- Bookmark
- Share
- CaseIQ
Budru Kashyap v. State Of Chhattisgarh And Others
Structured Summary of the Court's Oral Order
Factual and Procedural Background
Four writ petitions were before the Court. WP(C) Nos. 3908/2008, 4089/2007 and 4608/2008 arise out of Land Acquisition Case No. 10/A-82/04-05/04/2005 (Village Aghanpur). WP(C) No. 3693/2007 arises out of Land Acquisition Case No. 11/A-82/2004-05/2005 (Village Hatkachora).
The first batch of three petitions challenged the legality and validity of the land acquisition proceedings, including the award passed in Land Acquisition Case No. 10/A-82/04-05/04/2005 on 27.1.2007 (approved by the State Government on 10.5.2007). The latter petition challenged the award passed in Land Acquisition Case No. 11/A-82/2004-05/2005 on 21.11.2006 (approved by the State Government on 14.6.2007).
The principal factual/contentions raised by the petitioners included that notifications under Sections 4 & 6 were vague, principles of natural justice were not followed, objections to acquisition were wrongly treated as time-barred, the land was unsuitable for the stated purpose, nearby available Government land was not acquired, and private land was acquired mala fide.
Proceedings were initiated under the Land Acquisition Act, 1894 (referred to in the opinion as "the old Act"). During pendency of the writ petitions, interim orders were passed directing maintenance of status quo in respect of the petitioners' lands.
The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the "new Act") came into force with effect from 1.1.2014. A central legal issue raised in the petitions was whether Section 24(2) of the new Act operated to deem the existing acquisition proceedings under the old Act to have lapsed, because (it was argued) neither physical possession had been taken nor compensation paid to the petitioners.
Legal Issues Presented
- Whether Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 applies to land acquisition proceedings initiated under the Land Acquisition Act, 1894 in which an award was made more than five years prior to 1.1.2014, but physical possession has not been taken and compensation has not been paid, thereby causing those proceedings to be deemed to have lapsed.
- Whether deposit of compensation amount in the Government treasury is equivalent to payment of compensation to landowners for the purpose of avoiding the operation of Section 24(2).
- Whether interim orders of this Court (maintaining status quo) that prevented physical taking of possession preclude the operation of Section 24(2) of the new Act.
- Whether the writ petitions are barred by delay and laches because they were filed after passing of the award.
Arguments of the Parties
Petitioners' Arguments
- Reliance on Section 24(2) of the new Act: because neither possession has been obtained nor compensation paid, the acquisition proceedings must be deemed to have lapsed and the awards cannot be acted upon.
- Relied upon the Supreme Court judgment in Ram Kishan & others v. State of Haryana & others (2014 AIR SCW 6929) in support of the contention that Section 24(2) leads to lapse of proceedings in such circumstances.
Respondents' Arguments
- The Housing Board had not obtained possession of the lands only because of the interim orders passed by this Court directing maintenance of status quo; therefore Section 24(2) should have no application.
- The Housing Board had deposited the award amount of compensation in the treasury, and this deposit should be treated as payment to the petitioners (i.e., sufficient to prevent lapse under Section 24(2)).
