Sundari Ammal, Tuticorin District Another v. Kandappan Tuticorin District
Summary of Opinion
Factual and Procedural Background
The matter arises from R.C.O.P. No. 1 of 2003 in which the first revision petitioner (tenant) was defendant in an eviction petition filed by the respondent (landlord) on grounds including willful default and sub‑letting. The trial proceeded and the tenant did not appear for cross‑examination on 7.10.2003; as a consequence an ex‑parte order of eviction was passed on that date.
The tenants filed I.A. P. No. 4 of 2004 to set aside the ex‑parte eviction order. That application was allowed conditionally on payment of Rs. 200 to the landlord by 25.2.2004, but the conditional cost was not paid and I.A. No. 4 of 2004 was dismissed on 25.2.2004.
I.A. No. 6 of 2004 was then filed under Section 5 of the Limitation Act seeking condonation of a delay of 143 days in restoring I.A. No. 4 of 2004. The tenants explained they were out of station and did not receive the counsel's letters in time; the landlord resisted, alleging the application was a delay tactic and pointing out that E.P. No. 13 of 2004 for execution had been filed. The rent controller dismissed I.A. No. 6 of 2004, finding the delay unexplained and that the application was filed to delay eviction. The tenants challenged that dismissal by filing the present civil revision petition under Article 227 of the Constitution of India.
Legal Issues Presented
- Whether the revision petition filed under Article 227 of the Constitution of India invoking the supervisory jurisdiction is maintainable?
- Whether the order dismissing the application filed under Section 5 of the Limitation Act (declining to condone a delay of 143 days) suffers from any material irregularity warranting interference?
Arguments of the Parties
Revision Petitioners' (Tenants') Arguments
- The tenants did not receive the letter sent by the lower court's counsel in time and therefore could not comply with the conditional order requiring payment of costs.
- The delay of 143 days in filing the application to restore I.A. No. 4 of 2004 has been properly explained and should be condoned under Section 5 of the Limitation Act.
- Section 5 of the Limitation Act is applicable to rent control proceedings; reliance was placed on multiple decisions to support this contention.
Respondent's (Landlord's) Arguments
- The revision petition is not maintainable; only an appeal under Section 23(1)(b) of the Tamil Nadu Buildings (Lease and Rent Control) Act ought to have been preferred against the order of the rent controller. Reliance was placed on M. S. Hameed v. Kanniammal, (1981) 1 M.L.J. 477.
- On facts, the tenants have not properly explained the 143‑day delay and have not shown sufficient cause for it.
- Having chosen not to challenge the order of eviction earlier, the tenants cannot now seek to restore I.A. No. 4 of 2004 to delay eviction; the application is a dilatory tactic.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| m. S. Hameed v. Kanniammal, (1981) 1 M.L.J. 477 | Authority that revisional jurisdiction under Section 115 CPC (and by analogy other supervisory/revisional remedies) is not available where a special, self‑contained statute provides for appeal and revision; such statutory scheme limits resort to general revisional powers. | The court relied on this decision to hold that Article 227 cannot be used to challenge orders of the rent controller when the Act prescribes appeal (Section 23) and revision (Section 25) routes; hence the revision petition invoking Article 227 was held not maintainable. |
| Unreported decision of Natarajan, J. in S.R. No. 55329 of 1979 dated 17th August 1979 | Referenced as a contrasting/unreported view (different approach taken in that decision). | Mentioned in the context of showing there were differing views, but the court followed M. S. Hameed and held the special statutory scheme prevailed; the unreported decision was not adopted as authoritative for the present case. |
| e. K. Venkaimarban v. Dakshinamoorthy, (1981) 1 M.L.J. 275 | Cited by the revision petitioners' counsel to support the proposition that Section 5 of the Limitation Act applies to rent control proceedings. | The court accepted that Section 5 is applicable to rent control proceedings but held that applicability of Section 5 did not justify invoking Article 227 instead of the statutory appellate/revisional remedies under the Act. |
| municipal corporation, gwalior v. Rama cgandran (d) by l. Rs., (2002) 2 C.T.C. 349 | Cited by the revision petitioners' counsel to support the contention that Section 5 of the Limitation Act applies to the proceedings in question. | Similar to other authorities relied upon by the tenants: the court noted these decisions but determined that even accepting applicability of Section 5, the statutory remedy structure (Sections 23 and 25) governed the appropriate forum for challenge. |
| Chandrasekaran v. A. S. Chinnamuthu, (2002) 4 C.T.C. 484 | Relied upon by the tenants' counsel for the applicability of Section 5 of the Limitation Act to rent control matters. | The court acknowledged the reliance but held that acknowledgement of Section 5's applicability did not permit bypassing the appeal route prescribed by the Act; the revision under Article 227 remained unmaintainable. |
| p. S. Pareed kaka v. Shaee ahmed sahib, (2004) 5 S.C.C. 241 | Another decision cited by the tenants' counsel in support of the applicability of Section 5 of the Limitation Act. | The court accepted the general proposition that Section 5 applies but reiterated that the statutory procedure for challenge under the Rent Act (appeal and revision) dictated the proper remedy; Article 227 could not be used as a substitute. |
Court's Reasoning and Analysis
The court's analysis proceeded in two principal strands: (A) maintainability of the revision under Article 227, and (B) merits regarding condonation of delay under Section 5 of the Limitation Act.
