K.P. Latheef v. The Superintending Engineer Others

Kerala High Court
Feb 17, 1993
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The petitioner was awarded a contract (Ext. P-1 letter dated 4 January 1979) to widen, improve and lay an approach road from NH-47 to Indian Rare Earths, Chavara. An agreement was executed on 20 July 1979. The petitioner alleges that, when he commenced work, owners of lands acquired for the road obstructed construction demanding payment of compensation under the Land Acquisition Act; one such representation by residents is Ext. P-2. The petitioner sent a representation to the Government (Ext. P-4(a), dated 30 July 1980) explaining the obstruction and requesting relief or compensation. The first respondent issued Ext. P-3 (20 August 1980) threatening termination if work was not started; the petitioner replied by Ext. P-4 (8 September 1980) attributing delay to the department's failure to hand over and clear the site.

The petitioner later received a demand notice Ext. P-6 (10 December 1987) issued by the second respondent (Tahsildar) seeking Rs. 5,27,509 as damages alleged to have been suffered by the Government due to re-arrangement of the work. The petitioner obtained evidence (Exts. P-5, P-7, P-8, P-9) indicating the site remained uncleared and that the Government took possession of acquired properties only in 1984. Ext. P-10 indicates a subsequent tender (Viswambaran) was accepted by the first respondent (letter dated 22 April 1987).

The first respondent filed a counter-affidavit denying the petitioner's averments, asserting that the site was handed over in time (as reflected in the agreement) and that Ext. P-5 was a formal intimation; the first respondent maintained that the petitioner could have commenced work where there was no obstruction and is liable to compensate the Government to the extent claimed (difference between initial and subsequent tender amounts shown in Ext. P-10). The court heard counsel for the petitioner and the learned Government Pleader for the respondents.

Legal Issues Presented

  1. Whether Ext. P-6 (the demand notice dated 10 December 1987 seeking Rs. 5,27,509) can be sustained and is legally valid.
  2. Whether the Government (or its officer) may, without prior adjudication by an independent authority and without giving the contractor an opportunity of being heard, assess damages and recover them from the contractor.
  3. Whether, on the facts alleged (failure to hand over/clear site), the petitioner can be held liable for non-completion of the contract.
  4. Whether issuance and enforcement of Ext. P-6 violates the principles of natural justice and Article 14 of the Constitution of India.

Arguments of the Parties

Petitioner's Arguments

  • The petitioner was the lowest bidder and was awarded the work by Ext. P-1; an agreement was executed on 20 July 1979.
  • Work was obstructed by owners of acquired properties who refused entry until compensation under the Land Acquisition Act was paid (Ext. P-2 demonstrates such refusals).
  • The petitioner notified the Government by Ext. P-4(a) (30 July 1980) of the obstructions and requested relief/termination with compensation for losses already incurred.
  • The department failed to hand over and clear the site (telephone/electric posts, trees, buildings etc.); Exts. P-5 and P-7 to P-9 support that the site remained uncleared till 1987 and that possession by Government occurred only in 1984.
  • Despite obstructions the petitioner commenced some work (cutting hard soil, constructing a retention wall) demonstrating bona fides.
  • Ext. P-6 demand notice (issued in 1987) is unjustified because non-completion resulted from the department's failure to clear/hand over the site.

