Atlas Interactive (India) Pvt. Ltd. v. Bharat Sanchar Nigam Limited & Anr.

Delhi High Court
Feb 17, 2005
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The petitioner company entered into a Franchisee Agreement dated 20th April 2004 with respondent No. 1 for providing unique Broadband Services on TV across four areas using the respondent's existing copper network. The agreement was for 15 years, extendable by five years, and required the petitioner to position equipment within four months and commercially launch the project within six months. Delay would lead to forfeiture of the Bank Guarantee and potential termination. The respondent issued a notice dated 10th December 2004 terminating the agreement due to alleged delays. The petitioner sought suspension of this termination notice under Section 9 of the Arbitration and Conciliation Act, 1996, alleging that time was not the essence of the contract and that the termination was unjust and would cause significant financial loss. The respondent opposed the petition, asserting that time was the essence and that termination was justified.

Legal Issues Presented

  1. Whether time was the essence of the Franchisee Agreement between the parties.
  2. Whether the termination of the Franchisee Agreement by respondent No. 1 was lawful and justified.
  3. Whether the petitioner is entitled to an injunction restraining the respondent from terminating the Agreement pending arbitration.
  4. Whether Section 14 of the Specific Relief Act bars the grant of injunction in this case.
  5. The applicability and extent of the respondent’s discretion to terminate the contract.

Arguments of the Parties

Petitioner’s Arguments

  • Time was not the essence of the contract as the agreement did not specifically stipulate it and the parties’ conduct supported this.
  • There was delay on the respondent’s part in signing the Technology and Operations Agreement (OTA), which rendered the time schedule under the Franchisee Agreement otiose.
  • Petitioner had taken advance steps despite delays, including placing large equipment orders and conducting surveys with respondent’s knowledge.
  • The termination notice was illegal, unjust, and would cause enormous financial loss as the equipment was tailor-made for the project and not usable elsewhere.
  • Specific performance should be granted because damages would be inadequate, given the unique nature of the project and the petitioner’s substantial investment.
  • Respondent, as a State instrumentality, must act fairly, justly, and not arbitrarily in exercising its contractual rights.
  • The petitioner did not come to court with unclean hands; shipment of equipment after termination was under hope to persuade continuation of the project.

Respondent’s Arguments

  • Time was the essence of the contract, and petitioner’s failure to meet deadlines justified termination under Clause 7 of the Franchisee Agreement.
  • Respondent was entitled to terminate given petitioner’s delay in installation and commercial launch.
  • The petitioner was responsible for delays, including in signing the OTA, and never sought extension of time or blamed respondent for delays.
  • The petitioner’s prayer was tantamount to specific enforcement of a determinable contract, barred by Section 14 of the Specific Relief Act.
  • Monetary compensation would be an adequate remedy for petitioner, and no irreparable loss was likely.
  • The petitioner did not have exclusivity, and the equipment could be used with other service providers.
  • Petitioner acted in bad faith by shipping equipment after receiving termination notice, thus not entitled to equitable relief.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Mahabir Prasad Rungla v. Durga Dutta, AIR 1961 SC 990 In commercial contracts, time is ordinarily the essence of the contract. Court noted these cases involved supply of goods/services readily available and distinguished them from the present unique project.
China Cotton Exporters v. Beharilal Ramcharan Cotton Mills Ltd., AIR 1961 SC 1295 Time as essence in commercial contracts. Considered but distinguished due to different contract nature.
Sachidanand Patnaik v. G.P and Co., AIR 1961 Orissa 269 Time being essence in commercial contracts. Distinguished on facts.
Hind Construction Contractors v. State of Maharashtra, (1979) 2 SCC 70 Time can be made essence of contract even after commencement of proceedings. Used to show parties can modify contract terms regarding time.
Gomathinayagam Pillai v. Pallaniswami Nadar, (1967) 1 SCR 227 Intention to make time essence must be unmistakable and may be inferred from conduct. Relied upon to support view that time was not essence here.
Arosan Enterprises v. Union of India, (1999) 9 SCC 449 Time not necessarily essence in unique projects. Supported petitioner’s submission on unique nature of project.
Rajasthan Breweries Limited v. The Stroh Brewery Company, AIR 2000 Delhi 450 Contracts determinable in nature cannot be specifically enforced. Respondent relied upon but court distinguished as private commercial contract.
Vidya Securities Ltd v. Comfort Living Hotels Pvt. Ltd, 102 (2003) DLT 797 Determinable contracts and limitations on injunctions. Distinguished due to nature of contract.
BSM Contractors Ltd. v. Rajasthan State Bridge Corporation, AIR 1999 Delhi 117 Specific performance not granted for determinable contracts. Distinguished on facts.
Mahabir Auto v. Indian Oil Corporation, (1990) 3 SCC 752 Specific performance may be granted for unique contracts despite determinability. Relied upon by petitioner to argue for injunction.
Pioneer Publicity Corporation v. Delhi Transport Corporation, 103 (2003) DLT 442 Grant of injunction in unique contract situations. Supported petitioner’s claim for relief.

