This order concerns pending petitions in which the Central Empowered Committee (CEC) has submitted a final report dated 3-2-2012. The Court adjourns the petitions for two weeks to allow the CEC to take into account the parties’ responses to that final report. The Court also directs the CEC to consider an unnumbered interlocutory application (IA) filed by the petitioner in Writ Petition (C) No. 562 of 2009 for appropriate recommendations. Separately, the matter “as regards CBI” is directed to be listed after two weeks, and certain IAs are dismissed as withdrawn.
Legal Issues Presented
The opinion addresses a procedural matter and does not frame distinct legal issues.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Court considers it appropriate to stand over (adjourn) the petitions for two weeks so that the CEC can incorporate and evaluate the parties’ responses to its final report dated 3-2-2012. The Court emphasizes urgency in hearing the “reclamation and rehabilitation” aspects of the case and indicates that it wishes to hear the parties on these aspects at the earliest. To facilitate expeditious rehabilitation, the Court directs parties appearing before it to cooperate with the CEC and to work out suitable principles/parameters.
As an interim step, the Court directs the CEC to consider an unnumbered IA filed by the petitioner in Writ Petition (C) No. 562 of 2009 and to make appropriate recommendations. The Court also directs that the matter relating to the CBI be placed after two weeks. Finally, it records that IAs Nos. 40-41 and an unnumbered IA relating to “Chidananda” are dismissed as withdrawn.
Holding and Implications
ADJOURNED / STOOD OVER FOR TWO WEEKS to enable the CEC to consider the parties’ responses to its final report dated 3-2-2012, with directions to the parties to cooperate with the CEC and develop principles/parameters for expeditious rehabilitation.
DIRECTION ISSUED to the CEC to consider an unnumbered IA filed by the petitioner in Writ Petition (C) No. 562 of 2009 and make appropriate recommendations.
LISTING ORDER: The matter “as regards CBI” is to be placed after two weeks.
DISMISSED AS WITHDRAWN: IAs Nos. 40-41 and the unnumbered IA relating to Chidananda.
The direct effect of the order is to defer further hearing briefly while the CEC processes responses and considers an additional IA, and to set the CBI-related aspect for listing after two weeks. The order also clears certain pending IAs by dismissing them as withdrawn. No broader legal implications or new precedent are stated in the provided text.
Order
1. The petitions shall stand over for two weeks in order to enable the Central Empowered Committee to take into account the responses of the parties to its final report dated 3-2-2012. We make it clear that this Court would like to hear the parties on reclamation and rehabilitation aspect of the case at the earliest. We want the parties appearing before us to cooperate with CEC and work out appropriate principles/parameters for expeditious rehabilitation. In the meantime, we direct CEC to consider the unnumbered IA filed by the petitioner in Writ Petition (C) No. 562 of 2009 for appropriate recommendations.
2. Place the matter as regards CBI after two weeks.
3. IAs Nos. 40-41 and the unnumbered IA relating to Chidananda are dismissed as withdrawn.