First Respondent's (Government) Arguments

  • The first respondent, by counter-affidavit, repudiated the petitioner's claims and maintained the site had been handed over in time (the agreement itself reflects timely handing over).
  • Ext. P-5 is, according to the first respondent, only a formal intimation not reflecting the true position.
  • The petitioner could have commenced work in portions of the site where there was no obstruction.
  • The petitioner is liable to compensate the Government to the extent of the amount demanded under Ext. P-6, being the difference between the initial tender and the subsequent tender accepted (Ext. P-10).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Sushila Devi v. Hari Singh, AIR 1971 SC 1756 Performance of a contract becomes impracticable/useless with respect to the parties' object and purpose; such supervening events must strike at the root of the contract to render performance impossible. The court acknowledged that the doctrine has definite bearing on the facts but declined to decide the case on this ground, preferring to dispose of the matter on the validity of Ext. P-6 under Article 14.
Govindbhai v. Gulam Abbas, AIR 1977 SC 1010 Reiteration of the law on impossibility/frustration of contract; cites classic exposition of frustration. Cited to support discussion of impossibility/frustration doctrine; court agreed with the proposition but did not rest its decision on it.
Tamplin Steamship Co. Ltd. v. Anglo-Mexican Petroleum Products Co. Ltd., (1916) 2 AC 397, 403 Famous articulation of frustration: parties are excused if substantially the whole contract becomes impossible of performance by a cause for which neither party is responsible. Quoted in the opinion (via Govindbhai) to explain the standard for frustration; the court accepted the principle but did not base the final decision upon it.
Satyabrata Ghose v. Mugneeram Bangur & Co., AIR 1954 SC 44 Support for the proposition that performance becomes impossible if impracticable from the point of view of the object and purpose envisaged by parties. Referred to as supporting authority for the frustration/impossibility analysis; the court invoked it as part of the jurisprudential backdrop but did not decide the case solely on this ground.
State of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli, AIR 1987 SC 1359 Holds that a State officer's power under a contract to assess damages is confined to cases where breach is admitted or not disputed; a party to the contract cannot be the adjudicator of a disputed breach. The court relied on this decision to hold Ext. P-6 illegal/arbitrary. The decision was used to emphasize that the Government cannot unilaterally adjudicate disputed breaches and assess damages without independent adjudication and fair hearing.
State of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli, AIR 1985 SC 607 (as cited in the opinion) (As cited) Similar proposition restricting the State's power to assess damages where breach is disputed; emphasises that the power to assess damages is subsidiary and does not carry with it a power to decide disputed breaches. The court references this authority in support of the proposition that the State cannot act as its own arbiter; the opinion indicates reluctance to enforce any clause (if present) that would permit such adjudication by the State.
Central Inland Water Transport Corporation Ltd. v. Broja Nath, AIR 1986 SC 1571 Authority wherein the Supreme Court declined to give effect to a clause in a standardized contract because of unequal bargaining power; supports non-enforcement of unfair contract clauses. The court cited this decision to justify reluctance to enforce any clause (if present) empowering the Government to adjudicate disputed breaches, on the basis that such clauses may be unfair where bargaining power is unequal.
Hyderabad Municipal Corporation v. Krishna Swamy, AIR 1987 SC 1359 Also cited as an instance where the Supreme Court declined to give effect to a clause in a standardized contract. Cited in conjunction with Central Inland Water Transport to support the court's approach to clauses in standardized contracts that permit one party to adjudicate disputes unilaterally.
Kamavarma Raja v. Tahsildar, Thaliparamba, 1988 (1) KLT (SN) P. 4 Holds that in disputes between Government and private parties the Government cannot be the arbiter of its own cause; in absence of proper adjudication Government cannot realise amounts purportedly due. This court noted that Kamavarma Raja followed the State of Karnataka decision and applied the same principle: the Government cannot unilaterally adjudicate and recover amounts without independent adjudication.

Court's Reasoning and Analysis

The court's analysis proceeded in identifiable steps grounded in fact-finding and principle:

  1. Evaluation of evidentiary material: The court examined Exts. P-2, P-4(a), P-5 and Exts. P-7 to P-9 and found that these documents collectively showed the site was not cleared of obstructions and that possession by Government occurred only in 1984. The court treated these documentary materials as confirming the petitioner's contention that the first respondent failed in the duty of handing over the cleared site to enable performance of the contract.
  2. Consequence for contractual performance: On the factual matrix, the court held that the petitioner could not properly be faulted for non-completion because the department's failure to clear and hand over the site prevented performance. The court observed that the events that occurred had affected the bargain and made performance impossible or impracticable in respect of the contract's foundation.
  3. Choice of legal grounds: Although the court acknowledged the relevance of the doctrine of impossibility/frustration (citing Sushila Devi, Govindbhai, Tamplin and Satyabrata Ghose), it expressly declined to decide the matter solely on that basis. Instead, the court chose to dispose of the matter by scrutinising Ext. P-6 under Article 14 and by considering applicable authorities on the limits of executive adjudicatory power under a contract.
  4. Principles of natural justice and Article 14: The court stressed that any order imposing civil consequences must be issued in accordance with natural justice; a citizen cannot be presented with a sudden demand without prior adjudication by a competent and independent authority and without opportunity to be heard. The court stated that adjudication of breach and assessment of damages are matters for an independent tribunal or court, not for one contracting party to decide against the other.
  5. Application of precedent on State adjudicatory power: Relying primarily on State of Karnataka v. Shree Rameshwara Rice Mills (and related decisions), the court held that the power of the State (or its officers) to assess damages is confined to cases where breach is admitted or undisputed; where breach is disputed the State cannot be the adjudicator. The court further cited authorities that caution against enforcing clauses in standardized contracts that permit one party (the State) to be the arbiter in its own cause.
  6. Conclusion on Ext. P-6: Based on these analyses, the court concluded that Ext. P-6—issued by the second respondent treating the petitioner as a defaulter and demanding a large sum—was issued without proper adjudication, was arbitrary and illegal, and violated Article 14 principles. Consequently, Ext. P-6 was quashed.

Holding and Implications

Holding: The court granted the petition and quashed Ext. P-6 (the demand notice dated 10 December 1987). The original petition was allowed. There was no order as to costs.

Implications:

  • Direct effect: The specific demand notice extant in this matter (Ext. P-6) stands quashed and the petitioner is relieved from the claimed liability under that notice.
  • Procedural principle reinforced: The decision reaffirms that where a contractual breach is disputed, the State (or its officer) cannot, without prior independent adjudication and without affording the affected party a hearing, unilaterally assess and recover damages; such action would violate principles of natural justice and Article 14.
  • Broader precedent: The opinion relies on existing Supreme Court authority and a High Court decision to apply established principles; the court did not purport to lay down a new, broader principle beyond the application of those precedents. The opinion does not state that it has created new law; it applies and follows cited authorities to the facts before it.

No other relief was ordered; the court recorded "There is no order as to costs."

Show all summary ...

1. This original petition is filed to quash Ext. P-6 demand notice issued by the second respondent for realisation of a sum of Rs.5,27,509 due as damages alleged to have been suffered by the Government on re-arrangement of work which was originally awarded to the petitioner by Ext. P-1 letter. The work in question relates to widening, improving and laying the approach road from N-H. 47 to Indian Rare Earths, Chavara.

2. First respondent invited tenders for the above work in June, 1978. The petitioner being the lowest bidder, the work was awarded to him by Ext. P-1 letter dated 4th January 1979 of the first respondent, and pursuant to Ext. P-1, the necessary agreement was executed by the petitioner on 20th July 1979. Under the terms of the agreement, the work has to be executed from the property acquired for the said purpose by the Government. The petitioner started the work immediately after the execution of agreement and according to the petitioner, when he started the work, the owners of the property whose lands were acquired on both sides caused obstruction as they did not allow the construction to proceed until compensation under the Land Acquisition Act is paid to them. The owners had made representations to Government claiming compensation, copy of one such representation (dated nil) is Ext, P-2 and a copy of which was served on the petitioner also. On receipt of Ext. P-2, the petitioner also made a representation Ext. P-4 (a) dated 30th July 1980 to Government. In Ext. P-4 (a) the petitioner, detailed the circumstances which resulted in the petitioner being not able to carry out the work because of the obstruction caused, by the owners whose property has been acquired and submitted to the Government that he will not be able to execute the work until compensation in full is paid to the owners of land and requested the Government to relieve him from the contractual obligations and to pay him the damages he has already suffered. The Government has not so far passed any order on Ext. P-4 (a), gays the petitioner. Shortly, after Ext. P-4(a), the first respondent served Ext. P-3 notice dated 20th August 1980 on the petitioner stating that the petitioner has not started work so far and if he does not complete the work within 10 days, the work will be terminated and got done by other agency at the petitioner's risk and cost. To Ext. P-3 the petitioner sent Ext. P-4 reply dated 8th September 1980 stating that the delay was caused solely on account of the lapses on the part of the Department in not handing over the site and clearing the site by cutting of trees, removal of telephone and electric posts, pillars, slab's, demolition of buildings on the acquired land, etc. The petitioner submits that he has not received any reply to Ext. P-4 or Ext. P-4(a) so far.