Court's Reasoning and Analysis

The Court began by emphasizing the onus on the party pleading that time is the essence of a contract. While ordinarily in commercial contracts time is the essence, this principle does not rigidly apply to unique projects where unforeseen difficulties can arise. The Franchisee Agreement did not explicitly state that time was the essence, nor did the parties’ conduct indicate such an intention. Respondent’s delay in signing the OTA and failure to respond promptly to petitioner’s requests for extension undermined the claim that time was critical.

The Court observed that the respondent did not terminate the contract immediately upon delay notices but waited almost two months, during which the petitioner continued investing in the project. The presence of penalty clauses for delay also indicated that strict adherence to time was not mandated.

Regarding the nature of the contract, the Court noted that it was unique, involving tailor-made equipment and a novel service, and that the petitioner had invested substantial funds. The respondent, being a State instrumentality, was held to a higher standard of fairness and could not act arbitrarily in terminating the agreement. The Court distinguished private commercial contract precedents on determinable contracts and specific performance, holding that Section 14 of the Specific Relief Act did not bar relief in this case due to the unique circumstances and public interest considerations.

The Court rejected the respondent’s contention that the petitioner came with unclean hands, finding that shipment of equipment after termination was a reasonable act under the circumstances. The Court clarified that the ultimate questions of contract termination validity and time being essence would be adjudicated by the Arbitral Tribunal, and the Court’s findings were prima facie and tentative for the purpose of the Section 9 petition.

Balancing the equities, the Court found the petitioner’s position stronger, noting the risk of irreparable loss and damage to reputation if terminated abruptly. The respondent’s conduct was held to be arbitrary and inequitable. The Court therefore restrained the respondent from terminating the Franchisee Agreement pending arbitration, conditioned on the petitioner initiating arbitration proceedings promptly.

Holding and Implications

The Court’s final decision is as follows:

The petition is allowed. The operation of the termination notice dated 10th December 2004 is stayed, and respondent No. 1 is restrained from treating the Franchisee Agreement as terminated until the Arbitral Tribunal passes its award.

The Court ordered that the petitioner must invoke the arbitration clause and initiate arbitral proceedings within two weeks, failing which the restraint order will lapse.

This decision directly prevents respondent No. 1 from terminating the contract prematurely and protects the petitioner’s investment pending arbitration. No new legal precedent was established; the ruling is a prima facie injunction based on the facts and circumstances of this unique contract and the parties’ conduct.

Show all summary ...

R.C Chopra, J.—In this petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’ only), the petitioner company prays for suspending the operation of the notice dated 10th December, 2004, issued by respondent No. 1 informing the petitioner that the Franchisee Agreement dated 20th April, 2004, between the parties shall stand terminated upon expiry of thirty days from the date of the notice. The petitioner was claiming injunction against the invocation of the performance Bank Guarantee also but this prayer is not being pressed as the Bank Guarantee already stands invoked.

