Construction And Design Services v. Delhi Development Authority .

Supreme Court Of India
Feb 4, 2015
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The Delhi Development Authority (DDA) awarded a contract dated 4-10-1995 to the appellant, Construction & Design Services, U.P. Jal Nigam, for construction of a sewerage pumping station at Kondli-Gharoli, Delhi. Clause 2 of the agreement permitted the Superintending Engineer to levy compensation of up to 10% of the estimated cost for every day of delay, subject to a ceiling of 10% of the project cost.

The contractor failed to complete the work and the contract was terminated on 17-9-1999. On 21-7-1999 the Superintending Engineer imposed compensation of ₹20,86,446 under Clause 2. DDA filed Suit No. 1311/2002 in the Delhi High Court to recover this amount with interest.

The learned Single Judge dismissed the suit, holding that time had not been treated as the essence of the contract and the stipulated amount was penal in nature. On appeal, a Division Bench reversed the decision and decreed the suit for the full amount with interest @ 9% p.a. The appellant’s review petition was dismissed. The contractor then appealed to the Supreme Court, depositing the decretal amount as directed.

Legal Issues Presented

  1. Whether, in the absence of specific proof of actual loss, the entire sum stipulated as liquidated damages under Clause 2 can be treated as genuine pre-estimated compensation or is liable to be reduced as a penalty under Section 74 of the Indian Contract Act, 1872.
  2. On whom lies the burden of proving that the amount stipulated for breach is in the nature of a penalty—the party committing the breach or the party seeking to enforce the clause.

Arguments of the Parties

Appellant's Arguments

  • Clause 2 specifies only the maximum liability (10% of estimated cost); it does not automatically render the entire 10% a reasonable estimate of loss.
  • DDA led no evidence of actual loss or of additional expenditure on an alternative contractor; accordingly, only a portion of the amount, if any, could be considered compensatory.
  • The Division Bench misapplied ONGC v. Saw Pipes because that decision concerned a fixed sum acknowledged as a genuine estimate, unlike the present “up to 10%” provision.

Respondent's Arguments

  • Before imposing compensation, notice was given to the contractor; on his failure to respond, the Superintending Engineer reasonably determined the entire 10% as payable.
  • Delay in completing a public-utility project like a sewage pumping station inherently causes loss—environmental degradation and interest on blocked capital—which need not be proved in figures.
  • The burden was on the contractor to prove that no or lesser loss was suffered, which he failed to discharge.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Arosan Enterprises Ltd. v. Union of India (1999) 9 SCC 449 Extension of time may show that time was not of the essence of the contract. Single Judge relied on it to conclude that DDA had not treated time as essential.
Fateh Chand v. Balkishan Dass, AIR 1963 SC 1405 Section 74: penalty clauses are unenforceable beyond reasonable compensation. Single Judge invoked it to label Clause 2 as penal in the absence of proof of loss.
Maula Bux v. Union of India (1969) 2 SCC 554 Burden lies on claimant to justify liquidated damages; court must award reasonable compensation. Supported the Single Judge’s conclusion that DDA had not shown basis for the amount claimed.
M.L. Devender Singh v. Syed Khaja (1973) 2 SCC 515 Reiterated Fateh Chand principles on penalty and reasonable compensation. Cited by Single Judge for the same proposition.
P. D’Souza v. Shondrilo Naidu (2004) 6 SCC 649 Section 74 applies even when no actual loss is proved; only reasonable sum recoverable. Referenced by Single Judge in treating Clause 2 as penal.
ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 If a stipulated sum is a genuine pre-estimate of loss, the claimant need not prove actual damage; burden shifts to breaching party to disprove loss. Division Bench—and later the Supreme Court—applied it to hold that delay in a public-utility project justifies compensation without exact proof of loss.

Court's Reasoning and Analysis

The Supreme Court accepted that delay in constructing a sewage pumping station—a public-utility project—inevitably causes loss through environmental degradation and interest on blocked capital. Therefore, some compensation was warranted even without precise proof of damages. Referring to Saw Pipes, the Court observed that:

  • When loss is difficult to quantify, a pre-estimated amount may be accepted unless shown to be penal.
  • The burden to establish that the amount is a penalty lies on the party in breach.

