- Bookmark
- Share
- CaseIQ
Fertilizer Corporation Of India Ltd., New Delhi v. I.D.I. Management (U. S.A) And Others
Factual and Procedural Background
This arbitration arose out of a contract dated 12-2-1964 between the Fertilizer Corporation of India (the Corporation) and Girdler Corporation (later C.I Girdler Inc.) for the erection and installation of a Methanol Plant at the Corporation's Trombay Division in Bombay. The plant was to produce 100 metric tons of Methanol per day and was supplied on a turn-key basis for 45 million rupees. The plant's performance was erratic and unsatisfactory, particularly due to failures in the Catalyst installed in the Reformer Furnace. After negotiations and a March 21, 1967 agreement (the March Agreement) defining outstanding disputes, the Corporation terminated the contract and took juridical possession of the plant.
Disputes were referred to arbitration as per the contract's arbitration clause. The Corporation and Contractor appointed arbitrators, who nominated Lord Devlin as Umpire. A three-member Tribunal was constituted, and hearings were held between 1971 and 1974. The Tribunal issued an interim award on August 21, 1973, and a final award on February 16, 1974, both decided by majority (Lord Devlin and J. Russell Wilson) with Mr. B. Sen dissenting.
The Corporation filed objections to the awards under Sections 30 and 33 of the Arbitration Act, 1940, which were dismissed by a learned Judge who made the awards a rule of the Court. The Corporation appealed against this order.
Legal Issues Presented
- Whether the majority arbitral awards disclose an error of law apparent on the face of the award.
- Whether the March Agreement of March 21, 1967 superseded the original contract and defined the rights and duties of the parties.
- Whether the dissenting note of the minority arbitrator can be considered as reasons for the majority awards.
- Whether the Corporation was entitled to damages for loss of production under Section 16 of the Sale of Goods Act and Section 73 of the Indian Contract Act.
- Whether the Court can interfere with the arbitral awards for lack of reasons given by the majority arbitrators.
- Whether the respondent is entitled to interest under Section 29 of the Arbitration Act and whether future interest can be awarded under Order 41, Rule 33 of the Code of Civil Procedure.
Arguments of the Parties
Corporation's Arguments
- The majority awards were flawed as they failed to consider the fundamental breach of the original contract, entitling the Corporation to damages for loss of production.
- The dissenting note of Mr. B. Sen should be examined to understand the reasons behind the majority awards.
- The original contract was not superseded by the March Agreement; thus, the Contractor remained bound to fulfill the original obligations.
- The Corporation sought future interest on the decretal amount and contended that Order 41, Rule 33, C.P.C. should be invoked to award such interest.
Contractor's Arguments
- The March Agreement constituted a full and final settlement superseding the original contract, thus barring claims for loss of production.
- The majority awards were valid despite being non-speaking and did not disclose any error of law on their face.
- The dissenting note of the minority arbitrator cannot be used to interpret or challenge the majority awards.
- The discretion to award future interest lies with the Court and cannot be overridden by invoking Order 41, Rule 33, C.P.C.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Holland and Couser v. City of Vancouver, (1959) 1 DLR (ed) 404 (Canada) | Majority awards prevail over dissenting opinions in arbitration. | Supported the principle that the dissenting arbitrator's reasons do not form part of the award and cannot be considered as reasons for the majority's decision. |
| Yarrows Ltd. v. C.N Steamship Co. Ltd., (1951) 2 DLR 204 (Canada) | Majority awards are binding; dissenting opinions are not part of the award. | Reinforced that only the majority arbitrators' awards are binding and dissenting opinions have no legal effect. |
| Union Of India v. A.L Rallia Ram, AIR 1963 SC 1685 | Arbitral awards should not be disturbed except for error of law apparent on the face of the award or misconduct. | Applied to uphold the majority awards as there was no error of law apparent on the face of the awards. |
| Jivrajbhai v. Chintamanrao Balaji, AIR 1965 SC 214 | Court cannot speculate on arbitrators' reasoning if reasons are not disclosed in the award. | Held that the Court cannot probe the mental process behind the awards and must accept them unless an error of law is apparent. |
| Bungo Steel Furniture (Pvt.) Ltd. v. Union of India, AIR 1967 SC 378 | Same as above regarding finality of arbitral awards and limited grounds for setting aside. | Supported the conclusion that the awards should stand unless clear error or misconduct is shown. |
| Upper Ganges Valley Electricity Supply Co. Ltd. v. U.P Electricity Board, AIR 1973 SC 683 | Finality of arbitral awards and scope of judicial review. | Reinforced the limited scope of judicial interference with arbitral awards. |
| N. Chellappan v. Secy., Kerala Electricity Board, AIR 1975 SC 230 | Errors in law or fact by arbitrators do not invalidate awards unless apparent on the face of the award. | Applied to uphold arbitral awards despite alleged errors in law or fact. |
| Rohtas Industries Ltd. v. Rohtas Industries' Union, AIR 1976 SC 425 | Judicial demolition of awards only for erroneous legal propositions stated in the award. | Supported refusal to set aside majority awards lacking erroneous legal propositions. |
| Champsey Bhara and Co. v. Jivraj Balloo Spinning and Weaving Co., AIR 1923 PC 66 | Arbitrators' interpretation of contracts is final unless tied down to an erroneous legal proposition. | Applied to hold that the tribunal's construction of the March Agreement was final and not subject to judicial interference. |