2. The facts relevant for the disposal of this petition, briefly stated, are that the petitioner had entered into a Franchisee Agreement dated 20th April, 2004, with respondent No. 1 for providing Broad Band Services on TV on the existing copper network of respondent No. 1 in Noida, Ghaziabad, Faridabad and Gurgaon. This service is stated to be unique and being introduced in India for the first time. The agreement was initially for a period of 15 years and could be extended by five years if agreed to between the parties. Under the Agreement, the equipment was to be placed in position by the petitioner within four months i.e by 19th August, 2004, and the project was to be commercially launched within six months of the signing of the Franchisee Agreement i.e by 19th October, 2004. It was also agreed that delay by the petitioner in performing its obligations would render the petitioner liable to forfeiture of the Bank Guarantee apart from termination of the Agreement itself. The clause provided liquidated damages also in case of delay.

3. According to the petitioner, time was not the essence of the contract, the Agreement contained an Arbitration Clause also; and Technology and Operations Agreements (in short referred to as ‘OTA’ only) was also to be signed between the parties within 15 days of the signing of the Franchisee Agreement. The petitioner pleads that the OTA could be signed on 4th June, 2004 and hence from the inception of the project, there was delay on the part of respondent No. 1. According to it, this rendered the time schedule under the Franchisee Agreement otiose. The petitioner pleads that in spite of delay on the part of the respondent in executing the OTA, the petitioner with a view to minimise the effect of the delay, started undertaking advance work by negotiating contracts, undertaking technical design work and procuring equipment from the suppliers. All these facts were within the knowledge of respondent No. 1. The survey of SSA exchanges was to be done after OTA to enable the petitioner to work out the exact requirements of the infrastructure. The respondent No. 1 delayed the necessary permission in respect of the survey of the exchanges and petitioner could conduct surveys in various exchanges between July and August, 2004 only after permission was granted by respondent No. 1.

4. Vide letter dated 21st August, 2004, the respondent No. 1 complained that the equipment had not been deployed till date. Vide letter dated 24th August, 2004, the petitioner replied that it would adhere to the delivery and installation schedules. According to the petitioner it had already placed orders on ZTE Corporation on 16th August, 2004 for equipment worth about 100 crores. Despite the fact that the petitioner had placed orders for supply of middleware, software of ORCA interactives for which RBI permission even was required, the respondent No. 1 did not issue a letter of support for obtaining the permissions. On 6th December, 2004, the petitioner sent a letter to respondent No. 1 reiterating its earlier request in respect of extension of time, allocation of NOC's space and also intimated the respondent No. 1 about its investment of about 115 crores already made in the project. It also informed respondent No. 1 that the entire access equipment to be installed in various exchanges was on its way to India. According to the petitioner, in view of certain directives issued by Department of Telecommunications not to encourage rolling out TV Broad Band Services in India, the respondent No. 1 issued letter dated 10th December, 2004, terminating the Franchisee Agreement between the parties. According to the petitioner, this action of respondent No. 1 is illegal, unjust and unwarranted and would cause enormous financial loss to the petitioner as the equipment designed for the project is not capable of being used in any other project. The petitioner is stated to be fully geared up for immediate launch of the Broad Band TV Services in terms of the Franchisee Agreement.

5. The respondent No. 1 opposes the prayer of the petitioner to suspend the operation of the termination notice dated 10th December, 2004 on various grounds including that time was the essence of the contract and as such respondent No. 1 was fully justified in issuing termination notice in terms of Clause (7) of the Franchisee Agreement as the petitioner was badly behind schedule. It had neither installed the equipment by 19th August, 2004 nor commercially launched the service by 12th October, 2004. The respondent No. 1 pleads that now it has decided to itself set up and launch the Broad Band Services on TV. It is submitted that the petitioner is to be blamed for the situation and respondent No. 1 has committed no breach of the contract by issuing the impugned notice. It is pointed out that in commercial agreements, time is ordinarily the essence of the contract and in this case complete discretion was with respondent No. 1 in the matter of termination of the Agreement. It is denied that respondent No. 1 is to be blamed for delay and it is submitted that from the very beginning the petitioner was behind schedule but was assuring respondent No. 1 that it would be in a position to launch the project in terms of the Agreement. The OTA was also stated to be delayed on account of defaults of the petitioner but at no stage the petitioner asked for extension of time for completion of the project nor blamed respondent No. 1 for the delay. It is also pleaded that the petitioner has not come to the Court with clean hands and is not entitled to an equitable relief for the reason that the equipment in question was shipped by the petitioner after coming to know that respondent No. 1 had terminated the Agreement. Therefore, it cannot take shelter under a situation which is its own creation. It is also pointed out that a false plea of exclusivity was raised in the petition as the Franchisee Agreement clearly provided that respondent No, 1 could entrust Broad Band Services to others also besides the petitioner. It is also stated that no irreparable loss/damage is likely to be caused to the petitioner as the equipment in question can be utilized through other service providers including M.T.N.L It is submitted that the prayer made by the petitioner amounts to specifically enforcing a contract against which provisions of section 14 are clearly attracted. It is argued that the petitioner is not entitled to the restraint order, as prayed, for the reason that monetary compensation by way of damages would be an adequate relief for the petitioner. Both the parties filed additional affidavits to which counter affidavits were also filed.