3. But, to the petitioner's utter consternation he received . a demand notice Ext. P-6 dated 10th December 1987 issued by the second respondent Tahsildar asking the petitioner to remit a sum of Rs. 5,27,509 being the loss suffered by the Government for re-arranging the work awarded to the petitioner as per Ext. P-1 letter. On receiving Ext. P-6 the petitioner made enquiries whether the Government have passed any orders on Exts. P-4 and P-4 fa) or any order terminating his work was passed by the Government. On. such enquiry, the petitioner came to know that the Government took possession of the acquired properties only in 1984 (i.e. 5 years after the award of the work) and the petitioner was able to obtain a copy of the intimation issued by the Land Acquisition Officer to the Assistant Executive Engineer (who is connected with the work) requiring the latter to be present on 30th August 1984 to take possession of the land acquired for the purpose of widening the road. Ext. P-5 is the copy of the letter addressed from the .Land Acquisition Officer to the Assistant Executive Engineer (B & R), Chavara. Ext. P-5 shows the details of the property directed to be taken possession of by the Land Acquisition Officer. Exts. P-7 P-8 and P-9 are also produced by the petitioner which will go to show that the site remained uncleared till 1987. Ext. P-7 dated 16th October 1987 is the letter from the Assistant Executive Engineer to "the Executive Engineer to take speedy steps for removal of obstruction and Ext. P-8 is again letter from Assistant Engineer to the Assistant Executive Engineer relating to improving and widening of approach road. Ext. P-9 is letter from the Manager of Indian Rare Earths Ltd., addressed to the Assistant Executive Engineer complaining that the department has not cleared the site by cutting the trees and demolishing and disposing of other structures. Ext. P-10 letter dated 22nd April 1987 produced by the petitioner shows that the tender submitted by one Viswambaran has been accepted by the first respondent.

4. A counter affidavit has been filed on behalf of the first respondent repudiating the averments contained in the original petition. According to the counter affidavit, the site was handed over to the petitioner well in time and the said fact is reflected in the agreement itself and Ext. P-5 is only a formal intimation to the petitioner which does not depict the correct position, that the petitioner could have commenced the work at places where there was no obstruction and, at any rate, the petitioner is liable to compensate the Government to the extend of the amount demanded under Ext. P-6 being the difference between the initial tender amount and subsequent tender amount for re-arranging the work through other agency as per Ext. P-10.