- The writ petitions were filed after the passing of the award and therefore suffer from delay and laches; they should be dismissed on that ground irrespective of whether Section 24(2) applies.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Pune Municipal Corporation and another v. Harakchand Misirimal Solanki and others, (2014) 3 SCC 183 | Interpreted Section 24(2) of the 2013 Act; held that deposit in Government treasury is not equivalent to payment to landowners, and where award was made over five years prior to commencement of the 2013 Act and neither possession taken nor compensation paid, proceedings are deemed to have lapsed. | The Court treated this as the first Supreme Court decision interpreting the rigor of Section 24(2) and relied on its reasoning to hold that the subject acquisition proceedings have lapsed under Section 24(2). |
| Agnelo Santimano Fernandes, (2011) 11 SCC 506 | Held that deposit of the compensation amount in the State’s revenue account is not equivalent to payment to landowners and liability to pay interest subsists until the amount is deposited in court. | Cited to support the proposition that deposit in the treasury is of no avail and does not amount to payment for purposes of Section 24(2). |
| Prem Nath Kapur, (1996) 2 SCC 71 | Earlier authority relied upon in Agnelo Santimano Fernandes concerning the law on deposit and payment of compensation. | Referred to as antecedent authority underpinning the principle that treasury deposit is not equivalent to payment. |
| Union of India and others v. Shiv Raj and others, (2014) 6 SCC 564 | Followed and relied upon Pune Municipal Corporation in interpreting Section 24(2) of the 2013 Act. | Noted as a subsequent Supreme Court decision that relied on the Pune Municipal Corporation reasoning; used to demonstrate consistency of Supreme Court authority. |
| Bimla Devi and others v. State of Haryana and others, (2014) 6 SCC 583 | Quashed awards passed under the old Act where neither compensation was paid nor physical possession taken. | Cited as supporting authority that awards can be quashed for non-payment and non-taking of possession. |
| Bharat Kumar v. State of Haryana and another, (2014) 6 SCC 586 | Quashed awards where neither compensation was paid nor physical possession taken. | Cited together with Bimla Devi to demonstrate consistent outcomes where Section 24(2) conditions are satisfied. |
| Ram Kishan & others v. State of Haryana & others, (2014 AIR SCW 6929) | Applied the principle that where an award was made over five years before the 2013 Act and neither possession taken nor compensation paid, Section 24(2) operates to deem acquisition proceedings lapsed. | Relied upon by petitioners; Court noted this more recent decision as consistent with the prior line of authorities and applied the same legal principle to the facts of the present petitions. |
| Prahlad Singh and others v. Union of India and others, (2011) 5 SCC 386 | Observed that writ petitions preferred after passing of award and obtaining possession by the Government may suffer from delay and laches. | Invoked by respondents to argue delay and laches; the Court considered and distinguished it because, in the present cases, possession had not been taken. |
Court's Reasoning and Analysis
The Court began by reproducing Section 24(2) of the 2013 Act, which provides that where an award under Section 11 of the Land Acquisition Act, 1894 has been made five years or more prior to the commencement of the 2013 Act but physical possession of the land has not been taken or compensation has not been paid, the proceedings shall be deemed to have lapsed and the appropriate Government may, if it so chooses, initiate fresh acquisition proceedings under the 2013 Act.
The Court examined the factual matrix in light of Section 24(2). It accepted the respondents' factual concession that the Housing Board had not obtained physical possession of the subject lands and that, although the award amount had been deposited in the Government treasury after the award, the petitioners had not actually received compensation. The Court therefore concluded that the two conjunctive conditions in Section 24(2) — (a) award made five years or more prior to commencement of the 2013 Act and (b) neither physical possession taken nor compensation paid — were satisfied.
To determine whether a treasury deposit could amount to payment, the Court relied on the Supreme Court's analysis in Pune Municipal Corporation and related authorities (including Agnelo Santimano Fernandes and Prem Nath Kapur). Those authorities establish that deposit of compensation in the State's revenue account or treasury is not the same as payment to the landowners, and that the prescribed procedure in the 1894 Act for payment (including deposit in court where applicable) must be followed. The Court quoted and followed the reasoning that treasury deposit is "of no avail" for the purpose of treating compensation as paid.
The Court considered the respondents' contention that interim orders of this Court (maintaining status quo) prevented physical possession and therefore Section 24(2) should not apply. The opinion records the submission but does not accept it as a factor negating the operation of Section 24(2); rather, the absence of possession (regardless of reason) is one of the factual predicates leading to lapse under Section 24(2).
The Court also addressed the respondents' plea of delay and laches, grounded on Prahlad Singh (2011). That authority was acknowledged for the proposition that a writ filed after award and after obtaining possession may be barred by delay and laches. However, because in the present matters possession had not been taken from the petitioners, the Court held the plea of delay and laches was not attracted.
