Hulli Electricity Co. Ltd. v. Province Of Bombay

Privy Council
Dec 20, 1948
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Opinion (Lord Uthwatt)

Factual and Procedural Background

The appellants sought a declaration that the respondent Government's purported revocation (by letter of 28 January 1944, effective 1 May 1944) of a licence to supply electricity to the town of Hubli was invalid, together with consequential relief. The High Court of Judicature at Bombay dismissed the suit in its original jurisdiction and affirmed that decision in its appellate jurisdiction (with Stone C.J. dissenting). The core disputes before the Privy Council were confined to questions of statutory construction under the Electricity Act, 1910.

Background facts relevant to the statutory issues: the Government granted the Hubli Electric Licence in June 1924, which was transferred to the appellants on 28 January 1925. Distributing mains were laid and the appellants commenced supply. During the war the appellants experienced operational difficulties, including interruptions in supply noted at the end of 1941 and a planned shutdown in December 1942 for overhaul. The Government's Electrical Inspector visited the works on 10 February 1943 and reported serious defects in generating plant and inadequate capacity relative to the average peak load.

On 3 April 1943 the Government wrote to the appellants: describing the deficiencies, stating that it was satisfied there were grounds for revocation under section 4(1) of the Electricity Act, but electing under section 4(2) to allow the licence to remain in force subject to two new conditions (reconditioning the plant within six months and making proper maintenance arrangements), with a warning that failure would lead to revocation. The conditions were not fulfilled, and the Government notified revocation on 28 January 1944 (to take effect 1 May 1944).

Legal Issues Presented

  1. Whether, for the purpose of section 4(1)(a) of the Electricity Act, the Government's "opinion" that a licensee has made a wilful and unreasonably prolonged default is a subjective opinion immune from judicial inquiry (i.e., not subject to objective tests), or whether that opinion is subject to objective legal standards.
  2. Whether, if the Government was entitled to revoke the licence under section 4(1) at the date of the 3 April 1943 letter, it was thereby entitled under section 4(2) to impose new conditions as an alternative to revocation (and whether the later revocation based on breach of those imposed conditions was valid).
  3. Whether the Government, in forming the opinion under section 4(1)(a), was required to act judicially and to comply with rules of natural justice (as contended by the appellants).

Arguments of the Parties

Appellants' Arguments

  • The "opinion" referred to in section 4(1) is not merely the Government's subjective opinion but is an opinion subject to objective tests — i.e., the sufficiency of the grounds for that opinion can be examined by a court.
  • In forming its opinion under section 4(1)(a) the Government was bound to act in a judicial manner and to observe the rules of natural justice; the appellants alleged the Government failed to act so.

Respondent Government's Arguments

  • The Government pleaded that on 3 April 1943 it had formed the opinion required by section 4(1)(a) (that the appellants had made a wilful and unreasonably prolonged default and that the public interest required revocation) and that the court was not entitled to go behind that opinion.
  • The Government relied on section 4(2) to justify imposing further conditions instead of immediate revocation, and relied on the appellants' failure to comply with those conditions as the basis for the eventual revocation.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court's analysis proceeded in clearly identified steps:

