Housing Board Haryana Petitioner. v. National Construction Co. .

Punjab & Haryana High Court
Apr 23, 1991
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Opinion — V.K. Jhanji, J.

Factual and Procedural Background

The Housing Board, Haryana (the Board) filed four Civil Revision petitions (Nos. 1/1991, 2/1991, 3/1991 and 190/1991) challenging orders that made arbitrators' awards rule of the court. In Civil Revisions Nos. 1 and 2 the counterparty was M/s National Construction Co.; in Nos. 3 and 190 the counterparty was Shri B.D. Mittal. Each contractor had entered into construction agreements with the Housing Board containing an arbitration clause. A dispute arose and the Board appointed Shri H.L. Dhammi, S.E. (Retd.), PWD (B&R) Haryana, as arbitrator.

The arbitrator issued four awards (amounts: Rs. 4,35,875; Rs. 4,65,330; Rs. 3,35,235; Rs. 7,01,255), each with interest at 18% per annum "from the date of the Award till realisation or till the passing of the decree whichever was earlier." The Awards were filed in Court under Section 30 of the Indian Arbitration Act, 1940. The Board filed objections under Section 30 seeking to set aside the Awards; the trial Court dismissed those objections, made the Awards rule of the Court and passed decrees for the awarded amounts.

The trial Court awarded interest following the decrees at differing rates: in the first two cases at 15% p.a. from date of decree till realisation; in the other two cases at 12% p.a. Appeals followed. The first appellate Court affirmed the trial Court in the first three cases; in the fourth case the appellate Court dismissed the Board's appeal but allowed the contractor's cross-objection and enhanced post-decree interest from 12% to 18% p.a. The Board then filed the present revision petitions under Section 115 of the Civil Procedure Code impugning the orders of the courts below that made the Awards rule of the Court.

Legal Issues Presented

  1. Whether the courts below (in Chandigarh) had territorial jurisdiction to entertain proceedings to make the Awards rule of the Court, given the Board's contention that it was not carrying on business at Chandigarh.
  2. Whether the arbitrator had jurisdiction to make the Awards where the Awards were delivered after the expiry of four months from the arbitrator entering on the reference (i.e., whether the arbitrator exceeded time limits for making the Award).
  3. Whether the arbitrator exceeded jurisdiction in awarding interest at the rate of 18% per annum from the date of the Award until realisation or the passing of the decree (as opposed to other interest periods or rates).

Arguments of the Parties

Petitioner's (Board's) Arguments

  • The courts below lacked territorial jurisdiction because the Board was not carrying on business at Chandigarh; reliance was placed on Section 31(1) of the Indian Arbitration Act, 1940 and the Supreme Court decision in Bakhtawar Singh Balkrishan v. Union of India, AIR 1988 SC 1003.
  • The arbitrator had no jurisdiction to give the Awards because they were delivered after the statutory four-month period from entering on the reference; reliance was placed on State of Punjab v. Hardayal, AIR 1985 SC 920.
  • The arbitrator exceeded jurisdiction by awarding interest at 18% per annum from the date of the Award until realisation or passing of the decree; reliance was placed on State of Andhra Pradesh v. Associated Engg. Enterprises, AIR 1990 A.P. 294.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Bakhtawar Singh Balkrishan v. Union of India, AIR 1988 SC 1003 Referenced regarding territorial jurisdiction objections taken when an Award is made rule of the Court (the opinion notes that in that case the objection was taken when the Award was made rule under sections 14 and 17 of the Act). The Court distinguished the present case from Bakhtawar Singh on the basis that in Bakhtawar Singh the territorial objection had been taken at the trial stage when the Award was made rule of Court, whereas in the present case the Board did not take such objection in the trial Court.
Pathumman v. Kuntalan, A.I.R. 1981 S.C. 1683 Sets out three conditions under which an appellate or revisional Court may entertain an objection to territorial jurisdiction: (1) objection was taken in the Court of first instance; (2) it was taken at the earliest possible opportunity (and where issues are settled, at or before such settlement); and (3) there has been a consequent failure of justice. The Court applied this three-condition test and found that the Board did not satisfy these conditions (in particular, the objection was not taken in the first instance nor shown to cause failure of justice), and therefore the territorial jurisdiction objection could not be entertained at the revisional stage.
State of Punjab v. Hardayal, A.I.R. 1985 S.C. 920 Explains time limits for making an award: if no time is specified in the arbitration agreement, the award must be given within four months of the arbitrator entering on the reference unless the Court extends time under Section 28; Sub-section (1) of Section 28 gives wide discretion to the Court to enlarge time; Sub-section (2) indicates that only the Court has power to extend time and a clause in the arbitration agreement giving the arbitrator power to enlarge time is void unless all parties consent. The Court treated the ratio as covering the present facts, observed that the parties had given written consent for enlargement of time before the arbitrator, and held that the petitioner was estopped from raising the time-limit objection at the revisional stage when no such objection had been taken earlier.
State of Andhra Pradesh v. Associated Engg. Enterprises, A.I.R. 1990 A.P. 294 Cited for the proposition that an arbitrator's power to award interest (particularly interest from date of Award to date of decree) may be restricted; the opinion notes uncertainty in that judgment's applicability due to timing relative to the Interest Act, 1978. The Court distinguished that case on the ground that it is not clear whether the reference there was made before the commencement of the Interest Act, 1978; therefore, the ratio was not applied to bar the arbitrator's award of post-award interest in the present matters.
Executive Engineer, Irrigation v. Abanaduta Jena, A.I.R. 1989 S.C. 1520 Noted in the opinion as having not specifically considered the arbitrator's power to grant interest for the period from the date of the Award till the date of the decree. The Court observed that this Supreme Court decision did not directly resolve the specific issue of post-award-to-pre-decree interest and therefore did not preclude the arbitrator's award of interest in the present cases.

