Mohanlal Kashinath v. Krishna Premji & Co.

Bombay High Court
Dec 8, 1927
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Summary of the Opinion (extracts only from the provided text)

Factual and Procedural Background

This appeal arises from a judgment of Mr. Justice Kemp. The defendants (appellants) were purchasers from the plaintiff (respondent vendors) of 100 tons of steel baling hoops under a contract dated 17 August 1925. The contract provided for shipment in four lots: one in September, two in October and one in November 1925 (or earlier).

The September lot was taken and paid for. Disputes arose about alleged late delivery of two of the remaining lots (one of the October lots and one other). Among the contentions raised were (a) that a force majeure clause (Clause No. 3) did not apply, (b) that Clause 1 (allowing an extra 15 days) did not apply, and (c) principally, that because the written part of the contract described the price as "£11-3-0 per ton c.i.f.c.i Bombay," the contract was in substance a c.i.f contract obliging the vendor to tender a policy of insurance among the shipping documents; the appellants relied on this failure to tender to repudiate or resist payment.

The plaintiffs produced evidence that the goods were insured and the insurance policies were put in evidence as Exhibit I. The trial judge held that Clause 1 did apply and that the contract was not a normal c.i.f contract obliging tender of a policy of insurance; the present appeal challenges that conclusion. Both Marten C.J. and Crump J. delivered reasons and dismissed the appeal with costs.

Legal Issues Presented

  1. Whether Clause 1 of the contract (giving an extra 15 days) applied to shipments alleged to be late.
  2. Whether the contract, although partly written and partly printed and containing the written notation "c.i.f", was in substance a normal c.i.f contract such that the vendors were obliged at completion to tender a policy of insurance among the shipping documents (and whether failure to tender such a policy amounted to breach).
  3. Whether the force majeure clause (Clause No. 3) applied to excuse late shipment (this contention was raised below but was not persisted in before the Court).

Arguments of the Parties

Appellants' (Defendants') Arguments

  • The written portion of the contract used the term "c.i.f" in the expressed price ("£11-3-0 per ton c.i.f.c.i Bombay"); the written terms thus prevail over printed terms and import the full set of c.i.f obligations.
  • Under a c.i.f contract the vendor must tender, among the shipping documents tendered against payment, a policy of insurance; the vendors failed to tender such a policy and thereby breached the contract.
  • On specific lots the appellants also contended that Clause 1 (15 days) did not apply to excuse late delivery; and, separately, they raised a contention that the force majeure Clause No. 3 did not apply (though that force majeure point was not pressed in this Court).

