State Of Jammu And Kashmir & Ors v. Under Secretary To Government & Ors.
Judicial Opinion Summary
Factual and Procedural Background
The petitioner, initially appointed as a Clerk in the Revenue Department on 6-8-1965, was later promoted to Stenographer and served in various departments (Revenue; Irrigation & Flood Control; Superintending Engineer PWD Udhampur) and on deputation to Central Government hydroelectric projects (Salal and Dulhasti) until 30.11.1991. On 11.6.1991 the National Hydroelectric Power Corporation (NHPC) invited applications for the post of Private Secretary; the petitioner applied, was selected and, because NHPC required his services on a permanent basis, submitted a resignation dated 24.2.1992 stating it was "consequent upon my absorption in NHPC with effect from 1st December, 1991" and that he submitted his "technical resignation" effective 30th November, 1991.
The Government passed an order on 9-7-1992 accepting the resignation w.e.f. 1.12.1991(AN) (the order text references "Power Transmission Corporation Limited"). After resignation, the petitioner sought to have that resignation treated as voluntary retirement so as to obtain pensionary benefits, making multiple representations (4.11.1992, 19.11.1992, 19.1.1993, 11.2.1993, 2.3.1993 and 28.9.1993). When those representations were not decided in his favour, he filed the present writ petition claiming entitlement to pensionary/post-pensionary benefits on the basis that he had more than twenty years' qualifying service at the time of resignation.
Legal Issues Presented
- Whether the resignation tendered by the petitioner on his absorption in NHPC should be treated as a letter of voluntary retirement (entitling him to pension and gratuity) or as a resignation simplicitor which does not attract pensionary benefits.
- Whether Article 185-0(111) of the Jammu & Kashmir Civil Service Regulations (the provision permitting an option within six months after absorption into a Public Sector Undertaking where the absorption is in the public interest and with prior permission) applies to the petitioner's factual situation.
Arguments of the Parties
Petitioner's Arguments
- The resignation submitted upon his absorption in NHPC should be treated as voluntary retirement because he had qualifying service of more than 20 years and therefore was eligible for pensionary benefits.
- He made multiple representations requesting his resignation be treated as voluntary retirement and that his case be processed for monthly pension and post-pensionary benefits.
- The petitioner relied on Article 185-0(111) of the Jammu & Kashmir Civil Service Regulations (quoted in the opinion) and relied on a Supreme Court judgment (Welfare Association Central Government Employees v. Union of India, AIR 1996 SC 1201) to support his claim.
- As supporting material, the petitioner produced a government order (No. 412-GAD of 1994 dated 27-4-1994) concerning Shri D.V. Khosla, whose resignation was treated as voluntary retirement and who was given pensionary benefits after absorption in NHPC.
Respondents' Arguments
- The petitioner's case is not one of voluntary retirement; he voluntarily resigned from service and therefore is not entitled to pension or post-pensionary benefits.
- The petitioner submitted a resignation with effect from 30.11.1991(AN), and the Government accepted that resignation on 9-7-1992; had the petitioner intended voluntary retirement he should have applied for it at the time of tendering his resignation.
- The Government examined the later request to treat the resignation as voluntary retirement and concluded that an option once exercised (resignation) cannot be changed.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Welfare Association Central Government Employees v. Union of India, AIR 1996 SC 1201 | Authority concerning treatment of retirement/absorption cases where government servants were absorbed in Public Sector Undertakings and were offered retirement benefits (context of absorption in public interest). | The Court held the facts of that Supreme Court decision were materially different from the present case. The Supreme Court's reasoning related to cases where officers were absorbed in PSUs in the public interest and where the Government had devised measures to deem their retirement as in "public interest." The present case involved a competitive appointment on selection and not an absorption in the public interest, and the Court therefore distinguished the precedent and found it inapplicable. |
Court's Reasoning and Analysis
The Court analyzed the matter primarily by reference to Article 185-0(111) of the Jammu & Kashmir Civil Service Regulations (as quoted in the opinion). The article provides that where a permanent government servant while on deputation is permanently absorbed in a Public Sector Undertaking/Autonomous Body in the public interest and with prior permission from his present department, he has an option (to be exercised within six months of absorption) to choose between:
- Receiving a monthly pension and gratuity; or
- Receiving gratuity and a lump sum in lieu of pension calculated by reference to the commutation table.