Court's Reasoning and Analysis

The Court addressed each of the three contentions sequentially and based its reasoning on procedural requirements, prior authority, statutory provisions and the facts recorded in the opinion.

First contention — Territorial jurisdiction

The Court found the contention lacking merit primarily because the Board did not raise the territorial jurisdiction objection in the trial Court when it filed its petition under Section 30 of the Arbitration Act. The Court relied on Section 41 of the Arbitration Act (which makes the Civil Procedure Code applicable to proceedings before the Court subject to the Act) and the Pathumman v. Kuntalan test requiring three conditions for appellate/revisional consideration of a territorial objection. The Board failed to show that those conditions were satisfied (in particular that the objection had been taken in the court of first instance and that there was consequent failure of justice). The Court also contrasted the present facts with Bakhtawar Singh where the objection had been taken at the appropriate stage.

Second contention — Time for making the Award

The Court observed that no time-limit objection had been taken in the trial or appellate Courts; it was first raised in revision. Citing State of Punjab v. Hardayal, the Court summarized the law that the Court (under Section 28) has the discretion to enlarge time for making an award and that only the Court can extend time unless all parties jointly consent to extension. The Court noted that in the present case the parties had given written consent for enlargement of time before the arbitrator, and thus the Board was estopped from raising the time-limit objection at the revisional stage. The Court held that the Supreme Court's ratio in Hardayal covered the facts here.

Third contention — Power to award interest from date of Award to date of decree

The Court noted that the arbitrator had not awarded pendente lite interest (i.e., interest from date of reference until date of Award). The Court observed that the Supreme Court in Executive Engineer, Irrigation v. Abanaduta Jena had not specifically decided whether an arbitrator can grant interest from the date of the Award to the date of the decree. The Court further considered State of Andhra Pradesh v. Associated Engg. Enterprises but found its facts unclear with respect to whether the reference was made before the commencement of the Interest Act, 1978.

The Court then relied on Section 2(a) of the Interest Act, 1978 which defines "Court" to include a tribunal and an arbitrator. The opinion reasons that, as the arbitrator is "in the nature of a Court" under that definition, an arbitrator in a reference made after the commencement of the Interest Act is not prohibited from granting interest from the date of the Award to the date of the decree. Since the reference in these matters was made on 16th June, 1987 (after commencement of the Interest Act, 1978), the Court concluded that the arbitrator was entitled in law to award interest from the date of the Award until the date of the decree.

Holding and Implications

Holding: The revision petitions filed by the Housing Board, Haryana are dismissed.

Implications and immediate consequences:

  • The orders of the courts below making the arbitrators' Awards rule of the Court and the consequent decrees are upheld.
  • The arbitrator's awards of interest at 18% per annum (from the date of the Award until realisation or till passing of the decree, as applicable) were held to be legally permissible in these references because the references were made after the commencement of the Interest Act, 1978.
  • The Board was not permitted to raise the territorial jurisdiction and time-limit objections at the revisional stage because those objections were not taken at the trial (or other earlier) stages as required by law; the Court applied established procedural rules (including the Pathumman test and provisions of the Arbitration Act and CPC) to reach this conclusion.
  • No order as to costs was made by the Court.

