Union Of India v. Tirupati Texco Products (P) Ltd.

Delhi High Court
Apr 24, 2014
Smart Summary (Beta)

Factual and Procedural Background

This appeal arises under Section 37 of the Arbitration & Conciliation Act, 1996, challenging a judgment dated 10.11.2010 of the court below under Section 34 which had allowed the respondent's objections and set aside an arbitral Award dated 13.2.2001. The Award had granted the appellant/claimant (Union of India) a money decree of Rs. 29,925/- on account of risk purchase arising from cancellation of the contract by the appellant after the respondent allegedly failed to supply contracted cotton ropes within the delivery period.

Procedurally, there was a 48-day delay in re-filing the appeal. C.M. No. 11020/2011 condoned that delay when notice in the appeal was issued. The respondent's counsel contested the condonation, seeking recall of the condonation order; the court below has not issued any recall application and the present court refused to recall the condonation order.

On the merits, the factual matrix (as found in the opinion) is: the appellant invited tenders for three types of cotton rope; the respondent's tender dated 28.9.1990 was accepted; quantities were increased pursuant to a +25% variation clause and delivery dates were amended. A sequence of communications between the parties (notably the respondent's letter dated 20.11.1991, the appellant's letter dated 13.12.1991, the respondent's letter dated 20.1.1992, and the appellant's letter dated 10.2.1992) is central to the dispute about whether a concluded contract existed for a refixed delivery period up to 28.2.1992. The arbitrator found the contract concluded; the trial court treated a key letter as a counter-offer and set aside the Award. This appeal challenges that setting aside and seeks restoration of the Award.

Legal Issues Presented

  1. Whether the 48-day delay in re-filing the appeal (condoned by C.M. No. 11020/2011) ought to be recalled or the condonation permitted to stand.
  2. Whether the correspondence between the parties (in particular the respondent's letter of 20.11.1991 and subsequent letters) resulted in a concluded contract for supply with a refixed delivery period up to 28.2.1992 (i.e., whether the letter dated 20.11.1991 was an offer accepted by the appellant by letter dated 13.12.1991), or whether that correspondence was a counter-offer such that no concluded contract arose.
  3. Whether, assuming breach by the respondent, the award of the risk purchase amount of Rs. 29,925/- was justified given the existence of lower offers in the risk purchase process.

Arguments of the Parties

Respondent's Arguments

  • The respondent contended that the condonation of the 48-day delay in re-filing the appeal ought not to have been allowed and that the condonation order should be recalled.
  • The respondent argued that the letter dated 20.1.1992 (quoting from the record) should be treated as a counter-offer rather than as evidence of a concluded contract; the court below accepted this view and set aside the Award.
  • Even if found guilty of breach, the respondent argued the risk purchase amount of Rs. 29,925/- ought not to have been awarded because six other offers pursuant to the risk purchase were lower than the tender accepted for risk purchase.

Appellant's Arguments

  • The appellant maintained that the 48-day delay in re-filing was innocuous, necessitated by registry objections, caused no real prejudice to the respondents, and was properly condoned; no application to recall that condonation was filed.
  • The appellant (and the arbitrator) contended that the respondent's letter dated 20.11.1991 amounted to an offer for refixation of the delivery period to 28.2.1992 and that the appellant's letter dated 13.12.1991 was an acceptance, resulting in a concluded contract; subsequent letters (respondent's 20.1.1992 and appellant's 10.2.1992) demonstrate acceptance and reaffirmation.
  • On the risk-purchase quantum, the appellant argued that the lower tenderers in the risk purchase were unregistered partnership firms or lacked requisite experience; therefore, there were legitimate reasons for awarding the risk purchase to a higher-priced but acceptable tenderer (M/s S.R Enterprises), making the respondent liable for the resultant higher cost of Rs. 29,925/-.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Union Of India… v. Daisy Trading Corporation…. Corporation2006 (130) DLT 471 Counsel for the respondent relied on this decision to argue that where the terms of the risk purchase tender differ from the cancelled tender, the arbitrator errs in awarding the amount of a higher risk-purchase tender. The court considered the reliance but disagreed with the respondent's application of the precedent: it held that if there are valid reasons for not accepting lower risk-purchase tenders (e.g., unregistered firms, lack of experience), the higher risk-purchase cost may legitimately be awarded against the breaching party; accordingly, the precedent did not require denying the award in the present facts.