However, the clause did not stipulate a fixed sum; it only set an upper limit of 10% subject to the Superintending Engineer’s discretion. Neither party produced evidence on the quantum of actual loss. In such circumstances, the Court exercised its power under Section 74 to award “reasonable compensation” on a “guesswork” basis. It concluded that awarding the entire 10% would be excessive and that one-half of the imposed amount represented a fair estimate of probable loss.

Holding and Implications

PARTLY ALLOWED. The decree is modified: DDA is entitled to half of the claimed ₹20,86,446, with pendente lite and future interest at 9% p.a. The respondent may withdraw that portion from the amount deposited in court; the balance is to be returned to the appellant.

Implications: The judgment reaffirms that a liquidated-damages clause fixing only an upper ceiling, absent evidence of calibrated estimation, may be pruned by the court to award reasonable compensation. The burden remains on the breaching party to disprove loss, but the claimant may still receive less than the ceiling if the court finds the stipulated maximum excessive. No new legal principle is created, but the decision illustrates calibrated application of Sections 73 and 74 in public-utility construction contracts.

Show all summary ...

Adarsh Kumar Goel, J.— Leave granted. These appeals have been preferred against the final judgment and order dated 10-2-2012 in DDA v. Construction & Design Services, U.P Jal Nigam U.P Jal Nigam, RFA (OS) No. 35 of 2010, decided on 10-2-2012 (Del) and dated 1-6-2012 in DDA v. Construction & Design Services, U.P Jal Nigam Review Petition No. 369 of 2012 in RFA (OS) No. 35 of 2010, order dated 1-6-2012 (Del) passed by the High Court of Delhi at New Delhi.

2. The question raised for our consideration is when and to what extent can the stipulated liquidated damages for breach of a contract be held to be in the nature of penalty in the absence of evidence of actual loss and to what extent the stipulation be taken to be the measure of compensation for the loss suffered even in the absence of specific evidence. The further question is whether burden of proving that the amount stipulated as damages for breach of contract was penalty is on the person committing breach.

3. The respondent, Delhi Development Authority, awarded a contract vide agreement dated 4-10-1995 to the appellant for constructing a sewerage pumping station at CGHS area at Kondli Gharoli at Delhi. Clause 2 in the agreement provided as follows:

“The contractor shall comply with the said time schedule. In the event of the contractor failing to comply with this condition, he shall be liable to pay as compensation an amount equal to one per cent or such smaller amount as the Superintending Engineer, Delhi Development Authority (whose decision shall be final) may decide on the said estimated cost of the whole work for everyday that the due quantity of work remains incomplete; provided always that the entire amount of compensation to be paid under the provisions of this clause shall not exceed ten per cent of the estimated cost of work as shown in the tender.”

4. Since the work proceeded at a slow pace and the appellant-defendant failed to complete the same, the contract was terminated on 17-9-1999. Under Clause 2 of the agreement, the Superintending Engineer of the respondent levied compensation of Rs 20,86,446 for delay in execution of the project by an order of penalty dated 21-7-1999 and called upon the appellant to deposit the same. The said order reads thus:

“The work was being executed by you at extremely slow pace. You had to complete the job by 7-1-1997. You had failed to complete the work even after expiry of two years six months after the stipulated date of completion. Despite the clear direction from the Hon'ble Supreme Court to expedite the work and complete the job by June 1999, you have failed to comply with the direction of the Court and have rather abandoned the work since 6-4-1999 and you failed to complete the work till date.
In exercise of the power conferred on me under Clause 2 of the agreement, I, R.C Kinger, the SE/CC-10.DDA decide and determine that you are liable to pay Rs 20,86,446 (Rs Twenty lakhs eighty-six thousand four hundred forty-six only) as and by way of compensation as stipulated in Clause 2 of the agreement.”

