- Bookmark
- Share
- CaseIQ
K. Majeed v. Pappa Madurambal 2. Natarajan.
Factual and Procedural Background
The appellant filed a suit for specific performance of a contract to purchase a property. On 9.7.1983, the plaintiff entered into an agreement of sale with the first defendant for Rs. 66,500, paying Rs. 10,000 as advance. The agreement required execution of the sale deed within 30 days. On 16.7.1983, the plaintiff paid an additional Rs. 5,000 and claimed the agreement period was extended by two months. The first defendant allegedly postponed execution of the deed, prompting the suit. The second defendant was impleaded on the basis that the first defendant intended to sell the property to him, which he denied. The trial court dismissed the suit, leading to the present appeal.
Legal Issues Presented
- Whether the period of the agreement was validly extended by two months beyond the original 30-day term.
- Whether the plaintiff was ready and willing to perform his part of the contract at all material times.
- Whether the reply notice cancelling the agreement was properly served on the plaintiff.
- Whether the plaintiff is entitled to the return of the advance payments made under the agreement.
Arguments of the Parties
Appellant's Arguments
- The endorsement (Ex. A-2) clearly shows an extension of time by two months, signed by the first respondent, and no suspicious alterations were apparent.
- The first defendant failed to prove that the reply notice (Ex. B-2) cancelling the agreement was sent, as there was no postal seal on the acknowledgment card.
- At least, the appellant should be entitled to the return of the advance payment of Rs. 15,000 paid under the agreement.
Respondent's Arguments
- The extension of time for two months was a material alteration inserted subsequently without agreement, thus invalid.
- The plaintiff was not ready and willing to perform his part of the contract.
- The reply notice (Ex. B-2) was duly sent by registered post and refused by the plaintiff, constituting valid service.
- The agreement contained a clause forfeiting the advance if the plaintiff failed to perform within the stipulated time, hence no refund of advance is due.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The court examined the endorsement (Ex. A-2) and noted the first defendant's specific denial that the two-month extension was agreed upon, considering it a subsequent material alteration. Since the plaintiff failed to call any witnesses, including the scribe of the endorsement, to prove the extension, the court held that the extension was not established. The court further held that the reply notice (Ex. B-2) cancelling the agreement was validly sent by registered post and refused by the plaintiff, constituting effective service. Regarding readiness and willingness, the court found no evidence that the plaintiff was prepared to perform after cancellation; the plaintiff did not enclose stamp papers as claimed, failed to deposit the balance consideration, and showed inaction for nearly three years before filing the suit. The plaintiff's conduct, including entering into another agreement to sell the property portion to a third party and subsequent suit to recover money, undermined his claim of readiness. Finally, the court upheld the clause forfeiting the advance payment if the plaintiff failed to perform, rejecting the claim for its return.
Holding and Implications
The court DISMISSED THE APPEAL, affirming the trial court's judgment and decree refusing specific performance of the contract.
This decision directly affects the parties by confirming that the plaintiff is not entitled to specific performance or return of the advance payment. No new legal precedent was established.
Judgment — N.V Balasubramanian, J.
This appeal is preferred against the judgment and decree rendered in a suit filed for specific performance which was dismissed and the plaintiff who lost his case before the trial Court is the appellant herein.
2. The brief facts necessary for the disposal of the appeal are that on 9.7.1983 the plaintiff entered into an agreement of sale (Ex. A-1) with the first defendant, who is the first respondent herein, for the purchase of suit property for a total consideration of Rs. 66,500/- and on the date of agreement, the plaintiff has paid a sum of Rs. 10,000/- towards advance of the sale consideration. Page: 693Under the terms of the agreement, the deed of sale has to be executed within a period of 30 days. On 16.7.1983 the plaintiff has paid a further advance amount of Rs. 5,000/- and it is his case that on the same date, namely, 16.7.1983, the period of agreement was extended for a further period of two months. The plaintiff has stated that after 16.7.1983 he requested the first defendant to complete the deed of sale, but the first defendant was postponing the execution of the deed of sale and hence, he filed the suit for specific performance. The second defendant was impleaded as a party on the basis that the first defendant was trying to dispose of the property in favour of the second defendant, but the second defendant has taken a stand that there was no such proposal for the purchase of the suit property from the first defendant.