5. Heard learned counsel for the petitioner and the learned Government Pleader for the respondents.

6. It is the definite case of the petitioner that though the contract work in question was awarded to him as per Ext. P-1 letter of the first respondent as early as 4th January 1979, the first respondent failed to hand over the site in time after clearing obstructions like telephone and electric posts, buildings, etc., and hence the petitioner was prevented from executing the work. The petitioner has produced Ext. P-2 representation preferred by the residents of the locality to the Minister of Public Works claiming compensation for the property acquired. In Ext. P-2, the signatories had clearly stated that they will not allow any construction in the area till the compensation due to them is fully paid. On receipt of a copy of Ext. P-2, the petitioner also submitted Ext. P-4 (a) representation dated 30th July 1980 to Government detailing the circumstances which resulted in the petitioner being not able to carry out the work and stating that "till this day the departmental officials were not able to hand over the site and thus the petitioner's case could be treated as genuine and reasonable to have a termination of the work with the compensation for his loss." The statement of the petitioner contained in Ext. P-4 (a) is seen confirmed by Ext. P-5 letter of the Land Acquisition Officer addressed to the Assistant Executive Engineer requiring the latter to depute an officer to take possession of the land from the Revenue Inspector, Karunagappally at 10 a.m. on 30th August 1984. Further, Exts. P-7 to P-9 will show that the site was not cleared of obstructions and no action was taken to dispose of the building and other structures which were in dilapidated condition. The cumulative effect of Exts. P-4 (a), P-5 and P-7 to P-9 is that the first respondent failed in his duty in handing over the site to the petitioner after clearing all obstructions so as to enable the latter to commence the work. Under such a situation the petitioner cannot be faulted for non-completion of work. In fact, the bona fides of the petitioner is borne out by the fact that he commenced the work in spite of the fact that the site was not handed over to him and it was after cutting the hard soil for a considerable distance and putting up a retention wall after de-watering the pond which is not " provided for in the schedule of work.' The petitioner was resisted by the land owners stating that until the acquisition proceedings are completed and compensation is paid to them, they will not allow any work to be done in the property. According to me, the unexpected turn of events has affected the bargain which the parties have made and on account of the unexpected turn of events, the performance of the contract has become impossible for which the petitioner cannot be saddled.

7. In Sushila Devi v. Hari Singh AIR 1971 SC 1756 it was held (at page 1759) that "If the performance of a contract becomes impracticable or useless having regard to the object and purpose the parties had in view then it must be held that the performance" of the contract has become impossible. But the supervening events should, take away the basis of the contract and it should be of such a character that it strikes at the root of the contract." The above preposition was reiterated by the Supreme Court in a later decision in Govindbhai v. Gulam Abbas AIR 1977 SC 1010 wherein the court held as follows at page 1024:

"10. The meaning of the aforesaid expression 'impossible of performance as used in the above quoted section would be clear from the following observations made by Lord Loreburn in Tamplin Steamship Co. Ltd. v. Anglo-Mexican Petroleum Products Co. Ltd., (1916) 2 AC 397, 403 which is generally considered to contain a classic and terse exposition of the law relating to frustration:

The parties shall be excused if substantially the whole contract becomes impossible of performance or in other words impracticable by some cause for which neither was responsible."

11. We find ourselves in complete accord with this view which also finds support from the decisions of this court in Satyabrata Ghose v. Mugneeram Bangur and Co. (AIR 1954 SC 44) (Supra) and Smt. Sushila Devi v. Hari Singh, [(1971) 2 SCC 288 = AIR 1971 SC 1756] where it was held that the performance of a contract becomes impossible if it becomes impracticable from the point of view of the object and the purpose which the parties had in view and if an untoward event or change of circumstances totally upsets the very foundation upon which the parties rested their bargain, it can very well be said that the promisor found it impossible to do the act which he promised to do." 8. Though the legal principles enunciated in the above decisions have a definite bearing on the facts of the case, I decline to enter a finding based on the same as according to me, the matter can be disposed of on a consideration of the validity of Ext. P-6 demand notice in the light of Art.14 of the Constitution of India and in the light of judicial pronouncement touching on the subject.