A. Maintainability under Article 227
The court examined the statutory scheme of the Tamil Nadu Buildings (Lease and Rent Control) Act. Section 23(1)(b) provides that any person aggrieved by an order of the controller may prefer an appeal in writing to the appellate authority within fifteen days (excluding time to obtain certified copy). Section 23(3) describes the appellate authority's powers and mode of disposal. Section 23(4) declares the decision of the appellate authority (and, subject to it, the controller's order) final and not liable to be called in question in any court except as provided in Section 25. Section 25 permits the High Court to call for and examine the record of the appellate authority and exercise revisionary powers in specified circumstances.
From a combined reading of Sections 23 and 25, the court concluded that the Act creates a special, self‑contained remedial scheme: orders of the rent controller are to be challenged by appeal to the appellate authority, and further revision lies under Section 25 to the High Court. Consequently, invoking Article 227 to challenge an order of the rent controller would circumvent the Act's specially provided remedies and render Sections 23 and 25 nugatory.
The court relied on the authority in M. S. Hameed v. Kanniammal to reinforce that where a special statute provides specific appeal/revision mechanisms, resort to general revisional or supervisory jurisdiction is impermissible. The High Court's supervisory powers under Article 227 are to be sparingly exercised and normally only in cases of jurisdictional error apparent on the face of the record.
B. Merits — Condonation of Delay under Section 5
Even assuming maintainability, the court considered whether the tenants had established sufficient cause for the 143‑day delay. The factual timeline accepted by the court: P.W.1 was examined in chief and the case posted for his cross‑examination on 7.10.2003; the tenants did not appear and were set ex‑parte on that date with an eviction order. I.A. No. 4 of 2004 to set aside the ex‑parte order was allowed subject to payment of Rs. 200 on or before 25.2.2004; the tenants failed to pay and the application was dismissed on 25.2.2004. I.A. No. 6 of 2004 (seeking condonation) was filed on 15.8.2004 — approximately five months later — seeking to condone 143 days of delay.
The tenants' explanation (being out of station and not receiving the counsel's letter in time) was considered inadequate. The rent controller's findings of negligence and inactivity on the part of the tenants, and that the application appeared to be a dilatory tactic to delay eviction, were accepted by the High Court as not suffering from any jurisdictional error apparent on the face of the record. The court therefore upheld the rent controller's conclusion that the delay was not sufficiently explained and that condonation was rightly declined.
Holding and Implications
DISMISSED: The civil revision petition was dismissed and the impugned order dated 19.10.2004 passed by the District Munsif, Sathankulam in I.A. No. 6 of 2004 in I.A. No. 4 of 2004 in R.C.O.P. No. 1 of 2003 was confirmed.
Implications:
- Direct effect on the parties: the dismissal confirms the rent controller's refusal to condone the 143‑day delay and leaves the eviction/order proceedings intact; there was no order as to costs.