3. The first defendant in her written statement has taken a stand that the time was the essence of the contract and the sale should be completed within a period of thirty days from the date of agreement. Her case was that even though on 16.7.1983, a sum of Rs. 5,000/- was received by the first defendant and an endorsement of acknowledgment (Ex. A-2) for the receipt of Rs. 5,000/- was made on the agreement of sale dated 9.7.1983, the extension of time for a period of two months from the date of payment of Rs. 5,000/- found in the endorsement was subsequently inserted and it would amount to material alteration in the agreement as there was no such agreement between the parties for the extension of time for completion of the contract by two months. The first defendant has also raised a plea that the plaintiff was not ready and willing to perform his part of the contract. The trial Court on the basis of evidence dismissed the suit and against the judgment and decree, the present appeal has been preferred.
4. Mr. V. Raghavachari, learned counsel for the appellant submitted that the learned Subordinate Judge was not correct in holding that the period of agreement was not extended by two months in Ex. A-2. He referred to Ex. A-2 and submitted that it is clear from Ex. A-2 that time was extended by two months and the first respondent has signed below the endorsement and when the document itself has been produced, there is no necessity of further proof to substantiate the recitals in Ex. A-2. Learned counsel also submitted that the contents of the endorsement have been written in the same ink and there are no suspicious circumstances to show that the last line of the said endorsement providing for the extension of time by two months was inserted later. We are unable to accept the submission of Mr. V. Raghavachari, learned counsel as the first defendant in her written statement has taken a definite stand that the words in Ex. A-2 extending the period of agreement by two months were inserted subsequently and there was no agreement between the parties for the extension of time by two months. We are of the view that when there is a specific denial by the first defendant, the plaintiff should establish that the time for performance was extended by two months. However, the plaintiff has not chosen to examine any one of the witnesses of the agreement or even the scribe who wrote the endorsement. Another aspect of the matter is that in the notice issued by the plaintiff dated 8.8.1983 (Ex. B-1), which was subsequent to the endorsement dated 16.7.1983 in Ex. A-2, there was no reference to the extension of time for performance of the contract by two months, though there was a reference to the payment of Rs. 5,000/- made on 16.7.1983 In the notice the plaintiff has stated other details, but there was a conscious omission that the time mentioned in Page: 694the original agreement was extended by two months. We are therefore of the view that the plaintiff has failed to establish that there was no addition in Ex. A-2 for the extension of time for the performance of the agreement by two months.
5. The next submission of Mr. V. Raghavachari, learned counsel is that the first defendant has failed to prove that reply, Ex. B-2 was sent by the first defendant and there is no postal seal found on the acknowledgment card. However, we are unable to accept the submission of the learned counsel for the appellant for the reason that the document Ex. B-2 itself shows that a reply notice was sent to the plaintiff by registered post and further, the endorsement in Ex. B-2 shows that it was refused to be received by the plaintiff. The plaintiff has admitted that the address given in Ex. B-2 was his own and from the fact that the plaintiff had refused to receive the same, it must be taken that the reply notice was properly served. Further, the advocate who had issued the reply notice Ex. B-2 was examined as D.W 2 and he also deposed that the reply notice in Ex. B-2 was despatched to the appellant/plaintiff. In other words, there is evidence to show that the notice in Ex. B-2 was properly addressed; necessary stamps were paid; and it was sent by registered post. Hence, it can be safely drawn that notice in Ex. B-2 was duly delivered and served when the endorsement shows that it was refused to be received. The first defendant in the reply notice Ex. B-2 has taken a definite stand that the appellant failed to comply with the terms of the agreement of sale and hence, he was cancelling the agreement. The reply notice was issued on 12.8.1983 Therefore the submission of the learned counsel for the appellant that there is no evidence for the despatch of reply notice dated 12.8.1983 (Ex. B-2) is not acceptable and it is rejected.