5. On failure of the appellant to respond to the above order, the respondent filed Suit No. 1311 of 2002 before the Delhi High Court for recovery of the said amount with interest. The appellant-defendant failed to contest the suit in spite of service but made an application raising objection to the maintainability of the suit on the ground that vide order dated 19-12-2001, a former Judge of the Delhi High Court had been appointed arbitrator to decide the disputes arising out of the contract. The said application was, however, dismissed on the ground that the matter in the suit was not within the purview of arbitration. The Court proceeded to decide the suit on merits.

6. The learned Single Judge dismissed U.P Jal Nigam, 2009 SCC OnLine Del 3762 , (2009) 165 DLT 208 the suit holding that the plaintiff had not treated the time fixed for performance of the contract as of essence and the compensation stipulated in Clause 2 of the agreement was in the nature of penalty. The basis for levy of compensation had not been indicated so as to determine whether the compensation claimed was reasonable. Reliance was placed on the judgment of this Court in Arosan Enterprises Ltd. v. Union of India (1999) 9 SCC 449 in support of the view that the time stipulated in the agreement was not treated to be of essence. It was further observed that since the claim for compensation was based on sole discretion and not on the basis of loss suffered, the same was in the nature of penalty and thus, the said Clause could not be enforced in view of Section 74 of the Contract Act as laid down in Fateh Chand v. Balkishan Dass AIR 1963 SC 1405 , (1964) 1 SCR 515, Maula Bux v. Union of India (1969) 2 SCC 554, M.L Devender Singh v. Syed Khaja (1973) 2 SCC 515, P. D'Souza v. Shondrilo Naidu (2004) 6 SCC 649 and ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 The learned Single Judge concluded as follows: (Construction & Design Services case U.P Jal Nigam, 2009 SCC OnLine Del 3762 , (2009) 165 DLT 208, SCC OnLine Del para 22)

“22. The Court is of opinion that the plaintiff having not treated the contract as of the essence, and having extended the time for performance on several occasions, cannot now fall back on a presumptive condition to impose the maximum compensation leviable; enforcement of such action would be giving effect to a penalty clause. As far as granting reasonable compensation is concerned, the plaintiff has not shown even the basis for levying the compensation that it did in this case. As said earlier, this aspect assumes significance, because the plaintiff was aware what extent of the contract was performed, as well as what was the exact extent of loss, in monetary terms, either by way of payment to another contractor, or the amount spent for completing the work. In the circumstances, the Court is of opinion that the relief sought cannot be granted.”

7. On appeal, the Division Bench reversed the view taken by the learned Single Judge. It was held that delay in a contract of construction of a public utility service could itself be a ground for compensation without proving the actual loss. Accordingly, the suit was decreed for payment of Rs 20,86,446 with pendente lite and future interest @ 9% per annum. It was observed:

“5. The respondent had been proceeded against ex parte at the trial and has chosen not to appear even before us. The evidence led by the appellant has remained unrebutted.
6. It would suffice to state that the observations of the Supreme Court in para 68 of the decision reported as ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 are squarely applicable in the instant case as per which delayed constructions such as completing construction of road or bridges within stipulated time would be difficult to be linked with actual losses suffered by the State and in such cases the pre-estimated damages envisaged in the contract have to be paid.
7. Now, a sewage pumping station is not something from which revenue would be generated by the State. It is a public utility service and has a role to play in maintaining or preserving clean environment. If sewage pumping stations are not set up, sewage would stagnate as cess pools in low lying areas would cause environmental degradation, both air and soil. That apart, in a delayed project, interest on blocked capital would obviously be a measure of damages.
8. The learned Single Judge has ignored as aforesaid and held that in the absence of proof of damages, compensation levied under Clause 2 cannot be recovered. The learned Single Judge is incorrect in view of the law declared by the Supreme Court (2003) 5 SCC 705 and thus we allow the appeal and set aside the impugned decree. The suit filed by the appellant is decreed in sum of Rs 20,86,446 with pendente lite and future interest @ 9% per annum from date of suit till realisation and the suit filed by the appellant is disposed of accordingly with costs all throughout.”

