The State Of Bihar And Another v. Gulabi Devi And Others
Factual and Procedural Background
This appeal was brought by the State of Bihar against an arbitral award in favour of a contractor (the respondent). The opinion opens with the factual matrix: the State issued a notice inviting tenders for supply of boulders and construction of embankments; the respondent firm submitted tenders and agreements were executed by the Executive Engineer and the contractor. The opinion records the following agreements (as listed in the judgment):
- Agreement No. 28H2 of 1974-1975 — supply of stone boulders at Koilwar; value Rs. 1,31,976/-.
- Agreement No. 1 H 2 of 1975-1976 — supply of stone boulders at Babura; value Rs. 1,09,247/-.
- Agreement No. 11 H 2 of 1975-1976 — supply of stone boulders at Koilwar; value Rs. 2,04,225/-.
- Agreement No. 28F2 of 1974-1975 — construction of embankment along the right bank of West Gangi; value Rs. 10,00,000/-.
- Agreement No. 18F2 of 1974-1975 — construction of embankment from Railway line near Jamuria in East Gangi; value Rs. 2,50,000/-.
A dispute arose: the State complained of incomplete work beyond the stipulated period, while the contractor blamed the State for delays and obstructions. The respondent filed a petition dated 9.9.1978 in the Court of Subordinate Judge I, Patna, challenging the suitability of the designated arbitrator (the Superintending Engineer) under clause 14 of the agreements and expressing lack of faith in him. The trial court proceeded under section 20 of the Arbitration Act, obtained the agreements, and, after noting that the designated arbitrator had been transferred, accepted names suggested and ultimately appointed an arbitrator (identified in the opinion as Sri K.N. Lall).
The arbitrator proceeded despite an objection to his appointment, rejected that objection, and the State applied for an adjournment to pursue the matter in a higher court (adjournment refused). Both parties participated and led evidence; the arbitrator ultimately made an award in favour of the contractor granting a sum of Rs. five lakhs with 10% interest per annum from 1.1.1976. When the award was transmitted to the Court, the State filed objections; the Court below rejected those objections on several grounds (including that the arbitrator had not given reasons and that the State had participated in the arbitration), and the State appealed to the High Court.
Legal Issues Presented
- Whether objections to the appointment of the arbitrator, the arbitration procedure followed (including non-compliance with section 14 of the Arbitration Act), the validity of the agreements (including reliance on Article 299 of the Constitution) and the consolidation of multiple agreements into one arbitration proceeding are foreclosed by the State's participation (i.e., whether the doctrine of estoppel / waiver applies).
- Whether a court can inquire into the merits or correctness of an arbitral award that does not set out reasons for the arbitrator's conclusions (i.e., whether a "bald" award precludes judicial scrutiny of correctness).
- Whether multiple disputes arising from more than one agreement (here, agreements arising from a single tender) could properly be resolved in a single arbitration proceeding and award.
- Whether the arbitrator erred in allowing a claim for compensation for idle labour and in denying the State's cross-claim.
- Whether a later objection to the award (characterised by the appellant as clarification of an earlier timely objection) should have been treated as time-barred by the Court below.
- Whether notice requirements under section 14 of the Arbitration Act (relating to signing and filing of the award and notice to parties) were violated and, if so, whether that vitiates the award or the appellant's objections.
Arguments of the Parties
Respondent (Contractor) — principal factual claim
- On entering into the contracts and receiving work orders, the contractor mobilised a labour force (imported labour of about 1,000 men from Bilaspur), paid advances and travel, arranged accommodation and implements, and began work.
- Progress was delayed initially because the Chief Engineer had not approved alignment of the embankment, leading to idling of labour and financial loss.
- Further progress was impeded by public obstructions linked to non-acquisition of land; as a result the contractor completed only part of the work. The agreement was then closed, measurements taken and a final bill prepared.
- Payments were not made despite repeated demands, which led to arbitration.
Appellant (State of Bihar) — principal assertions and objections
- The contractor obtained false and excess measurements and thereby received excess payments from the department (claimed excess payment Rs. 1,45,128/-; other figures of excess payments also asserted).