6. I have heard learned Counsel for the petitioner and learned Counsel for the respondent. I have gone through the records.

7. Before adverting to the facts of the case, it would be appropriate to examine as to when and under what circumstances time is considered to be the essence of the contract. At the outset, it has to be stated that the onus of establishing that “the time was the essence of a contract” is upon the party which pleads that the time was the essence of the contract. In commercial contracts, ordinarily, time is the essence of the contract but in those contracts, which pertain to a unique product or project, it cannot be always held that the time was the essence of the contract unless the parties specifically say so in contract and their conduct while entering into contract and thereafter conveys that they intended the time to be the essence of the contract. In unique products as well as projects, unimaginable and unanticipated hassles and bottlenecks may appear in producing the product or completing the project and, as such, time schedule may not be strictly adhered to.

8. Learned Counsel for the respondent has heavily relied upon the judgments Mahabir Prasad Rungla v. Durga Dutta, AIR 1961 SC 990; China Cotton Exporters v. Beharilal Ramcharan Cotton Mills Ltd., AIR 1961 SC 1295; Sachidanand Patnaik v. G.P and Co., AIR 1961 Orissa 269 and Hind Construction Contractors v. State of Maharashtra, (1979) 2 SCC 70, to contend that in commercial contracts, ordinarily time is the essence of the contract. However, in all these cases, the contracts were in regard to supply of goods or services which are easily available in the open market. In Hind Construction Contractors v. State of Maharashtra (supra), an observation was made by the Apex Court that even after coming to the Court, the parties could make the time essence of the contract meaning thereby that the contract could be modified and kept alive. Learned Counsel for the petitioner relies upon the judgments in Gomathinayagam Pillai v. Pallaniswami Nadar, (1967) 1 SCR 227 and Arosan Enterprises v. Union of India, (1999) 9 SCC 449, in support of his submissions that in a case like the present one regarding an altogether unique and novel project, the time could not be the essence of the contract. In the case of Gomathinayagam Pillai v. Pallaniswami Nadar (supra), the Apex Court observed that the intention of parties to make time essence of the contract must be unmistakable and may also be inferred from the conduct of parties and surrounding circumstances at or before the terms of contract.

9. In the case in hand, the question as to whether the time was or not the essence of the contract has to be considered keeping in mind the fact that the contract between the parties was to introduce in four areas a unique Broadband Service through TV which has not so far been introduced anywhere else in the country. In the Franchisee Agreement dated 20.4.2004 also, it was nowhere specifically stipulated that the time was the essence of the contract. It is true that the Clause 7 of Schedule 1 of this Agreement provides that the petitioner shall launch the broadband services in the four SSAs within six months of the signing of the Agreement and it would also ensure the positioning of the equipment in four months' time but it was not at all stipulated therein that the time was the essence of the contract and, as such, the franchisee should ensure that there is no delay. In this agreement Clause 6(b) provided that the delay by the franchisee/petitioner in the performance of obligations shall render the franchisee liable to forfeiture of the performance Bank Guarantee submitted by him, imposition of damages and/or termination of the franchisee agreement for default as per the decision of the respondent. But here also, it was not recorded that the time was the essence of the contract and, as such, strict adherence to time schedule was required.