On the basis of the statutory provision, the admitted factual position that possession was not taken and compensation not paid to the petitioners (despite deposit in treasury), and the binding precedents of the Supreme Court construing Section 24(2), the Court concluded that the acquisition proceedings had lapsed by operation of that subsection.
Holding and Implications
HOLDING: All the writ petitions are ALLOWED. The Court held that, in view of Section 24(2) of the 2013 Act, and on the admitted facts that neither possession has been obtained from the petitioners nor compensation has been paid to them, the relevant land acquisition proceedings have lapsed.
Direct implications for the parties: The respondents are permitted to initiate fresh acquisition proceedings, if they so choose, in accordance with the provisions of Section 24(2) of the 2013 Act and applicable law. The immediate consequence is that the existing awards and acquisition proceedings are quashed or deemed lapsed insofar as they relate to the petitioners' lands.
Broader implications: The decision follows and applies established Supreme Court authority interpreting Section 24(2) of the 2013 Act. The opinion does not purport to lay down a new legal principle beyond applying existing precedent; it applies that settled principle to the facts at hand. No statement in the opinion purports to create a departure from the cited Supreme Court rulings.
Oral Order:
1. WP(C) Nos.3908/2008, 4089/2007 and 4608/2008 are arising out of Land Acquisition Case No.10/A-82/04-05/04/2005 (Village Aghanpur) whereas WP(C) No.3693/2007 is arising out of Land Acquisition Case No.11/A-82/2004-05/2005 (Village Hatkachora).
2. In the first batch of three writ petitions, challenge has been thrown to the legality and validity of the Land Acquisition Proceeding including the award passed in Land Acquisition Case No.10/A-82/04-05/04/2005 on 27.1.2007 which was approved by the State Government on 10.5.2007 whereas in the latter writ petition, challenge has been thrown to the legality and validity of the Land Acquisition Proceeding including the award passed in Land Acquisition Case No.11/A-82/2004-05/2005 on 21.11.2006 which was approved by the State Government on 14.6.2007.
3. Initially challenge is on the ground that notification under Sections 4 & 6 are vague; principles of natural justice have not been followed; objection to the acquisition has illegally been rejected by treating the same as time barred; the subject land is not suitable for the purpose for which it is acquired; nearby available Government land has not been acquired and the private persons' land is acquired which is malafide.
4. The proceedings have been drawn under the Land Acquisition Act, 1894 (hereinafter referred to as 'the old Act'). In all the writ petitions, interim orders have been passed directing the parties to maintain status quo with respect to land of the petitioners.
5. During the pendency of the writ petitions, the Central Government has enacted the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (30 of 2013) (hereinafter referred to as 'the new Act') which has been made applicable with effect from 1.1.2014.
6. Before proceeding to argue other points urged in the writ petitions, learned counsel for the petitioners would raise a purely legal submission to the effect that in view of the provisions contained in Section 24 (2) of the new Act and neither possession has been obtained from the petitioners nor compensation has been paid, the land acquisition proceeding would lapse and the award cannot be acted upon. They would refer to the law laid down by the Supreme Court in Ram Kishan & others Vs. State of Haryana & others (2014 AIR SCW 6929)
7. Per contra, Shri Sao, learned Deputy Advocate General and Shri Pali, learned counsel for the respondent/Housing Board, would submit that although it is true that the Housing Board has not obtained possession of the lands, but the same happened because of the interim orders passed by this Court, therefore, Section 24(2) of the new Act has no application. They would also submit that the Housing Board having deposited the amount of compensation in the treasury, the amount should be deemed to have been paid to the petitioners and the award would not lapse.
8. Shri Sao would also submit that the writ petitions have been preferred after passing of the award, therefore, the writ petitions suffer from delay and laches and irrespective of the fact whether the award would lapse or not, the writ petitions deserve to be dismissed on this count alone.