- Excess payments were allegedly detected in the department's final measurement (cited date 21.9.1979 and records).
- The alleged public obstructions due to non-acquisition of land were denied: the State argued that, had there been such obstructions, the contractor would have refused to work at the outset and closed the contract instead of continuing and drawing payments; the contractor's refusal to work on 22.3.75 was said to be a pretext after alleged fraudulent payments.
- The State denied the claim of idle labour and other claims advanced by the contractor.
- The State challenged the authority of the Additional Chief Engineer (and later reliance on Article 299) and contended that the Additional Chief Engineer had no locus to close the contract; only the Superintending Engineer could act under the terms of the agreement.
- While accepting some entitlement (e.g., that Rs. 72,892/- was due from the department on account of earnest money and security deposit), the State contended that such amounts stood forfeited because the contractor did not complete the work in time.
- Legal objections pressed in appeal included: invalid appointment of the arbitrator; contracts being void under Article 299; impermissibility of arbitrating disputes arising from multiple agreements in a single proceeding; illegality of the arbitrator allowing idle labour claim and denying State's cross-claim; alleged time-bar on a second objection before the Court as it was a fresh objection; and alleged failure to serve notices under section 14 of the Arbitration Act.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Bhikraj Jaipuria v. Union of India (AIR 1962 SC 113) | Authority that a special authority to an officer (to bind the Government) may be given in respect of particular contracts and S.230(3) of the Indian Contract Act may apply where contracts are not expressed to be made by the President/Governor. | The Court relied on the principle to reject the State's contention under Article 299: having acted upon the agreements (advances paid, work orders issued) the State had the onus to show lack of authority; the Executive Engineer's signing was sufficient absent prior objection. |
| Chatturbhuj Vithaldas Jasani v. Moreshwar Parashram (1954 SCR 817) | Illustration that an Article 299 attack (that contracts are void because not expressed to be made by President) can be met by application of S.230(3) Indian Contract Act. | The Court cited this reasoning to support that the agreements were not void merely because they were not expressly made in the Governor's name, and thus the Article 299 argument failed absent proof that the Executive Engineer lacked authority. |
| Union of India v. N.K. Private Ltd. ((1973) 3 SCC 388 : AIR 1972 SC 915) | Authority relied upon by the appellant to challenge contracts entered into on behalf of government; typically applied where the executing officer lacked authority. | The Court held this precedent inapplicable here because the appellant failed to show that the Executive Engineer was not authorised to enter into the contracts on behalf of the Governor. |
| Jaikishan Dass Mull v. Luchhiminarain Kanoria & Co. ((1974) 2 SCC 521 : AIR 1974 SC 1579) | Case where the contract itself was held void in law and arbitration clauses therefore effaced. | The Court found this precedent inapplicable because, in the present case, the agreements were not demonstrated to be void: the Executive Engineer had signed and the State had acted upon them. |
Court's Reasoning and Analysis
The Court's analysis proceeded in two principal strands, framed explicitly by the judge and then applied to the facts and each contention raised by the appellant.
-
Estoppel / Waiver by Participation:
The Court held that objections relating to the appointment of the arbitrator, the arbitration procedure (including compliance with section 14), the validity of the agreements (Article 299), and the consolidation of disputes into one arbitration could not be entertained when the appellant had actively participated in the arbitration proceedings without timely raising these objections. The Court noted that the appellants had run the gamut of the arbitration (participated, led evidence, did not pursue a remedy in a higher court when adjournment was refused) and therefore could not, after an unfavourable result, raise these procedural or jurisdictional objections. The adjudicative posture of the trial court (proceeding under section 20, calling for agreements, and appointing another arbitrator on transfer) was described as compliant with the Act and unassailed at the relevant stages.
-
Effect of a "Bald" Award (No Reasons):
The Court emphasised the settled legal position that when an award does not set out reasons for the arbitrator's conclusions, courts are excluded from examining the justifiability or correctness of the award. The judge examined the award "in extenso" and found that the arbitrator had largely recited the parties' contentions and made no reasoned findings. Consequently, the award (which granted Rs. 5,00,000 with 10% interest from 1.1.1976) was characterised as a bald award. Given that classification, factual objections to the award could not be examined or resurrected by the Court.
