Union Of India v. Popular Builders, Calcutta .

Supreme Court Of India
Oct 17, 2000
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The respondent contractor entered into an agreement with the Union of India for construction of an annex building to Telephone Bhawan in Calcutta. The agreement contained an arbitration clause (Clause 25).

After completion of the works, the competent authority prepared a final bill. The contractor accepted and encashed this final bill without raising any protest. Subsequently, the contractor addressed a letter to the Chief Engineer alleging omission of several additional works and requesting appointment of an arbitrator under Clause 25. The Chief Engineer appointed an arbitrator on 25-11-1993; the arbitrator was later changed pursuant to an order of the High Court.

During arbitration, the contractor filed multiple claims and the Union of India filed objections and a counter-claim. The arbitrator passed an award in favour of the contractor. The award was filed in the Calcutta High Court under Section 14 of the Arbitration Act, 1940. The Union of India objected under Sections 30 and 33, essentially on limitation grounds. A Single Judge rejected the objections and made the award a rule of court. The Union’s appeal under Section 39 was dismissed by a Division Bench on 28-1-1999. The Union of India then appealed to the Supreme Court.

Legal Issues Presented

  1. Whether acceptance of the final bill by the contractor without protest extinguished any “arbitrable dispute”, thereby invalidating the reference under Clause 25.
  2. Whether, in the absence of a specific plea in its objections, the Union of India could raise this issue at the Supreme Court stage.

Arguments of the Parties

Appellant (Union of India)

  • The contractor’s unconditional acceptance of the final bill meant no dispute survived for arbitration; therefore, the award is liable to be set aside in its entirety.
  • Reliance on Supreme Court decisions in P.K. Ramaiah & Co. v. NTPC and Nathani Steels Ltd. v. Associated Constructions, where acceptance of a “no-claim” certificate barred arbitration.

Respondent (Contractor)

  • The plea of “no arbitrable dispute” was never specifically raised in the objections under Sections 30 and 33; hence it should not be entertained for the first time in the Supreme Court.
  • The Union fully participated in arbitration, requested rectification of the award only on quantum, and thus acquiesced in the existence of disputes fit for arbitration.
  • The cited precedents deal with challenges before appointment of an arbitrator, not after an award following full participation.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
P.K. Ramaiah & Co. v. Chairman & Managing Director, NTPC, 1994 Supp (3) SCC 126 Acceptance of final bill/no-claim certificate extinguishes disputes; no arbitration lies thereafter. Used to support the view that receipt of the final bill without protest negates existence of an arbitrable dispute for Claim Item 2.
Nathani Steels Ltd. v. Associated Constructions, 1995 Supp (3) SCC 324 Existence of dispute is a condition precedent for appointment of an arbitrator; no dispute exists once the contractor signs a no-claim certificate. Reinforced the decision to set aside the award on Claim Item 2 for want of an arbitrable dispute.

Court's Reasoning and Analysis

The Supreme Court first noted that the Union’s original objections focused on limitation, a ground rejected concurrently by the Single Judge and Division Bench. Nevertheless, the Court examined whether any arbitrable dispute existed after the contractor accepted the final bill without protest, because existence of such a dispute is a condition precedent to invoking Clause 25.

Key analytical steps:

  • The award itself disclosed that, in relation to Claim Item 2, the Union had pleaded that the claim was barred due to acceptance of the final bill.
  • Applying the principles in P.K. Ramaiah and Nathani Steels, the Court held that receipt of the final bill without protest precludes arbitration on matters covered by that bill.
  • While agreeing with the respondent that the Union had not pressed this ground before the courts below for other items, the Court distinguished Claim Item 2, where the plea had at least been raised before the arbitrator.
  • For the remaining claim items, the Union neither raised the “no arbitrable dispute” objection in arbitration nor specified it in Sections 30/33 objections; consequently, the Court refused to entertain the plea at this late stage.

Holding and Implications

Held: The appeal is allowed in part. The arbitral award is set aside only in so far as it relates to Claim Item 2; the remainder of the award stands affirmed.

Implications: The contractor loses the amount awarded under Claim Item 2 but retains the balance award. The judgment reiterates that unconditional acceptance of a final bill may extinguish disputes for arbitration, yet parties must timely raise such objections; failure to do so can forfeit the defence for other claim items. No new legal principle is created, but the decision reinforces existing precedent on “no-claim” situations.

Show all summary ...

G.B Pattanaik, J.— Leave granted.