| Allen Berry and Co. Ltd. v. Union of India, AIR 1971 SC 696 | Contracts or clauses are incorporated in awards only if arbitrators explicitly base awards on them. | Held that general references to contracts in awards do not incorporate them; the majority awards here did not incorporate the March Agreement or other documents. |
| Rameshwar Prasad v. Shambehari Lal, AIR 1963 SC 1901 | Discretion in applying Order 41, Rule 33, C.P.C. to reopen final decrees only in exceptional cases. | Applied to reject the invocation of Order 41, Rule 33 to award future interest where no rights require readjustment. |
| Commissioner of Income-tax, Assam, Tripura and Manipur v. Panbari Tea Co. Ltd., AIR 1965 SC 1871 | Limits on the power to reopen final decrees under Order 41, Rule 33, C.P.C. | Supported the discretion exercised in refusing to award future interest under Order 41, Rule 33. |
| Tummalla Atchaiah v. Venka Narasingarao, AIR 1978 SC 725 | Order 41, Rule 33 is for adjusting rights where interference in appeal affects other parties. | Applied to conclude that no readjustment of rights was needed here, so the rule did not apply. |
| Kelantan Govt. v. Duff Development Co., (1923) AC 395 | Dissent of Court from arbitrator's construction is insufficient to set aside award. | Reinforced that courts do not sit in appeal over arbitrators' findings of contract construction. |
| Andrews v. Mitchal, (1905) 74 LJ KB 333 | Arbitrators need not strictly observe legal formalities; their decisions are based on rough justice. | Used to explain the nature of arbitration and why arbitrators are not required to give reasons. |
| Dr. S. Dutt v. University Of Delhi, AIR 1958 SC 1050 | Example of award set aside for erroneous legal proposition. | Distinguished from present case where no erroneous legal proposition was found. |
Court's Reasoning and Analysis
The Court analyzed the arbitration awards and the underlying contract dispute, focusing on the March Agreement as a key document. The majority arbitrators held that the March Agreement defined the parties' rights and duties, superseding the original contract and constituting a full and final settlement. The Court emphasized that the awards were majority awards signed by two arbitrators, while the third arbitrator dissented and provided a detailed note which was not part of the awards.
The Court held that the dissenting opinion cannot be used to interpret the majority awards or to find reasons for them. The majority awards were non-speaking, meaning they did not disclose reasons, but this is permissible under the Arbitration Act. The Court cannot speculate on the arbitrators' mental processes or reasons where none are stated.
The Court found no error of law apparent on the face of the awards. The question whether the March Agreement superseded the original contract was a matter of fact and construction for the arbitrators, not for the Court on appeal. The Court reiterated that judicial interference is limited to cases of error of law apparent on the face of the award or misconduct, neither of which were shown here.
Regarding the claim for future interest, the Court held that the discretion to award such interest lies with the trial Court and cannot be overridden by invoking Order 41, Rule 33, C.P.C., especially as the appeal was dismissed and no rights required readjustment. The Court declined to award future interest to the respondent.
Holding and Implications
The appeal of the Fertilizer Corporation of India is dismissed with costs.
The Court upheld the majority arbitral awards, emphasizing the finality of arbitration and limited grounds for judicial interference. The dissenting arbitrator's note was held to be irrelevant to the majority awards. The March Agreement was affirmed as the defining document of the parties' rights, barring claims for loss of production damages. The Court declined to award future interest, respecting the trial Court's discretion and established legal principles.
No new legal precedent was established; rather, the decision reinforces the established legal framework governing arbitration awards, their finality, and the limited scope of judicial review under the Arbitration Act, 1940 and the Code of Civil Procedure.
AVADH BEHARI ROHATGI, J.:— This arbitration has been a long drawn out affair. By a contract dated 12-2-1964 between the Fertilizer Corporation of India (the Corporation) and Girdler Corporation later known as C.I Girlder Inc. (the contractor), the contractor agreed to erect and instal a Methanol Plant at the Corporation's Trombay Division at Bombay of the description and on the terms set out in the said contract. The plant was supplied on a turn-key basis. It was to have a capacity to produce 100 metric tons of Methanol per continuous day of 24 hours with either refinery gas or petroleum naptha as the feed stock. The contractor was to be paid 45 million rupees as the price of the plant.
2. Article XIV of the said contract contained an arbitration clause which is as follows:
“All disputes and differences between the Contractor and the Corporation shall be referred to arbitration, each party appointing an arbitrator, and the two arbitrators nominating an Umpire, as the first step before consideration of any specific issue referred to them. The decision arrived at unanimously by the two arbitrators, or on their failure to reach unanimous decision the award of the Umpire shall be accepted as final and binding upon both the parties. The provisions of the Indian Arbitration Act, 1940 shall govern the said arbitration proceedings. The venue of the arbitration shall be New Delhi. The parties hereby expressly submit to the jurisdiction of the Courts at New Delhi for all disputes arising out of the agreement, the arbitration proceedings and the enforcement of any award that may be made therein.”