-
Individual Points:
- Appointment and Procedure: The court found the lower court's process under section 20 of the Arbitration Act to be proper; the appellants had not objected in time to the nomination of Sri K.N. Lall and had participated in the proceedings; the arbitrator's dismissal of the appointment objection was appropriate and, if any misconduct was alleged, the State had other remedies it did not pursue.
- Article 299 / Authority to Contract: The Court observed that the parties had acted on the agreements (advances paid, work orders issued). The court placed the burden on the State to demonstrate that the Executive Engineer lacked authority; absent such proof and absent prior objection, the agreements stood and were not void under Article 299. The Court relied on the cited precedents to support that special authority can be implied or conferred for particular contracts.
- Single Arbitration for Multiple Agreements: The Court held there was no legal bar to resolving disputes arising out of several agreements in a single arbitration, particularly where they related to the same tender and the same parties; the objection was raised late in the High Court and was also foreclosed by participation.
- Idle Labour Claim and Cross-Claim: Because the award was bald, the Court refused to probe whether the arbitrator had properly allowed the idle labour claim or denied the State's cross-claim. The judge noted that the contractor had claimed a much larger amount (about Rs. 12 lakhs) and that the arbitrator had awarded only Rs. 5 lakhs, so the exact treatment of particular items could not be discerned from the award and therefore could not be judicially examined.
- Section 14 Notice: The appellant argued that no notice under section 14 had been given. The Court treated this contention as academic because the appellant's first objection had been filed within time; the later objection being time-barred did not demonstrate absence of notice when an earlier timely objection had been lodged.
Holding and Implications
Appeal Dismissed with costs.
Direct effect on the parties:
- The High Court declined to interfere with the arbitral award that granted Rs. five lakhs with 10% interest per annum from 1.1.1976; the State's appeal was dismissed with costs.
- The State's procedural and substantive objections (appointment, Article 299 attack, consolidation of disputes, section 14 notice) were rejected primarily because of the State's participation in the arbitration and, secondarily, because the award was a bald award precluding examination of merits.
The opinion does not announce the setting of any novel legal precedent; it rests its decision on established principles concerning waiver/estoppel by participation in arbitration and the limited scope of judicial scrutiny of an award that contains no reasons.
S. Shamsul Hasan, J.:— In this appeal by the State of Bihar, the scenario is familiar, the dramatis personae usual, the start, the climax and the anti climax routine, that is, a contractor, a tender, the Executive Engineer, four agreements unaccomplished contract, claim and counter claim, arbitration, award and appeal, the contractor being the hero, the State the victim, and the arbitrator, the usual villain, with the court bringing no succour to the victim, hence the appeal. A notice was issued by the State of Bihar inviting tenders for several constructions and supply in connection with supply of boulders and construction of embankment. The respondent firm filed their tenders leading ultimately to the execution of four agreements signed by the Executive Engineer on one hand and the contractor on the other. The details of work in the four agreements are as follows:—
(i) Agreement no. 28H2 of 1974-1975 for supply of stone Boulders at Koilwar. Value of work-Rs. 1,31,976/-.
(ii) Agreement No. 1 H 2 of 1975-1976 for supply of stone boulders at Babura. Value of work Rs. 1,09,247/-.
(iii) Agreement No. 11 H 2 of 1975-1976 for supply of stone Boulders at Koilwar. Value of work Rs. 2,04,225/-.
(iv) Agreement No. 28F2 of 1974-1975 for construction of embankment along with the right bank of West Gangi. Value of work Rs. 10,00,000/-.
(v) Agreement No. 18F2 of 1974-1975 for construction of embankment from Railway line near Jamuria in East Gangi. Value of work Rs. 2,50,000/-.
