Namasivaya Gurukkal And Ors. v. Kadir Ammal And Ors.

Madras High Court
Oct 5, 1893
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Provided Opinion

Factual and Procedural Background

Seven defendants, who were salt manufacturers holding pans at the Vattanam factory, entered into a contract (referred to as A.) dated 16 November 1884 with one Nur Mahomed. Under the contract the defendants agreed, in consideration of Nur Mahomed discharging Government taxes, executing certain repairs and paying them Rs. 11 1/2 per garce of salt, to manufacture and store salt in the factory in the name of and for the benefit of Nur Mahomed for seven seasons from 11 April 1885 to 10 April 1892.

It was found by the lower courts that the 1st plaintiff (Mahomed Aliar Row-ther) was a party with Nur Mahomed to the contract though not expressly named; his share was 2 1/5 shares and Nur Mahomed's was the balance (3 3/8). Nur Mahomed assigned his share to the 2nd plaintiff by deed Z dated 11 January 1886.

The plaintiffs sued in February 1887 alleging that while the contract was fulfilled for the 1885 season up to 14 January 1886, the defendants failed to perform for the 1886 season. The plaintiffs prayed for delivery of salt collected and heaped in 1886, for damages (specifically against defendants Nos. 2, 4 and 7), for separate powers of attorney to be executed by each defendant, and for a general declaration of rights. The trial yielded numerous issues; most were found for the plaintiffs. The trial court decreed (10 January 1890) a general declaration of plaintiffs' rights, recognized the 2nd plaintiff's right to sue as assignee, directed each defendant to execute separate powers of attorney, and ordered each defendant to pay damages for the years 1886–1889 at Rs. 5-12-0 per garce with quantity to be ascertained in execution, and to pay plaintiffs' costs.

The opinion describes defects in that decree (see below), and notes the appellate court sustained and aggravated those defects (adding year 1885, enhancing the rate of damages to Rs. 45-10-0 per garce, and again treating defendants as jointly and severally liable for costs, while leaving amounts to be determined in execution).

Legal Issues Presented

  1. Whether the 2nd plaintiff had a right of suit under the assignment from Nur Mahomed (i.e., whether the contract was assignable).
  2. Whether the suit was bad for misjoinder (i.e., improper joinder of parties or causes).
  3. Whether the trial and appellate decrees were defective in particular respects identified by the court (damages awarded for more years and against all defendants, leaving quantification to execution, joint-and-several costs despite separate contracts).
  4. Whether the rate of damages allowed by the appellate court was opposed to the terms of the contracts between the parties.

Arguments of the Parties

Appellants' (First Six Defendants') Arguments

  • The 2nd plaintiff had no right of suit because Nur Mahomed was not competent to assign his interest in contract A — the contract was based on personal considerations and/or rights coupled with liabilities, rendering it non-assignable.
  • The suit was bad for misjoinder (improper joining of parties/issues).
  • The decrees were defective in the respects identified by the court (overbroad award of damages, leaving quantification to execution, and joint-and-several costs contrary to separate contracts).
  • The appellate court's assessed rate for damages (as enhanced on appeal) was contrary to the contractual terms between the parties.
  • In support of the non-assignability contention, appellants' counsel relied on the cases Farrow v. Wilson, Humble v. Hunter, and Arkansas Valley Smelting Co. v. Belden Mining Co., and on principles discussed in Pollock's Treatise on Contracts.