3. The plant was ready for commissioning on Dec. 29, 1965. The performance of the plant was erratic and unsatisfactory. It did not produce the required quantity of hundred metric tons of Methanol per day. This was the main complaint of the Corporation. They said that the Catalyst installed in the Reformer Furnace which was specifically guaranteed under the contract to function satisfactorily for a period of one year had repeatedly failed to perform its function, there being repeated failures and shut downs in the plant. There was considerable correspondence between the parties. On Feb. 16, 1967 the Contractor notified the Corporation that performance test would be carried out by Feb. 19, 1967. Performance test was given accordingly.
4. As a result of various discussions and negotiations that took place between the parties certain understandings were arrived at which were recorded in a letter of March 21, 1967 (the March Agreement). In this agreement the outstanding disputes between the parties were defined. The case of the Corporation is that despite the assurances given by the Contractor there was a failure of the Catalyst in operation and the performance of the plant was far from satisfactory. It is alleged that there being something basically wrong with the Reformer Furnace, which was a vital part, the plant was not capable of giving sustained production of 100 metric tons per day. As the Contractor failed to remedy the defects in the plant the Corporation terminated the contract and took “Juridical possession” of the plant by its letter dated July 8, 1967.
In or about 1967 disputes and differences arose between the Corporation and the Contractor and in accordance with the said Article XIB the Corporation duly appointed Mr. B. Sen as an arbitrator and the Contractor duly appointed Mr. J. Russell Wilson as an arbitrator and the two arbitrators on Feb. 7, 1969 nominated Lord Devlin as Umpire. By a supplemental agreement between the parties made on 1-3-1973 it was provided that the disputes and differences aforesaid should be considered as having always been referred to Lord Devlin, Mr. Russel Wilson and Mr. B. Sen as the three arbitrators, that Lord Devlin should act as the Chairman of the Arbitral Tribunal and that the award or awards should be made in the manner provided in S. 10 (2) of the Indian Arbitration Act.
5. This was an eminent Tribunal of Arbitration consisting of members of three countries. Mr. Russell Wilson is a patent attorney of the United States. Mr. B. Sen, is a senior advocate of India. Lord Devlin was a law-lord in England. They held various sessions between 1971 and 1974. The cost of the arbitration assessed by the Tribunal ran into twelve lacs, parties' own expenses being separate.
6. On Oct. 3, 1969 the Corporation filed a request for arbitration which concluded with four claims (hereinafter called Claims I, II, III and IV). On March 14, 1970 the Contractor filed the reply which concluded with four claims (hereinafter called counter-claims I, II, III and IV, counter-claims III and IV being in the alternative).
7. In the course of the arbitration proceedings IDI Management, the respondent to this appeal succeeded to all the rights and liabilities of the Contractor under the contract.
8. The Arbitral Tribunal held 33 sessions on and between May 24, 1971 and March 3, 1973, to take evidence. They required the parties to submit their arguments in writing and also heard oral arguments.
9. On March 3, 1973 the parties agreed that the Tribunal should make an interim award or awards on certain disputes which were specified in the order dated March 3, 1973 made with the consent of the parties. Accordingly the Tribunal made an interim award on August 21, 1973. The material portion of the award is as under :
“AND WHEREAS we have considered all the evidence put before us and the arguments addressed to us and have deliberated thereon AND WHEREAS we have decided to hear oral arguments on Claim II AND WHEREAS a majority of us are agreed upon an award in relation to Claim I and counter-claim I and in the premises counter-claims III and IV do not arise.
NOW we Patrick Lord Devlin and J. Russell Wilson hereby award and declare as follows:
1. The claimants are not entitled under Claim I to a sum to be assessed in respect of lost production; and
2. The respondents are entitled under counter-claim I to be paid such sum not exceeding $ 302,740.53 as may be shown to be the outstanding balances due to them under the said Contract in dollars as well as in Indian currency.
IN WITNESS HEREOF we have subscribed our signatures as on the 21st day of August one thousand nine hundred and seventy three.
Sd/- Lord Devlin
Sd/- J. Russell Wilson.”
10. It will be seen from the interim award that the claim of the Corporation which was the subject matter of the interim award was the loss of production. They claim Rs. 471.45 lakhs as damages on account of lost production during the period 9-3-1967 to 31-12-67 and additional period of 18 months, that is, 1-1-68 to 30-6-69 during which the plant failed to give the rated capacity of 100 metric tons of Methanol per day. The majority rejected this claim of the Corporation in its entirety.
11. The counter-claim of the Contractor was that, though they had been paid 95 per cent of the price of the plant, the remaining five per cent of the price was not being released to them in spite of the fact that they had done all that was required of them under the contract. The majority allowed this claim of the Contractor. In substance this was the decision of the majority in their interim award. Mr. B. Sen did not concur with the majority and therefore did not sign the award.