10. Not only that Franchisee Agreement did not say that the time was the essence of the contract subsequent conduct also of parties does not convey that it was so. On 11.8.2004, respondent No. 1 wrote a letter to petitioner pointing out delay and other irritants but did not say that the Franchisee Agreement would be terminated on account of delay. If the time was the essence of the contract, the respondent No. 1 ought to have terminated the agreement on 21.8.2004 itself when it had written another letter to the petitioner complaining about the delay. It ought to have done so inasmuch as the equipment required for the project had to be in place by 19.8.2004, which had not been done, and the respondent No. 1 knew that the petitioner was still in the process of procuring equipment and taking various other steps for its installation. Not only this, on 15.10.2004, the petitioner wrote a letter to respondent No. 1 for extension of time for the completion of the project. Reminders even were issued by petitioner on 1.11.2004 and 15.11.2004 reiterating difficulties but there was no response from the side of respondent No. 1. Had the respondent No. 1 been so particular about the time schedule and had it considered the time essence of the contract, it would have immediately responded to the letter dated 15.10.2004 to say that the contract was liable to be terminated as the last date for commercial launch of the services was 19.10.2004 but till 15.10.2004, the petitioner had not even installed its equipment which was to be set up by 19.8.2004 Without replying to the aforesaid letters, the respondent No. 1 chose to terminate the contract vide notice dated 10.12.2004 which was done after about two months of the first letter dated 15.10.2004 The respondent No. 1 ought to have realized that by keeping silent it was making petitioner invest more and more in the project although the project was running behind schedule. Clause 6(c) of the agreement envisages penalties also for delays which indicates that the time was not the essence of the contract.

11. It was in the knowledge of the respondent No. 1 that till about the end of September, 2004, the petitioner was carrying out site surveys but still, the respondent No. 1 took no steps to assert that the time was the essence of the contract and the petitioner was lagging behind. It is also noticed that OTA was to be signed within 15 days of Franchisee Agreement but it was signed on 4.6.2004 only which shows that since inception of contract parties never understood that time was the essence of the contract. Had it been so, their conduct would have been altogether different. The mere fact that the petitioner was assuring the respondent No. 1 that the project will be on time does not establish that the time was the essence of the contract inasmuch as the assurances could be given under a hope that the project would be completed soon but at no point of time, the petitioner got any indication that respondent No. 1 was going to plead that the time was essence of the contract. This Court, therefore, is of the considered view that the time was not the essence of the contract. The respondent No. 1 is merely trying to wriggle out of the agreement of certain other reasons which have nothing to do with the delay in the launching of the project. The question as to whether the time was the essence of the contract or not has to be finally adjudicated by the Arbitrator only in terms of the arbitration agreement but prima facie, this Court can safely say that time was not the essence of the contract.

12. Learned Counsel for respondent No. 1 has further argued that the Franchisee Agreement between the parties was determinable and, as such, the petitioner has no right to seek specific performance thereof. He relies upon Section 14 of the Specific Relief Act to contend that such a contract cannot be specifically enforced. In support of his plea, he relies upon the judgments in Rajasthan Breweries Limited v. The Stroh Brewery Company., AIR 2000 Delhi 450; Vidya Securities Ltd…Petitioner v. Comfort Living Hotels Pvt. Ltd…, 102 (2003) DLT 797 and BSM Contractors Ltd. v. Rajasthan State Bridge Corporation, AIR 1999 Delhi 117. It is true that the contracts which are determinable in nature cannot be specifically enforced and injunctions cannot be granted to prevent breach of such contracts but this principle primarily applies to private commercial contracts as held in the case of ‘Rajasthan Breweries’. The case of BSM Contractors was regarding construction of a building. In the case of Vidya Securities, the agreement was for running a restaurant which included catering of food even. Therefore, all these judgments are not squarely applicable to the facts of the present case. Learned Counsel for the petitioner on the other hand relies upon the judgments in Mahabir Auto v. Indian Oil Corporation, (1990) 3 SCC 752 : AIR 1990 SC 1031 and Pioneer Publicity Corporation… v. Delhi Transport Corporation & Anr.…, 103 (2003) DLT 442. He argues that the contract may be determinable in nature but since it was for setting up a unique project for which petitioner had procured tailormade equipment, which could not be utilized anywhere else, specific performance may be ordered. It is argued that in case the petitioner is left to pursue the remedy of damages only it would result in its ruination, as it has already pumped in over Rs. 115 crores in the project. He further argues that there may be a discretion with respondent No. 1 to terminate or not the contract but this discretion should not be exercised arbitrarily without there being goods grounds for terminating the contract. It is submitted that respondent No. 1 is an instrumentality of the State and must act in a fair, just and equitable manner.

