Sarishta Devi v. Omkar Lal

Jammu and Kashmir High Court
Sep 9, 1981
Important Paras
Please sign up to view Important Paras.

(1) The petitioner filed civil 1st Misc Appeal No : 24 of 1981 and Civil 1st Misc Appeal No 25 of J981 against the order and decree of the District Judge, Kathua, dated l'9-9-81. where the petition of the respondent under section 13 of Hindu Marriage Act had been allowed while the petition filed by the petitioner under section 10 of the Hindu Marriage Act had been dismissed. Along with the said two appeals, the petitioner filed the present Civil Misc petition under Section 5 of the Limitation Act seeking condonation of delay, in filing the appeals, Notice of the said application was issued to the respondent whe has appeared through Mr Parmodh Kohli.

(2) Mr. Kohli has taken a preliminary objection to the maintainability of the application on the ground that the provisions of Section 5 of the Limitation Act dp not extend to the appeals under the Hindu Marriage Act,

{3) Mr, Padha has on the other hand had argued that Section 5 of the Act was applicable to cases under the J&K Hindu Marriage Act, 1980.

(4) The short question therefore, which requires determination is whether the provisions of Section 5 of the Limitation Act extend to appeals filed under the Jammu and Kashmir Hindu Marriage Act 1980

(5) Subsection (4) of S. 34 of H. M. Act, 1980 provides that every appeal under section 34 shall be preferred 'within the period of 30 days from the date of the decree or the order.' Under the Limitation Act (Article 156), general period of 90 days is prescribed for filing appeals against decrees and orders. There is, thus, a difference between the period of limitation prescribed under the Hindu Marriage Act, a special law and the limitation Act, for filing appeals against the order and the decree. In such a situation S 29 (2) of the Limitation Act provides :

"29 (2) whereby by special or local law prescribed for any suit, appeal or application a period of limitation different from the period prescribed therefore by the first schedule , the provisions of section 3 shall apply, as if such period were prescribed therefor in that schedule and for the purpose of determining any period of limitation prescribed for any suit, appeal or application by any special or local law:

(a) the provisions contained in section 4, sections 9 to 18 and section 22 shall apply in so far as, and to the extent to which they are not expressly excluded by such special, or local law ; and

(b) the remaining provisions of this Act shall not apply.

(6) A plain reading of the aforesaid provision shows that by a legal fiction it is provided that the period of limitation provided under a special law shall be deemed to be the period prescribed under the 1st Schedule of the Act for the purposes of reckoning limitation under section 3 of the Act. Clause (a) of Sub-section (2) of section 29 of the Limitation Act extends the benefits of some of provisions of the limitation act to the special law. However, Section 5 of the Limitation Act is not one of those provisions, the benefit of which has been extended to the special law. Sub-clause (b) of Section 29 (2) of the Limitation Act expressly lays down that other than those provisions which are mentioned in sub-clause (a) of section 29 (2), the remaining provisions of the Limitation Act shall not apply. The result in the nut shall will be, that the benefit of Section 5 of the Limitation Act cannot be extended to condone the delay in filing an appeal under the Hindu Marriage Act, 1980. as the applicability of the said Section is not covered by sub. clause (a). It is therefore obvious that the petition under Section 5 of the Limitation Act is misconceived,

(7) Faced with this situation. Mr Padha urged that the delay in the filing of the appeal in the instant case be condoned firstly because, according to him, delay was caused due to a mistake of the court and secondly because the mistake was bonafide. Elaborating on the first ground, Mr Padha submitted that in one of the orders granting myintenance pendente lite and litigation expenses, the court had mentioned in the heading "Section 24" instead of ''Section 30", thereby creating an impression, that the main case was to be disposed of under the old Hindu Marriage Act, in which the period for filing the appeal was 90 days. It was also urged that the court under the H, M- Act 1980 was under a mandatory obligation to provide a copy of the decree to the parties "at the time of passing the decree", and that since the court did not supply a copy of decree to the petitioner" at the time of passing of the decree'^, the petitioner was prevented from filing the appeals within time and as the non-supply of the copy of the decree, according to Mr Padha, was due to a mistake of the court, the petitioner cannot be penalised. He has relied upon AIR 1953 Calcutta 800 and AIR 1954 Pepus in support of his submissions.