The Court emphasized three elements drawn from that Article as necessary for its operation: (1) permanent absorption in a Public Sector Undertaking, (2) absorption made in public interest, and (3) prior permission from the parent department — and that the option must be exercised within six months of absorption.
Applying those principles to the facts, the Court found the present case did not satisfy the preconditions. NHPC had advertised for the post of Private Secretary; the petitioner applied and was selected. The appointment was, in the Court's view, a fresh appointment by selection rather than an absorption in the public interest at the request of the Public Sector Undertaking. Because the petitioner's joining NHPC followed a competitive selection process and was not shown to be an absorption in the public interest with prior government permission, Article 185-0(111) did not apply.
The Court noted that if the petitioner had intended voluntary retirement he could and should have applied for it when he tendered his resignation; instead he resigned. The Government accepted the resignation and was entitled to treat it as such. The petitioner later attempted to convert that resignation into a request for voluntary retirement, which the Government examined and declined on the ground that an option already exercised (resignation) could not be allowed to be changed.
With respect to the petitioner's reliance on the Supreme Court decision (Welfare Association), the Court explained that the facts of that case involved central government officers initially deputed to PSUs and later absorbed because the Government had specifically arranged for such absorption in the public interest; thus that authority did not apply to the petitioner's factual matrix.
Finally, regarding the petitioner’s example of Shri D.V. Khosla (a government order treating his resignation as voluntary retirement and granting pensionary benefits), the Court observed that an erroneous governmental action in another case does not entitle the petitioner to have the Government repeat the same error. The Court also noted that Shri Khosla was not a party to the present proceedings and his order had not been challenged in these proceedings.
Holding and Implications
Holding: The petition is dismissed. The Court concluded that the resignation tendered by the petitioner is a resignation simplicitor and not a request for voluntary retirement attracting pensionary benefits.
Implications:
- Direct effect on the parties: The petitioner is not entitled to pensionary or post-pensionary benefits from the parent department in respect of the service rendered to the State based on the resignation tendered effective 30.11.1991 (AN) and accepted by Government on 9-7-1992; the petition seeking treatment of that resignation as voluntary retirement has been dismissed.
- No broader legal change or new precedent was announced: the Court distinguished existing authority relied upon by the petitioner (the Supreme Court decision) on factual grounds and indicated that the regulatory provision (Article 185-0(111)) applies only where absorption into a Public Sector Undertaking is in the public interest with prior permission — facts not present here.
Order dated: 16/5/1997 (Jammu)
1. The petitioner was appointed as a Clerk in the Revenue Department by Deputy Commissioner, Udhampur, on 6-8-1965. He was promoted to the post of Stenographer after some time and then posted with Deputy Commissioner, Poonch. He served in the Revenue Department upto the year, 1970 when his services were transferred to Irrigation and Flood Control Department on 17th of November, 1970. From 1970 to 1975, the petitioner served in the Irrigation and Flood Control department, Jammu and remained attached with Superintending Engineer PWD Udhampur subsequently upto August 1978. In August, 1978 petitioner was deputed to Salal Hydroelectric Project, Jyotipuram (Reasi) which is a Central Government Undertaking Project. The petitioner served in the said Project upto January, 1982. The petitioner was then recalled back in the Irrigation and Flood Control department. Again by an order No.PW-118 of 1984 dated 14.2.1984 the services of the petitioner alongwith various other employees were transferred on deputation basis for a period of two years to Dulhasti Hydroelectric Project, where he continued on deputation upto 30.11.1991. On 11.6.1991, the National Hydroelectric Project invited applications from eligible candidates for the post of Private Secretary in the National Hydroelectric Power Corporation Ltd. (NHPC). Petitioner being eligible applied for the said post. Selection was made and a letter was addressed to the petitioner by Executive Director Regional NHPC, Jammu informing him that he had been selected against the said post. Since, the NHPC was interested in employing the services of the petitioner on permanent basis, he was required to get himself relieved from the parent department, therefore, he submitted his resignation on 24.2.1992. Annexure "P/6" to the writ petition is the letter of resignation submitted by the petitioner. It reads, as under:
"The Commissioner-cum-Secretary,
Public Works Department,
J&K Government, Civil Sectt.,
Jammu(J&K).
