Trusses & Towers (P) Ltd. v. Assam State Electricity Board And Another
Factual and Procedural Background
This opinion addresses an application filed under Article 226 of the Constitution of India seeking a direction to respondents to comply with Section 4 of the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993. The petitioner, a registered small scale industry, claims to have supplied P.S.C. coals to ASEB pursuant to orders dated 17.2.92 and 17.3.92 and raised bills for the supply. The bills were ultimately paid on 8.10.93, and no amount remains due. The petitioner’s claim is limited to entitlement of interest for delayed payment under the Act. The application is not for recovery of the principal amount but seeks a writ directing compliance with the interest payment provisions. The court notes that recovery of amounts due under the Act is to be pursued through a suit or other appropriate proceeding, not by writ petition.
Legal Issues Presented
- Whether a writ direction should be issued commanding the respondents to comply with the requirements of Section 4 of the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The court examined the statutory scheme of the Interest on Delayed Payments Act, particularly Sections 4, 5, and 6. Section 4 mandates interest payment by buyers on delayed payments, while Section 6 provides the remedy for recovery through a suit or other legal proceeding. The court emphasized that this writ application is not a substitute for such a suit and that the petitioner has not initiated the prescribed recovery procedure. Since the principal amount was already paid and no amount remains due, the court found no basis to grant the writ relief seeking direction for interest payment compliance. The writ court is not the appropriate forum to adjudicate disputes regarding the entitlement and calculation of interest under the Act, which must be resolved in a suit or proceeding under applicable law.
Holding and Implications
The writ application is dismissed for lack of merit.
The direct consequence of this decision is that the petitioner is not entitled to a writ directing the respondents to comply with Section 4 of the Act in the absence of a pending suit or proceeding for recovery. The judgment leaves open the petitioner’s right to file a civil suit for recovery of interest under the Act. No new legal precedent is established by this decision; it reiterates the procedural requirement that recovery under the Act must be pursued through appropriate legal proceedings rather than writ petitions.
1. This application under Article 226 of the Constitution of India has been filed praying the relief that a direction be issued to the respondents to comply with the requirements of Section 4 of the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 (hereinafter referred to as the ‘Act’). This Act was enacted to provide for and regulate the payment of interest on delayed payment to small Scale and ancillary industrial undertakings and for matters connected there with or incidental thereto. The Act came into force on the 23rd day of September, 1992.
2. Section 2 provides for definitions. Section 2(a) is the definition of “ancillary industrial undertakings” Section 2(b) as the definition of “appointed day” and the explanation to that sub-section also defines what is the “day of acceptance;” the day of deemed acceptance”.
3. Section 2(c) defines “buyer”. Section 2(d) defines “goods”. Section 2(e) defines “small scale industrial undertaking”. Section 2(f) defines “suppliers”. Section 3 provides the liability of buyer to make payment. Section 4 provides the date from which and rate at which interest is payable. Section 4 is quoted below:
“4 Where any buyer falls (sic, fails) to make payment of the amount to the supplier, as required under section 3, the buyer shall, notwithstanding anything contained in any agreement between the buyer and the supplier or in any law for the time being in force, be liable to pay interest to the supplier on that amount from the appointed day or, as the case may be, from the date immediately following the date agreed upon at such rate which is five per cent points above the floor rate for comparable lending.
Explanation-For the purposes of this section, “floor rate for comparable lending” means the highest of the minimum lending rates charged by scheduled banks (not being, co-operatives banks) on credit limits in accordance with the directions given or issued to banking companies generally by the Reserve Bank of India under the Banking Regulation Act, 1949.”
4. Section 5 provides for liability of the buyer to pay compound interest. Section 6 provides for recovery of the amount due. Section 6 is quoted below:
“6. The amount due from a buyer, together with the amount of interest calculated in accordance with the provisions of section 4 and 5, shall be recoverable by the supplier from the buyer by way of a suit or other proceeding under any law for the time being in force.”
5. Section 7 provides for appeal. We are not concerned with the other sections for determination of the controversy in this matter.
6. The only question which arises for determination is as to whether a direction should be issued commanding the Respondents to comply with the requirements of Section 4 of the Act. As indicated above, Section 6 provides for recovery of the amount due and this application is not an application for recovery of the amount due. So, as and when such a proceeding is brought by way of a suit or other proceeding, that question is to be determined by an appropriate court and remedies sought for in this writ proceeding is not necessary to be given in the instant case. Yet, let us have a look on the facts of the present case. The petitioner in paragraph 2 of the writ application claims that it is a small scale industry and it is registered as such, by the District Industries Centre. There was a direction on 17.2.92 and 17.3.92 for supply of P.S.C coals to ASEB. The petitioner claims to have supplied the coals numbering 3,900/- by both the orders dated 17.2.92 and 17.3.92 Bills were raised for the supply of coals and ultimately the bill were finally paid on 8.10.93 So, as on today, no amount of the bills is due to the petitioner. The only claim in this writ application is that they are entitled to interest for delayed payment under the Act. But what is the due amount has not been stated anywhere and there is necessity to decide this claim and question in an appropriate suit and/or proceeding. The writ court cannot decide that matter. This writ application cannot be short cut for recovery of the amount said to be due to the petitioner. Section 6 provides for filing of a suit or other proceeding under any law for the time being in force. That procedure provided for has not been resorted by the petitioner and this writ court is not the appropriate court to grant relief an claimed by the petitioner.
7. In that view of the matter, there is no merit in this writ application and accordingly, the same is dismissed. I, however leave the parties to bear their own costs.
8. I have heard Sri B.K Goswami, learned counsel for the petitioner and Sri N.N Saikia, learned Standing counsel for the ASEB.
9. This judgment shall not be a bar for filing the civil suit.