12. After the Interim Award the Tribunal held six sessions on and between Feb. 5 and 17, 1974 to hear further arguments and to take evidence upon all other claims and matters remaining in the arbitration. The Corporation abandoned Claim IV and were given leave to add three further claims. The Contractor abandoned counter-claim No. II. On the remaining disputes the majority made the final award on Feb. 16, 1974. The material portion of the final award is in these terms:
“AND WHEREAS we have considered all the evidence put before us and the arguments addressed to us and have deliberated thereon. AND WHEREAS a majority of us are agreed upon an Award or Awards in relation to all the said claims and matters NOW we Patrick Lord Devlin and J. Russell Wilson hereby award to the claimants:
(a) In satisfaction of Claim IIA Rupee 1,06,121 with interest thereon from 8 July, 1967,
(b) In satisfaction of Claim IIC Rupees 2,50,069 with interest thereon from 5 Aug., 1967, and
(c) In satisfaction of Claim III Rupees 2,35,306 with interest from 31 July, 1969
All such interest to be at the rate of 6 per cent per annum and to run until the date of the award.
AND WE DECLARE that, save as aforesaid, the respondents are not liable upon any of the claims.
AND WE AWARD to the respondents in satisfaction of counter-claim I, US $ 302,600.50 with interest thereon at 6 per pat per annum from 8 July, 1967 until the date of this award.”
13. From this final award it will be seen that the Corporation's claims were allowed in respect of the specific items: Claim IIA for the Quenchpot, Claim IIC in respect of Catalyst, Claim III on accounting. In respect of the Contractor's claim they were awarded US $ 302,600.50 with interest. In the Interim Award it was held that the Contractor was “entitled under counter-claim I to be paid such sum not exceeding $ 302,740.53 as may be shown to be the outstanding balance due to them under the said contract” This counter-claim I was now in the final award quantified as US $ 302.600.50 which the Contractor was held entitled to receive from the Corporation. This was in the main the balance 5 per cent of the price of the plant which the Corporation had refused to release on account unsatisfactory performance of the plant.
14. The final award, as was the interim award, was the decision of the majority consisting of Lord Devlin and J. Russell Wilson. Mr. B. Sen did not agree with the majority. Nor did he sign the interim and the final awards. He issued a dissenting note dated 16-2-1974 giving reasons as to why he did not agree with majority awards, interim and final. This note, unlike the majority awards, is a detailed document of 32 pages setting out his reasons why he was not concurring with the majority.
15. In 1974 the Contractor made a petition before a learned Judge on the Original Side of this Court under S. 14 of the Arbitration Act, 1940 (the Act), stating that the award dated 16-2-74 be made a rule of the Court. The arbitrators filed both the interim award dated August 21, 1973 and the final award dated 16-2-74. On notice being given the Corporation on 26-10-74 filed objections to the award, both interim and final under Ss. 30 and 33 of the Act. The Corporation raised a large number of objections to the majority awards.
16. Prithvi Raj, J. by his order dated April 14, 1970 dismissed the objections of the Corporation. He made the awards - interim as well as final - a rule of the Court and passed a decree in terms thereof. From his order the Corporation appeal to this Court.
17. The majority awards are non-speaking awards. In his separate dissenting note dated 16-2-1974 Mr. B. Sen has given his reasons for differing from the majority. The Corporation relies heavily on Mr. B. Sen's note in order to attack the majority awards. On behalf of the Corporation it is contended that the note of Mr. B. Sen dated 16-2-1974 is a minority award and it can be looked at for the purpose of finding the reasons of the majority awards.
18. The opinion of Mr. B. Sen formed the principal topic of discussion and was submitted as a ground for setting aside the majority awards. I cannot agree with this submission. The majority arbitrators refrained from giving reasons for their awards, which they had every right to do. The minority arbitrator, Mr. B. Sen, is a well known and reputed member of the legal profession. He gave reasons for his dissent. That he did so can only be attributed to an honest and understandable desire on his part to indicate to his colleagues where and how he differed from them; and of course to give those interested the same information. The reasons which he has given cannot be said to be reasons of the majority. Mr. B. Sen's reasons are minority reasons and as such form no part of the award.
19. The awards clearly state that they are the awards of the majority. Only Lord Devlin and Mr. J. Russell Wilson signed the awards. Mr. B. Sen did not sign. He was a dissenting member. In his dissenting note he disagrees with the view of the majority. But that is neither here nor there. The dissenting opinion of Mr. B. Sen simply shows, what everybody knows, that there are two sides to every question. Like the two sides of a coin. That there can be different and differing points of view on every conceivable question under the sun is all that the note of Mr. B. Sen shows. But no value can be attached in taw to his dissenting opinion. The awards of the majority will prevail. (See Holland and Couser v. City of Vancouver, (1959) 1 DLR (ed) 404 (Canada) and Yarrows Ltd. v. C.N Steamship Co. Ltd., (1951) 2 DLR 204 (Canada)).