2. The construction remained only to sink in the quagmire of claim and counter claim. The appellant complained of incomplete work beyond the stipulated period and the contractor blamed the State Government for the existence of that state of affairs. The aforesaid situation led to the filing of a petition dated 9.9.1978 in the Court of Subordinate Judge I, Patna, by the Respondent in which it was, after stating the facts, stated that the petitioner-respondent had no faith in the Superintending Engineer who was designated arbitrator under clause 14 of the agreement because the said Superintending Engineer had earlier held out a threat to fix the petitioner-respondent etc. The court issued notice to the State of this petition. The court then proceeded in the manner as Courts do in a proceeding under section 20 of the Arbitration Act and ultimately called for the filing of the agreements. It will be relevant, in order to answer the points raised to set out certain extract from the order-sheet undiluted by any interpretation which is as below:—
It appears from the order-sheet that the designated arbitrator was transferred but no incumbent had joined the post. Since probably the petitioner was keen to get an early arbitration of his dispute, at his request, in the absence of the Superintending Engineer, the court suggested three names that was given in the Court by the petitioner-respondent for being appointed as an arbitrator. Ultimately, the Court appointed the present arbitrator without any objection thereafter by the State in spite of an opportunity being given to do so. From the order-sheet, it also appears that a considerable time elapsed between the reference to the arbitrator by the Court and the arbitrator entering into the arbitration. A petition was filed before the arbitrator objecting to his proceeding with the reference on the ground of improper appointment. The arbitrator dismissed this petition. The State then filed an application for adjournment in order to take the matter upto a higher Court. Though the adjournment was refused but this was not done and the appellant participated in the arbitration proceeding throughout. Evidence was led by both the sides and several points were urged both by the contractor-respondent and the appellant resulting ultimately in the award. When the award was transmitted to the Court, the appellant filed an objection. The Court, however, rejected the objection, basically and broadly, on two grounds apart from others. It held that in the award in which the arbitrator did not state the reasons for the conclusions arrived at, the Court cannot embark upon an inquiry into the correctness of the award and the appellant having participated in the arbitration proceedings could not raise any objection they did. The Court, however, held partially the point of bar of limitation hitting the filing of the objection in favour of the appellant rejecting however, the second objection which they claimed to be a mere clarification of the points raised in the first objection but the Court treated it as a separate objection.
Schedule XLII—High Court No. (J)9(Old(M)164)
FROM OF ORDER SHEET
COURT OF Sub-Judge I, Patna.
Misc. Judl. Case No. 53 of 1978.
Shri R.P Gupta v. Executive Engineer, Flood Central Division, Arrah.
3. The claim of the respondent-applicant their contractor was as follows:—
On entering into the contract and on receipt of the work order, he started work with imported labour force of 1000 men from Bilaspur in Madhya Pradesh. He paid advance money to each of them and also the railway fares. At the site of the work, he made arrangements of their accommodation in tents and purchased implements for the work and then he started the work with a view to complete the work in time. For some days, progress of the work was held up for want of approved alignment of the embankment by the Chief Engineer which caused his labour to sit idle and thereby he suffered heavy financial loss. However, the work was started but the progress of the work dwindle down due to public obstructions on account of want of land acquisitions. Due to this handicap and other obstructions, the contractor-applicant could complete only part of the work. Thereafter the agreement of the applicant was closed and all the works done by him was ordered to be measured and final bill was prepared. On payments not being made after repeated demands, the matter gave rise to the arbitration.
4. The claim of the State appellant is as follows:—
(i) The contractor had falsely got excess measurements of his works done by the department vide pages 72 to 83 of M.B No. 21 submitted and has thus managed to receive excess payments of Rs. 1,45,128/- from the department fraudulently.
(ii) The above excess payment has been detected by the opposite party after taking the final measurement of the contractor's earth on 21.9.1979 vide pages 62 to 72 of M.B No. 26 submitted.
(iii) It was incorrect to say that there were public obstructions in borrowing earth for the construction of embankment due to non-acquisition of lands because had there been any public obstruction due to non-acquisition of land, he would have refused to work in the very beginning and would have asked the department then to close his contract. The contractor refused to work vide his letter no nil dated 22.3.75 because he after receiving false and fraudulent payments of Rs. 2,98,508/- upto 2nd on a/c bills wanted to get away from the work on false plea of public obstructions due to non-acquisition of land.
(iv) The opposite party has denied the claims of idle labour stating that there was no public obstructions.