Respondents' (Plaintiffs') Arguments

  • The contract must be read as an entirety: both the written and printed portions must be construed together and, where possible, reconciled into one intelligible whole.
  • The written reference "c.i.f" relates to the price only, not to the full regime of a normal c.i.f contract; the printed terms govern the mode and performance of the contract.
  • Specific printed clauses (e.g., Clause 2 on passing of property, Clause 4 on payment against bill-of-lading or delivery order, Clause 5 on clearing, and Clauses 11 & 13 on insurance) indicate this was not a normal c.i.f contract and do not impose an absolute obligation to tender a policy against payment.
  • In practice the goods were insured (policies produced as Exhibit I) and the defendants had not specifically requested the insurance policy at the relevant times (their complaint on shipping documents arose late and was not pursued until they consulted solicitors).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Glynn v. Margetson & Co. Authority for giving special importance to written terms in a contract partly written and partly printed. The court acknowledged the authority but emphasised that it does not justify neglecting the printed portion; the whole document must be construed together.
Paul Beier v. Chotalal Javerdas (Sir Lawrence Jenkins) Similar statement that written terms merit special attention where contract is partly written and partly printed. Cited to support the general principle but the court rejected the notion that the printed terms may be ignored; read contract as a whole.
In re Denbigh Cowan & Co. and R. Atcherley & Co. Interpreted the word "documents" as naturally meaning all shipping documents; substitution of a delivery order takes the place only of the bill-of-lading, not all documents. The court observed that the present contract used the word "bill-of-lading" (not "documents"); on that reading the Denbigh decision was against the appellants and supported construing Clause 4 as meaning "bill-of-lading or delivery order (in place of bill-of-lading)".
Biddell Brothers v. E. Clemens Horst Co. (Lord Justice Kennedy) Sets out the ordinary attributes of a c.i.f contract: vendor sends shipping documents including bill-of-lading and policy of insurance, together with invoice; tendering may be irrespective of arrival of the ship. The court cited this as a lucid statement of ordinary c.i.f attributes but used it to show what a normal c.i.f contract entails, then explained why the present contract did not have those attributes.
The Miramichi (Prize Court case) Example that property does not normally pass to purchaser merely by shipment where the vendor retains a jus disponendi. Used to illustrate ordinary c.i.f principles and to contrast with Clause 2 of the contract (which here treated property as passing on delivery to the steamship company).
Johnson v. Taylor Bros. and Co. Ltd. (Lord Birkenhead and Lords Atkinson) Sets out ordinary conditions of a c.i.f contract; Lords Atkinson enumerated six vendor obligations (invoice, ship correct goods, procure affreightment, arrange insurance, send shipping documents - invoice, bill-of-lading and policy - and dispatch them with reasonable despatch). Cited to explain the standard obligations in a normal c.i.f contract; the court used that enumeration to show differences between a normal c.i.f contract and the present contract.
Forbes & Co. v. County Tailoring Co. (Stein / Mr Justice Atkin) Emphasised that no universal rule applies to all c.i.f contracts; the intention of the parties governs whether property passed on shipment; referred to Section 10 of the Sale of Goods Act, 1893. Quoted to support the proposition that intention governs and that facts of the transaction (e.g. bill-of-lading made to order of financiers, reservation of jus disponendi) inform whether property passed; used to contrast with the printed Clause 2 here.
Polenghi Brothers v. Dried Milk Co. Contract with payment in cash on arrival against shipping or railway documents; illustrates complexity when shipping and railway documents are mixed and not a normal c.i.f contract. Relied on as an example that one must construe the contract according to actual intention and that mixing of document types shows departure from a normal c.i.f contract.
Wilson Holgate & Co. Ltd. v. Belgian Grain and Produce Co. Ltd. Holds that under a c.i.f contract it is obligatory to tender a policy of insurance and that a mere cover-note will not suffice. Cited for the proposition that a policy is a necessary shipping document under a normal c.i.f contract; the court noted there was no such deficiency (i.e., no mere cover-note) in the present case and that the contract was not a normal c.i.f.
Orient Co. Ltd. v. Brekke & Howlid (Referenced) Concerned with independence of policy of insurance from safe arrival of ship or goods. The court stated it was unnecessary to deal with the points raised in this case for present purposes.
Manbre Saccharine Co. v. Corn Products Co. Decision on independence of the policy from safe arrival; also cited for the proposition that a repudiation may stand even if the wrong reason was initially given. The case was cited but the court said it was unnecessary to go into its points; it was mentioned in relation to the subsidiary argument that the purchasers' eventual repudiation need not rest on the initially stated reason.
Taylor v. Oakes, Roncoroni and Co. (Cited in connection with the same subsidiary point) That a repudiation need not depend on the correctness of the initially given reason. Cited as a supporting authority for the proposition mentioned in the context of Manbre Saccharine, but the court considered the point immaterial if purchasers were wrong on the main issues.

Court's Reasoning and Analysis

The Court undertook a close textual construction of the contract, following these primary steps and observations (as expressed in the opinion):