The opinion does not state that it is laying down a novel precedent beyond applying and distinguishing existing authorities; it confines its decision to the facts and the legal principles discussed above.

Show all summary ...

V.K Jhanji, J. — This order of mine will dispose of four Civil Revisions No. 1 of 1991, 2 of 1991, 3 of 1991 and 190 of 1991 filed by Housing Board, Haryana through its Chief Administrator, Chandigarh.

2. Briefly the facts are that M/s. National Construction Co. in Civil Revisions No. 1 and 2 of 1991, and Shri B.D Mittal in Civil Revision No. 3 of 1991 and 190 of 1991 respectively entered into agreements with the Housing Board, Haryana for the construction of different categories of houses. The said agreements contained a clause for settlement of disputes between the parties. Dispute having arisen between the parties, the Housing Board appointed Shri H.L Dhammi, S.E (Retd.) PWD (B&R) Haryana as Arbitrator for adjudication of disputes between the parties. The Arbitrator in the first case gave an Award of Rs. 4,35,875/- plus 18% p.a interest from the date of the Award till realisation or till the passing of the decree whichever was earlier. In the second case, an Award of Rs. 4,65,330/- with interest at the rate of 18% p.a was given from the date of the Award till realisation or till the passing of the decree. In the third case, an Award of Rs. 3,35,235/- with interest at the rate of 18% p.a was made whereas in the fourth case, the Arbitrator gave an award of Rs. 7,01,255/- with interest at the ate of 18% p.a from the date of the Award till realisation or till the passing of the decree whichever was earlier. The Awards were filed in the Court for making them rule of the Court. The Board under Section 30 of the Indian Arbitration Act, 1940 (hereinafter referred to as the Act) challenged the Awards on Page: 177various objections and prayed for the setting aside of the Awards. The learned trial Court dismissed the objection petition and made the Award Rule of the Court and consequently passed the decrees for the realisation of the amounts awarded by the Arbitrator. The trial Court in the first two cases also interest at the rate of 15% p.a from the date of the decree till realisation and in the otherr two cases, interest was awarded by the trial Court at the rate of 12% p.a from the date of the decree till realisation. In the first two cases decree was passed by Shri Birinder Singh, Sub Judge Ist Class, Chandigarh; in the third case decree was passed by Mrs. Rekha M-Ittal, Sub Judge Ist Class, Chandigarh and in the fourth case the decree was passed by Shri T. R. Bansal, Sub Judge Ist Class, Chandigarh.

3. Being aggrieved of the orders of learned trial Court, the Board preferred four appeals before the first appellate Court. In the fourth case, gross objections were also filed by the contractor against the order of the trial Court granting interest at the rate of 12% p.a In the first three cases, appeals were dismissed affirming the order of the trial Court. In the fourth case, appeal of the Board was dismissed and the cross-objections were allowed and interest was enhanced by the first appellate Court from 12% p.a to 18% p.a from the date of the decree till realisation.

4. The Board has filed the present revisions impugning the order of the courts below making the Awards rule of the Court Learned counsel for the petitioner has raised the following three contentions:

(i) The orders of the courts below are without jurisdiction as Board is not carrying on my business at Chandigarh and, therefore, civil Court at Chandigarh had no jurisdiction to entertain any proceeding for making the Award rule of the Court

In support of this contention, he has referred to Section 31(1) of the Act which reads as under:—

“Subject to the provisions of this Act, an award may be filed in any Court having jurisdiction in the matter to which the reference relates.”

5. He has also placed reliance on the judgment of the Supreme Court reported as Bakhtawar Singh Balkrishan…Plaintiff v. Union Of India…Defendant, AIR 1988 SC 1003.

(ii) The Court had no jurisdiction to make an Award as rule of the Court as the Award was not given by the Arbitrator within the period of four months from the date of entering into reference.

6. He has submitted that reference was made on 16th January, 1987. Claim petition was filed on 18th June, 1987 and the Award was given on 28th December, 1987 and thus the Arbitrator had no jurisdiction to give Award after the expiry of four months. For the proposition, he has relied upon State of Punjab v. Hardayal, A.I.R 1985 S.C 920.

(iii) That the Arbitrator had exceeded its jurisdiction in awarding interest at the rate of 18% per annum from the date of the Award till realisation of the passing of the decree whichever was earlier.

