Shri Satish Kumar v. Cpwd (Through Shri A.P Singh, Chief Engineer) Public Authority.

Central Information Commission
Jan 7, 2009

By his letter of 12.4.2008, the appellant had requested for information on 6 points relating to year-wise vacancies available/filled up for the post of Executive Engineer (Civil) under RR 1954 & RR 1996.

2. As the CPIO did not provide him any information, he has filed the present appeal.

3. The matter was heard on 7.1.2009. The appellant appeared before the Commission. CPWD is represented by the officer mentioned above. During the hearing Shri R.P. Meena, Dy. Director (Admn) furnished a copy of letter dated 4.11.2008 addressed to the appellant containing the information sought by him. The appellant, however, is not satisfied with the information furnished to him and requests for inspection of the relevant file. Shri A.P. Singh has no objection to inspection of the file by the appellant. DECISION

4. In view of the above, Shri A.P. Singh, Chief Engineer is hereby directed to permit inspection of the concerned file/files by the appellant in the presence of CPIO and furnish copies of documents as requested for by him, as per the provisions of the RTI Act.

5. The order of the Commission may be complied with in 04 weeks time.

6. The matter is disposed of with the above directions. Sd/- (M.L. Sharma) Central Information Commissioner Authenticated true copy, Additional copies of orders shall be supplied against application and payment of the charges, prescribed under the Act, to the CPIO of this Commission Sd/- (K.L. Das) Assistant Registrar