8. The appellant filed a review petition which was dismissed.

9. We have heard the learned counsel for the parties.

10. On 19-11-2012 notice was issued subject to the appellant depositing the entire decretal amount in this Court and by a subsequent order, the amount was directed to be kept in term deposit for a period of one year to enure for the benefit of the successful party. Accordingly, the amount of Rs 20,86,500 is said to have been deposited which has been kept in FDR which is going to mature on 8-2-2015.

11. The learned counsel for the appellant submitted that the Division Bench erred in holding that the entire amount of stipulated damages was genuine measure of compensation when instead of any fixed amount, only the maximum amount of compensation was stipulated. The contract in question only envisaged the upper limit of damages which could be claimed. It is submitted that the agreement quoted in the earlier part of the order clearly shows that what is stipulated is that the compensation shall not exceed 10% of the estimated cost and the amount to be recovered as compensation was required to be determined by the Superintending Engineer. The respondent-plaintiff has failed to show the actual amount of loss suffered in getting the work executed from any other contractor. In these circumstances, at best a part of it could be taken to be compensation and the remaining penalty. He submitted that the judgment of this Court in Saw Pipes Ltd. (2003) 5 SCC 705 relied upon by the High Court is distinguishable in the fact situation of the present case. Without determining that the stipulated compensation was reasonable, the maximum amount stipulated could not be treated as compensation.

12. The learned counsel for the respondent-plaintiff on the other hand submitted that even though in the order passed by the Superintending Engineer no specific basis has been shown, notice was duly issued to the appellant-defendant before determining the reasonable amount of compensation and claiming 10% of the project cost which was stipulated to be the maximum compensation, on account of delay in execution of the project. On failure of the appellant to respond, the entire amount has been rightly held to be the estimate of damages for the loss. Burden was on the defendant to show that no loss or lesser loss was suffered by the plaintiff.

13. We have given due consideration to the rival submissions.

14. There is no dispute that the appellant failed to execute the work of construction of sewerage pumping station within the stipulated or extended time. The said pumping station certainly was of public utility to maintain and preserve clean environment, absence of which could result in environmental degradation by stagnation of water in low lying areas. Delay also resulted in loss of interest on blocked capital as rightly observed in para 7 of the impugned judgment U.P Jal Nigam, RFA (OS) No. 35 of 2010, decided on 10-2-2012 (Del) of the High Court. In these circumstances, loss could be assumed, even without proof and burden was on the appellant who committed breach to show that no loss was caused by delay or that the amount stipulated as damages for breach of contract was in the nature of penalty. Even if technically the time was not of essence, it could not be presumed that delay was of no consequence. Thus, even if there is no specific evidence of loss suffered by the respondent-plaintiff, the observations in the order of the Division Bench that the project being a public utility project, the delay itself can be taken to have resulted in loss in the form of environmental degradation and loss of interest on the capital are not without any basis.

15. Once it is held that even in the absence of specific evidence, the respondent could be held to have suffered loss on account of breach of contract, and it is entitled to compensation to the extent of loss suffered, it is for the appellant to show that stipulated damages are by way of penalty. In a given case, when the highest limit is stipulated instead of a fixed sum, in the absence of evidence of loss, part of it can be held to be reasonable compensation and the remaining by way of penalty. The party complaining of breach can certainly be allowed reasonable compensation out of the said amount if not the entire amount. If the entire amount stipulated is genuine pre-estimate of loss, the actual loss need not be proved. Burden to prove that no loss was likely to be suffered is on the party committing breach, as already observed.