  1. Pleading and factual finding: The Government had pleaded that it had formed the opinion required by section 4(1). The trial judge, in the light of the Government's letter of 3 April 1943 (which detailed defects and imposed conditions), ruled that it was not necessary for the Government to call further evidence to show that such an opinion had been formed and found as a fact that the Government entertained the relevant opinion. That ruling was acquiesced in by the appellants at trial and not specifically challenged on appeal. The Privy Council held that, given this procedural posture, the appellants could not now question the trial judge's factual finding that the Government had formed the requisite opinion.
  2. Construction of section 4(1)(a): The court examined the language of the subsection and its subject-matter and concluded that the phrase refers to the Government's opinion. The language did not support the view that that opinion was to be subjected to objective tests by the courts. In other words, the statute makes the Government's opinion the relevant matter; it does not on its face require courts to entertain an inquiry into the sufficiency of the Government's grounds in forming that opinion.
  3. Limits of the Government's opinion — law versus fact: The court recognized a necessary limitation: while the Government's opinion as to whether there has been a wilful and unreasonably prolonged default is decisive for the purposes of s.4(1)(a), questions of law remain open. Specifically, what duties or obligations are imposed "by or under" the Act is a question of law. If the Government, in forming its opinion, acted on a wrong conception of what the Act requires, its purported opinion would not be an opinion of the sort referred to in the subsection. Thus, although the Government's opinion is central and generally conclusive on the factual question the subsection addresses, it is not decisive if based on an erroneous view of the legal obligations created by the statute.
  4. Application to the Schedule and Clause VI: The court considered whether performance of Clause VI(1) of the Schedule (requiring the licensee to supply within one month of requisition once distributing mains are laid and the supply has commenced) was required "by or under" the Act. The court held that the Schedule's conditions are incorporated into licences by section 3(2)(f) (unless excluded or varied) and therefore do form part of the licence and are required "under" the Act. Section 47's provision for penalties on breach of such conditions reinforced that construction. On that basis, the performance of Clause VI was an obligation required by or under the Act, and therefore properly the subject-matter of the Government's opinion under section 4(1)(a).
  5. Conclusion on the imposition of conditions and eventual revocation: Because the Government had formed the requisite opinion under section 4(1)(a) and because the Schedule's obligations (including Clause VI) were obligations required under the Act, the Government was entitled under section 4(2) to permit the licence to remain in force subject to further conditions (as it did by the letter of 3 April 1943). The appellants failed to comply with those conditions, and on the facts found in the suit the subsequent revocation (letter of 28 January 1944) was effective.
  6. On procedural fairness and judicial character of the Government's decision: The court noted the appellants' contention that the Government was required to act judicially and observe natural justice in forming its opinion, a point relied on by Stone C.J. in dissent below. The Privy Council held that this contention was not open to the appellants on the pleadings because no averment was made on the particular facts needed to support that argument; the only pleading was that the Government had no sufficient grounds for revocation. Consequently, the Privy Council did not decide whether formation of the opinion under s.4(1)(a) is a judicial, ministerial, or administrative act and expressly declined to resolve that issue.

Holding and Implications

Holding: The Privy Council APPEAL DISMISSED. Their Lordships advised His Majesty that the appeal be dismissed and ordered that the appellants pay the costs of the appeal.

Direct consequences for the parties:

  • The Privy Council upheld the High Court's finding that the Government had formed the opinion contemplated by section 4(1)(a) when it wrote on 3 April 1943, and that the Government was therefore entitled to impose the conditions under section 4(2).
  • Because the appellants did not comply with those imposed conditions, the revocation effected by the Government (by letter of 28 January 1944, effective 1 May 1944) was held to be effective.
  • The appellants were ordered to pay the costs of the appeal.

Broader implications: The opinion confines itself to statutory construction in this case. The court did not reach or decide whether formation of the Government's opinion under s.4(1)(a) must be carried out as a judicial act subject to natural justice; that contested point was treated as not open on the pleadings and remained undecided by their Lordships.

Show all summary ...

Lord Uthwatts.-

In the proceedings out of which this appeal arises the appellants sought a declaration that the purported revocation by the respondent Government on 28th, January 1944, of a licence to supply electricity to the town of Hubli was invalid and asked for consequential relief on the footing of that declaration. Their suit was dismissed by the High Court of Judicature at Bombay acting in its original jurisdiction and that decision was affirmed by that Court in its appellate jurisdiction (Stone C. J. dissenting). Many matters at issue in the suit are not now in controversy. The substantial questions before their Lordships are confined to questions of construction arising under the Electricity Act (No. IX [9] of 1910).

[3] Under that Act the Government was empowered to grant to persons to be selected by the Government licences to supply electrical energy in areas to be specified in the licences and to lay down electric supply lines for the transmission of such energy.