  1. General approach to construction: The Court accepted the principle that written terms in a partly printed/partly written contract deserve special attention (citing Glynn v. Margetson and Paul Beier v. Chotalal Javerdas), but rejected any rule that the printed portion can be ignored. The whole instrument must, if possible, be construed into "one intelligible whole."
  2. Examination of specific printed clauses: The Court identified several printed clauses that are inconsistent with the attributes of a normal c.i.f contract:
    • Clause 2 (printed): Declares that property in the goods shall be deemed to have passed to purchasers as soon as they are delivered to the steamship company at the port of shipment — a provision not typical of ordinary c.i.f contracts (where property often does not pass merely by shipment if seller retains jus disponendi).
    • Clause 4 (printed): Requires payment "fully in cash against bill-of-lading or delivery order" within seven days from arrival of the steamer named on the bill-of-lading or within 30 days from invoice — language that limits the vendor's obligation to tender a bill-of-lading (or delivery order in lieu of bill-of-lading) and ties completion to arrival of the steamer, both atypical of a normal c.i.f.
    • Clause 5 (printed): Obliges purchasers to clear goods from the docks and allows vendors to elect to clear goods themselves — again not a feature of a standard c.i.f contract.
    • Clauses 11 and 13 (printed): Clause 11 indicates insurance included in price (f.p.a.) up to purchase value; Clause 13 conditions the purchaser's entitlement to any insurance claim upon taking delivery of documents and paying within a week — these clauses do not expressly impose the orthodox c.i.f obligation that a policy must be tendered against payment.
  3. Interpretation of the written term "c.i.f" in the price: The Court read the written phrase "Price: £11-3-0 per ton c.i.f.c.i Bombay" as indicating price only, not as importing all the standard c.i.f obligations into the contract. The printed terms, as the operative performance clauses, govern the manner of performance.
  4. Application of precedent to textual features:
    • In re Denbigh Cowan was used to show that where the contract says "bill-of-lading" (not "documents") the contractual obligation is to tender a bill-of-lading (or delivery order in lieu of bill-of-lading) rather than a full set of documents; this decision ran against the appellants' argument.
    • Authorities describing ordinary c.i.f obligations (Biddell Brothers; Johnson v. Taylor Bros.; Forbes/Stein) were recited to explain what a normal c.i.f contract requires (invoice, bill-of-lading, policy of insurance, etc.), and then contrasted with the printed terms of the present contract to demonstrate dissimilarity.
    • Wilson Holgate was cited to show the principle that a policy of insurance is required under a normal c.i.f and a cover-note is insufficient; the Court observed, however, that the present contract does not comport with a normal c.i.f and no mere cover-note issue arose here.
  5. Practical evidence and conduct: The Court took into account factual conduct and documentary evidence:
    • The insurance policies were actually produced in evidence (Exhibit I) and the goods were in fact insured.
    • The purchasers did not expressly request a policy of insurance for earlier lots purchased and paid for, and they only raised the c.i.f/document complaint after involving solicitors; the correspondence did not specifically demand production of the policy of insurance. The Court regarded this as supporting the construction that the parties did not treat the policy as an obligatory document to be tendered against payment.
  6. Conclusion of analysis: Considering textual terms (especially the printed provisions governing passing of property, payment and delivery), precedent descriptions of an ordinary c.i.f, and the parties' conduct, the Court concluded the contract was not a normal c.i.f contract and did not impose an absolute obligation on the vendor to tender a policy of insurance at the time of payment; tender of the bill-of-lading was sufficient under Clause 4.
  7. Collateral: Clause 15 (a printed clause the learned Judge below considered overriding written terms) was described as "most peculiar" and the present Court did not rely upon it; Marten C.J. explicitly said his opinion would be the same as if Clause 15 were obliterated.

Holding and Implications

APPEAL DISMISSED WITH COSTS

Holding (core ruling): The Court held that the contract, read as a whole, was not a normal c.i.f contract obliging the vendor to tender a policy of insurance among the shipping documents against payment of the price. Clause 1 applied to permit 15 days extra (so one disputed shipment was within time under Clause 1), and the vendors were not bound by the strict technical requirement contended for by the appellants. It followed that the vendors did not breach the contract by failing to tender a policy of insurance as a condition precedent to payment, and the appeal was dismissed.

Immediate consequences for the parties: The defendants (appellants) failed in their challenge and must pay costs. The plaintiffs (vendors) were not held to have breached for not tendering a policy of insurance as part of completion; under Clause 4 a bill-of-lading (or delivery order in substitution of a bill-of-lading) was sufficient in the contract's terms.

The opinion does not purport to establish any novel, broad legal rule; the Court applied established principles of contractual construction and distinguished the present contract from the attributes of a normal c.i.f contract as described in existing authorities.

Show all summary ...