Sir,
Consequent upon my absorption in NHPC with effect from 1st. December, 1991. I hereby submit my technical resignation from the post of PA(Sr. Scale Stenographer) from J&K Irriagtion and PC Department, Jammu with effect from 30th November, 1991.
Thanking You Sir,
2. The Government passed an order on 9-7-1992 which reads, as under:
"Consequent upon his permanent absorption in Power Transmission Corporation Limited the resignation tendered by Shri Dharam Singh Sr.Scale Stenographer from the Irrigation & Flood 'Control Department, Jammu is accepted w.e.f. 1.12.1991(AN).
By order of the Government of J&K."
3. The case of the petitioner now before this Court is that the resignation which he had submitted for getting himself permanently absorbed in NHPC was infact a letter of voluntary retirement from service. He had a qualifying service of more than 20 years to his credit at the time he tendered his resignation, and therefore, the petitioner was entitled to all the pensionery benefits from the parent department. Petitioner submits that he made various representations on 4.11.1992,19.11.1992, 19.1.1993,11.2.1993. 2.3.1993 and 28.9.1993 in this regard that his resignation be treated as voluntary retirement and his case be processed for monthly pension and he be given all the post pensionary benefits. He also submitted in his representations that he had put in more than 26 years of service with the Government of J&K, and he was qualified for voluntary retirement, by putting in twenty years of service. He further submitted that he had been absorbed permanently in NHPC only after he had obtained permission from the Government. He further submits that as the Government did not decide his aforesaid representations, therefore, he was forced to approach this Court through the medium of present writ petition.
4. The controversy which needs to be decided in this case is whether the resignation tendered by the petitioner on his absorption in the Central Government Corporation has to be treated as a letter of voluntary retirement or as a voluntary resignation. The respondents have filed their objections, stating there in that the petitioner's case was not a case of voluntary retirement, and therefore, he was not entitled to any pension or post pensionary benefits. It has also been submitted that the petitioner submitted his resignation w.e.f. 30.11.1991 (AN) and it was accepted by the Government on 9.7.1992. It has further been stated that had the intention of the petitioner been to seek voluntary retirement, what stopped him from making such a request when he tendered his resignation. Had he applied for voluntary retirement, it was for the Government to decide whether to relieve the petitioner on superannuation or not? But since he resigned from the service, therefore, the Government took a view to accept his resignation; may be on the ground that no benefits would have to be granted to the petitioner. It has further been stated that after tendering the resignation, the petitioner made a representation submitting there in that his resignation be treates as voluntary retirement from service. This request was examined by the Government, and the Government came to the conclusion that once an option had been exercised by the petitioner, it cannot be allowed to be changed. The petitioner has placed reliance on Articles 185-0(111) CSR, which reads as under:
"185-0(111) (1) Notwithstanding anything contained in Art. 185-D(l) where a permanent Government servant while on deputation is permanently absorbed in public interest and with the prior permission from his present Department in a Public Sector Undertaking/Autonomous Body which does not have a pension scheme, such a Government servant, has an option to be exercised by him within six months of his absorption for either of the alternative indicated below:
(a) Receiving a monthly pension and gratuity;
(b) Receiving a gratuity and a lump sum amount in lieu of pension worked out with reference to commutation table obtaining on the date from which the pension could be disbursable;......."