Plaintiffs' / 2nd Plaintiff's Arguments (as presented in the opinion)

  • The plaint alleged the defendants failed to fulfil their obligations for the 1886 season and sought delivery of salt collected in 1886, damages (against specific defendants), separate powers of attorney, and declarations of right.
  • The 2nd plaintiff contended that after assignment defendants accepted payment from him for salt delivered, as shown by entries in accounts C to C4 and D — argued as evidence of recognition of the 2nd plaintiff's rights as assignee.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Farrow v. Wilson, L. R. 4 O. P. 744 Principle that contracts founded on personal considerations (e.g., principal and agent, master and servant) are dissolved by the death of a party; such personal-service contracts are not assignable in substance. The appellants relied on this principle to argue non-assignability. The court summarized the case and accepted the underlying principle as part of the body of authority showing when contracts are non-assignable; it found analogous elements (personal credit/liability and reliance on the particular contracting party) present in the contract A.
Humble v. Hunter, 12 Q. B. R. P. 310 Principles discussed: (1) a principal may sue on a contract made by his agent; (2) parol evidence cannot contradict a written contract; and the right of a contracting party to obtain the benefit from the particular character, credit and substance of the party contracted with. The case was relied upon to show that where the contracting party is described in a special way (asserting title/character) or where personal attributes were crucial to the contract, assignment or substitution is barred. The court considered these principles among the authorities supporting the conclusion that contract A involved personal considerations affecting assignability.
Arkansas Valley Smelting Co. v. Belden Mining Co., 127 U.S. 379 Rule that a contracting party has the right to select with whom he contracts and cannot be compelled to accept another person in place of the original contracting party where rights are coupled with liabilities and reliance on the original party's character/solvency exists. The court cited this American case to illustrate that executory contracts involving continuing obligations and reliance on the credit/solvency of the original contracting party are not assignable without consent. The court applied the same reasoning to contract A (credit period, liabilities, and discretion vested in Nur Mahomed), concluding the assignment to the 2nd plaintiff was invalid absent assent.
Govind Bin Lakshman Shet v. Dhondbarav Bin Ganbarav Tambye, I.L.R. 15 B, 104 Authority that a small cause suit is not open to second appeal (i.e., limited appellate remedy for small cause matters). The court cited this authority in addressing the res judicata contention. It noted that a previous small-cause suit (No. 447 of 1886) was not open to second appeal and thus could not produce res judicata on the point raised in the present suit; the court therefore rejected the res judicata objection based on that line of authority.
Vithilinga Padayachi v. Vithilinga Mudali, I.L.R. 15 M, 111 Followed the principle in Govind Bin Lakshman Shet regarding small cause suits and appealability. The court referenced this decision as following the same principle and relied on it to support the conclusion that the earlier small-cause decision did not bar the present suit by res judicata.

Court's Reasoning and Analysis

The court examined the character of contract A and the nature of the assignment Z, and applied established principles concerning assignability of contracts:

  1. The court identified contractual provisions demonstrating that Nur Mahomed had been given credit (Article (1): four months' time for payment), assumed liabilities (Article (4): payment of Government taxes and dues; Article (5): execution of all but petty repairs), and had discretion in the quantity of salt to be demanded (Article (6)). These features showed the contract involved both rights and liabilities dependent on Nur Mahomed's solvency and discretion.
  2. The assignment Z was an assignment of an executory or continuing contract (made 11 January 1886) and the breach complained of occurred after that date. The court considered the authorities cited by appellants which establish that rights cannot be transferred when they are coupled with liabilities or when the contract is predicated on personal confidence in the particular contracting party.
  3. The court found no evidence of the defendants' assent to the assignment, nor any evidence amounting to a novation as contemplated by Section 62 of the Indian Contract Act. Hence the assignment lacked the necessary consent or novation to be effective against the defendants.
  4. The plaintiffs' reliance on account entries (C to C4 and D) showing payments was examined; the court observed that those entries were kept in the names of both the 1st and 2nd plaintiffs and thus did not constitute distinct proof of direct recognition by the defendants of the 2nd plaintiff's rights as assignee.
  5. On these grounds the court allowed the objection that the contract was not capable of assignment to the 2nd plaintiff and concluded that the 2nd plaintiff had no right of suit under the assignment.
  6. Separately, the court analyzed the decrees of the trial and appellate courts and found multiple procedural and substantive defects: (a) damages were decreed for multiple years and against all seven defendants where the plaint claimed damages for 1886 only and against specific defendants; (b) the decree improperly reserved for execution matters (quantification of each defendant's damages) that should have been determined by the decree itself; and (c) the decree made defendants jointly and severally liable for costs despite findings that each defendant's contract was separate.
  7. The court addressed a res judicata objection based on an earlier small-cause suit (No. 447 of 1886). It held that the earlier suit (a small cause matter) was not open to second appeal and only decided that the plaintiff there had not executed repairs; it did not determine that the contract was void or rescinded and therefore did not bar the present cause of action. The court disallowed the res judicata objection.
  8. Finally, the court instructed that the second appeal be treated similarly to the bulk of appeals: it would reverse and remand with directions to ascertain and decree the actual amount due by the defendants to the 1st plaintiff.