7. For the proposition, he was relied upon State of Andhra Pradesh v. Associated Engg. Enterprises, A.I.R 1990 A.P 294.

8. As far as first contention of learned counsel for the petitioner is concerned, the same is devoid of any merit. Firstly, no such objection was taken by the Board when it had filed petition under Section 30 of the Act before the trial Court. By virtue of section 41 of the Act, the provisions of Civil Procdure Code have been made applicable all the proceedings before the Court subject to the provisions of Act and the rules made thereunder. The objection with regard to the territorial jurisdiction ought to have been taken by the Board at the first instance and that too when they filed petition under section 30 of the Act. The same cannot be allowed to be taken before this Court and that too when it is exercising powers under Section 115, Civil Procedure Code. It has been ruled by the Supreme Court in Pathumman v. Kuntalan, A.I.R 1981 S.C 1683 that an objection with regard to territorial jurisdiction may be entertained by an appellate Court or revisional Court on fulfilment of the following three conditions:—

1. The objection was taken in the Court of first instance.

2. It was taken at the earliest possible opportunity and in cases where issues are settled, at or before such settlement.

3. There has been a consequent failure of justice.

All these three conditions must co-exist.

9. Section 21 of the Civil Procedure Code provides that no such objection shall be allowed to be entertained by any appellate or revisional Court unless the three conditions are fulfilled.

10. In the present case, the objection of territorial jurisdiction was not taken in the first instance for was it taken when the issues were settled. Counsel for the petitioner has also failed to satisfy me as to how there has been consequent failure of justice. In Bakhtawar Singh's Case (supra), objection with regard to the territorial jurisdiction was taken when Award was made rule of the Court under sections 14 and 17 of the Act.

11. As far as the second contention of learned counsel for the petitioner is concerned, the same has also no merit No such objection was taken by the petitioner in the trial or the appellate Court. It is only for the first time that such an objection is taken before this Court. Learned counsel for the petitioner has stated that the parties to the agreement gave a consent in writing for the enlargement of time when the matter was pending before the Arbitrator. In State of Punjab v. Hardayal (supra), it has been held by the Supreme Court as under:—

“It is open to the parties to Arbitration agreement to fix a time within which the Arbitrator must give Page: 178Award, but it has to be so stated in the agreement itself. If per chance, no time has been specified by the parties in the arbitration agreement then by virtue of operation of Section 3 read with clause 3 of the First Schedule, the Award must be given with in four months of the Arbitrator entering on the reference or after having been called upon to act by notice in writing from any party to the arbitration agreement or within such extended time as the Court may allow. Sub-section (1) of Section 28 is very wide and confers full discretion on the Court to enlarge time of making the Award at any time. The discretion under Sub-section (1) of Section 28 should, however, be exercised judiciously. Subsection (2) of Section 28 also makes it evident that the Court alone has the power to extend time. It further provides that a clause in the arbitration agreement giving the arbitrator power to enlarge time shall be void and of no effect except when all the parties consent to such enlargement. It is not open to arbitrators at their own pleasure without consent of the parties to the agreement to enlarge time for making the Award.”

The ratio of the judgment of the Supreme Court fully covers the facts of this case.

12. In the present case the parties to the agreement had given their consent in writing for the enlargement of time before the Arbitrator for making the Award. Even otherwise the petitioner is estopped from making this objection at the revisional stage when no such objection was taken by the Board in the trial Court or in its objections under Section 30 of the Act.

13. The third contention of learned counsel for the petitioner is also devoid of any merit Admittedly, the arbitrator has not granted pendente lite interest i.e the period commencing from the date of the reference till the date of the Award. The Supreme Court in Executive Engineer, Irrigation v. Abanaduta Jena, A.I.R 1989 S.C 1520, had not specifically considered the power of the arbitrator to grant interest for the period from the date of the Award till the date of the decree. From the facts of the judgment in State of Andhra Pradesh (supra), it is not clear as to whether the reference to the arbitrator was made after the commencement of the Interest Act, 1978. Reference to arbitrator in that case may have been made before the commencement of the Interest Act and as such the Court did not allow interest from the date of the Award till the passing of the decree as the reference to the arbitrator in that case was made without the intervention of the Court.

14. Under Section 2(a) of the Interest Act, expression ‘Court’ includes a Tribunal and an Arbitrator. In view of Section 2(a) of the Interest Act, the arbitrator is in the nature of a Court. Therefore in a reference to arbitrator madee after the commencement of the Interest Act, 1978, the aribitrator is not prohibited from granting interest from the date of the Award to the date of the decree.

15. In the present case, reference to the arbitrator was made on 16th June, 1987 i.e after the commencement of the Interest Act, 1978 and thus the arbitrator was justified in law in awarding interest from the date of the Award till the date of the decree.

16. In the result, the revision petitions are dismissed. However, there shall be no order as to costs.

Petition dismissed.