[3] Sections 3 (2) and 4 (1) and (2) of the Act so far as relevant provided as follows :

"3 (2). In respect of every such licence and the grant thereof the following provisions shall have effect namely : -

(a) ....(b) ....(c) ....(d) a licence under this Part-

(i) may prescribe such terms as to the limits within which, and the conditions under which, the supply of energy is to be compulsory or permissive, and as to the limits of price to be charged in respect of the supply of energy, and generally as to such matters as the Provincial Government may think fit.X X X X X

(e) the grant of a licence under this Part for any purpose shall not in any way hinder or restrict the grant of a licence to another person within the same area of supply for a like purpose;

(f) the provisions contained in the Schedule shall be deemed to be incorporated with, and to form part of, every licence granted under this Part, save in so far as they are expressly added to, varied or excepted by the licence and shall, subject to any such additions, variations or exceptions which the Provincial Government is hereby empowered to make, apply to the undertaking authorized by the licence :

Provided that, where a licence is granted in accordance with the provisions of Cl. IX of the Schedule for the supply of energy to other licensees for distribution by them, then, in so far as such licence relates to such supply, the provisions of Cls. IV, V, VI, VII, VIII and XII of the Schedule shall not be deemed to be incorporated with the licence.

4.-(1) The Provincial Government may, if in its opinion the public interest so requires, revoke a licence in any of the following cases namely :-

(a) where the licensee in the opinion of the Provincial Government makes wilful and unreasonably prolonged default in doing anything required of him by or under this Act;

(b) where the licensee breaks any of the terms or conditions of his licence the breach of which is expressly declared by such licence to render it liable to revocation;

(c) where the licensee fails, within the period fixed in this behalf by his licence or any longer period which the Provincial Government may substitute therefor by order under sub-s. (3), Cl. (b), and before exercising any of the powers conferred on him thereby in relation to the execution of works-

(i) to show, to the satisfaction of the Provincial Government, that he is in a position fully and efficiently to discharge the duties and obligations imposed on him by his licence, or

(ii) to make the deposit or furnish the security required by his licence ;

(d) where the licensee is, in the opinion of the Provincial Government, unable, by reason of his insolvency fully and efficiently to discharge the duties and obligations imposed on him by his licence.

(2) Where the Provincial Government might, under sub-s. (1), revoke a licence, it may, instead of revoking the licence, permit it to remain in force subject to such farther terms and conditions as it thinks fit to impose and any further terms or conditions so imposed shall be binding upon, and be observed by the licensee, and shall be of like force and effect as if they were contained in the licence."

[4] Section 5 of the Act provided that where the Government revokes a licence under S. 4 (1) the Government should serve a notice of revocation upon the licensee.

[5] The only other section to which it is necessary to refer is S. 47 which provides that where a licensee makes default in any of the conditions of a licence the licensee should be liable to the fines therein set out.

[6] The Schedule referred to in S. 3 (2) (f) contained many provisions relating to the conduct of the undertaking under the licence. It is necessary only to refer to sub-cl, (1) of VI which runs as follows :

"VI.-(1) Where after distributing mains have been laid down under the provisions of Cl. IV or Cl. V and the supply of energy through those mains or any of them has commenced, a requisition is made by the owner or occupier of any premises situate within the area of supply requiring the licensee to supply energy for such premises, the licensee shall, within one month from the making of the requisition, or within such longer period as the Electric Inspector may allow, supply, and, save in so far as he is prevented from doing so by cyclones, floods, storms or other occurrences beyond his control, continue to supply, energy in accordance with the requisition."

[7] On 26th June 1924, the Government granted a licence- The Hubli Electric Licence, 1924- to Amti and Co., Hubli, and such licence was on 28th January 1925, duly transferred to the appellants with the consent of the Government. The result of this transfer was that for all the purposes of the Act and the licence the appellants stood in the shoes of the original licensee.

[8] It is unnecessary to refer in detail to the provisions of the licence. The area of supply and compulsory area of supply were set out. No condition of the licence (save one which was shortly after the grant of the licence complied with) was expressed to be a condition the breach of which was declared to render the licence liable to revocation. No material variation was made in any of the conditions set forth in the Schedule to the Act.

[9] The distributing mains referred to in cl. V (1) of the Schedule were duly laid down shortly after the grant of the licence and thereupon the appellants began to supply electricity under the licence.

[10] It appears that the appellants were during the war faced with difficulties in the conduct of their undertaking. It is not necessary to consider their difficulties at length. Suffice it to say that at the end of 1941 the Government demanded and received explanations as to an interruption in the supply, but there is nothing to show whether or not the Government was satisfied with the explanations which were given. In December 1942, the appellants informed their customers and the Government that they pro. posed to shut down their works altogether on 18th December for the purpose of a thorough overhaul and stated that they anticipated resuming supply by 1st January 1943.