Holding and Implications

Core Ruling: The court held that the assignment of contract A to the 2nd plaintiff was invalid against the defendants and therefore the 2nd plaintiff had no right of suit under that assignment.

Additional rulings and consequences explicitly stated in the opinion:

  • The court found multiple defects in the trial and appellate decrees (awarding damages for additional years and against all defendants beyond the plaint, leaving quantification to execution, and imposing joint-and-several liability for costs despite separate contracts). These defects were noted as legal errors.
  • The court rejected the res judicata objection based on the earlier small-cause proceeding, finding that the earlier decision did not bar the present suit.
  • The court directed a reversal and remand of the relevant appeal(s) with instructions to determine and decree the actual amount due by the defendants to the 1st plaintiff. The opinion indicates that the matter should be treated like most of the other appeals and remanded for precise ascertainment of liability (i.e., quantification of damages properly determined at decree rather than left to execution).

The opinion does not state any broader legal precedent newly established; the decision applies existing authorities and legal principles to the facts to reach the conclusions above.

Show all summary ...

1. The seven defendants were salt manufacturers holding pans in the factory at Vattanam and they entered into the contract A. dated the 16th November 1884 with one Nur Mahomed engaging themselves in consideration of the said Nur Mahomed discharging the Government taxes and executing certain repairs and paying them at the rate of Rs. 11 1/2 per garce of salt, to manufacture and store in the factory in the name of, and for the benefit of, the said Nur Mahomed such quantities of salt as he might require them to manufacture each season for seven years from 11th April 1885 to 10th April 1892.

2. It has been found as a fact by both the lower courts on the 4th issue raised in the case that the 1st plaintiff Mahomed Aliar Row-ther (now deceased but represented by respondents Nos. 1 to 4) was a party with Nur Mahomed to the contract, though he is not expressly mentioned therein. The 1st plaintiff's share was 2 in 5f shares ; and Nur Mahomed's share was the balance 3| shares. Nur Mahomed assigned his 3 3/8 shares to 2nd plaintiff (now deceased but represented by respondents Nos. 5 and 6) under the deed of assignment Z dated 11th January 1886.

3. This suit was brought in February 1887 against the seven defendants alleging that while the contract had been fulfilled on both sides for the season of 1885 up to the 14th January 1886, the defendants had failed to fulfil their part of it for the season of 1886 and praying that all the defendants should be directed to deliver to plaintiffs the salt they had collected and heaped in 1886, and that defendants Nos. 2, 4 and 7 should be specially held liable for any damages plaintiffs might suffer through a fall in the price of salt. There was also an incidental prayer that each defendant should be directed to execute a separate power of attorney to the plaintiffs as required by the salt department in lieu of a single instrument that had been jointly executed by them, and for a general declaration of plaintiff's rights. Several issues of law and of fact were raised at the trial, all of which have been found in favor of plaintiffs except that the agreement A was held good so far as the stamp duty was concerned only as against one of the defendants, and penalties were levied upon it in regard to the other six defendants, it being rightly held that it contained seven separate and distinct contracts, each defendant having entered into a separate engagement in regard to his own pans only. The decree of the Court of First Instance after a general declaration of plaintiff's rights including the right of the 2nd plaintiff to sue as the assignee of Nur Mahomed and a direction for each defendant to execute a separate power of attorney as prayed in the plaint, further directed each of the seven defendants to pay plaintiff's damages for the years 1886 to 1889 (the decree being dated 10th day of January 1890) at the rate of Rs. 5-12-0 per garce for the salt collected by each of them during those years leaving the quantity to be ascertained in the execution of the decree, and also directed the defendants to pay the plaintiff's costs.

