B.S.M. Contractors Pvt. Ltd. v. Rajasthan State Bridge & Construction Corpn. Ltd. & Anr.
Structured Summary of the Court Opinion
Factual and Procedural Background
This order disposes of OMP No. 196/98 and the connected IAs: IA No. 7479/98, IAS Nos. 8503/98, 10451/98 and 11511/98 (and separately referenced IA No. 1511/98). IA No. 7479/98 is an application under Order 39, Rules 1 and 2, C.P.C. filed by the petitioner seeking an ad interim injunction. IAS Nos. 8503/98 and 10451/98 are applications filed by the respondents seeking vacation of an ex parte injunction order dated 2-9-98. IA No. 1511/98 (referred to in the opinion) is an application under Order 7, Rule 11, C.P.C. filed by respondent No. 2 for rejection of OMP No. 196/98.
Substantively, respondent No. 3 awarded a contract to respondent No. 1 for construction of the D.I.T. Complex at Dwarka (Phase I and II) for Rs. 5,45,72,958/-. Respondent No. 1 in turn invited labour rate tenders for construction of a Boys Hostel and, after accepting the petitioner's tender, entered into two agreements with the petitioner dated 20-10-1997 (Agreement No. 1/97 and Agreement No. 2/97) for work estimated at Rs. 225 lacs. The commencement date was 20-10-1997 and the completion date was stipulated as 19-10-1998.
The petitioner alleges completion of the work under Agreement No. 1/97 within six months but says certain item quantities exceeded deviation limits and requested rates for deviated quantities and award of the balance work; the petitioner further alleges harassment by respondent No. 2 and that respondents sought to take the unexecuted part away. A dispute arose between petitioner and respondent No. 1 which the petitioner says is governed by an arbitration agreement. The petitioner filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim injunctions restraining respondents from awarding the work to others and from using the petitioner's materials and plant at the site.
The respondents opposed the petition, alleging suppression of facts, that the petitioner did not complete the contract and that the contract was rescinded, with the unexecuted work to be completed departmentally. Respondent No. 1 claimed entitlement to recover Rs. 54,94,684/- from the petitioner and contended that the materials at site belonged to respondent No. 1. Respondent No. 3 contended it was not a party to the arbitration agreement and the petition was not maintainable against it.
Legal Issues Presented
- Whether the petitioner has made out a prima facie case for grant of an interim injunction under Section 9 of the Arbitration and Conciliation Act, 1996.
- Whether the petition is maintainable against respondent No. 3, who is not a party to the arbitration agreement.
- Whether an injunction under Section 9 can reasonably be used to restrain respondents from using materials lying at the site claimed by the petitioner.
- Whether granting the injunction sought would amount to specific performance of a building contract and whether such relief is available under Section 9.
Arguments of the Parties
Petitioner's Arguments
- The petitioner contends it completed the work under Agreement No. 1/97 and that finishing items under Agreement No. 2/97 could only be executed after completion of the entire structural work of the complex; therefore the petitioner sought award of balance structural work.
- Due to alleged attempts by respondent No. 2 to give the unexecuted work to another contractor and alleged harassment, the petitioner sought interim relief under Section 9 to restrain respondents from awarding the work to others and from using the petitioner's materials, T&P, centring and shuttering lying at the site.
- The petitioner relies on the arbitration agreement and seeks interim protection until the arbitrator resolves the disputes.
Respondents' Arguments
- Respondents Nos. 1 and 2 alleged that the petitioner failed to complete the contract within the stipulated time; despite notice the petitioner did not execute the remaining work and the contract was rescinded.
- They asserted the unexecuted part would be completed departmentally and respondent No. 1 is entitled to recover Rs. 54,94,684/- from the petitioner for excess payment.
- They further contended that the material lying at the site belonged to respondent No. 1.