Court's Reasoning and Analysis

The court's analysis proceeded in two main strands: procedural (delay condonation) and substantive (existence of a concluded contract and quantum of risk purchase damages).

Procedural: The court noted a 48-day delay in refiling the appeal which had been condoned by C.M. No. 11020/2011 when notice was issued. The respondent contended this condonation should be recalled, but no application to recall that order had been filed. The court reasoned that (a) the delay was caused by removal of registry objections, (b) the 48-day period caused no real prejudice to the respondent, and (c) in any event there was no recall application; accordingly the court refused to recall the condonation order.

Substantive — existence of contract: The court identified the central factual-legal issue as whether the respondent's letter dated 20.11.1991 constituted an offer for refixation of the delivery period to 28.2.1992 and whether the appellant's letter dated 13.12.1991 amounted to acceptance, thereby creating a concluded contract. The arbitrator had held the contract was concluded; the court below treated the correspondence as a counter-offer and set aside the Award.

To resolve this, the judge examined the language of the respondent's letter dated 20.1.1992 (which acknowledged receipt of the appellant's amendment dated 13.12.1991 and "thanks for the same") and the appellant's subsequent letter dated 10.2.1992. The court emphasized that the respondent's first paragraph expressed thanks for the refixation up to 28.2.1992 — showing acceptance of the amended delivery period — and that the later request for further extension related only to the respondent's delay in receipt of the 13.12.1991 letter, and could not negate that a final delivery date had been fixed. The appellant's 10.2.1992 letter further confirmed that the delivery period "was refixed accordingly as per your offer" and advised supply and reporting of developments.

On this basis the court concluded the arbitrator was justified in treating the correspondence as evidence of a concluded contract (acceptance by the appellant of the respondent's offer), and that the court below erred in characterizing the correspondence as a counter-offer. Therefore, the court set aside the court-below's findings and restored the Award.

Substantive — quantum of risk purchase: The respondent argued the awarded sum (Rs. 29,925/-) should not have been allowed because six other risk-purchase offers were lower. The appellant's position before the arbitrator was that the lower tenders were from unregistered partnership firms and lacked requisite experience; the appellant therefore legitimately rejected those lower tenders. The court accepted that where valid reasons exist for rejecting lower tenders, the higher risk-purchase cost awarded to the appellant is payable by the breaching respondent. Accordingly, the court rejected the respondent's reliance on the cited precedent as inapplicable to the factual matrix.

Holding and Implications

APPEAL ALLOWED; the impugned judgment dated 10.11.2010 is set aside and the Award dated 13.2.2001 is restored.

Implications:

  • The arbitral Award in favor of the appellant for Rs. 29,925/- (risk purchase amount) is reinstated and is enforceable as against the respondent in this litigation.
  • The court refused to recall the earlier condonation of a 48-day delay in refiling the appeal; that condonation stands.
  • The court held that the correspondence between the parties showed a concluded contract for the refixed delivery period up to 28.2.1992, supporting the arbitrator's award.
  • On the quantum issue, the court ruled that accepting a higher risk-purchase tender is permissible when there are valid reasons for rejecting lower tenders; therefore no reduction of the award was required on the basis of the existence of lower offers.
  • Parties were directed to bear their own costs. The opinion does not purport to lay down a novel principle of law beyond application of existing contractual and arbitral review principles to the facts; no broader precedent was expressly stated to be created by this decision.
Show all summary ...

VALMIKI J. MEHTA, J (ORAL)

1. At the outset it is stated that there was a delay of 48 days in refiling the appeal and therefore while issuing notice in the appeal, delay of 48 days in re-filing the appeal was condoned by allowing C.M No. 11020/2011. Counsel for the respondent contends that delay in re-filing the appeal ought not to have been condoned. I note that there is no application for recalling of the order dated 31.5.2011 Even assuming that there was such an application, yet, the delay of 48 days in re-filing the appeal is condoned inasmuch as delay of 48 days causes no real prejudice to the respondents and which period of 48 days is for removing objections raised by the registry. I therefore refuse to recall the order of condonation of delay in re-filing the appeal as passed on 31.5.2011 including because no application is filed for recall of this order.