Marten, C.J:— This is an appeal from a judgment of Mr. Justice Kemp by the defendants who were the purchasers from the plaintiff of 100 tons of steel baling hoops under a contract of 17th August, 1925, providing for shipment in four lots: one in September, two in October and one in November 1925 or earlier. Out of those four lots we are not concerned with one, viz. the September lot. That was taken and paid for. As regards one of the October lots, and as regards one other, objections were raised of late delivery. One objection was based on this: that the force majeure Cl. (No. 3) in the contract with reference to accidents, etc., and giving a further time of 12 weeks, did not apply on the facts of the present case. That contention has not been persisted in this Court.

2. One other contention which was persisted in was that Cl. 1 of the contract, which gave an extra 15 days beyond the period stipulated thereunder, did not apply having regard to the express terms of the document, viz., the provision for shipment which I have already mentioned. In our judgment, the learned Judge was clearly right in holding that Cl. 1 did apply. Consequently the appellant fails on that point. We are thus left with a comparatively narrow objection to two out of the four lots, viz., that this was either a c.i.f contract in substance, or else had a similar effect having regard to the true construction of certain terms and that consequently it was obligatory on the vendors to tender amongst the shipping documents a policy of insurance, and that as the vendors failed to do that, they broke their contract, and cannot succeed in this suit. This is really in the nature of a technical objection, because it is common ground that in fact the goods were duly insured. The policies were put in evidence as Ex. I. Moreover, from first to last the defendants never expressly asked for a policy of insurance to be produced, although they did specifically ask, for instance, for proof of the force majeure. They rely on this: that we have here a document partly in printed terms and partly in written terms; that the written terms must prevail, and that as those written terms provide that the price is £11-3-0 per ton c.i.f.c.i Bombay, that necessarily implies that all the necessary conditions of a c.i.f contract must be carried out.

3. Now it may be conceded that where there is a contract, such as we have here, partly printed and partly written, special importance should be given to that part of the contract which is written. We may find statements to that effect in Glynn v. Margetson & Co.(1) and Paul Beier v. Chotalal Javerdas(2), a decision of Sir Lawrence Jenkins. But that is a very long way from saying that the printed portion is to be neglected and in my judgment it would be clearly wrong to ignore in the present case the printed portion. The whole of the document, both printed and written, must be construed, and if possible one intelligible whole made of it.

4. Now taming to the contract itself: there are many indications that this is not a normal c.i.f contract. What the learned Judge finds in the Court below is that the words “c.i.f” apply to the price and not to the entire terms and mode of carrying out the contract. Turning, for instance, to Cl. 2 of the contract: it provides that the property in the goods is to be deemed

to have passed to the purchasers as soon as they are delivered to the steamship Company at the port of shipment, but you will have a lien on goods for the amount of your dues.

5. That clearly, in spite of an argument to the contrary of rather an astonishing character, is not a normal feature of a c.i.f contract, as I will presently show on referring to certain well-known authorities on the point.

6. Then a very important clause is Cl. 4 as regards payment. It runs:

We undertake to pay your invoice fully in cash against bill-of-lading or delivery order for the goods, …. within seven days from the arrival of the steamer named on the bill-of-lading or within 30 days from the date of your invoice, whichever should happen first.

7. That is to be read with the clause in the written part of the document viz.,

Payment: Within seven days after the arrival of the steamer.

8. Now we have been treated to an argument that under Cl. 4 a bill-of-lading means all documents, viz., invoice, bill-of-lading and a policy of insurance, and that consequently the vendors were in error. One short answer is that this is not what the document says. The document says “bill-of-lading.” That being so, this is not the normal mode of completion of a c.i.f contract, nor, strictly speaking, is the substitution of a delivery order.

9. One case was cited to us, viz., In re Denbigh Cowan & Co. And R. Atcherley & Co.(3), where the words “c.i.f” were used, but as regards payment cash (before delivery if required) against documents or delivery order.

10. What was held there was that the word “documents” naturally meant all the shipping documents, and that the substitution of a delivery order did not mean that it was to take the place of all the documents but only of one of them, viz., the bill-of-lading. Consequently, as we have not got the word “documents” but “bill-of-lading,” this particular case is against the appellants rather than in their favour, because on that reading it would mean that Cl. 4 is to be construed as meaning bill-of-lading or delivery order in place of bill-of-lading.

