The South Indian Railway Company Limited . v. S.M Bhashyam Naidu (Deceased) And Others

Madras High Court
Sep 3, 1934
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Provided Opinion

Factual and Procedural Background

The opinion examines three documents (Exs. I-a, KK and II) in the context of a dispute arising from a contractor's claim under a suit contract for payment (relating to earthwork and "lift"). Ex. I-a is a circular dated 29 October 1926 from the acting Chief Engineer to Executive and Assistant Engineers on the Mayavaram–Tranquebar Railway, giving an instruction under paragraph 19 of S. 3 of Ex. IV; it contained no reference to any particular contract. Ex. KK is a letter dated 22 December 1926 from the Chief Engineer to the Executive Engineer of the Shoranur–Nilambur Railway, stating an interpretation of earthwork rates as being "through rates from ground to formation level" and explaining why partial claims for the first 6 feet would be absurd. Both Exs. I-a and KK were executive instructions to subordinates and were not communicated to the contractor.

The contractor submitted a bill in which the Executive Engineer allowed a smaller rate than the Company later insisted upon. The contractor then submitted a claim (Ex. D-1). Following closure of the sub-office handling the Shoranur–Nilambur Railway, Ex. D-1 was forwarded to the Engineer-in-Chief (the Chief Engineer), who discussed the claim with D. W. 1 (an officer) but without the contractor being present. The Engineer-in-Chief then communicated his answer in Ex. II, stating that "the measurements for lift recorded in the final measurements are in accordance with the agreement and specifications and as per my instructions on the subject and payment in the manner claimed by you is inadmissible."

The central procedural question posed to the court was whether Ex. II (and, by implication, the preceding executive instructions) amounted to a decision within the meaning of Clause 41 of the parties' agreement such that the Engineer's decision would be final and conclusive between the parties and therefore preclude the Court from deciding the contractual construction itself. The court reviewed the documentary record and the evidence (including testimony by D. W. 1) and considered relevant authorities before reaching its conclusion.

Legal Issues Presented

  1. Whether Ex. I-a and Ex. KK — general executive instructions issued by the Chief Engineer to subordinates before any specific claim was made — can be connected to, or treated as, a decision under the suit contract (and thus within Clause 41).
  2. Whether Ex. II, the communication sent by the Engineer-in-Chief after the contractor's claim (Ex. D-1) was put forward, constitutes a decision within the meaning of Clause 41 of the agreement (i.e., whether it was made with the consciousness and judicial independence required to render it final and conclusive between the parties).
  3. If Ex. II does not amount to a Clause 41 decision, whether the Court is therefore entitled to put its own construction on the suit contract and grant the contractor what he is entitled to under the contract.

Arguments of the Parties

Appellant's Arguments

  • Reliance was placed chiefly upon Ex. II — i.e., the appellant argued that Ex. II represented the Engineer-in-Chief's decision and should be treated as final under Clause 41.

Plaintiff's (Respondent's) Arguments

  • It was suggested on the plaintiff's side that Ex. II was in reality prepared by D. W. 1 and forwarded as an ordinary office communication with the Engineer-in-Chief's signature, implying that it was not a conscious exercise of the decision-making power under Clause 41.
  • The plaintiff also pointed out that Exs. I-a and KK had not been communicated to the contractor, and that the contractor had not been heard prior to Ex. II being sent, arguing these facts undermine the contention that Ex. II was a Clause 41 decision made with judicial consciousness.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Burmah Trading Corporation Limited v. Aga Mahomed Khaleel Shirazi (Privy Council) Emphasises that engineers or architects exercising final decision-making powers discharge "judicial" functions and, particularly when employees of one contracting party, are in a delicate position requiring conscious judicial exercise of power. The court relied on the principle that such decision-makers must act with awareness of their judicial responsibilities; this supports requiring evidence that the Engineer-in-Chief consciously exercised Clause 41 powers when issuing Ex. II.
Hickman & Co. v. Roberts (House of Lords) Similar principle: persons granted final decision-making powers in contracts perform quasi-judicial functions and must act judicially and independently. Used to underline that before treating an engineer's expression of opinion as final, the court must be satisfied the officer intended to exercise the conferred power judicially; applied to assess Ex. II.
Bristol Corporation v. John Aird and Co. (House of Lords) Affirms the delicate position of an engineer/architect who is an employee of a contracting party and stresses the need for judicial procedure when finality is conferred. Cited to support the requirement that the Engineer-in-Chief show conscious exercise of Clause 41 powers; influenced the court's insistence on evidence of a hearing or equivalent procedural indicia absent here.
Stevenson v. Watson Deals with how far an Engineer or architect acting under such circumstances can be held liable for negligence. The court stated this case is "not much in point" for the specific question before it (whether the Engineer acted judicially under Clause 41), because it concerns negligence rather than the judicial nature of a decision.
Chambers v. Goldthorpe; Restell v. Nye Address the liability of engineers/architects in negligence when acting under contractual powers. The court observed these cases do not throw light on whether an engineer acted judicially in a particular instance; they focus on negligence and thus were not of direct assistance here.