(v) The order of the then Addl. Chief Engineer of Flood Control Organisation, Patna, contained in his letter no. 2076 dated 13.12.1975 to close the contract was void in law as the Additional Chief Engineer has no locus standi under the terms of the agreement to interfere with the performance of the contract. It is only the Superintending Engineer and none else.
(vi) The opposite party accepted that Rs. 72,892/- of the applicant is due from department on account of earnest money and security deposits but the money now stands forleitted to Government since the contractor did not complete the work in time.
(vii) All other claims of the applicant were denied by the opposite party State.
5. Learned counsel for the appellant Mr. M.S Madhup with a good deal of forensic skill created, I must confess, a mirage which ultimately on a closer approach was found to be without substance. He raised several points but great stress was laid on the following:—
(i) Since the appointment of the arbitrator was not in accordance with law and the arbitrator chose to proceed with the arbitration in spite of the objection by the appellant, the award cannot be sustained.
(ii) Since the agreement entered into between the contractor and the Executive Engineer was not in accordance with law and Article 299 of the Constitution of India, the entire proceeding was void and no right accrues to the respondent contractor.
(iii) The arbitrator in terms of section 20 of the Arbitration Act, 1940 (hereinafter referred to as ‘the Act’) and other sections of the Act cannot arbitrate that dispute arising out of five agreements in one arbitration proceeding followed by a single award. Each one being a separate dispute, should have been subjected to separate arbitration proceeding and separate award.
(iv) The arbitrator should not have allowed the claim for idle labourers which claim strictly prohibited by the agreement itself and also should not have denied cross-claim of the State.
(v) The second objection filed before the Court to the award should not have been ignored as barred by time because they were really elucidation of initial objection which was filed within time and was not a fresh objection at all.
(vi) No notice was served on the appellant under section 14 of the Act either by the Court or by the arbitrator for the purpose of filing the objection.
6. Collectively, these points and all other smaller points raised, though not mentioned by me, can be disposed of by deciding the two points—(i) whether the objections now raised or raised before the Court were hit by the doctrine of estoppel and (ii) whether an inquiry can be made into the correctness or otherwise of the award if it is found that the conclusion of the arbitrator is not based on any reason or finding but is what is described, in common parlance, as a bald award, thus, precluding any scrutiny by the Court. These points can then be disposed of by their individual examination also.
7. Taking up the first point, any objection regarding the appointment of the arbitrator, the procedure followed in this connection, the validity of the agreements, the observance of the provisions of section 14 of the Act and the amalgamation of various disputes in one arbitration proceeding cannot now be countenanced because the appellants surrendered to the arbitration without raising these objections at the appropriate stage and in the case of the appointment of arbitrator allowing the refusal of adjournment without taking the matter to the higher forum to stay there without any further step. In other words, having run the gamut of the entire arbitration proceeding, it is not open to the appellants to raise this issue. The details of these points will be highlighted hereafter.
8. As to the second point, the situation in law is well settled that if an award does not set out any reason for the conclusion of the arbitrator, the Courts are excluded from examining the justifiability of the award. Learned counsel for the appellant took me through certain passages of the award and submitted that the Court has stated its reasons and given its findings before coming to the final award and has further submitted that while giving the award when the Court mentions that it has examined the records of both the sides, heard arguments, considered the whole matter, it then clearly conveys that the arbitrator has discussed the points raised by the parties and has given definite findings on the questions disputed between the parties. I am afraid, I cannot accept this submission also. I have examined the entire award in extenso The award sets out the case of the applicant respondent first in detail and then has repeated the same over and over again while dealing with the various agreements but they are all clearly and patently statements of the state of affairs as claimed by the applicant-respondent. The arbitrator then sets out the case of the State. He sums it up at one place followed again by a long summing up of the case of the applicant respondent but again there appears to be no finding or reasons. This is also patent from the fact that had any conclusion or finding been intended by the arbitrator, then I have no matter of doubt that the objection of the appellant would have been considered in just opposition to the claim of the applicant. The size of the statement of the case of the parties indeed created a misgiving that the Court has arrived at reasoned conclusions and had recorded findings also on each point. The deeper examination of the matter clearly shows that it was not so. I have, therefore, no hesitation in holding that ultimate award of the arbitrator allowing a sum of Rs. five lakhs with ten per cent interest per annum thereon with effect from 1.1.1976 was without assigning any reasons whatsoever and the award indeed is a bald one. Having found this, the factual objection to the award disappears automatically and cannot be resurrected for examination by this Court.