20. Section 10 (2) of the Arbitration Act says that the opinion of the majority will prevail. The majority is a term signifying greater number. Section 10 (2) is based on the theory of numbers. It requires counting of heads. If there are three arbitrators, two will have the deciding voice because they constitute the majority. The remaining one will be in a minority. The opinion of the minority cannot be looked at for any purpose. The award with which the law is concerned is the award of the majority.
21. The majority awards as I have said, are non-speaking awards. The majority has not given any reasons for their decision.
22. The two outstanding and substantial disputes raised before the arbitrators were these: (1) the claim of the Corporation for the loss of production and (2) the claim of the Contractor with regard to the balance 5 per cent price of the plant. The majority rejected the Corporation's claim for lost production without giving any reasons. Counsel for the Contractor drew our attention to Art. X of the contract which provided that neither party would be liable to the other for any loss of profit or for any similar indirect damages. He also called our attention to the March Agreement which narrowed down the disputes between the parties. From the March Agreement one thing is quite clear. And it is this that the Corporation accepted the plant. It says, “FCI accepts the Methanol Plant which specifically fulfilled its Naptha performance guarantee during the performance test held during the period beginning at 1200 hours on March 4, 1967 and ending at 1200 hours on March 9, 1967”. Thereafter it refers to a few outstanding disputes which required to be resolved. The Contractor in his turn agreed to “give its attention for suitable remedial measures to the Hot Spot on Waste Heat Boiler and to the design of the Quenchpot”. He agreed that he shall remove “the defects in the design of the Quenchpot and the Waste Heat Boiler.” He also agreed to replace at no cost to the Corporation spare charges of Catalyst used by him in the plant. The Corporation in its turn agreed “to pay or arrange to pay Girdler Corporation the outstanding balances due to them under the contract in dollars as well as in Indian currency immediately” upon receipt of a bank guarantee in its favour. These rights and duties defined by the March Agreement were “in full and final settlement of all obligations of the parties as set forth in the contract executed in supersession of the agreement dated 12-2-1964”.
23. On the basis of this March Agreement Lord Devlin, the Chairman of the Tribunal, in the course of the arbitration proceedings wrote to the parties a letter dated Oct. 9, 1973 of which the following is an extract :
“It will be apparent from the nature of the award that the majority of the arbitrators considered that the supplemental agreement of March 21, 1967 defined the rights of the parties as alleged by the respondents. Mr. Sen's opinion was to the contrary, but he accepts that any further argument must be governed by the majority decision. Accordingly, the oral arguments on the various heads of Claim II will be concerned with the rights and duties of the parties under the March Agreement.”
24. Counsel for the Corporation made a two-fold submission. Firstly, he submitted that the majority went wrong in holding that the March Agreement defines the rights and duties of the parties. He submitted that the original contract of 1964 was not wiped out by the March Agreement and that the Contractor was bound to fulfil his obligations under the original contract. He argued that as there was a fundamental breach of the implied term of the original contract that the plant will produce 100 metric tons per day of Methanol, the Corporation was entitled to damages on account of loss of production under Section 16 of the Sales of Goods Act and S. 73 of the Indian Contract Act. It appears to me that on a construction of the contract the majority were entitled to come to the conclusion they did. Having accepted the Methanol Plant, as is explicitly stated in the March Agreement, it was not open to the Corporation to make any claim of damages for loss of production. The original contract also did not entitle the Corporation to claim remote or indirect damages such as loss of production.
25. The awards of the majority were attacked on the ground that there was an error apparent on their face. When we pointed out to counsel for the Corporation that the awards of the majority gave no reasons he invited us to read the dissenting note of Mr. B. Sen to find the reasons of the majority. We expressed our inability to accede to this request.
26. Counsel said that the approach of the majority is disclosed by Mr. B. Sen's note. It will, he said, give us a clue to the mind of the majority. The basis of the majority reasoning, he submitted, can be gleaned from Mr. B. Sen's note. I do not agree. Neither reasons nor “basis” nor “clue” nor “approach” can be found from the note of Mr. B. Sen. He was in the minority of one. When the majority awards are non-speaking awards we cannot impute to the majority the reasons given by the minority. It will be a strange thing if the minority can give to the Court the reasons of the majority, when the majority has chosen to remain silent. The basis must come from the mind and hand of the maker of the award. There are only two awards and they are the awards of the majority. The dissenting opinion of one arbitrator is not part of the award. Under S. 10 (2), Arbitration Act the awards of the majority shall prevail.
27. The March Agreement is a crucial document in this case. The arbitrators realised its importance. The majority took the view that it defined the rights and duties of the parties, as Lord Devlin put it. Mr. B. Sen did not concur with the majority. He thought that the original contract continued to govern the parties and the March Agreement was not a complete repository of parties' rights and duties.