13. It is true that the Franchisee Agreement between the parties could be terminated by giving one month's notice or could be determined even after commissioning of the project but considering the fact that the petitioner has invested fairly large amount in the project which is unique and the respondent No. 1 is an instrumentality of the State which remains under an obligation to act in a just and fair manner, it has to be seen as to whether the decision of respondent No. 1 to terminate the Franchisee Agreement is prima facie sustainable or not. In the realm of private contracts, the freedom, which is available to a private party, in respect of the performance of contractual obligations, is not available to the State or its instrumentalities in the same measure because every action of the State has to be just, fair and devoid of arbitrariness. The State or its instrumentalities cannot conduct themselves like ordinary businessmen playing games with others for monetary gains. State cannot behave like a man in the street and indulge in arm-twisting tactics. Its conduct and actions have to be exemplary and decisions have to be free from arbitrariness, bias and unreasonableness. The reputation of the country and its credibility in business world are far more important than certain economic gains which appear to be unfair and unjust.

14. In this case, the delay on the part of the petitioner was not too much and it is shown on record that in spite of the fact that the project was behind schedule, the respondent No. 1 was never raising any serious objection and conveying that the time schedule was to be strictly adhered to. Penalties provided for the delay indicate that determination of contract was not necessary. The agreement was not for an ordinary article of trade and commerce. It is also shown that the respondent No. 1 is not spending anything on the project but is to share only the income that may be made by the petitioner after the launching of the project. The petitioner has no exclusivity in the project and respondent No. 1 itself or others may also join the fray. The petitioner has already pumped in huge investments in the project and if at this stage, the petitioner is ousted from the contract without sufficient and good reasons on account of little delay only, it would be a difficult situation for it and would cause irreparable loss and injury to it.

15. It is not shown that the respondent No. 1 is in a position to launch the project on its own very soon. If the respondent No. 1 still needs time to start the project on its own, why it cannot give some time to petitioner also for completing the project. It is not at all alleged by respondent No. 1 that the petitioner had committed any other breach or default except delay in the commissioning of the project. It is also not understandable as to why the respondent No. 1 should run the risk of paying damages to the petitioner for breach of contract which the situation can be saved by permitting the petitioner to continue with the project in which petitioner has no exclusivity. Had the respondent No. 1 been a private party, it would have thought hundred times before raising such a plea as the damages, if awarded, may be enormous. The petitioner is pleading that it has already spent over 22 million dollars on the project. In case the Arbitrator holds that termination of contract was not lawful, the respondent No. 1 may have to pay this amount as damages. Since the respondent No. 1 is an instrumentality of the State and the damages are not to go from the pockets of its officers, a plea is easily raised that the petitioner should seek damages. The respondent No. 1 and its officers dealing with the Franchisee Agreement should appreciate that risk of paying such heavy damages should not be taken lightly. Public money has to be protected with utmost care and concern. Hazardous and adventurous pleas should not be taken when public money is at stake.

16. The plea of learned Counsel for respondent No. 1 that Section 14 of the Specific Relief Act prohibits grant of injunctions in respect of the contracts mentioned therein and in this case all the clauses of section 14 are attracted. Learned Counsel for the petitioner has opposed this submission by referring to Section 10(ii)(a) of the said Act and submits that since the project under the agreement is unique and the equipment created tailor made for respondent No. 1 and since the respondent No. 1 is an instrumentality of the State, it has no right to act arbitrarily and unreasonably. It is submitted that Section 14 of the Specific Relief Act does not stand in the way of petitioner.