[11] On 10th February 1943, the Government's Electrical Inspector paid a visit or inspection to the appellants' works and made a report to the Government. Following on that report the following letter was on 3rd April 1913, sent by the Government to the appellants:

3rd April 1943.

"From

The Deputy Secretary to the Government of Bombay, Public Works Department.

Messrs. The Hubli Electricity Company Limited. Subject:-Hubli Electric Licence, 1924.

"Dear Sirs,

The Electric Inspector, Bombay Province, who recently visited your Company reports as under :

'There is no qualified Engineer or other person in charge of the Supply Company's station and works, either electrical or mechanical. There are six generating seta in the power house.

Description of the Sets.Condition of the Sets.

1.750 B. H. P. engine 600 KVA. generator.with Unserviceable owing to broken crankshaft.

2.480 B.H. P. engine 296 KW generator.withUnserviceable owing to broken crankshaft.

3.350 B.H.P. engine 275 KVA. generator.withUnserviceable, cylinder heads and piston heads cracked.

4.150 B.H.P. engine 130 KVA. generator.withHas been dismantled and new parts are being fitted from the Railway workshop.

5.150 B H.P. engine 130 KVA. generator.withThe engine is in such bad condition that not more than 60 KW load can be put on the generator.

6.115 B H.P. engine 82 KVA. generator.withThe set is in a very bad condition and repairs are badly needed.

'It will be seen from the above that only one set No. (5), can be used for obtaining power, the maximum being 60 KW against the Company's average peak load of 180 KW'.

2. Government is satisfied that there are sufficient grounds for revoking your licence under S. 4 (1), Electricity Act, but it is pleased to permit the licence to remain in force under S. 4 (2) of the Act subject to the following conditions :

(a) that within a period of six months from the date of this letter you recondition your plant and put the same in proper working order for the purpose of ensuring a continuous and efficient supply to all consumers connected to the system and in order to fulfil the obligation imposed on you by virtue of the contract with the consumers as laid down in Cl. VI of Schedule to the I. E. Act, 1910, subject to the limitations imposed by the order issued under the Defence of India Rules, and

(b) that you make proper arrangements for the maintenance of the plant immediately.

3. Should you fail to take necessary steps to fulfil the above conditions your licence will be revoked.

Yours faithfully,

Sd. C. G. KALE

3-4-43

Deputy Secretary to the Government of Bombay, Public Works Department."

[12] The new conditions contained in that letter were not, it was held in the suit, complied with and on 28th January 1944, the Government wrote to the appellants informing them that their licence was revoked as at 1st May 1944.

[13] The matter at issue before their Lordships centres on the validity of the imposition of the new conditions. If when the letter of 3rd April 1943, was written, the Government was not entitled to revoke the appellants' licence, the condition precedent to the right of the Government to introduce new conditions under S. 4 (2) of the Act was not fulfilled, and a revocation based on a breach of the new conditions would be a nullity. On the other hand, if the Government was at the date of the letter entitled to revoke the appellants' licence then the Government was entitled to introduce the new conditions and, on the facts found in the suit, the revocation of the licence on 28th January 1944, was effective.

[14] In the proceedings the Government pleaded that on 3rd April 1943, it was of opinion that the appellants had made a wilful and unreasonably prolonged default in doing what was required of them under the Act and that the public interest required the revocation of the licence. The Government contended that on the true construction of the Act the Court was not entitled to go behind that opinion.

[15] The appellants disputed this contention, their point being that the opinion of the Government referred to in S. 4 (1) was not the subjective opinion of the Government but an opinion subject to objective tests. They further contended that in exercising its functions under S.4 (1) (a) the Government was bound to act in a judicial manner and not contravene the rules of natural justice and that in fact the Government failed so to act.

[16] The first raises only a question of construction; the second raises also a question of fact.

[17] The second contention on which Stone C. J. rested his dissenting judgment, may be shortly disposed of. Their Lordships share the opinion of Chagla J., and Coyajee J., that this point was not open to the appellants upon the pleadings. There was no averment directed to the matter of fact upon which the contention rests, the only matter alleged being that in April 1943, the Government had no sufficient grounds for revoking the licence. It is unnecessary therefore for their

Lordships to decide whether in forming an opinion the Government had to act judicially or whether the formation of an opinion was a pure ministerial or administrative act.