11. Then, when we come to Cl. 5 of the contract, it provides that the purchasers are to undertake to clear the goods from the docks and that they shall have no objection if the vendors elect to clear the goods themselves. Again that is not an ordinary term of a c.i.f contract. Here I may draw attention to the written provision about payment within seven days after the arrival of the steamer.

12. As was pointed out by counsel for the respondents, in the first place the arrival of the steamer has normally nothing whatever to do with an ordinary c.i.f contract. If the steamer, for instance, did not arrive then under the suit contract the obligation would be at an end. If on the other hand the steamer did arrive, then under the contract there would still be seven days before it would be obligatory on the purchasers to pay. That is not a condition of a normal c.i.f contract. Further, supposing the steamer discharged the cargo, say within one or two days, what is to happen to it pending the rest of the seven days before completion? That again is not a matter which comes under a c.i.f contract. The matter is still further complicated by the printed provision in Cl. 4 for payment within seven days from arrival of the steamer named on the bill-of-lading or within 30 days from the date of your invoice whichever should happen first.

13. Then we come to Cls. 11 and 13 about insurance. Cl. 11 provides that the insurance included in the prices is understood to be f.p.a (freight paid in advance) for not more than the purchase value,

but if covered otherwise on our request or on your discretion the difference will be payable by us.

14. Then Cl. 13 is important. It runs:

We shall not be entitled to any insurance claim or moneys to be received from the insurance company in respect of the goods unless we take delivery from you of the documents by paying the contract price and all your previous dues, if any, within a week of the arrival of the documents.

15. Now, no doubt, it may well be that the defendants were entitled to have these goods insured, and if necessary to have the policy of insurance handed over to them. But that does not necessarily mean that the technical requirement of a c.i.f contract, namely, that at completion one of the shipping documents to be tendered against the price must be a policy of insurance, is to be imported into this contract. As I have already mentioned the defendants never even asked for the insurance policies of the first two lots which they bought and paid for. Similarly, as regards the other two lots, the defendants never raised this technical objection about the shipping documents until they went to their solicitors when they took up a totally different position. Even then the correspondence shows that their solicitors never specifically mentioned the policy of insurance. Whether this omission was intentional or not it is unnecessary to speculate.

16. I should here mention that as regards Cl. 15, which is a most peculiar clause, the learned Judge took the view that it entirely overrides the written terms of the contract which, if they are inconsistent with the printed terms, are to be treated as a mere request. That clause is not relied on by the respondents before us, and I in no way rely on it as part of my judgment. My opinion is based on the same considerations as if Cl. 15 was obliterated from the contract and I hope it will be obliterated in future from the documents of the respondents.

17. Now that being shortly the position under this contract, it is to my mind quite clear that this document was not an ordinary c.i.f contract, and that further, under the terms of it, there was no necessity for the vendors to tender the policy of insurance; but that it was sufficient under Cl. 4 to tender the bill-of-lading. The invoice in the present case had of course been sent long before that. Under these circumstances I need only make a very short reference to the authorities and I only do so at all because the appellants seem to be under some curious misapprehension as to the ordinary attributes of a c.i.f contract. One of the most lucid and well accepted statements on the point will be found in the judgment of Lord Justice Kennedy in Biddell Brothers v. E. Clemens Horst Co.(4). I need not repeat them: but substantially they amount to this that in an ordinary c.i.f contract the vendor sends forward the necessary shipping documents, viz., the bill-of-lading and policy of insurance, and that they together with the invoice have to be tendered by the vendor or his agents to the purchaser, and that this may be irrespective of the arrival of the ship. This is obviously a convenience to merchants. The Prize Court case of The Miramichi(5) exemplifies this, and shows that normally the property does not pass to the purchaser merely by shipment. Consequently, in that case the fact that the vendor thus retained a jus disponendi prevented the property from passing to the buyers.