5. From persual of the said Article, it appears that within six months of permanent absorption in a Public Sector Undertaking, a person so absorbed has to exercise his option either to receive a monthly pension and gratuity or a lump sum amount in lieu of pension worked out in accordance with rules. This Article applies to those person who are absorbed on a request of the Public Sector Undertaking, when the same is made in Public interest. The present case is altogether a different case, wherein applications were invited by the NHPC from all eligible candidates. It was not the case of the Corporation that they needed the services of the petitioner in public interest. They only needed the services of a well qualified person as Private Secretary, for which they invited the applications from eligible candidates. The petitioner applied for the said post and was selected. At that time, he had the option to request the State Government to retire him prematurely. But instead, he resigned from the State Service perhaps on the ground that he thought that better opportunities of service were available to him in the Corporation. After getting his resignation accepted, the petitioner has turned round and wants that his resignation letter be treated as a request for his voluntary retirement.
6. From bare perusal of the Rule mentioned above, it becomes very much clear that the employees of the State who are absorbed in Public Sector Undertaking permanently, are entitled to certain benefits like pension and gratuity; provided the absorption are made in public interest. Since, it is not the case of the petitioner that he was absorbed in the Corporation in public interest, therefore, his resignation has to be treated as a resignation simplicitor and nothing else. Learned counsel for the petitioner has placed reliance on a judgement of the Supreme Court in case titled Welfare Association Central Government Employees V/s Union of India reported in AIR 1996 SC 1201. The facts of said case are altogether different than the facts of the present case. In the case before the Supreme Court, the petitioners were Central Government employees. The Central Government sometime back had decided to start Public Sector Undertaking. To start with, the Government of India sent some of its officers/officials on deputation to some Public Sector Undertakings. It was felt that services of the Officers with sufficient experience and skill were needed for the Public Sector Enterprises, therefore, the Central Government devised measures to induct willing officers to continue in the Public Sector Enterprises. Such officers were allowed to be absorbed in such Public Sector Undertaking subsequently. The Government offered to deem their retirement as retirement in "Public interest". Consequent to their absorption in the Public Sector Undertaking, they were offered retirement benefits. The Rules laid down in the Central Civil Services Pension Rules are almost similar to the Rules laid down in Jammu and Kashmir Civil Service Regulations, but even if one goes to the core of the judgement of the Supreme Court (supra) it becomes clear that a resignation by a Government servant from the Government service for absorption in a Public Sector Undertaking in public interest, only entitles such Government servant to retirement benefits. As has been stated herein-above, the Corporation had advertised the posts, and by selection the petitioner had been appointed in the Corporation. It was a fresh appointment made on the basis of a selection and not absorption of the petitioner in public interest. Therefore, I am of the view that the petitioner's resignation from Government service was a resignation simplicitor, which would give him no benefits for the service rendered by him to the State. In his rejoinder, the petitioner has annexed a copy of Govt. order NO. 412-GAD of 1994 dated 27-4-1994 pertaining to one Shri D.V. Khosla Senior Assistant . The petitioner submits that he was also absorbed in the NHPC, but he was given the retirement benefits. From persual of the said order, it appear that although Shri Khosla had resigned from Government service, but his resignation was treated as voluntary retirement. He was given pensionary benefits in terms of Article 185-0(111) of the Jammu and Kashmir Civil Service Regulations. It is now well settled proposition that if Government commits one wrong, this Court cannot ask it to repeat the same. In any case, Mr. Khosla's order has neither been challenged nor is he a party in the present proceedings. In my view," Mr. Khosla could not also have been given the pensionary benefits, which have been given to him after he had tendered his resignation, and his absorption in the NHPC was not also made in public interest.
For the aforesaid reasons, I do not find any merit in this petition, which is dismissed accordingly.
Jammu
Dated 16/5/1997
Alert