[18] Before dealing with the question of construotion raised by the first contention reference should be made to two matters.

[19] First. It will be observed that the letter of 3rd April 1943, does not in terms refer to head (a) of S. 4 (1) of the Act nor does it state that the Government had formed the opinion referred to in that head. But the terms of the letter, which begins by specifying the deficiencies in the appellants' machinery and the disparity between the average peak load and the maximum capacity of the machinery and ends by imposing conditions as to the reconditioning of the plant so as to ensure a continuous and efficient supply to all consumers, make it clear that the Government had and was in no uncertain terms expressing, an opinion as to past failure of the appellants to give a supply. The requirements of cl. VI of the Schedule were obviously in the mind of the Government and the recipients of the letter could not have any doubt but that the Government was founding itself on S. 4 (1) (a) of the Act and entertained the opinion as to the public interest and the default of the appellants referred to in that sub-section.

[20] Second. As has been stated the Government in the pleadings alleged that it had formed the opinion referred to in S. 4 (1). At the trial the Judge ruled that in view of the production by the appellants of the letter of 3rd April 1943, it was not necessary for the Government to call evidence to prove-as the Government stated it was prepared to do-that the Government had formed the opinion required by S. 4 (1) (a) and the trial Judge thereupon found as a fact that the Government entertained the relevant opinion. This ruling was acquiesced in by the appellants at the trial, and in the memorandum of appeal to the High Court in its appellate jurisdiction the appellants did not take specific objection to this ruling. It is clear that the substantial dispute at the trial was not that the Government did not entertain the opinion referred to in S. 4 (1) (a) but that it bad no grounds for entertaining that opinion. In the circumstances, their Lordships do not think it is Open to the appellants to question before their Lordships the trial Judge's finding that the Government entertained the opinion mentioned in S. 4 (1) (a).

21Their Lordships now turn to the question of construction of S. 4 (1) (a). Their Lordships are unable to see that there is anything in the language of the sub-section or in the subject-matter to which it relates upon which to found the suggestion that the opinion of the Government is to Be subject to objective tests. In terms the relevant matter is the opinion of the Government-not the grounds on which the opinion is based. The language leaves no room for the relevance of a judicial examination as to the sufficiency of the grounds on which the Government acted in forming an opinion.

22Further the question on which the opinion of the Government is relevant is not whether a default has been wilful and unreasonably prolonged but whether there has been a wilful and unreasonably prolonged default. Upon that point the opinion is the determining matter and -if it is not for good cause displaced as a relevant opinion-it is conclusive. But there the area of opinion ceases. The phrase "anything required under the Act" means "anything which is required under the Act." The question what obligations are imposed on licensees by or under the Act is a question of law. Their Lordships do not read the section as making the Government the arbiter upon the construction of the Act or as to the obligations it imposes. Doubtless the Government must in expressing an opinion for the purpose of the section also entertain a view as to the question of law. But its view on law is not decisive. If in arriving at a conclusion it appeared that the Government had given effect! to a wrong apprehension of the obligations imposed on the licensee by or under the Act the result would be that the Government had not expressed such an opinion as is referred to in the section.

23The question that then emerges is whether the performance of condition VI of the Schedule incorporated in the licence by S. 3 (2) (f) is required by the licensee by or under the Act. In their Lordships' view it is. The scheduled conditions, unless excluded or modified, necessarily form part of the licence to be granted under the Act : the licence is required to be operated in accordance with these conditions and not otherwise and the authority to operate the licence is derived from the Act. To this it may be added that the latter part of S. 3 (2) (f) expressly provides that the scheduled conditions are to apply to the undertaking and that S. 47 provides for penalties judicially exigible on breach of the conditions. Performance of the scheduled conditions may not on a strict reading be required of the licensee "by" the Act it is clearly required "under" the Act.

[24] The appellants' contention therefore fails. The Government held and sufficiently expressed the opinion required by S. 4 (1) (a) and was therefore entitled to impose the conditions specified in the letter of 3rd April 1913. The

licence was effectually revoked by the letter of 28th January 1944.

[35] Their Lordships will humbly advise His Majesty that this appeal be dismissed. The appellants will pay the costs of the appeal.

Appeal dismissed.