28. This raises a question of construction each case, for it has to be decided as a fact whether there was “a full and final settlement” of all the obligations of the parties and whether there was a “supersession of the agreement dated Feb. 12, 1964”. By agreement between the parties dated 21-3-1967 the Corporation accepted the promise of something else than the remedy to repudiate, assuming that they were entitled to repudiate on a fundamental breach. There was agreement. There was accord. In a climate of conciliation a new agreement was executed in March, 1967. This March Agreement is a definitive statement of the outstanding disputes and reciprocal promises. The capital importance of this settlement is that the plant was accepted by the Corporation. If the plant has been accepted where is the question of damages for loss of production or profits. The right to claim damages on this score was not reserved. It was given up. This would appear from the express terms of the March Agreement which was “a full and final settlement” of the old standing disputes.
29. The March Agreement was a composition settlement. There was mutual surrender on certain points. The parties by this agreement agreed to be bound in supersession of the original agreement. The original cause of action was discharged from the date when the March Agreement was made. The execution of the March Agreement is of central importance in this case. This was the view of the majority whose word is, and must be, final. Were it not so there would be no end to controversy.
30. The March Agreement was a clear case of accord and satisfaction. The parties put their past behind them. In all amity they chalked out a course of action for the future. In a spirit of give and take the differences were composed on this condition that if certain things are done by each party all disputes will stand settled.
31. The single question in this case is whether the majority awards disclose an error of law on their face. There is no statement of reasons in the awards. Nor do they incorporate any legal proposition as the basis of the awards. The question whether the majority were right in holding that the March Agreement defined the rights and duties of the parties is not for us to decide. It is not for us to weigh the evidence. That task belonged to the Tribunal. And there can be no doubt that the finding of the Tribunal, which in this case means the majority, should not be disturbed except in cases where there is an error of law on the face of the award or misconduct. As to this there are strong and abundant authorities, e. g. : Union Of India v. A.L Rallia Ram, AIR 1963 SC 1685; Jivrajbhai v. Chintamanrao Balaji, AIR 1965 SC 214; Bungo Steel Furniture (Pvt.) Ltd. v. Union of India, AIR 1967 SC 378; Upper Ganges Valley Electricity Supply Co. Ltd. v. U.P Electricity Board, AIR 1973 SC 683; N. Chellappan v. Secy., Kerala Electricity Board, AIR 1975 SC 230; and Rohtas Industries Ltd. v. Rohtas Industries' Union, AIR 1976 SC 425.
32. The celebrated decision in Champsey Bhara and Co. v. Jivraj Balloo Spinning and Weaving Co., AIR 1923 PC 66. Generations of lawyers and Judges have paid a respectful tribute to the masterly exposition by Lord Dunedin. This decision has stood for half a century and alone. In the Champsey Dhara case it was held that the arbitrators were entitled to give their own interpretation or construction of Art. 52 of the Rules of the Bombay Cotton Trade Association and that the finding was not open to review on a motion to set aside the award. The Principle enunciated was that the award must stand unless on the face of it the arbitrators had tied themselves down to some legal proposition which was erroneous.
33. Lord Dunedin in the Champsey Bhara case says that that case differs from Landauer v. Asser, (1905) 2 KB 184 “in an essential particular”. The difference is that in the Landauer case a legal proposition stated in terms on which the award proceeded while in Champsey case no legal position at all is stated as a ground of the award. Lord Dunedin says at p. 69 “to make this equipparate with that of Landauer Co. v. Asser and Co., (1905) 2 KB 184 the award would have to run somewhat thus :
“In respect of the ground of rejection contained in the letters of the 11th and 25th Nov., and in respect of clause 52 of the Articles, I decide that, etc.”
If these words are added in the Champsey award it would have the result of tying the arbitrators down to some legal proposition. If the arbitrator says: “On the wording of this clause I hold so and so, then that clause impliedly incorporated into the award because he invites the reading of it”. (Blaiber and Co. v. Leopold Newborne (London) Ltd., (1953) 2 Lloyd's Rep 427 at p. 429 per Denning, L. J.).
34. The other principle Lord Dunedin enunciated is that if in a narrative a reference is made to a contention of one party, that alone does not open the door to seeing first what that contention is and then going to the contract on which the parties' rights depend to see if that contention is sound.
35. In Allen Berry and Co. Ltd. v. Union of India, AIR 1971 SC 696, the Supreme Court has said (at p. 699) :
“The question whether a contract or a clause of it is incorporated in the award is a question of construction of the award. The test is, does the arbitrator come to a finding on the wording of the contract. If he does, he can be said to have impliedly incorporated the contract or a clause in it whichever be the case. But a mere general reference to the contract in the award is not to be held as incorporating it. The principle of reading contracts or other documents into the award is not to be encouraged or extended. The rule thus is that as the parties choose their own arbitrator to be the Judge in the dispute between them, they cannot, when the award is good on the face of it, object to the decision either upon the law or the facts. Therefore even when an arbitrator commits a mistake either in law or in fact in determining the matters referred to him, “but such mistake does not appear on the face of the award or in a document appended to or incorporated in it so as to form part of it, the award will neither be remitted nor set aside notwithstanding the mistake.”
36. Applying these principles to this case I find that there is no error in the majority awards because the arbitrators have not tied themselves down to any legal proposition.