18. Then there is another useful case which my brother Crump has referred to in Johnson v. Taylor Bros. and Co. Ld.(6) where at p. 149 Lord Birkenhead sets out the ordinary conditions of a c.i.f contract and at pp. 155-156 Lords Atkinson sets out the six things which the vendor is bound to do, viz.:

First, to make out an invoice of the goods, sold. Second, to ship at the port of shipment goods of the description contained in the contract. Third, to procure a contract of affreightment under which the goods will be delivered, at the destination contemplated by the contract. Fourth, to arrange for an insurance upon the terms current in the trade which will be available for the benefit of the buyer. Fifthly, with all reasonable dispatch to send forward: and tender to the buyer these shipping documents, namely, the invoice, bill-of-lading and policy of assurance, delivery of which to the buyer is symbolical of delivery of the goods purchased, placing the same at the buyer's risk and entitling the seller to payment of their price.

19. In Stein, Forbes & Co. v. County Tailoring Co.(7) Mr. Justice Atkin, as he then was, deals with the question of the property passing. He says (p. 449):

It seems to me impossible to lay down a general rule applicable to all c.i.f contracts. The overruling question is: Does the intention of the parties appear in the course of the making and the fulfilment of the contract?’…In the present case the goods were shipped at New York on behalf of the plaintiffs, and the bill-of-lading was taken to the order of the banking firm which financed the transaction for the plaintiffs. On arrival of the ship the plaintiffs had to take up the bill-of-lading from the bankers, and, as the defendants would not take nip the documents, the plaintiffs had to take delivery … from the ship. It seems quite plain that the seller or his banker reserved the jus disponendi. It was said that the property passed to the buyer on shipment, and the seller only received his unpaid vendor's lien. That view seems to me inconsistent with Section 10 of the Sale of Goods Act, 1893, and with every business probability.

20. In the present case the mode of business was that the transaction was financed from London and the bill-of-lading was sent forward to the plaintiffs in Bombay, and made out to the plaintiffs or order. Normally under a c.i.f contract, it would be perfectly clear that the property in the goods has not passed, but that is in direct conflict with Cl. 2 of the printed terms which I have already alluded to.

21. Then there is the case of Polenghi Brothers v. Dried Milk Co.(8), where payment was directed to be in cash on the arrival of the goods against shipping or railway documents, and the goods were sent partly by sea and partly by rail. There what the learned Judge said was that you must construe that contract according to what the intention of the parties actually was. But when you get railway documents muddled up with shipping documents, one could hardly say that particular case is an example of a normal c.i.f contract.

22. Then, in Wilson Holgate and Co. Ltd. v. Belgian Grain and Produce Co. Ltd.(9), a decision of Mr. Justice Bailhache, that merely amounts to this that it is obligatory under a c.i.f contract to tender a policy of insurance, and that a mere cover-note will not do. We have nothing of that sort in the present case.

23. Further, it is unnecessary to deal with the points raised in Orient Co. Ltd. v. Brekke & Howlid(10), and Manbre Saccharine Co. v. Corn Products Co.(11), that a policy of insurance is not dependent on the safe arrival of the ship or goods. The case of Manbre Saccharine Co. v. Corn Products Co., was also relied on in connexion with another point, viz., that provided the defendants were entitled to repudiate the contract, it did not matter that a wrong reason was given in the first instance. Taylor v. Oakes, Roncoroni and Co.(12), is also relied on in that respect. But if, in the present case, the purchasers are wrong on both points, that contention is really immaterial. Of course it is quite clear that a policy of insurance, as I have already said, is one of the documents which a vendor in a normal c.i.f contract must tender against the purchase price.

24. After carefully considering the contract in the present case and all the surrounding circumstances, I am clearly of opinion that this was not a normal c.i.f contract, and that consequently the normal requirements of a c.i.f contract did not apply here. As regards the contract itself, whether one takes the printed portion or the written portion, there is no absolute obligation on the vendor to tender a policy of insurance against the purchase price. Under these circumstances, in my judgment the decision of the learned Judge is correct, and this appeal ought to be dismissed with costs.

25. Crump, J.:— This litigation arises out a contract of 17th August, 1925. It was a contract by which the defendants agreed to purchase 100 tons of steel hoops. Shipment was to be in four lots: one in September, two in October and one in November 1925. The first lot of September shipment arrived in the SS. Japan, and delivery was taken. As to that there is no question in this case. The second lot was shipped on 3rd November in the SS. Delhi, and delivery of that was taken by the defendants, they say, as being of November shipment. The third and fourth lots, that is to say, the second lot of October shipment and the lot of November shipment, arrived in the SS. Rana on 8th January, 1926, having been shipped on 29th November, 1925.