(8) For what shall follow, the submissions of Mr Padha are totally misconceived and wholly untenable.

(9) The Hindu Marriage Act, 1980 provides in section 46 that the proceedings which had commenced under the old act shall continue as if the same had been instituted under the New Act. Therefore, the application under Section 24 of the FL M. Act 1955 which was filed admittedly before the commencement of the New Act had to be disposed of as if it be filed under the New Act. The mere mention of ,'Section 24" in the heading of the order instead of "Section 30" could not have therefore mislead the petitioner or the counsel. Ignorance of law can be no excuse nor can it provide justification for condoning the delay in filing the appeals. It hardly lies in the mouth of the counsel to urge that even after the repeal of the old Act, the petitioner still believed that the case would be disposed of under the old Act instead of the New Act, more so when in the very next breath learned counsel has relied upon Sub-section (4) of Section 28 of the New Act to urge an additional ground for seeking condonation of delay.

(10) According to Mr Padha, the court, under Sub-section (4) of Section 28 of the 1980 Act was under an obligation to supply" at the time of passing of the decree" a copy of the decree to the petitioner and that since it did not do so, the petitioner cannot be penalised for not filing the appeal within the prescribed period of limitation.

(11) This argument appears to be an argument of despair. Sub-section (4) of Section 28 reads:

"(4) In every case where a marriage is dissolved by a decree of divorce, the court passing the decree shall give a copy thereof free of cost to each of the parties."

(12) It is impossible to read in this section any mandate of the legislature requiring the court passing a decree of divorce to "supply at the time of passing the decree" a copy thereof to the parties, the words which Mr Padha seeks to read in it. The mandate of sub-section (4) of S. 28 only is that in every case where a marriage is dissolved by a decree of divorce, the copy of that decree shall be given "free of costs" to the parties. The party shall, however, have to apply for a copy and obtain it. It is not the case of the petitioner, that she applied for a copy of the decree and did not get it. If the argument of Mr Padha is accepted, then the court shall have to re-enact the section, which admittedly is not its function and is opposed to the basic rules of interpretation of statutes. The trial court, therefore, did not commit any mistake in not giving a copy of the decree to the petitioner" at the time of passing the decree". Both the judgments relied upon by Mr Padha are, therefore, not of any assistance and are distinguishable and in-applicable to the present case. The delay, therefore cannot be condoned on the grounds urged by Mr Padha.

(13) There is still one more aspect of the case which shows that the petitioner cannot claim the indulgence of this court in seeking condontion of delay in filing the appeals.

(14) The order and decree under appeal was passed by the trial court on 19-3-81. The petitioner applied for a copy of the order and decree on 14. 4 1981 The appeal under section 30) (4) of the 1980 Act could be filed till 18-4-1981. The petitioner therefore had still three days time to file the appeals within the prescribed period of limitation. She, however, filed the appeals on 15. 5. 81. What was she doing during all this period has been explained ? The affidavit of the petitioner is singularly silent about explanation for not filing the appeals between 15-4-1981 when the copy of the decree was in her hand and 15-5-81. The petitioner was obviously negligent in prosecuting her case and there was thus no "bonafide mistake" on her part for a mistake would cease to be "bonafide" where it is caused due to lack of diligence or negligence. On this ground also there is no justification made out for condoning the delay of about 24 days in filing the appeals. The petitioner has miserably failed to make out any case for condoning the delay in filing -the appeals beyond the prescribed period of limitation.

(.15) For all what has been said above. there is no justification to condone the delay in the filing of the appeals. The application is accordingly dismissed.

(16) As a consequence of the dismissal of the petition, Civil 1st Misc. Appeals No 24 of 81 and 25 of 81 and Civil Misc. Petition No. 82 of 1981 are also hereby dismissed.