P.A. Mohammed Kannu v. H.A. Asanar Kunju
1. The petitioner in this writ petition is the landlord. He filed a petition for eviction of the tenant from the building T. C. No. 288/32 of Chenthitta Ward in Trivandrum City. The building was rented out to the 1st respondent on a monthly rent of Rs. 10. It is used as a shop building and the 1st respondent carries on a hawker's business in it. The petitioner was the owner of two lorries which were plying as public carriages. As there was no lorry shed available for the petitioner he required the shop building for reconstruction and for using it after reconstruction as a shed for the purpose of keeping the lorries. The petitioner is in occupation of 3 buildings in the vicinity of the building sought to be recovered from the 1st respondent. These buildings are kept vacant. The petitioner wanted to build a lorryshed in the premises on which all the buildings stand. The Rent Control Court found that the building in question was required for the occupation of the petitioner viz., for the purpose of constructing a lorry shed and that since the petitioner had offered an alternative accommodation to the 1st respondent in a shop room just near the one sought to be recovered, the court directed the 1st respond ant to surrender the possession of the building to the petitioner. An appeal was filed by the 1st respondent against this order marked Ext. P 1 to the Subordinate Judge, Trivandrum, and the Subordinate Judge held in his order which is marked Ext. P 2 that the petitioner was not entitled to recover possession of the building for the reason that his claim for eviction was only under S.11(3) of Act 16 of 1959 as amended and that the petitioner had abandoned his claim under S.11(4). Against this order a revision, petition was filed by the petitioner before the District Court, Trivandrum and the revision was dismissed by the District Judge by Ext. P3 order. Exts. P 2 and P 3 orders are questioned by the petitioner.
2. The main reason given by the appellate and the revisional authorities for negativing the claim of the petitioner to get recovery of possession of the building is that the petitioner's application was only under S.11(3) of the Act and not under S.11(4). S.11(4) reads as follows:-
"A landlord may apply to the Rent Control Court for an order directing the tenant to put the landlord in possession of the building.
(iv) If the building is in such a condition that it needs reconstruction and if the landlord requires bona fide to reconstruct the same and if he satisfies the court that he has the plan and licence, if any, required, and the ability to re build and if the proposal is not made as a pretext for eviction; Provided that the landlord who evicts a tenant and does no; reconstruct completely the building within a time which may be fixed or extended by the Rent Control Court, shall on a petition before that court, be liable to a fine of rupees five hundred, if it is proved that he has wilfully neglected to reconstruct completely the building within such time
Provided further that the court shall have power at any time to issue directions regarding the reconstruction of the building and on failure of compliance by the landlord, to give effect to the order in any manner the court deems fit and in appropriate cases to put the tenant back in possession or award to the evicted tenant damages equal to the excess rent he has to pay for another building that he is occupying in consequence of such eviction:
Provided further that the tenant who was evicted shall have the first option to have the reconstructed building allotted to him with liability to pay its fair rent; or
(v) if the tenant ceases to occupy the building, continuously for six months without reasonable cause."
If the petitioner bona fide needed the building for his own. occupation and the finding of the Rent Control Court is that he so needed it, the petitioner was entitled to recover possession of the building notwithstanding the fact that he has to demolish the present building and reconstruct it for the purpose of such occupation. The fact that the building requires reconstruction for the purpose of occupation does not mean that the petitioner, does not require it for his own occupation. In other words the purpose of the occupation may be such that building may have to be demolished and reconstructed; that does not mean that the landlord's claim is not under S.11(3). In fact the appellate and the revisional authorities assumed that the need of the petitioner was bona fide, but because he abandoned his claim under S.11(4) they thought that the petitioner was not entitled to claim recovery of possession under S.11(3). This view seems to be not correct. See the ruling reported in 1958 KLT 534. It has therefore to be held that as the landlord required the building bona fide for the purpose of his occupation he was entitled to recover possession under S.11(3) though the building required reconstruction to suit the purpose of his occupation. The authorities were wrong in holding that the petitioner was not entitled to recover possession of the building under S.11(3). I think the reason mentioned by the Rent Control Court for allowing recovery of possession of the building would constitute also the special reason for recovery of the building. I quash Exts. P 2 and P 3 orders.
3. The only question which remains for consideration is whether the 1st respondent has got another building to carry on the trade, as it is found that he is depending for his livelihood upon the income of the business carried on in the building. The petitioner had offered to give the 1st respondent a building on rent adjacent to the building in question for enabling him to carry on his business, but there is no finding by the appellate authority whether this building is suitable for the purpose of carrying on the business of the 1st respondent. I would therefore direct the appellate authority to consider that question and pass the appropriate order in the light of the observations made in the judgment. The writ petition is allowed to the extent indicated. No costs.