9. On these two grounds, therefore, all the objections of the learned counsel for the appellant become unsustainable. I would, however like to examine the points raised in appeal individually also.
10. Coming to the first point, the order-sheet of the court below clearly indicates that the procedure followed was entirely in accordance with the provisions of the Act. The order-sheet set out by me is indicative of it and does not warrant any objection. The Court adopted the procedure laid down under section 20 of the Act and asked for the filing of the agreements which were duly filed and then proceeded to hear the matter and on being told that the designated arbitrator has been transferred, proceeded to appoint another arbitrator. The information with regard to the transfer of the arbitrator was given by the appellants and the appellants did not raise any objection to the nomination of Sri K.N Lall as arbitrator who gave the award. Even half hearted objection made before the arbitrator himself was given its burial there and the appellants then proceeded to participate fully and completely with the arbitration proceeding. It is too late in the day now, in my view, to raise any objection on these grounds. The objection filed was rightly rejected by the arbitrator. If the arbitrator was misconducting himself, the remedy was open to the State which was never adopted. I, therefore, see no merit in this point.
11. As to the second point, at all times, the agreements that are being assailed as being hit by Article 299 of the Constitution, were being acted upon by the parties concerned and it cannot be disputed that the advance payments were made, work orders were issued and some raw materials were supplied on the basis of these agreements. It was again on the basis of these agreements that, the contractor set up the organisation of his labourers for executing the works for which he had secured the tender and had entered into the concerned agreements. I have examined the copies of the agreements on the record filed by the State again without any objection in relation to its nature and find that the Executive Engineer had signed it on behalf of the Governor of Bihar. The counsel for the State submitted that the onus was on the contractor to show that the Executive Engineer was the duly authorised person to execute the contract. I am afraid, I cannot accept this submission as well particularly, in absence of any objection at any prior stage to the validity of the agreement raised in the manner now. The onus was entirely on the State to show that the agreement was signed by an unauthorised person and the Executive Engineer was not so authorised. The agreement purports to be in the name of the Governor of Bihar. Thus, having worked upon the basis of the agreements, in my view, it is no longer open to the State to raise an objection that is sought to be done in this appeal either in relation to the arbitration proceeding or the agreements leading to the arbitration. Further, it was not necessary to state in express words that the Executive Engineer was authorised to sign the agreement by expressly promulgated order in that behalf or by formal notifications. The special authority may validly be given in respect of a particular contract or contracts by the Governor to an officer other than the officer notified under the rules (See AIR 1962 SC 113 : Bhikraj Jaipuria v. Union Of India ). In the case of Chatturbhuj Vithaldas Jasani v. Moreshwar Parashram (1954 SCR 817) it was held as follows:—
“That the contention that the contracts in question were void because the Union Government could not be sued by reason of Art. 299(1) of the Constitution as the contracts were not expressed to be made by the President was without force because this was the type of case to which S. 230(3) of the Indian Contract Act would apply.”
12. This shows that the objection of the appellant on this ground is untenable.
13. In this connection, another decision of the Supreme Court reported in. (1973) 3 SCC 388 : AIR 1972 SC 915 (Union of India v. N.K Private Limited) was also relied upon by the learned counsel for the appellant but since he has not been able to show that the Executive Engineer was not authorised to enter into the contract on behalf of the Governor, this decision does not apply. Similarly, the decision reported in (1974) 2 SCC 521 : AIR 1974 SC 1579 Jaikishan Dass Mull v. Luchhiminarain Kanoria & Co.) relied upon by the learned Counsel for the appellant has no application to the instant case because this decision proceeds on the finding that the contract itself was void in law and, therefore, the arbitration clauses also stand effaced. As I have already held, the agreements by their being executed by the Executive Engineer are not void, hence this decision has no application. Further, the question of there being one arbitration proceeding in a dispute arising out of four agreements, this objection is also affected adversely against the appellant due to his participation in the arbitration proceeding without any objection. I, therefore, hold that the appellants are precluded from raising any objection, procedural or otherwise, on the aforesaid points and any other point that they have raised due to their participation in the proceeding without demur. Having run the gamut of the entire proceeding in a hope of a favourable decision, the appellants cannot raise this issue having lost their opportunity by participation.