9. Now coming to the question of recovery of damages from the petitioner as per Ext. P-6, I am of the view that the said proceedings cannot be legally sustained. Ext. P-6 demand notice is seen issued by the second respondent treating the petitioner as a defaulter and asking him to pay a sum of Rs. 5,27,509 being the loss suffered by Government. It. is settled law that an order entailing civil consequences to a individual shall be passed strictly in accordance; with the principles of natural justice. The State shall not spring order of this nature like a magician pulling rabbits out of his hat. A citizen cannot be suddenly confronted with a demand notice without where being a prior adjudication by a competent authority in accordance with the principles of natural justice and fair play both of which are intrinsic in the concept of equality before the law enshrined under Art.14 of the Constitution of India. To satisfy the fundamentals of fair play in action the individual concerned should be given an opportunity of presenting his case before he is made liable , and the adjudication in question has to be at the hands of an Independent authority totally unconnected, with the bargain. The question whether there is a breach of contract and if so what is the quantum of damages, etc., are all matters which are left to be adjudicated upon by a court or tribunal and not "by one of the contracting parties. Adjudication of liability by one of the contracting parties as against the other contracting party and that too without proper notice and hearing resulting in heavy pecuniary liability to the latter is abhorrent to all notions of fair play and justice and has been frowned upon by courts. Viewed in this background, Ext; P-6 cannot but be dubbed as wholly arbitrary, illegal and passed without jurisdiction as it has been passed without proper adjudication

10. The view I am taking is fortified by the decision of the Supreme Court in State Of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli AIR 1987 SC 1359, wherein it has been held as follows:

"The powers of the State Government under an agreement entered into by it with a private person providing for assessment of damages for breach of conditions of the agreement and recovery of the damages is confined only to those cases where the breach of conditions is admitted or it is not disputed. The crucial words in the relevant clause of the agreement are 'and for any breach of conditions set forth hereinbefore, the first party (contractor) shall be liable to pay damages to the second party (State Government) as may be assessed by the second party'. The terms of the clause do not afford scope for a liberal construction being made regarding the powers of the officer of the State Government to adjudicate upon a disputed question of breach as well as to assess the damages arising from the breach. On a plain reading of the words it is clear that the right of the State Government to assess damages would arise only if the breach of conditions is admitted or if no issue is made of it. If it was the intention of the parties that the officer acting on behalf of the State was also entitled to adjudicate upon a dispute regarding the breach of conditions the wording of the clause would have been entirely, different. A right to adjudicate upon an issue relating to a breach of conditions of the contract cannot be said to flow from or is inhered in the right conferred to assess the damages arising from a breach of conditions. The power to assess damages is a subsidiary and consequential power and not the primary power. Even assuming that the terms of the relevant clause afford scope for being construed as empowering the officer of the State to decide upon the question of breach as well as the quantum of damages, the adjudication by the officer of the State Government regarding the breach of the contract cannot be sustained under law because a party to the agreement cannot be an arbiter in his own cause. Interests of justice and equity require that where a party to a contract disputes the committing of any breach of conditions the adjudication should be by an independent person or body and not by the other party to the contract."

In the absence of the production of agreement by either side, I am proceeding on the assumption that the agreement does not contain a clause empowering the Government to adjudicate the disputed question of breach and even assuming that such clause existed, this court will be loath to enforce the same as unfair and unreasonable being one entered into between parties whose bargaining power is not the same vide Central Inland Water Transport Corporation Ltd. v. Broja Nath AIR 1986 SC 1571 at 1611, Hyderabad Municipal Corporation v. Krishna Swamy AIR 1987 SC 1359 where the Supreme Court declined to give effect to a clause in a standardised contract. State Of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli AIR 1985 SC 607, supra, was followed by this court in Kamavarma Raja v. Tahsildar, Thaliparamba 1988 (1) KLT (SN) P. 4, wherein it was held that in a dispute between Government and a private party, the Government cannot be the arbiter of its own cause and decide the dispute. It was also held that in the absence of proper adjudication the Government cannot realise any amount from the petitioner therein.

11. In the light of the legal principles enunciated in the above decisions, I have no hesitation in holding that Ext. P-6 as illegal and arbitrary and issued without jurisdiction besides being violative of Art.14 of the Constitution of India, Ext. P-6 is therefore quashed and the original petition is allowed. There is no order as to costs.