- Procedural/legal implication: the High Court affirmed that where a special statutory scheme (Sections 23 and 25 of the Rent Act) prescribes appeal and revision routes, invoking the High Court's supervisory jurisdiction under Article 227 to challenge orders of the rent controller is not maintainable except in cases of jurisdictional error apparent on the face of the record. The court accepted that Section 5 of the Limitation Act applies to rent control proceedings but held that applicability does not displace the statutory appellate/revisional scheme.
- The court did not indicate that it was laying down any novel precedent beyond applying the statutory scheme and existing authority; it affirmed the established principle that Article 227 is to be sparingly exercised and not as a substitute for the remedies provided by the Rent Act.
Disposition: Petition dismissed. No order as to costs.
This civil revision petition is directed against the order dated 19. 10. 2004 passed by the district munsif, sathankulam in i. A. No. 6 of 2004 in i. A. No. 4 of 2004 in r. C. O. P. No. 1 of 2003, dismissing the petition filed under sec. 5 of the limitation act declining to condone the delay of 143 days in filing the application to restore i. A. No. 4 of 2004. Tenant is the revision petitioner.
2. R. C. O. P. No. 1 of 2003: the first revision petitioner is the tenant under the respondent/ landlord. The eviction petition was filed on the grounds of willful default, sub‑letting etc. The trial commenced and the case was posted on 7. 10. 2003 for cross‑examination of the respondent/landlord. On that date, the revision petitioner/tenant has not appeared in the lower court and hence, an ex‑parte ‑ order of eviction was passed on 7. 10. 2003.
3. I. A. P. No. 4 of 2004: this application was filed by the revision petitioners/tenants to set aside the ex‑parte order of eviction dated 7. 10. 2003. This application was ordered with condition to pay rs. 200 to the respondent/landlord on or before 25. 2. 2004. The cost was not paid and the conditional order was not complied with. Hence, i. A. No. 4 of 2004 was dismissed on 25. 2. 2004.
4. I. A. No. 6 of 2004:‑ this application has been filed under sec. 5 of the limitation act to condone the delay of 143 days in filing the application to set aside the ex‑parte order in i. A. No. 4 of 2004 and to restore the same. According to the revision petitioners/tenants, they were out of station and the letters sent by the lower court counsel intimating them about the conditional cost was not received by them in time and hence, they could not comply with the order. By filing the counter statement, the respondent/ landlord has resisted the application contending that the application has been filed only with a view to delay the order of eviction. It was pointed out that e. P. No. 13 of 2004 was already filed.
5. In consideration of the contentions of both parties, learned rent controller dismissed the application finding that the delay has not been properly explained. It was further held that the application has been filed only to delay the eviction proceedings. Learned rent controller has observed that despite time has given to the tenants to pay the around, the t ants have not chosen to pay the rent and, application has been filed only to delay eviction. The rent controller has observed the tenants have been negligent and inactive in pursuing the matter.
6. As against the order of dismissal of the application in i. A. No. 6 of 2004, the revision petitioners/tenants have preferred this civil revision petition. Assailing the impugned order, learned counsel for the revision petitioners has submitted that the tenants did not get the letter sent by the counsel in time and hence, they could not comply with the conditional order. It is further submitted that the delay has been properly explained, which was not properly appreciated by the courts below, submitting that sec. 5 of the limitation act is applicable to the rent control proceedings, learned counsel for the revision petitioners has relied upon number of decisions.
7. Countering the arguments, learned counsel for the respondent/landlord has raised objection regarding the maintainability of the revision petition. Submitting that only appeal ought to have been preferred against any order of the rent controller, learned counsel for the respondent/landlord has relied upon the decision reported in m. S. Hameed v. Kanniammal, (1981) 1 m. L. J. 477. It is further submitted that even on facts, the revision petitioner has not properly explained the delay and no sufficient cause has been shown for the delay and no sufficient cause has been shown for the delay of 143 days. It is further submitted that having not chosen to challenge the order of eviction, the revision petitioners/tenants cannot seek to restore the application in i. A. No. 4 of 2004.
8. In consideration of submissions of both sides, impugned order and other materials on record, the following points arise for consideration in this civil revision petition:
(i) whether the revision petition filed under art. 227 of the constitution of india invoking the supervisory jurisdiction is maintainable?