Court's Reasoning and Analysis

The court proceeded in discrete analytical steps, constrained strictly by the documentary record and the evidence before it:

  1. Characterisation of Exs. I-a and KK: Both were identified as general executive instructions issued by the Chief Engineer to subordinates before any claim under the suit contract had been made. The court found it "impossible to connect Ex. I-a with the suit contract" because no claim had been made at the date of Ex. I-a and because the suit contract did not follow the printed specification (Ex. IV) in the relevant respect. Ex. KK was likewise an instruction to subordinates and was not insisted on as amounting to a decision within Clause 41.
  2. Focus on Ex. II: The court accepted that Ex. II was sent after the contractor's claim (Ex. D-1) was submitted, and that the Engineer-in-Chief's communication (Ex. II) stated that the measurements were in accordance with agreement/specifications and that the claimed payment was inadmissible. The court examined the circumstances of its preparation: Ex. D-1 had been forwarded to the Engineer-in-Chief with remarks that were not before the court; the sub-office had been closed; the contractor was not present; the only materials before the Engineer-in-Chief were Ex. D-1 and the witness's knowledge; and Ex. II may have been drafted by D. W. 1 and sent for the Chief Engineer's signature.
  3. Legal standard derived from authorities: The court emphasised (citing Privy Council and House of Lords decisions) that a person vested with a final decision power under a contract must act with a "full realisation of the responsibilities of his position" and that the procedure followed is important as an indicator of whether the person intended to exercise the conferred judicial power rather than act merely as a servant of one party.
  4. Application of standard to Ex. II: The court asked whether the Engineer-in-Chief had acted "with the consciousness" that he was disposing of the matter under Clause 41. It found the evidence did not show such consciousness: Ex. II's language merely stated the measurements were in accordance with his instructions and did not clearly import a conscious judicial decision having regard to the particular contract (which differed in important respects from the printed specification). The court attached particular significance to the fact that the contractor had not been heard prior to Ex. II being issued — an absence inconsistent with a conscious exercise of adjudicative power.
  5. Conclusion from analysis: Given the absence of procedural indicia of a judicial decision (no hearing, no request for a Clause 41 decision, possible drafting by an officer and mere circulation of prior instructions), and in light of the authorities requiring consciousness and judicial independence, the court concluded Ex. II did not fall within Clause 41 as a final, binding decision precluding judicial construction of the contract.

Holding and Implications

Holding: The court held that Ex. II does not fall within the terms of Clause 41 of the agreement and therefore does not operate to preclude the Court from construing the suit contract.

Implications:

  • Direct effect on the parties: Because Ex. II is not a Clause 41 decision binding the parties, the Court may put its own construction on the suit contract and give the contractor what he is "undoubtedly entitled to under this head under the terms of his contract" (as the opinion states).
  • On precedent and broader law: The opinion applies established authorities about the requirement that an engineer exercising final contractual powers must act consciously and judicially, but it does not purport to lay down a new principle beyond those authorities. The decision turns on the particular facts and the absence of procedural indicia that the Engineer-in-Chief intended to exercise Clause 41 powers when issuing Ex. II.
N. R. R.

This summary is based exclusively on the text of the provided opinion and does not add or infer facts beyond those stated therein.

Show all summary ...