- Respondent No. 3 argued it was not a party to the arbitration agreement and therefore the petition was not maintainable against it.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The court proceeded with a step-by-step analysis based on the pleadings, documentary material and correspondence on record:
- Maintainability against respondent No. 3: The court noted it was "admittedly" common ground that respondent No. 3 was not a party to the arbitration agreement and therefore the petition was liable to be rejected against respondent No. 3 on that ground alone.
- Nature of petitioner's case: The court examined the petition and a letter from the petitioner to respondent No. 3 dated 13-8-1998 (quoted in the opinion) in which the petitioner explained the cause of delay and requested award of the balance work. From these materials the court observed that the petitioner appeared to assume that it had an understanding or expectation that it would be awarded the remaining structural work.
- Evidentiary support: The court found no document on record to support the petitioner's asserted assumption or entitlement to the balance work. The court emphasized that granting the injunction sought would, in effect, amount to granting specific performance of the contract (i.e., restraining the employer from awarding work to others), which Section 9 is not intended to accomplish.
- Authoritative text cited: The court referred to a passage from Donalds Keatings Law and Practice of Building Contracts (2nd Edition) to the effect that, ordinarily, a contractor cannot obtain an injunction restraining forfeiture by the employer because that would be equivalent to specific performance, and the court does not normally grant such relief in building contract cases; damages are the usual remedy for wrongful forfeiture.
- Application of principle: Applying that principle, the court concluded that a building contract of the instant nature could not be specifically enforced by an interim order under Section 9 of the Act, and that damages would be the appropriate remedy for breach.
- Balance of convenience: The court found that granting the injunction would further delay construction works which respondent No. 3 considered very urgent; on that basis the balance of convenience favoured respondents and weighed against granting interim relief to the petitioner.
- Claim regarding materials at site: With respect to the petitioner's claim restraining respondents Nos. 1 and 2 from using material lying at site, the court observed that respondent No. 1 had sufficient documentary evidence to show ownership of the material. The court also noted that this dispute could be resolved by the arbitrator under the arbitration agreement.
- Conclusion from analysis: On these combined grounds — lack of documentary basis for the petitioner's claimed right to the balance work, the unsuitability of Section 9 to effect specific performance of a building contract, the balance of convenience favouring respondents, and documentary support for respondent No. 1's ownership of site materials — the court held that the petitioner failed to make out a prima facie case for an injunction under Section 9.
- Limitation as to merits: The court expressly stated that nothing in the order should be taken into account when disputes on merits are decided in future proceedings that parties may initiate.
Holding and Implications
DISMISSED
Holding: The petition under Section 9 of the Arbitration and Conciliation Act, 1996 fails and is dismissed. The interim ex parte injunction previously granted is vacated. There is no order as to costs. The final line of the opinion records: "Petition dismissed."
Implications:
- Direct effect on the parties: The petitioner’s application for interim relief is refused; the petition is dismissed and the interim order is vacated. Disputes between the parties remain to be adjudicated on merits (including by arbitration where applicable).
- Scope of decision: The court indicated that the relief sought (an injunction preventing the employer from awarding work to others or using materials) would amount to specific performance of a building contract, which the court declined to grant by way of interim relief under Section 9. The court directed that disputes such as ownership of materials are matters for arbitration or subsequent proceedings.
- No broader precedent is identified or established by the opinion beyond the court's application of established principle that interim injunctions under Section 9 should not be used to effect specific performance of a building contract; the decision addresses the petition before the court and leaves merits to future adjudication.
Note: Nothing stated in this summary invents facts beyond those contained in the provided opinion; matters not addressed in the opinion have been omitted in accordance with the instructions accompanying the exercise.
Judgement
By this order, I propose to dispose of the OMP No. 196/98 and the IAS Nos. 7479/98, 8503/98, 10451/98 and 11511/98.
2. IA No. 7479/98 is an application under order 39, rules 1 and 2, c.p.c. filed by the petitioner seeking an ad interim injunction. IAS Nos. 8503/98 and 10451/98 are applications filed by the respondents seeking vacation of the ex parte injunction order dated 2-9-98. IA No. 1511/98 is an application u/O. 7, R. 11, C.P.C. filed by the respondent No. 2 for rejection of the OMP No. 196/98.