9. In order to dwell on the issue raised before this Court regarding application of Section 24 of the new Act, it would be apt to refer to the said provision, which is reproduced hereinbelow:-
"24. Land acquisition process under act no.1 of 1894 shall be deemed to have lapsed in certain cases.- (1) Notwithstanding anything contained in this Act, in any case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894),-"
(a) where no award under section 11 of the said Land Acquisition Act has been made, then, all provisions of this Act relating to the determination of compensation shall apply; or
"(b) where an award under said section 11 has been made, then such proceedings shall continue under the provisions of the said Land Acquisition Act, as if the said Act has not been repealed."
"(2) Notwithstanding anything contained in subsection (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said section 11 has been made five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act: Provided that where an award has been made and compensation in respect of a majority of land holdings has not been deposited in the account of the beneficiaries, then, all beneficiaries specified in the notification for acquisition under section 4 of the said Land Acquisition Act, shall be entitled to compensation in accordance with the provisions of this Act."
10. Sub-section (2) of Section 24 of the new Act, quoted above, makes it explicit that where an award under the old Act has been made five years or more, prior to the commencement of the new Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions contained in the new Act.
11. In the case at hand, Shri Pali, on instructions, would submit that because of the interim orders passed by this Court directing maintenance of status quo pertaining to the subject land, the Housing Board has not obtained possession of the land. There is also no dispute as to the position that after passing of the award, the Housing Board has deposited the amount in the treasury but the petitioners have not obtained payment of compensation. Thus, they have not yet been paid compensation.
12. The first judgment of the Supreme Court interpreting the rigor of Section 24(2) of the new Act has been reported in (2014) 3 Supreme Court Cases 183 {Pune Municipal Corporation and another Vs. Harakchand Misirimal Solanki and others}. In the said matter of Pune Municipal Corporation (Supra) also, the award amount was deposited in the treasury but the land owners had not received compensation. Referring to the provisions contained in Section 31 of the old Act which provided for payment of compensation or deposit of same in the Court and considering the same alongside Section 24(2) of the new Act, the Supreme Court concluded in paragraphs-18, 19 & 20 thus:-
"18. The 1894 Act being an expropriatory legislation has to be strictly followed. The procedure, mode and manner for payment of compensation are prescribed in Part V (Sections 31-34) of the 1894 Act. The Collector, with regard to the payment of compensation, can only act in the manner so provided. It is settled proposition of law (classic statement of Lord Roche in Nazir Ahmad ( AIR 1936 PC 253 (2)) that where a power is given to do a certain thing in a certain way, the thing must be done in that way or not at all. Other methods of performance are necessarily forbidden."
19. Now, this is admitted position that award was made on 31-1-2008. Notices were issued to the landowners to receive the compensation and since they did not receive the compensation, the amount (Rs 27 crores) was deposited in the Government treasury. Can it be said that deposit of the amount of compensation in the Government treasury is equivalent to the amount of compensation paid to the landowners/persons interested? We do not think so.
"In a comparatively recent decision, this Court in Agnelo Santimano Fernandes (( 2011) 11 SCC 506), relying upon the earlier decision in Prem Nath Kapur (( 1996) 2 SCC 71), has held that the deposit of the amount of the compensation in the State’s revenue account is of no avail and the liability of the State to pay interest subsists till the amount has not been deposited in court."