4. It may as well at once be noted that this decree is bad in three different respects :--1st, in decreeing damages for the four years 1886 to 1889 and that against all the seven defendants when in the plaint damages for the year 1886 alone was or could be asked for and that against only defendants Nos. 2, 4 and 7, the claim against the others being only for the delivery of specific salt ; 2ndly, in reserving for determination in execution what was necessary for determination by the decree itself, namely, the amount of each defendant's liability to damages ; and 3rdly, in mating the defendants jointly and severally liable to plaintiff's costs, when as it had been found that the contract of each was separate, they were liable only to pay costs on the amount of damages assessed against each of them separately. The decree of the appellate court without remedying any of the defects noticed perpetuates and even aggravates them. Thus another year--the year 1885--is added to the other four years 1886, 1887, 1888, and 1889 for which all the defendants are to pay damages apparently jointly and severally and they are again in appeal also made severally and jointly liable for the plaintiffs' costs ; the amount of their liability in damages being still left for determination in execution. The appellate court also enhanced the rate to be paid as damages from Rs. 5-12-0 to Rs. 45-10-0 per garce.

5. The chief points taken in second appeal by the first six defendants are as follows:

(1) That the 2nd plaintiff had no right of suit on the assignment.

(2) That the suit was bad for misjoinder.

(3) That the decrees are defective in regard to the matters just pointed out, and (4) That the rate allowed by the appellate court for damages is opposed to the terms of the contracts between the parties.

6. As to the 1st objection it is that Nur Mahomed was not competent to assign his interest in the contract A. It is argued that the contract was based on personal considerations and that the rights conferred upon Nur Mahomed by the contract were coupled with liabilities and that on both these grounds the contract was not assignable. In support of this contention the appellants' pleader relied on Farrow v. Wilson L. R. 4 O. P., 744, Humble v. Hunter 12 Q. B. R. P., 310, and Arkansas Valley Smelting Company v. Belden Mining Company 127 United States Reports, 379. In Farrow v. Wilson the contract in suit was an agreement whereby the plaintiff undertook to serve one Pugh as farm bailiff, the agreement being terminable upon six months' notice on either side, The question for decision was whether the death of Pugh put an end to the contract which did not contain the word 'assigns' and it was held that it did. The ground of decision was that in contracts for personal service, it is an implied condition that death of either party should dissolve the contract. Justice Willis laid down the principle which governed the case in these terms :--"Where personal considerations are of the foundation of the contract as in cases of principal and agent and of master and servant, the death of either party puts an end to the relation." The contract in Humble v. Hunter was a charter-party signed by the plaintiff's son on the one part and by the defendant on the other, and it recited that the son was the owner of the ship. The question was whether the plaintiff might show whether she was the real principal and that her son though he signed the contract was really agent. Two principles were discussed, viz., (1) that a principal may come in and take the benefit of a contract made by his agent, and (2) that no parol evidence shall be admitted to contradict a written contract. It was held that the evidence was not admissble, the reason being that the son gave himself a special description and asserted a title to the ship as owner, and that this circumstance took the case out of the general rule, that a principal may sue upon the contract made by his agent. Lord Denman, C.J. referred to the general principle that a party to a contract has a right to the benefit he contemplates from the character, credit and substance of the party with whom he contracted. In the American case, the contract was to sell and deliver lead ore from time to time at the smelting works of a firm of partners, that the ore was to become upon delivery the property of the partnership and that it was to be paid for after a subsequent assay of the ore and ascertainment of the price. The question was whether the partnership might assign the contract as to future deliveries and it was determined in the negative. The court stated that every one has a right to select and determine with whom he will contract and cannot have another person thrust upon him without his consent. It also referred to the principle mentioned by Lord Denman, namely "you have the right to the benefit you anticipate from the character, credit and substance of the party with whom you contract." It referred to the rule in Pollock's Treatise on Contracts, Fourth Edition, p. 425, that rights arising out of a contract cannot be transferred if they are coupled with liabilities or if they involve a relation of personal confidence such that the party whose agreement conferred those rights must have intended them to be exercised only by him in whom he confided. Applying that principle to the case before them the court remarked that during the time that must elapse between the delivery of the ore and the ascertainment and payment of the price the defendant had no security for the payment except in the character and solvency of Billing and Eilers, the parties with whom he made the original contract. The defendant therefore could not be compelled to accept the liability of any other person or corporation as a substitute for the liability of those with whom he had contracted.