2. This first appeal is filed under Section 37 of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) impugning the judgment of the court below dated 10.11.2010 by which objections filed under Section 34 of the Act by the respondent herein, petitioner before the trial court were allowed and the Award dated 13.2.2001 was set aside whereby the appellant/claimant was granted a money decree of Rs. 29,925/-. The court below has set aside the Award which granted damages on risk purchase caused to the appellant/Union of India as the contract with the respondent was cancelled as the respondent had failed to supply the contracted goods/cotton ropes within the delivery period. The court below held that there was no concluded contract and therefore there does not arise any issue of the appellant/Union of India contending that losses are to be compensated on account of risk purchase.

3. The facts of the case are that the appellant invited offers for supply of cotton ropes. Respondent submitted its tender on 28.9.1990 which was accepted by the appellant. Three different types of ropes measuring 69210 mtrs, 94350 mtrs, and 50,000 mtrs were ordered from the respondent in terms of the tender. The quantity was subsequently enhanced to 86512 mtrs from 69210 mtrs so far as first item is concerned, and from 94350 to 117938 mtrs so far as second item is concerned, and this was done vide letter dated 25.10.1990 of the appellant because the contract contained a + 25% variation clause. So far as the delivery period was concerned for item nos. 1 and 2 it was extended upto 31.12.1990 and for item no. 3 the date of delivery was 31.8.1990 There was a mistake on behalf of the appellant because whereas the amendment letter was issued on 25.10.1990 the delivery period so far as item no. 3 was given as 31.8.1990 and consequently a fresh amendment was issued for supply by 28.2.1992 The issue is that whether this fresh amendment dated 13.12.1991 issued by accepting of the letter of the respondent dated 20.11.1991, and received by the appellant on 2.1.1992, amounted to a concluded contract and which would be if the request of the respondent for extension of the delivery period to 28.2.1992 in terms of the letter of the respondent dated 20.11.1991 was accepted by the appellant by the appellant's letter dated 13.12.1991 In sum and substance, the issue is whether the letter of the respondent dated 20.11.1991 amounted to an offer and the same on being accepted by the appellant by issuing its letter dated 13.12.1991 results in a concluded contract.

4. The arbitrator held that the letter dated 20.1.1992 showed that the contract stood concluded and not that this letter of the respondent dated 20.1.1992 was a fresh counter offer. The court below has however accepted this letter dated 20.1.1992 as a counter offer and therefore objections of the respondent were accepted and the Award was set aside.

5. Since for determination of the issue, language of the letter dated 20.1.1992 is relevant, I reproduce the same alongwith another letter dated 10.2.1992 issued by the appellant to the respondent as under:-

“Letter dated 20.1.1992

No. 476.RC/91 Dated 20.1.92

Asstt. Director (Supplies)

7/29-B, Tilak Nagar, KANPUR

Sub:- A/T No. 101/504.K2.Tirupati/476.COAD dt.28.9.90 for supply of Rope Cotton.

Dear Sir,

With reference to the above A/T we are in receipt of your Regd. Letter No. 101/504.K2/476.Amd. No. 465 dt.13.12.91 by which you have refixed the D.P upto 28.2.92 as requested vide our letter No. 476.RC/91 dt.20.11.91 and thanks for the same. Your above letter was received by us on 2.1.92

In this regard we draw your kind attention towards personal meeting held with you on 19.11.91 in your office. It was requested by the undersigned to refix the D.P upto 31.3.92 as requested in our letter dt.15.11.91 In response to our letter you have assured that the refixation of the delivery shall be given to us immediately upto 28.2.92 But the refixation of the D.P letter No. 101/504.K2/476.Amdt. No. 465 dt.13.12.91 was only received by us on 2.1.92

We therefore, request you to kindly refix the D.P upto 31.3.92 as more than 45 days have passed from the Date of our discussion and receipt of your letter.

Thanking you,

Yours faithfully,

For Tirupati Texco Products (P) Ltd.

DIRECTOR.

Letter dated 10.2.1992

No. 101/584.K-2/476 Dated: 10.2.92

M/s Tirupati Texco Products (P) Ltd.,

132-B, Cooperative Industrial Estate, Kanpur-22.

Sub:- A/T No. 101/584.K-2/476/COAD dt.28.9.90 for supply of Rope Cotton.