It is necessary to refer only to Exs. I-a, KK and II. Ex. I-a is a circular letter addressed by the acting Chief Engineer to all the Executive Engineers and Assistant Engineers working on the Mayavaram-Tranquebar Railway, on the 29th October 1926. The material portions of Ex. I-a are the following: “Apparently there is some doubt existing about the interpretation of this item which reads: ‘Increment for additional height or depth over 6 feet with the sub items (a), (b) etc………….The whole section should not be paid at the initial rate plus the increment for a bank 18 feet high. The printed specification of works, III Earthwork, para 19 is quite explicit on how payments should be made.” Pausing here for a moment, we must point out that this apparently had no reference to any particular contract but was a kind of instruction which the Chief Engineer thought fit to issue under paragraph 19 of S. 3 of Ex. IV before him. On the terms of that provision there is hardly any room for doubt. But it will be impossible to connect Ex. I-a with the suit contract, not only because no claim had been made under the suit contract at the date of Ex. I-a but also because the suit contract has not followed the language of Ex. IV in this respect. The next document Ex. KK is a letter, dated 22nd December 1926, sent by the Chief Engineer to the Executive Engineer of the Shoranur-Nilambur Railway. Referring to the question of payment for earth-work the Chief Engineer there says: “This was discussed with you on the 16th instant at Angadipuram. The interpretation to be given to the clause ‘These are through rates from ground to formation level’ is, the rates are through from ground to formation, i.e, on the various steps, 0 to 6, 6 to 9, 9 to 12 and so on. It would be absurd to claim that the first 6 feet in a bank 9 feet high cost any more to throw up than the 6 feet in a bank 6 feet high. In fact it would be the other way round, as there would be less dressing to do in proportion to the contents.” Here, we must repeat what we have said before, in dealing with Ex. I-a, that this is a kind of executive instruction issued to his own subordinates before any particular claim had been made so far as the plaint contract was concerned; and even before us, it was not insisted on as amounting to any decision within the meaning of Cl. 41.

On behalf of the appellant, reliance was chiefly placed upon Ex. II. There can be no doubt that Ex. II, was sent after the claim for payment under the suit contract had been put forward by the contractor. But it is important to examine its terms to see whether it can be regarded as a decision within the meaning of Cl. 41. It is admitted that neither Ex. I-a nor Ex. KK, had been communicated to the Contractor, though D. W. 1 says that, sometime or other, in the course of a conversation between them he might have informed the contractor about the views stated in this document. In the bill which the contractor submitted, the Executive Engineer seems to have allowed only a much smaller rate as now insisted on by the Company, and the Contractor therefore wrote to the Engineer to say that he is unable to see why his claim at the higher rate had not been admitted by the Company. (See paragraph 1 of Ex. D-1). We may, however, mention that in a letter dated 23rd November 1927 sent by the Assistant Engineer in charge of the Shoranur-Nilambur Railway to various Contractors including the Plaintiff, there is a statement that the calculations for payment for “lift” have been made in-accordance with the Engineer-in-Chief's instruction and his decision. The letter then goes on to say

“I have therefore to refer you to Cl. 41, of your agreement and to ask you to call at the office to sign the final measurements and bills in full acceptance to enable their being passed for payment.”

It does not however appear that any further light was thrown on this reference to Cl. 41, or to the Engineer's decision, so far as the information available to the Contractors went. Soon after the claim under Ex. D-1 was made, it would appear from the evidence of D. W. 1 that the Sub-office dealing with matters relating to the Shoranur-Nilambur Railway was closed and all matters relating thereto were dealt with by the Chief Engineer himself. So far as the record discloses, that appears to be the reason why Ex. D-1 was sent up to the Chief Engineer for disposal. There is nothing either in the documentary evidence or in the evidence of D. W. 1 to suggest that it was by reason of any request to him to decide a dispute between the parties in terms of Cl. 41, that the matter was sent up to the Engineer-in-Chief. All that we find from a note (Ex. D-2) on Ex. D-1, is that it was forwarded to the Engineer-in-Chief with the statement of remarks by the Assistant Engineer and by D. W. 1. What those remarks are we do not know as they have not been placed before the Court. It is admitted by D. W. 1 that when Ex. D-1, was received by the Chief Engineer, he discussed the contractor's claim with D. W. 1, that the contractor was not present at the discussion, that there was no other evidence before the Engineer-in-Chief except what was contained in Ex. D-1 itself and that the Engineer-in-Chief relied upon his knowledge of the works and the witness's knowledge. Under these circumstances, a communication was sent to the Contractor giving the answer of the Engineer in-Chief to the claim made in Ex. D-1. That is Ex. II. In respect of the claim now in question, it states, in paragraph 1, that “the measurements for lift recorded in the final measurements are in accordance with the agreement and specifications and as per my instructions on the subject and payment in the manner claimed by you is inadmissibile.” There is a note, marked Ex. II-a in the case, dated 14th February 1928, which purports to be a note by D. W. 1 sending up the draft of Ex. II, to the Chief Engineer for approval and signature. It is suggested on the plaintiff's side, that Ex. II, has really been prepared by D. W. 1 himself and sent on in the ordinary course with the signature of the Engineer-in-Chief like any other office communication. D. W. 1 would, however, state that he drafted Ex. II under instructions given to him orally by the Chief Engineer. It does not seem to us very material whether the draft was made in one way or the other. The real question for decision is whether in sending Ex. II, the Chief Engineer could be held to have acted with the consciousness that he was disposing of the matter under Cl. 41 of the agreement.