2. This appeal by the Union of India is directed against the judgment dated 28-1-1999 of the Division Bench of the Calcutta High Court, dismissing the appeal of the Union of India, arising out of an arbitration proceeding. The undisputed facts are that the respondent had entered into an agreement with the appellant for construction of annex building to Telephone Bhawan at Calcutta. The agreement between the parties contained an arbitration clause therein. After the completion of work, the final bill was drawn and was sent to the respondent and he agreed to accept the final bill and in fact did receive the money under the final bill without any objection. But thereafter, he wrote a letter to the Chief Engineer concerned, indicating several items of claim and additional works which the respondent had executed pursuant to the directions of the appropriate authority and the said work had not been included in the final bill. He, therefore, requested the Chief Engineer, the authority under clause 25 of the agreement to appoint an arbitrator and pursuant to the said request, the Chief Engineer by his letter dated 25-11-1993 did appoint an arbitrator. Subsequently, the appointed arbitrator was changed. Pursuant to an order of the High Court and before the arbitrator, the respondent filed his claim under different heads. The Union of India, appellant herein, filed its objection as well as filed a counter-claim before the arbitrator. The learned arbitrator ultimately passed an award and that award was filed before the High Court, for being made a rule of Court under Section 14 of the Arbitration Act, 1940. The Union of India filed an objection under Sections 30 and 33 for setting aside the award. The learned Single Judge considered the objections filed by the Union of India and rejecting the same, made the award a rule of Court. Against the aforesaid order of the learned Single Judge, an appeal was carried to the Division Bench under Section 39 of the Arbitration Act. The Division Bench having dismissed the Union's appeal by the impugned order, the present appeal has been preferred by the Union of India. From the judgment of the learned Single Judge, rejecting the objections of the Union of India as well as the impugned judgment of the Division Bench, it appears that the Union of India had urged the sole point of limitation and the same had been negatived by the courts below and in our view rightly.

3. Mr A. Subba Rao, the learned counsel for the Union of India however raised the question that the final bill having been accepted by the respondent Contractor, without any objection, there did not subsist any arbitrable dispute to be referred to arbitration, invoking clause 25 of the agreement and, therefore, the impugned award has to be set aside. In support of this contention, reliance has been placed on two decisions of this Court — P.K Ramaiah and Co. v. Chairman & Managing Director, National Thermal Power Corpn. 1994 Supp (3) SCC 126 as well as a three-Judge Bench decision of this Court in Nathani Steels Ltd. v. Associated Constructions 1995 Supp (3) SCC 324.

4. Mr L. Nageswara Rao, appearing for the respondent claimant on the other hand contended that this objection had not specifically been taken in the objection that was filed under Sections 30 and 33 of the Arbitration Act and, therefore, the Union Government should not be permitted to take up this plea in this forum. He further contended that pursuant to the request made by the Contractor, the Chief Engineer himself having appointed an arbitrator on the ground that dispute subsists for arbitration and in the arbitration proceeding, the Union Government having fully participated and further, subsequent to the award, a rectification application having been filed by the Union Government and in that application also, only challenge being made on the quantum and not on the ground of absence of arbitrable disputes, it would not be appropriate for this Court to allow the Union Government to take this plea at this belated stage. He also contended that the two decisions referred to by the Union Government are prior to the appointment of arbitrator and none of these decisions are applicable to the case in hand, where an award has been passed by the appointed arbitrator after due participation of the Union Government in the arbitration proceedings.

5. Having considered the rival submissions at the Bar and on careful scrutiny of the objections filed by the Union Government under Sections 30 and 33 of the Arbitration Act, though we find sufficient force in the contention of Mr Nageswara Rao, but the existence of a dispute being the condition precedent for appointment of an arbitrator under clause 25 and in view of the two decisions of this Court and that the respondent claimant did receive the final bill without any protest, we are not persuaded to outright reject the contention of Mr Subba Rao, appearing for the Union Government. It transpires from the award itself that only as against Claim Item 2, the Union of India had pleaded that the said claim cannot be entertained in view of the receipt of the final bill by the Contractor without any protest, though the arbitrator had rejected the said plea of the Union of India. It is no doubt true as contended by Mr Nageswara Rao that neither the judgment of the learned Single Judge nor the judgment of the Division Bench, which is under challenge in this appeal before this Court did indicate the fact that the Union of India had raised this contention before the aforesaid two forums below but notwithstanding the same when the existence of an arbitrable dispute is the condition precedent for exercise of power for appointment of an arbitrator under clause 25 and since the final bill that was prepared by the appropriate authority was accepted by the respondent without any protest as is apparent from the letter of the claimant Contractor and the question had been raised before the arbitrator in respect of Claim Item 2 by the Union of India, we think it appropriate to hold that so far as Claim Item 2 is concerned, the same could not have been a matter of reference of an arbitrable dispute and as such, the award of the arbitrator to that extent must be set aside. So far as the other claim items are concerned, the Union of India not having taken any objection to the same on the aforesaid score and that even the objection filed under Sections 30 and 33 of the Arbitration Act not being specific on that issue, we do not think it appropriate to allow the Union Government to raise that objection, so far as the other items of claim are concerned. Accordingly, the impugned award in respect of Claim Item 2 is set aside and the rest of the award amount, stand affirmed. The appeal is allowed in part.