Ref:- Your letter No. 476.RC/91 dt. 20.1.92

Dear Sirs,

Please refer to your letter cited under reference, this is to inform you that the delivery period was refixed accordingly as per your offer. Any how you are hereby advised to supply the stores and regarding delivery period when you will approach for extension of D.P The delivery period shall be considered.

You are requested to inform the latest development of supplies to this office within 10 days.

This is however without any prejudice to the terms & conditions of the contract.

Yours faithfully

(D.N SINGH) ASSTT. DIRECTOR OR D.S & D.”

6. The court below has relied upon second para of the letter dated 20.1.1992 whereby the respondent has asked for extension of delivery period, however, in my opinion the court below has fallen into a clear error in overlooking the first para of this very letter which showed that the respondent thanked the appellant for re-fixing the delivery period i.e the respondent accepted the amended delivery period for supply. The respondent however only prayed for further extension of the delivery period because the fresh delivery period would expire on 28.2.1992 Delivery extension was asked because as per the respondent there was delay in receipt of the letter issued by the appellant dated 13.12.1991 inasmuch as the same was received by the respondent only on 2.1.1992 Whatever doubt remained that the contract was concluded/entered into by the appellant's letter dated 13.12.1991 becomes clear from the letter of the appellant to the respondent dated 10.2.1992 and which makes it more than abundantly clear that the delivery period upto 28.2.1992 was fixed/refixed according to the ‘offer’ of the respondent i.e the appellant re-affirmed the fact that the letter of the respondent dated 20.11.1991 was an offer and appellant accepted the offer by issuing its letter dated 13.12.1991 In my opinion, therefore, there cannot be any doubt that the contract stood concluded when the appellant issued its letter dated 13.12.1991 because this letter dated 13.12.1991 was an acceptance of the offer of the respondent given by the respondent's letter dated 20.11.1991 for re-fixing the delivery period upto 28.2.1992 As already stated above, the respondent thanked the appellant for accepting the fresh delivery period ending on 28.2.1992 but only requested a further extension of the same, however, such request cannot take away the fact that there was a finality with respect to a specific date of the delivery period being arrived at and hence a concluded contract.

7. In my opinion therefore the arbitrator was justified in referring to this letter dated 20.1.1992 for holding that contract was concluded, and this becomes clear from the first para last few lines of internal page 4 of the Award dated 13.2.2001 The court below accordingly was not justified in accepting the objections and setting aside the Award and therefore the findings and conclusions of the court below are set aside and the Award is restored.

8. Learned counsel for the respondent however vehemently argued that even assuming the respondent was guilty of breach of contract, yet, the risk purchase amount of Rs. 29,925/- ought not to have been awarded to the appellant because this risk purchase amount is on account of the acceptance of the fresh risk purchase tender ignoring the six other offers which were lower than the offer given by the respondent pursuant to the risk purchase tender. Learned counsel for the respondent however does not dispute that the case of the appellant before the arbitrator was that the persons whose tenders were not accepted were unregistered partnership firms, and appellant did not accept the tenders from them for that reason and also for the reason that those entities were not having requisite experience. Therefore once legitimate reasons exist for accepting a particular tender at a higher rate, because of lack of reliability and other factors pertaining to other tenderers, it cannot be said that respondent is not liable for the risk purchase amount of Rs. 29,925/-. I may note that the appellant has claimed this amount of risk purchase because the risk purchase tender was ultimately awarded to one M/s. S.R Enterprises from Kanpur.

9. Learned counsel for the respondent sought to place reliance upon the judgment of this Court in the case of Union Of India… v. Daisy Trading Corporation…. Corporation2006 (130) DLT 471 to argue that once the terms of the risk purchase tender are different than the tender which is cancelled on account of breach, then, the arbitrator has committed an error in awarding the amount of the higher risk purchase tender. I do not agree because no doubt ordinarily the amount of damages is as per the lowest risk purchase tender however if the lower tenders are for valid reasons not accepted by the Union of India, there is justification, and accordingly, the risk purchase amount for the higher cost would be payable by the respondent.

10. In view of the above, appeal is allowed. Impugned judgment of the court below dated 10.11.2010 is set aside and the Award of the arbitrator dated 13.2.2001 is restored whereby the appellant has been awarded a money decree for a sum of Rs. 29,925/-. Parties are left to bear their own costs.