37. This conclusion was countered by counsel for the Corporation by referring us to the letter of Lord Devlin dated Oct. 9, 1973 where he said that the “supplemental agreement of March 21, 1967 defined the rights of the parties”, and that they, the majority, will be concerned with “the rights and duties of the parties under the March Agreement”. The short answer to the argument is that this letter dated Oct. 9, 1973 is not incorporated in the awards - interim or final. Interim award is dated August 21, 1973. Final award is of Feb. 16, 1974. This letter stands midway between the two dates. It is true that it expresses the view of the majority on an important question but it was signed by Lord Devlin alone. It was not signed by J. Russell Wilson, though it must have been written with his concurrence. But it is no part of the award. Unless it is referred to in the award it cannot be said to be incorporated therein. “The principle of reading the contract or other document is not to be encouraged or extended”. (Allen Berry and Co. Ltd. v. Union of India (AIR 1971 SC 696) (supra)). To hold that the language used in the majority awards in the instant case incorporates the documents, such as the original contract of 1964, March Agreement of 1967, Lord Devlin's letter of October, 1973, or so closely connects them therewith that they must be treated as part of the awards, would seem to me personally, with great respect, to make too much out of too little.
38. The majority have not stated their reason. We do not know the route of reasoning they took in arriving at their conclusion. “It is mot open to the Court to attempt to probe the mental process by which the arbitrator has reached his conclusion where it is not disclosed by the terms of the award”. In Jivrajbhai Ujamshi Seth (AIR 1965 SC 214) (supra) at p. 220 Shah, J. said : “An award may be set aside by the Court on the ground of error on the face of the award, but an award is not invalid merely because by a process of inference and argument it may be demonstrated that the arbitrator has committed some misconduct in arriving at his conclusion.”
And again :
“It is not open to the Court to speculate, where no reasons are given by the arbitrator, as to what impelled the arbitrator to arrive at his conclusion on the assumption that the arbitrator must have arrived at his conclusion by a certain process of reasoning the Court cannot proceed to determine whether the conclusion is right or wrong.” (Jivrajbhai Ujamshi Seth (supra) p. 220).
39. Once it is accepted that the Court cannot explore the thought processes of the arbitrator how will it ever know what were his reasons for a given conclusion. The award which is the outer expression of the mind of the arbitrator does not give his inner thoughts.
40. What was referred to the arbitrators were the specific disputes raised by the Corporation against the contractor and the contractor's dispute against the Corporation. On these the arbitrators gave their findings. They awarded some sums to the Corporation and some to the contractor. They gave a practical decision on merits according to their business sense. The arbitrators have nothing on fundamental breach, implied warranty of fineness. Sec. 16 of the Sale of Goods Act or Section 73, Contract Act. These concepts figured prominently in the thinking of Mr. B. Sen as appears from his dissenting note. And it is on these that the Corporation stake their claim. But the majority awards are non-speaking awards.
41. The arbitrators' award differs fundamentally from judicial justice that we the Judges administer in Courts of law. The Judges are required in their judgments to give reasons because they have a Court of Appeal set over them. But it is not so with the arbitrator. His ropes and pulleys are different. The foot rules and the set-squares that he uses in arriving at his decisions are different from our known judicial methods. From his decision there is no appeal. The arbitrator is a domestic forum. He may be a lawyer or a layman. A lay arbitrator is not necessarily well versed in law. For that matter no one knows all the law, nor even lawyers and judges. In 1825 Abot, C.J said : “God forbid that it should be imagined that an attorney, or a counsel, or even a judge is bound to know all the law” (2C and P. 113).
42. An arbitrator is not required to give reasons. He hears both sides and gives his decision. He is not bound by the technical rules of evidence. Nor by any fixed legal procedure. As Lord Halsbury observed in Andrews v. Mitchal, (1905) 74 LJ KB 333, “we must not insist upon a too minute observance of the regularity of forms among persons who naturally by their education or by their opportunities cannot be supposed to be very familiar with legal procedure, and may accordingly make slips in what is mere matters of form without any interference with the substance of their decisions.” All that is expected of an arbitrator is that he will act impartially. It is presumed that he will do so to the best of his ability. After hearing the injured and the injuring party he gives rough justice of the work. For good or ill, for better or worse, the parties have chosen him and have agreed to be bound by his award. This is why the award is final both on facts and law. Only on the restricted ground stated in Sections 30 and 33 of the Act it can be set aside.
43. “Judicial demolition” of an award is possible only when some legal proposition is stated in the award and which is erroneous. Two striking examples of erroneous legal propositions on which the awards were set aside are Dr. Dr S. Dutt v. University Of Delhi, AIR 1958 SC 1050 and Rohtas Industries v. Rohtas Industries Union (AIR 1976 SC 425) (supra).
44. Suppose the majority were wrong in their view that the March Agreement defines the rights and duties of the parties. So what? This is neither misconduct nor an error of law on the face of the award. The award will not be set aside because the arbitrators or the majority of them went wrong in their construction of the contract. Unless the majority in their awards say : “On the wording of this clause we hold so and so” there is no error on the face of it. Nor is it misconduct to decide a question wrongly. “It is not misconduct for the arbitrator to make a mistake of law” (Russell on Arbitration 20th ed. p. 423).