14. Coming to the question of joint award arising out of different agreements, in my view, in law there is no such bar. It is true that section 20 of the Act and other sections of the Arbitration Act also use the expression ‘agreement’ in singular which indicates, as submitted by the learned Counsel for the appellant that dispute arising out of one agreement is a dispute in itself. This, however, does not mean that several disputes arising out of several agreements cannot be disposed of in one arbitration proceeding, particularly, when it relates to the same transaction as in this case. In this appeal, particularly, the agreements arise out of a single tender and thus can really be classified as a single dispute arising out of a single agreement. Had these agreements been in the name of different parties, as submitted by the learned Counsel for the appellant, the situation might have been different but both the parties being same in all the agreements and the agreements relating to a single tender, I see no legal disability in their being disposed of by a single arbitration proceeding because the totality of the claims had to be examined for the purposes of giving an award. This apart, this objection is seeing the light of the day for the first time in this Court. I, therefore, do not find any ground to efface the award on this ground.
15. In regard to the matter arising out of claim for compensation for idle labourers and cross-claim of the State, it is difficult for me to say anything after having held that the award is a bald one. Had the two grounds been dealt with, the validity of the award could have been examined, and the matter would have been dealt with. But since it is not possible for me to faith on whether this matter did form the basis of the award, I, cannot enter into this objection justifiably. In any event, the claim of the applicant respondent, as submitted by Mr. Rajgarhia was for Rs. 12 lacs and odd and, therefore, even if those items have been considered by deducting them, the result, perhaps, would be the same. Then the arbitrator having granted only five lacs out of 12 lacs and odd, as submitted by Mr. Rajgarhia, he might not have gone into this for the purposes of fixing the figure awarded by him. This point is mentioned by me hypothetically because as I have said, I cannot delve into nebulous. Lastly, coming to point nos. (v) and (vi), the learned Counsel for the appellants also assailed the award on the ground of absence of a notice as required by section 14(1)(2) and (3) of the Act. This section reads as follows:—
“14. Award to be signed and filed—(1) When the arbitrators or empire have made their award, they shall sign it and shall give notice in writing to the parties of the making and signing thereof and of the amount of fees and charges payable in respect of the arbitration and award.
(2) The arbitrations or umpire shall, at the request of any party to the arbitration agreement or any person claiming under such party or if so directed by the Court and upon payment of the fees and charges due in respect of the arbitration and award any of the costs and charges of filing the award, cause the award or a signed copy of it, together with any depositions and documents which may have been taken and proved before them to be filed in Court, and the Court shall thereupon give notice to the parties of the filing of the award.
(3) Where the arbitrators or empire state a special case under Cl. (b) of Sec. 13, the Court, after giving notice to the parties and hearing them, shall pronounce its opinion thereon and such opinion shall be added to and shall form part of, the award.”
16. According to the learned Counsel, no notice, particularly, provided under the Act, under the clauses abovequoted, was served upon the State Government. In my view, this point becomes really academic if the objection filed by the party is within the time prescribed. In this dispute, the appellant's objection was held to be within time. A subsequent objection however, was held to be beyond time but according to the learned Counsel for the appellant, this was not a new objection and it was only a clarification of the previous one. Therefore, in this regard also, the question of absence of notice becomes academic and 1 explain further, when the first objection was filed within time, there was no reason why the second objection should also not have been filed within that time. The fact that objection was filed after the due date does not indicate absence of notice anywhere when the earlier objection was within time. Therefore, there is no merit in these two points also.
17. In the result, therefore, I am unable to interfere with the award and I have no hesitation in dismissing this appeal with costs.
18. It is accordingly dismissed.