3. To appreciate the merits of the controversy, it will be necessary to give brief narration of the material facts. The respondent No. 3 entered into an agreement with the respondent No. 1 for construction of D.I.T. Complex at Dwarka (Phase I and II). The estimated cost of the contract was Rs. 5,45,72,958/-. The respondent No. 1 invited labour rate tenders for construction of Boys Hostel at D.I.T. Complex, Sector 3, Dwarka, New Delhi. Consequent upon acceptance of tender submitted by the petitioner, the respondent No. 1 and the petitioner entered into two separate agreements dated 20-10-1997 (agreement No. 1/97 and agreement No. 2/97 Annexure A-3) by virtue of which the petitioner was to execute the work of construction of DIT complex (R.C.C. frame and brick work, flooring, furnishing and electrical installation work etc.) for a total estimated cost of Rs. 225 lacs. The stipulated dates of commencement of the work and the completion thereof were 20-10-1997 and 19-10-1998 respectively. According to the petitioner, the petitioner completed the work stipulated in the agreement No. 1/97 within six months. But, in certain items the quantities exceeded beyond the deviation limits provided in the agreement and the petitioner requested the respondent No. 1 to take decision with regard to the rates to be applied for the deviated quantities. The petitioner also represented to the respondent No. 1 to award balance work of the entire contract to it as the finishing items of the agreement No. 2/97 could be executed only on completion of the entire structural work of the DIT complex. However, the said representation did not evoke any positive response from the respondent No. 1. Since the respondent No. 2 wanted to take the unexecuted part the work out of the hand of the petitioner and give to another contractor, he started harassing the petitioner. Thus, the disputes have arisen between the petitioner and the respondent No. 1 in relation to the said contract which are to be resolved by arbitration in accordance with the arbitration agreement. On these allegations, the petitioner filed the present petition u/S. 9 of the Arbitration and Conciliation Act, 1996 (for short "the Act") for an interim relief by way an injunction restraining the respondents from getting the construction work executed from any other agency or contractor and from utilising the petitioners material, T and P, Centring and Shuttering etc. lying at the site.
4. The petition has been opposed by the respondents on the ground that the petitioner has deliberately suppressed the material facts. According to the respondents Nos. 1 and 2, the petitioner did not complete the contract within the stipulated time. Despite service of notice, the petitioner did not execute the remaining work in accordance with the contract as a result whereof the contract was rescinded by the respondent No. 1. The unexecuted part of the work is to be completed departmentally. The respondent No. 1 is entitled to recover a sum of Rs. 54,94,684/- from the petitioner on account of excess payment made to it. It is further alleged that the material lying at the site belonged to the respondent No. 1. On these allegations, it is contended that the petitioner has failed to make out a case for grant of temporary injunction. The respondent No. 3 pleaded that since the respondent was not a party to the arbitration agreement, the present petition is not maintainable against it.
5. At the outset, I must make it clear that admittedly the respondent No. 3 is not a party to the arbitration agreement and so the petition is liable to be rejected against the respondent No. 3 on this count alone.
6. The question is : whether the petitioner has made out a prima facie case for grant of injunction under S. 9 of the Act. It is beyond the pale of controversy that the respondent No. 3 awarded a contract to the respondent No. 1 for construction of D.I.T. Complex, Sector 3, Dwarka, New Delhi for a total cost of Rs. 5,45,72,958. Part of the contract work was awarded to the petitioner vide two separate agreements dated 20-10-97 (Anneuxre A/3). The stipulated dates of commencement of the work and the completion thereof were 20-10-97 and 9-10-98 respectively. The petitioner did not complete the finishing work stipulated in the agreement No. 2/97 as a result whereof the hostel could not be occupied by the students of the D.I.T. According to the petitioner, the said work could be executed only on completion of the entire structural work of the complex. It is also undisputed that a dispute has arisen between the petitioner and the respondent No. 1 in relation to the contract, which is to be resolved by an arbitrator in accordance with the arbitration agreement. The petitioner and the respondent No. 1 has made claim and counter claim against each other.