16. It is not necessary to refer to all the judgments on the point in view of categorical pronouncement of this Court in Saw Pipes (2003) 5 SCC 705, laying down as follows:

“64. It is apparent from the aforesaid reasoning recorded by the Arbitral Tribunal that it failed to consider Sections 73 and 74 of the Indian Contract Act and the ratio laid down in Fateh Chand case AIR 1963 SC 1405 , (1964) 1 SCR 515 wherein it is specifically held that jurisdiction of the court to award compensation in case of breach of contract is unqualified except as to the maximum stipulated; and compensation has to be reasonable. Under Section 73, when a contract has been broken, the party who suffers by such breach is entitled to receive compensation for any loss caused to him which the parties knew when they made the contract to be likely to result from the breach of it. This section is to be read with Section 74, which deals with penalty stipulated in the contract, inter alia (relevant for the present case) provides that when a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, the party complaining of breach is entitled, whether or not actual loss is proved to have been caused, thereby to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named. Section 74 emphasises that in case of breach of contract, the party complaining of the breach is entitled to receive reasonable compensation whether or not actual loss is proved to have been caused by such breach. Therefore, the emphasis is on reasonable compensation. If the compensation named in the contract is by way of penalty, consideration would be different and the party is only entitled to reasonable compensation for the loss suffered. But if the compensation named in the contract for such breach is genuine pre-estimate of loss which the parties knew when they made the contract to be likely to result from the breach of it, there is no question of proving such loss or such party is not required to lead evidence to prove actual loss suffered by him. Burden is on the other party to lead evidence for proving that no loss is likely to occur by such breach. Take for illustration: if the parties have agreed to purchase cotton bales and the same were only to be kept as a stock-in-trade. Such bales are not delivered on the due date and thereafter the bales are delivered beyond the stipulated time, hence there is breach of the contract. The question which would arise for consideration is — whether by such breach the party has suffered any loss. If the price of cotton bales fluctuated during that time, loss or gain could easily be proved. But if cotton bales are to be purchased for manufacturing yarn, consideration would be different.
***
67. Take for illustration construction of a road or a bridge. If there is delay in completing the construction of road or bridge within the stipulated time, then it would be difficult to prove how much loss is suffered by the society/State. Similarly, in the present case, delay took place in deployment of rigs and on that basis actual production of gas from platform B-121 had to be changed. It is undoubtedly true that the witness has stated that redeployment plan was made keeping in mind several constraints including shortage of casing pipes. The Arbitral Tribunal, therefore, took into consideration the aforesaid statement volunteered by the witness that shortage of casing pipes was only one of the several reasons and not the only reason which led to change in deployment of plan or redeployment of rigs Trident II platform B-121. In our view, in such a contract, it would be difficult to prove exact loss or damage which the parties suffer because of the breach thereof. In such a situation, if the parties have pre-estimated such loss after clear understanding, it would be totally unjustified to arrive at the conclusion that the party who has committed breach of the contract is not liable to pay compensation. It would be against the specific provisions of Sections 73 and 74 of the Contract Act, 1872. There was nothing on record that compensation contemplated by the parties was in any way unreasonable. It has been specifically mentioned that it was an agreed genuine pre-estimate of damages duly agreed by the parties. It was also mentioned that the liquidated damages are not by way of penalty. It was also provided in the contract that such damages are to be recovered by the purchaser from the bills for payment of the cost of material submitted by the contractor. No evidence is led by the claimant to establish that the stipulated condition was by way of penalty or the compensation contemplated was, in any way, unreasonable. There was no reason for the Tribunal not to rely upon the clear and unambiguous terms of agreement stipulating pre-estimate damages because of delay in supply of goods. Further, while extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages.”

17. Applying the above principle to the present case, it could certainly be presumed that delay in executing the work resulted in loss for which the respondent was entitled to reasonable compensation. Evidence of precise amount of loss may not be possible but in the absence of any evidence by the party committing breach that no loss was suffered by the party complaining of breach, the court has to proceed on guesswork as to the quantum of compensation to be allowed in the given circumstances. Since the respondent also could have led evidence to show the extent of higher amount paid for the work got done or produce any other specific material but it did not do so, we are of the view that it will be fair to award half of the amount claimed as reasonable compensation.

18. Accordingly, this appeal is partly allowed and the decree granted by the High Court is modified to the effect that the respondent-plaintiff is entitled to half of the amount claimed with rate of interest as awarded by the High Court. Out of the amount deposited in this Court, the respondent will be entitled to withdraw the said decretal amount and the appellant will be entitled to take back the remaining.

19. The appeals are disposed of accordingly.