45. Nor is it open to me on this motion to set aside the award only because I might myself have come to a different conclusion. The Court does not sit in appeal over the decision of the arbitrators. “The mere dissent of the Court from the arbitrator's conclusion on construction is not enough to set aside an award.” (Kelantan Govt. v. Duff Development Co., (1923) AC 395). The decision of the arbitrator cannot be set aside by the Court only because the Court would have come to a different conclusion on a question of construction of the contract. I therefore hold that the awards do not disclose any error of law.
46. The awards do not set out any reasons. The majority awards are as inscrutable as the face of the sphinx. Nor is there any note appended to the awards by the majority stating the reasons for their judgment involving some legal proposition which is erroneous. The question of construction of contract is a question of law. But whether there was accord and satisfaction is essentially a question of fact. The questions of breach of contract and damages are questions of fact and are in the exclusive domain and province of the arbitrator. Even where an arbitrator makes a mistake either in law or in fact in determining the matters referred, the award is good notwithstanding the mistake. (N. Chellappan v. Secy. Kerala State Elec. Board (AIR 1975 SC 230) (supra)). If the arbitrators arrive at an erroneous lending of fact it is not a ground for setting aside the award. It must be an error of award. It must appear from the award or in some contemporaneous document delivered with the award from which the error of law is apparent e. g. a note appended to the award by the arbitrator stating the reasons for his decision involving some legal proposition which is erroneous. There is nothing of the kind in this case. In my opinion the majority were entitled to come to the conclusion they did and I am unable therefore to set aside the award.
47. One other question remains to be decided. The respondents' claim interest under Section 29 of the Arbitration Act on the decretal amount from the date of the decree till payment. They have filed neither cross-appeal nor cross-objections. But they invoke the powers of this Court under Order 41, Rule 23, Code of Civil Procedure.
48. The learned Judge has not awarded future interest. I think we ought not to interfere with his discretion. The matter of future interest is in the discretion of the Court.
49. In my opinion Order 41, Rule 33 cannot properly be invoked in the present case. Such a power is to be exercised in exceptional cases when its non-exercise will lead to difficulties in the, adjustment of the rights of the various parties. (See Rameshwar Prasad v. Shambehari Lal, AIR 1963 SC 1901). It is true that Order 41, Rule 33 is expressed in wide terms, but it has to be applied with discretion. It should be applied to cases where interference in favour of the appellant necessitates interference also with a decree which has by acceptance or acquiescence became final, so as to enable the Court to adjust the rights of the parties. If the appellate Court reaches a conclusion which is inconsistent with that of the Court appealed from and in adjusting the right claimed by the appellant it is found necessary to grant relief to a person who has not appealed, the power under Order 41, Rule 33 may properly be invoked. (See Commr. of Income-tax, Assam, Tripura and Manipur v. Panbari Tea Co. Ltd., AIR 1965 SC 1871). As the Supreme Court has said :
“No unrestricted right, however, is conferred by the Rule to reopen decrees which have become final merely because the appellate Court does not agree with the opinion of the Court appealed from.”
(See Commissioner of Income-tax, Assam, Tripura and Manipur (supra)).
50. The cases decided by the Supreme Court show that this power is exercised in cases where as a result of interference in favour of the appellant it becomes necessary to adjust the rights of the other parties; in other words in cases where the question is one of settling mutual rights and obligations. (See Tummalla Atchaiah v. Venka Narasingarao, AIR 1978 SC 725).
51. I do not think the respondent can take recourse to Order 41, Rule 33, Code of Civil Procedure and ask us to modify the decree of the trial Court by awarding him future interest. The main reason is that we are not interfering in favour of the appellant in this appeal. We are in fact dismissing the appellant's appeal. Why should we interfere with the decree of the learned single Judge or modify it so as to award interest to the respondent? No rights of the parties are required to be readjusted. We are letting things remain as they are.
52. Counsel for the contractor referred us to Makkala Narsimlu v. Gunnala Raghunandan Rao, AIR 1977 Andh Pra 374 in support of his contention. In this case it was held that interest could be allowed even though there was no appeal in this regard. With due deference to the learned Judges I do not think that it is a proper exercise of the power under Order 41, Rule 33, C.P.C. In view of the Supreme Court judgments I have referred to above I am not prepared to hold that even in a case like the present Order 41, Rule 33 empowers us to award future interest when the learned single Judge in his discretion has refused to award. The Andhra Pradesh decision is not in line with the Supreme Court rulings and makes a departure from the established law.
53. An application for review was made the learned single Judge. He dismissed it on the ground that he was functus officio. My opinion the respondent is not entitled to future interest. In this view of the matter I think it unnecessary to decide whether an appeal lies and if not, what is its effect ? The prayer for future interest is therefore rejected.
54. For these reasons the appeal of Fertilizer Corporation of India is dismissed with costs.
G. C.JAIN:— I agree.
Appeal dismissed.
Alert