7. Now in this case it will be seen from the terms of the contract A which are set forth in full in the judgment of the Lower Appellate Court, and need not therefore be repeated here, that by Article (1) the defendants were to allow Nur Mahomed four months' time for payment after delivery of their salt to him, by Article (4) that he was liable to pay the Government taxes and dues, by Article (5) that he was to execute all but petty repairs, and by Article (6) that he was to fix the quantity of salt to be delivered by defendants. There is therefore not only credit given to NUT Mahomed in the matter of payment but other liabilities are thrown upon him the discharge of which depended upon his solvency, and there is also a certain discretion vested in him in regard to the quantity of salt to be demanded, Further, the assignment Z upon which the 2nd plaintiff was suing was an assignment of an executory or continuing contract. The assignment was made on the 11th January 1886 and the breach of contract sued upon was for a breach subsequent to that date. Be that we have here all the eleirrents which we find in the principles above laid down for holding that the contract was based on personal considerations and that the assignment of it as an executory contract was invalid without"the assent of the defendants. It is not pretended that such assent was expressly given, nor is there evidence on the record of such a character as would amount to a novation of the contract such as is contemplated by Section 62 of the Indian Contract Act. It is contended for the 2nd plaintiff that after the assignment to him the defendants accepted payment from him for salt delivered as is shown by entries in the accounts C to C4 and D. But those accounts are kept in the name of the 1st plaintiff as well as of the 2nd plaintiff so that they afford no distinct proof of a direct recognition of the 2nd plaintiff's rights as, assignee. On the grounds that have been stated we must allow the objection that the contract was one not capable of assignment to 2nd plaintiff and therefore that he had no right of suit under it.

[The court, after having decided the other objections raised, proceeded as follows:]

8. In Second Appeal No. 94 the Munsif dismissed the plaintiff's suit as barred by res judicata but the judge reversed the Munsif's decree without apparently noticing this point. The appellant in this second appeal now urges that this suit should be dismissed on the ground stated but we do not agree with the Munsif that the case was res judicata by reason of the decision in a similar suit (No. 447 of 1886). -Not only was that a suit of a small cause nature and therefore not open to second appeal, (Govind Bin Lakshman Shet v. Dhondbarav Bin Ganbarav Tambye I. L. R. 15 B, 104 followed in Vithilinga Padayachi v. Vithilinga Mudali I. L. R. 15 M, 111), but the simple issue therein decided was that plaintiff was not entitled to relief as he had not executed repairs. It was not decided that the contract was void or had been rescinded and the cause of action now though upon the same contract being for a different year, there is no res judicata. We therefore disallow this objection and as the other special objection is abandoned, this second appeal falls to be treated like the bulk of them, and will be dealt with accordingly by a reversal and remand with similar directions to find out and decree what actual amount is due by defendant to 1st plaintiff.