6. The next question that arises is whether the appellant has proved that he was ready and willing to perform his part of contract under the agreement. We have already seen that the first respondent/first defendant in her notice dated 12.8.1983 in Ex. B-2, which is a reply to the notice dated 8.8.1983 (Ex. B-1) has taken a stand that the agreement of sale was cancelled by him. The suit was filed on 4.8.1986 and there is no evidence at all from the plaintiff/appellant to show that he was ready and willing to perform his part of the contract even after the cancellation of the agreement by the first respondent/first defendant. We find that there is a complete inaction on the part of the appellant from the date of notice, namely, 12.8.1983 till the suit was filed on 4.8.1986 and he has not taken any steps in furtherance of or to perform his part of the agreement.
7. There is also one another significant factor, namely, the conduct of the appellant himself. The appellant has taken the stand in the plaint that he was ready and willing to perform his part of the contract. The plaintiff has stated that he has enclosed stamp papers purchased by him for the execution of the deed of sale, but on perusal it is seen that stamp papers have not been enclosed along with the plaint. The appellant has taken a stand that he was ready and willing to perform his part of the contract and was willing to deposit the balance of sale consideration. However, the plaintiff was unable to deposit the balance of sale consideration and he filed an application before the trial Court in I.A No. 659 of 1986 for the extension of time to pay the balance of sale consideration and the said application was dismissed. If really the appellant had the requisite money to deposit the balance of sale consideration, there would have been no necessity for him to take out an application for extension of Page: 695time to deposit the balance of sale consideration. One another aspect urged by the learned counsel for the first respondent is that the appellant had entered into an agreement of sale with one Seenivasa Sharma for the sale of a portion of the suit property on 10.7.1983, that is, next day after he entered into the agreement of sale with the first respondent and received a sum of Rs. 7,000/- from the said Seenivasa Sharma as advance consideration. If the appellant really had the money for the purchase of the entire property, he would not have entered into an agreement of sale with Seenivasa Sharma even before the conclusion of sale in his favour. The appellant was not able to convey the property to Seenivasa Sharma which forced him to institute a suit for the recovery of money which shows that the appellant did not have the money to pay to Seenivasa Sharma when the return of money was demanded from him. Further, the plaintiff has not proved by any evidence that he had financial resources to discharge his obligations under the agreement. It is no doubt true that the plaintiff need not produce the actual cash before the Court, but he should establish his means to perform his part of the contract. As we have pointed out earlier, even after the reply notice dated 12.8.1983 (Ex. B-2) till the filing of the suit, there is a complete inaction on the part of the plaintiff and there is no evidence at all to show his readiness and willingness to perform his part of the contract. We hold that all the above factors would establish that the plaintiff has not proved that he was ready and willing to perform his part of the contract.
8. Mr. V. Raghavachari, learned counsel for the appellant submitted that at least there may be a direction for the return of the advance money of Rs. 15,000/- paid by the plaintiff. It is seen that there is no such prayer in the plaint for the return of advance money paid by the plaintiff. The appellant has not taken steps for amendment of the plaint. Further, we find that there is a specific clause in the agreement of sale, Ex. A-1 that if the plaintiff fails to perform his part of the contract within the time stipulated in the agreement, the advance amount would be forfeited and the agreement would stand cancelled. In view of the specific clause found in the agreement of sale, we are not inclined to order for the return of the amount of Rs. 15,000/- to the appellant.
9. Consequently, we hold that there is no error in the judgment and decree of the trial Court in refusing to grant the relief of specific performance to the plaintiff which warrants interference by this Court. Accordingly, the appeal stands dismissed. No costs.
VCJ/VCS
Alert