(ii) whether the order dismissing the application filed under sec. 5 of the limitation act declining to condone the delay suffers from material irregularity warranting interference?
9. The foremost question that arises for cons ration is as to the maintainability of the revision petition filed under art. 227 of the constitution of india. Sec. 23 (b) of the tamil nadu buildings (lease and rent control) act (hereinafter referred to as the act) embodies a special procedure for filing the appeal. Sec. 23 (1) (b) reads as follows:
Any person aggrieved by an order passed by the controller may, within fifteen days from the date of such order, prefer an appeal in writing to the appellate authority having jurisdiction. In computing the fifteen days aforesaid, the time taken to obtain a certified copy of the order appealed against shall be excluded.
The scope and the powers of the appellate authority as well as the mode of disposal of appeal are indicated in sec. 23 (3) of the act. Sec. 23 (3) of the act reads as under:
" the appellate authority shall call for there cords of the case from the controller and after giving the parties an opportunity of being heard and, if necessary, after making such further inquiry as he thinks fit either personally or through the controller, shall decide the appeal."
10. Sec. 23 (4) of the act gives effect to the finality of the order passed by the appellate authority. Sec. 23 (4) of the act lays down an interdict against such order being challenged in any court of law. Sec. 23 (4) of the act reads us under:
"the decision of the appellate authority, and subject to such decision, an order of the controller shall be final and shall not be liable to be called in question in any court of law, except as provided in sec. 25."
11. Sec. 25 of the act provides for the revision wherein the high court can cal i for and examine the record of the appellate authority or propriety of any decision and orders passed thereon. In reversing the orders, wide powers are conferred upon the high court to modify, reverse or remit the matter for reconsideration. Sec. 25 of the act reads as under:
" (1) the high court may, on the application of any person aggrieved by an order of the appellate authority, call for and examine the record of the appellate authority, to satisfy itself as to the regularity of such proceeding or the correctness, legality or propriety of any decision or order passed therein and if, in any case, it appears to the high court that any such decision or order should be modified, annulled, reversed for reconsideration, it may pass orders accordingly."
12. By a reading of secs. 23 and 25 of the act, it is seen that as against the order of the rent controller, only an appeal would lie under sec. 23 (1) (b) of the act. Only as against such order passed by the rent control appellate authority, a revision is maintainable under sec. 25 of the act. That is why sec. 23 (4) of the act declares the finality of the decision of the appellate authority and provides that those orders cannot be called into question except as provided under sec. 25 of the act. On a combined reading of secs. 23 and 25 of the act, it is clear that as against the order passed by the rent controller, only an appeal is to be filed before the appellate authority. The order passed by the rent controller cannot be challenged invoking art. 227 of the constitution of india. If each and every order of the rent controller is to be challenged invoking art. 227 of the constitution of india, secs, 23 and 25 of the act would be rendered nugatory. In view of the efficacious alternative remedy available, the revision is not maintainable.
13. The impugned order was passed by the rent controller in i. A. No. 6 pf 2004 declining to condone the delay of 143 days in filing the application to set aside the order made in i. A. No. 4 of 2004. Against the order made in i. A. No. 6 of 2004 only an appeal ought to have been preferred before the rent control appellate authority under sec. 23 (1) (b) of the act.
14. In a similar case reported in m. S. Hanwed v. Kanniammal, (198i) 1 m. L. J. 477, v. Ratnam, j. , taking a different view from the unreported decision of natarajan, j in s. R. No. 55329 of 1979, dated 17th august 1979 has held that the revisional jurisdiction under sec. 115, c. P. C. , is not a matter of assumption or presumption. In the said decision, it has been held as under:
.. Though the inapplicability of the jurisdiction of this court under sec. 115, c. P. C. , cannot be a matter of either assumption or presumption as stated by the learned judge, yet in view of the specific statutory provisions referred to already, such a conclusion is inevitable and the orders of the rent controller or the appellate authority constituted under the act cannot be questioned under sec. 115, c. P. C. As pointed out already, the act is a self‑contained act containing provisions for appeal as well as revision and enabling an aggrieved party to challenge the correctness of orders passed by the authorities under the act in the manner provided there under and no more. Consequently, resort to sec. 115, c. P. C. , in matters or proceedings arising out of the provisions of the act cannot be had to test the correctness of the orders passed under the act. Therefore, it may not be appropriate even to characterize the provisions of sec. 11,5 c. P. C. , and sec. 25 of the act as mutually exclusive and to hold that the revisional power under sec. 115, c. P. C. , is always available even with reference to the matters arising under the provisions of the act, under which special, but ‑limited provisions are made to question the correctness of orders passed under the provisions of that act. In view of these considerations, the civil revision petition filed by the petitioner purporting to be under sec. 115, c. P. C. , cannot entertained in this court and consequently has to be dismissed.