17. After considering the submissions made by learned Counsel for the parties and considering the facts and circumstances of this case and as discussed hereinbefore also, this Court is of the considered view that Section 14 of the Specific Relief Act does not stand in the way of the Court to grant the relief as prayed in as much as by the impugned act of respondent No. 1 the petitioner may be unreasonably ousted from Indian market and, therefore, compensation in terms of money may not be adequate relief. The contract may be determinable in nature but the instrumentality of the State has to act in a fair and just manner and not arbitrarily. This principle may hold good between private parties but not in those cases where the highhandedness appears to be on the part of the State or its instrumentality. It also cannot be said that the contract between the parties runs into minute details or the Court cannot enforce specific performance of its material terms nor it can be said that the contract involves performance of continuous duty, which the Court cannot supervise. The Franchisee Agreement between the parties is a detailed agreement containing duties and obligations of both the parties. Respondent No. 1 has to provide its cable network and the rest of the performance is to be by the petitioner. The agreement between the parties is non-exclusive and on revenue sharing basis under which the respondent No. 1 has to gain only. The nonperformance or the failure of the petitioner would not cause any financial loss to respondent No. 1 inasmuch as under the agreement itself, the respondent No. 1 can involve itself or others also for providing the same services. The plea of respondent No. 1 that the petitioner may utilize its equipment in other areas and through other service providers is also no answer to the claim of the petitioner that it is being ousted arbitrarily and without any good and sufficient cause.

18. The plea of learned Counsel for respondent No. 1 that the petitioner has not come to the Court with clean hands and, as such, is not entitled to any equitable relief cannot be sustained for the reason that mere shipment of the equipment by petitioner after the termination of the contract vide notice dated 10.12.2004 does not suggest that the petitioner was trying to create a situation under which it could plead that the equities were in its favour. As discussed earlier also, according to the petitioner, the equipment produced for the project is tailormade for the project and, as such, the petitioner committed no wrong in shipping the equipment to India after the termination notice even under a hope that it may be in a position to persuade the respondent No. 1 to permit the petitioner to go ahead with the project. In the letters dated 15.10.2004 and 1.11.2004, the petitioner was explaining to the respondent No. 1 the progress of the project and was asking even for extension of time hut no reply was given by respondent No. 1. This conduct of respondent No. 1 was curious and, as such, the petitioner could very well bring its equipment to India and then invoke legal remedies to assert that the termination of the contract was illegal, unjust and unfair. It may be recorded here itself that the questions as to whether the time was or not essence of the contract and as to whether the determination of the contract by respondent No. 1 was valid or not would be adjudicated by the Arbitral Tribunal only. The findings given by this Court in this petition are prima facie and tentative only with a view to consider the prayer of the petitioner under Section 9 of the Act.

19. Considering the submissions made by learned Counsel for the parties and the facts and circumstances of this case, this Court has no hesitation in coming to a prima facie conclusion that the time was not the essence of the contract and the respondent No. 1 is acting arbitrarily, unreasonably and in an inequitable manner by terminating the Franchisee Agreement merely on the ground of some delay to which the respondent No. 1 was also a party and to which it had never raised any serious objection. The respondent No. 1, by its conduct, allowed the petitioner to invest more and more funds in the project and thereby drove petitioner to a situation where it would not only suffer huge financial loss but loss of trade reputation and goodwill also which may not be compensated in terms of money. The balance of convenience is more in favour of the petitioner inasmuch as the agreement can still be acted upon by both the parties in terms of their obligations a detailed in the agreement. In this petition under Section 9 of the Act, this Court is not at all in a position to order specific performance of the contract inasmuch as it can be ordered by the Arbitral Tribunal only in terms of the arbitration agreement between the parties. This Court can only restrain respondent No. 1 from terminating the Franchisee Agreement in question till the Arbitral Tribunal adjudicates the controversies between the parties.

20. Accordingly the petition is allowed and the operation of the impugned notice dated 10.12.2004 is stayed and the respondent No. 1 is restrained from treating the Franchisee Agreement dated 29.4.2004 as terminated till the Arbitral Tribunal passes its award. With a view to ensure that there is no undue delay in the constitution of the Arbitral Tribunal, this order is made conditional that the petitioner shall invoke the Arbitration Clause and initiate steps for the appointment of the Arbitral Tribunal in terms of the agreement between the parties within two weeks from today failing which the restraint orders passed by this Court shall automatically lapse.

21. The petition stands disposed of.

Petition allowed.