Our attention has been drawn to several cases dealing with the position of architects or Engineers whose decision is made final, in respect of contracts whose execution is put under their supervision. It is not necessary to refer to them in detail. There has no doubt been a consensus of opinion that they are, not “arbitrators” in the sense in which that term is used in the Arbitration Act, but all the cases recognise that, whether called arbitrators or quasi-arbitrators or by any other label, they are, when exercising that kind of power, discharging “judicial” functions, Decisions of the Privy Council and of the House of Lords particularly emphasise that Engineers placed in that situation especially when they happen to be the employees of one of the contracting parties, are in a very delicate and embarrassing situation, and while on the one hand it is true that the other party is bound by a contract into which he has entered with his eyes open knowing that finality is attached to the decision of an employee of the other side, that party is entitled to insist that that person should have acted judicially with a full realisation of the responsibilities of his position in dealing with a matter of that kind.

We are not now called upon to define the extent of formal procedure which should be adopted by a person exercising Such a power; but the procedure followed by him is at least important as indicating whether in the particular instance he intended to act only as a servant of one of the contracting parties or in the conscious exercise of the powers conferred on him by the special terms of the agreement. This aspect of the question is adverted to by their Lordships of the Privy Council in Bombay, Burmah Trading Corporation Limited v. Aga Mahomed Khaleel Shirazi (1) and by the House of Lords in Hickman & Co. v. Roberts (2) and Bristol Corporation v. John Aird and Co. (3). Two other cases referred to by the learned counsel for the appellant, namely, Stevenson v. Watson (4) and Chambers v. Goldthorpe, Restell v. Nye (5) are not much in point. They deal with the question how far an Engineer or architect acting under such circumstances can be held liable for negligence. It is one thing to say that he will not be liable for negligence but quite another thing to say whether he could be held to have acted judicially or not, in a particular matter. For instance, an award may be void owing to the fact that certain well-understood rules have not been complied with but, all the same, the arbitrator may not be liable in damages. We therefore think that these two cases really do not throw any light on the question for decision.

Taking it, then, that a Court, called upon to hold any expression of opinion by such an Engineer in such circumstances final and conclusive between the parties, must at least be satisfied that the person was conscious of the fact that he was called upon to exercise that power and was exercising that power with the sense of responsibility and judicial independence required for the purpose, we have given our best consideration to the circumstances here and we see no reason to differ from the lower Court in the view that it took as to Ex. II. The evidence does not show that the Chief Engineer was at all conscious of the fact that the contract in this case differed in very important particulars from the printed specification in the company's Standard Book (Ex. IV). Paragraph I of Ex. II, already quoted, only states that the measurements have been prepared in accordance with the Engineer's instructions on the subject and it is difficult to read it as importing a further decision that these instructions are right, in view of the terms of the particular contract. It is from this point of view that we attach particular significance to the fact that the contractor had not been heard at all before Ex. H was sent. It is one thing to say that he agreed to abide by the decision of a person who might have pre-formed views in the matter; but it is a different thing to say that these pre-formed views must bind him merely because they are reiterated in a subsequent letter before he has had any opportunity to persuade the Engineer in favour of his own contention. For these reasons we are unable to hold that Ex. II falls within the terms of Cl. 41 so as to preclude the Court from putting its own construction on the suit contract and giving to the contractor what he is undoubtedly entitled to under this head under the terms of his contract.

******

N. R. R.