7. It is significant to mention that on 13-8-1998, the petitioner addressed a letter (at page 87 of the Part II of the paper book) to the respondent No. 3 explaining the cause of delay in executing the work stipulated in the agreement No. 2/97. The relevant paragraphs of the letter are as under :-
"(1) The work was awarded to us on labour rates and we had executed the work of about Rs. 14 lacs when the RSBCC Ltd. awarded the work to us on with material basis. The total work to be executed was to be to the tune of Rs. 550 lacs. However, it was decided that the work could be divided into two agreements amounting to Rs. 225 lacs each because of departmental constraint of CMD. Each agreement which further sub-divided into two parts - one relating to RCC frame work, brick work and the other relating to finishing flooring and electrical installations etc. The date of start as per agreement was 20-10-97 and the stipulated date of completion was 19-10-98.
(2) That on the work being sub-divided into two parts the items with respect to structural work were completed by us way back in March 98 i.e. within a period of 5 months and also executed many items the quantities of which exceeded beyond the deviation limit provided in the agreement. We were unable to start the finishing items under agreement No. 2/97 due to the fact that the structural work was incomplete and in many cases quantities were exceeding. No decision till today has been taken with regard to the completion of the structural work, as a result of which the work of staff housing type I, II and III is at a stand still from the month of May, 1998. Till the time we are awarded the balance structural work, we cannot execute the finishing items under Agreement No. 2/97.
For the best interest of the project we request you to intervene and award us the balance work."
8. On a combined reading of the averments made in the petition and the aforesaid paragraphs of the letter, it appears that the petitioner wants to plead that the contract in question was awarded to it with a clear understanding that the contract for remaining part of the work would also be awarded to it. It is for this reason only, the petitioner has been insisting that the finishing work stipulated in the agreement No. 2/97 could be executed only on completion of the entire structural work of the complex. There is no document on record to support the said assumption of the petitioner. If the injunction sought by the petitioner is granted it would have the effect of practically granting the relief for specific performance of the contract, which relief cannot be granted under Section 9 of the Act. In Donalds Keatings Law and Practice of Building Contracts (2nd Edition), the remedy open to a contract on a wrongful termination of the contract is stated in following terms :
"In the ordinary case, the contractor cannot obtain an injunction restraining forfeiture by the employer because this would be equivalent to specific performance of the contract and the Court does not normally grant this remedy in the case of a building contract. The contractor can be adequately compensated in damages, for wrongful forfeiture."
9. On a consideration of the facts and circumstances of the case, I am of the opinion that a building contract of the instant nature cannot be specifically enforced by granting interim relief under Section 9 of the Act. If there is a breach of such a contract, the appropriate remedy is to compensate the party damnified in damages. That apart, the granting of an injunction in favour of the petitioner will further delay the construction work considered very urgent by the respondent No. 3. Thus, the balance of convenience also swings against the grant of injunction sought by the petitioner.
10. The petitioner has also sought an injunction restraining the respondents Nos. 1 and 2 from using the material lying at the site. It is alleged by the respondent No. 1 that the aforesaid material belonged to it. There is sufficient documentary evidence on record to support the said contention of the respondent No. 1. Moreover, this dispute also can be resolved by the arbitrator in terms of the arbitration agreement. I, therefore, hold that the petitioner has failed to make out a prima facie case for grant of the injunction sought by it.
11. Before I part with the order, I would like to make it clear that nothing stated herein shall be taken into consideration, when the disputes between the parties on merits are decided in any future proceedings that any party may be advised to initiate.
12. In the result, the petition under Section of the Act fails and is dismissed. Interim order is vacated. No order as to costs.
Petition dismissed.