"20. From the above, it is clear that the award pertaining to the subject land has been made by the Special Land Acquisition Officer more than five years prior to the commencement of the 2013 Act. It is also admitted position that compensation so awarded has neither been paid to the landowners/persons interested nor deposited in the court. The deposit of compensation amount in the Government treasury is of no avail and cannot be held to be equivalent to compensation paid to the landowners/persons interested. We have, therefore, no hesitation in holding that the subject land acquisition proceedings shall be deemed to have lapsed under Section 24(2) of the 2013 Act."(Emphasis supplied)
13.In Pune Municipal Corporation (Supra), the beneficiaries of the land acquisition proceedings also tried to take shelter under the provisions contained in Section 114 (2) of the new Act to argue that the proceedings under the old Act wherein an award has been passed are saved. Repelling the said contention, the Supreme Court held in paragraph-21 thus:-
"21. The argument on behalf of the Corporation that the subject land acquisition proceedings have been concluded in all respects under the 1894 Act and that they are not affected at all in view of Section 114(2) of the 2013 Act, has no merit at all, and is noted to be rejected. Section 114(1) of the 2013 Act repeals the 1894 Act. Sub-section (2) of Section 114, however, makes Section 6 of the General Clauses Act, 1897 applicable with regard to the effect of repeal but this is subject to the provisions in the 2013 Act. Under Section 24(2) land acquisition proceedings initiated under the 1894 Act, by legal fiction, are deemed to have lapsed where award has been made five years or more prior to the commencement of the 2013 Act and possession of the land is not taken or compensation has not been paid. The legal fiction under section 24(2) comes into operation as soon as conditions stated therein are satisfied. The applicability of Section 6 of the General Clauses Act being subject to section 24(2), there is no merit in the contention of the Corporation."
14. The judgment in the matter of Pune Municipal Corporation (Supra) has been relied by the Supreme Court in its subsequent decision in the matter of Union of India and others Vs. Shiv Raj and others ((2014) 6 SCC 564).
15. In 2 subsequent decisions in the matters of Bimla Devi and others Vs. State of Haryana and others ((2014) 6 SCC 583) and Bharat Kumar Vs. State of Haryana and another ((2014) 6 SCC 586), the Supreme Court quashed the award passed under the old Act on the ground that neither compensation was paid nor physical possession of the land was taken by the Government.
16. In a more recent judgment in the matter of Ram Kishan & others (Supra), the Supreme Court has taken note of its earlier decisions to conclude in paragraphs-12 & 13 thus:-
"12. By considering the aforesaid decisions of this Court and the facts and circumstances of the present case on hand, we are of the view that physical possession of the land belonging to the appellants has not been taken by the respondents and more than five years have elapsed since the making of the award on 14.01.2006 when the Resettlement Act, 2013 came into force on 01.01.2014. Therefore, the conditions stated in section 24(2) of the Act of 2013 are fulfilled for allowing the plea of the appellants that the land acquisition proceedings be deemed to have elapsed. The said legal principle laid down by this Court in the case of Pune Municipal Corporation and other cases referred to supra with regard to interpretation of section 24(2) of the Act of 2013 are applicable with all fours to the fact situation on hand with respect to the land covered in this appeal and for granting relief as prayed by the appellants in this application."
"13. In view of the aforesaid decisions of this Court referred to supra, and the findings and reasons recorded by us the application filed under section 24(2) of the Act of 2013 is allowed. Consequently, having regard to the facts of this case, this appeal is allowed by quashing the acquisition proceedings in so far as the land of the applicants/appellant Nos. 24- 28 are concerned. There shall be no order as to costs."(Emphasis supplied)
"17. Shri Sao, learned Deputy Advocate General would also argue that the writ petitions suffer from delay and laches because the writ petitions have been presented after passing of the award."
18. In the matter of Prahlad Singh and others Vs. Union of India and others ((2011) 5 SCC 386), it has been observed that in cases where the writ petition has been preferred after passing of the award and obtaining possession by the Government, it would suffer from delay and laches.
19. However, in the present case, admittedly, possession has not been taken from the petitioners. Thus, the writ petitions do not suffer from delay and laches.
20. For the aforestated reasons, all the writ petitions are allowed. In view of the provisions contained in Section 24(2) of the new Act and since neither possession has been obtained from the petitioners nor compensation has been paid to them, the land acquisition proceedings have lapsed. The respondents may proceed to re-acquire the land as provided under Section 24(2) of the new Act, in accordance with law.
Alert