15. In the above case, the tenant was set ex - parte and an ex‑parte order of eviction was passed. An application was filed for setting aside the ex‑parte order of eviction, which was allowed on payment of conditional cost of rs. 25 to the landlord. The tenant has not paid the cost within the time granted by the rent controller. The application was dismissed. The correctness of the order is challenged by the tenant by filling the revision under sec. 115, c. P. C. Though the present revision petition has been filed under art. 227 of the constitution of india, the above observation applies to the case in hand. When efficacious alternative remedy is available to the revision petitioners/tenants by way of filing the appeal before the rent control appellate authority, the revision petition filed invoking the supervisory powers of this court under art. 227 of the constitution of india is not maintainable.
16. Even on merits, the revision petitioners/ tenants have not made out a case. P. W. 1 was examined in chief. For his cross‑examination, the case was posted on 7. 10. 2003. The tenants have neither appeared nor had given in structions to their counsel to get along with the matter. Because of their non‑appearance, they were set ex‑parte on 7. 10. 2003 and ex‑parte order of eviction was passed on the same date. I. A. No. 4 of 2004 was allowed on condition of payment, of cost of rs. 200 to be paid to the rd on or before 25. 5. 2604. The revision petitioners/tenants have not complied with the nearly after a period of five months, i. A. No. 6 of 2004 was filed on 15. 8. 2004. No le explanation is forthcoming for such inordinate delay in filing the application. It is that the respondent/landlord has already e. P. No. 13 of 2004 for executing the or perhaps after knowing about proceedings, the revision petitioners/tenants have filed the application under of the limitation act seeking to codone the delay in filing the application to set aside the order made in i. Ano. 4 of 2004 and to restore that application. The reasons stated by revision petitioners/tenants seeking condo‑11 of delay are not convincing. Learned controller has rightly declined to condone delay.
17. Learned counsel for the revision petitioners/tenants has relied upon number of decisions in reported in e. K. Venkaimarban v. Dakshinamoorthy, (1981) 1 m. L. J. 275: municipal corporation, gwalior v. Rama cgandran (d) by l. Rs. , (2002) 2 c. T. C. 349; chandrasekaran v. A. S. Chinnamuthu, (2002) 4 c. T. C. 484; p. S. Pareed kaka v. Shaee ahmed sahib, (2004) 5 s. C. C. 241, to support his contention that sec. 5 of the limitation act is applicable to the rent control proceedings. There is no denying that sec. 5 of the limitation act is applicable to the rent control proceedings. The question is whether such an order passed by the rent controller, is to be revised under art. 227 of the constitution of in at. As against the order passed by the rent controller only an appeal ought to have been preferred under sec. 23 (1) (b) of the act.
18. The powers conferred under art. 227 of the constitution of india is to be sparingly exercised. Exercising the power under art. 227 of the constitution of india the, high court would not interfere with the impugned order unless it suffers from any jurisdictional error apparent on the face of record. In this case, the impugned order does not suffer from any jurisdictional error apparent on the face of record warranting interference. This civil revision is neither maintainable nor the impugned order suffers from any infirmity or illegality.
19. For the foregoing reasons, the order dated 19. 10,2004 passed by the district munsif, sathankulam in i. A. No. 6 of 2004 in. I. A. No. 4 of 2004, in r. C. O. P. No. 1 of 2003, is confirmed and this civil revision petition is dismissed. In the circumstances of the case, there is no order as to costs.
Petition dismissed.