12. The second issue i.e claim for payment of additional works however would stand on a different footing. Clauses 91.1 and 91.2 contemplate the making/raising of claims by the contractor for additional works and consideration thereof by the Engineer-in-chief. The decision of the Engineer-in-chief is final and binding. The finality attached to such a decision cannot be a unilateral act beyond the pale of further scrutiny. Such a view would negate the arbitration clause in the agreement. Justifiability of such a decision though stated to be final, must be subject to a process of enquiry/adjudication which the parties in the present case have agreed would be by way of arbitration. The objections raised by the respondent on the aforesaid score, therefore, does not commend to the Court for acceptance and is hereby rejected.

13. Accordingly, the claims made by the petitioner for payment of additional works under both the contracts are referred to arbitration by Shri Justice M.M Kumar, Chief Justice (Retd.), the Jammu and Kashmir High Court, who is hereby appointed as the sole arbitrator. The learned sole arbitrator is requested to enter upon the reference and conclude the same at an early date. The terms of appointment of the sole arbitrator as well as the venue of arbitration will be decided by the parties in consultation with the learned arbitrator.

14. Consequently and in the light of the above, the arbitration petitions are allowed to the extent indicated above.