26. As to the last two lots a controversy arises. As to the first which arrived in SS. Delhi, it is said that it is not an October shipment; and, as to the last two which arrived in SS. Rana, defendants' case is that under the contract the plaintiffs were bound to tender a policy of insurance. That ground may be cleared as regards the point relating to the first lot which was shipped about 3rd November by the SS. Delhi. It appears to us that by virtue of Cl. 1 of the contract that shipment was in time, being less than fifteen days beyond the stipulated period; and no more need be said about that.

27. As to the other two lots; the defendants contended that the force majeure clause, viz., No. 3 in the contract, for some reason or other, did not apply. It is fair, I think, to say that objection was not pressed before us here, and the only point which remains as regards them was that the seller was bound to tender the policy of insurance. The argument, I think, may fairly be summarized as follows: The contract consists of printed and written terms. That being so, the written terms must prevail over the printed terms. In the written terms the words “c.i.f” are used. Therefore this is a c.i.f contract and (as has been laid down in cases already cited by the learned Chief Justice) under such a contract the seller is bound to tender a policy of insurance. But it is not strictly correct to say that where a contract consists of printed and written terms, the written terms must prevail over the printed terms. The true canon of construction, as I understand it, is that the Court will pay special attention to written terms, but will not neglect the printed terms, and will rather read the contract as a whole, remembering that the written terms express more particularly the intention of the parties, and will endeavour, if possible, to make one congruous whole out of the document. That principle the argument has overlooked.

28. I may say here that Cl. 15 has not been relied upon in this Court. It seems to me that what we have to do in this case is, as I have already said, to consider the document as a whole and to consider how the conflicting portions of it—if there are conflicting portions—can most easily be reconciled. In the printed terms the words “c.i.f” are nowhere used. But in the written terms the words “Price £ 11-3-0 per ton c.i.f.c.i Bombay” are used. An examination of the printed terms, as compared with these words, appears to me to indicate that the true canon of construction is this: that the printed terms are intended to govern the performance of the contract, and that the words I have quoted from the written terms are intended to indicate the price to be paid for the goods. If that view is accepted—and I know of no canon of construction on which that view should not be accepted—then all difficulty, I think, disappears.

29. I now turn to the printed terms in this case. It is, I think, at once apparent that there is much in them which is inconsistent with what may be called a normal c.i.f contract. In the first place-there is the question of the passing of the property in the goods. Under the written terms the property passes as soon as the goods are delivered to the steamship company for shipment. That is not an incident of an ordinary c.i.f contract. Next as regards the payment Cl. 4 says:

We undertake to pay your invoice fully in cash against bill-of-lading or delivery order for the goods.

30. That, again, is not an ordinary term of a normal c.i.f contract. There the seller is bound to tender documents other than the bill-of-lading.

31. Then it has been pointed out that the words “within seven days from the arrival of the steamer” in Cl. 4 introduce something which is quite inconsistent with the normal c.i.f contract, for the arrival of the steamer is not a matter with which the completion of such a contract is concerned. Then in Cl. 5 we find that the seller may, if he wishes, elect to clear the goods himself, that is to say, he may take the goods in performance of the contract, or he may take the documents in performance of the contract. That is not an incident of a normal c.i.f contract. I do not think it necessary to labour this point further, because, as I understood him, the appellants' counsel felt himself constrained to admit that this was after all not a normal c.i.f contract; and really, in the light of that admission, one may almost say cadit quaestio. The question that would then arise would be whether there is anything in this contract to impose upon the seller an obligation to tender a policy of insurance against payment of price. There is nothing to that effect in the contract. It is not so distinctly laid down, nor, as I read the contract, can that be fairly inferred from anything stated in it. Cl. 13 comes nearest to it, but it does not necessarily bear that meaning. It means nothing more than that if the purchaser desires to make a claim for insurance, he must get a policy of insurance from the buyer within a week of the arrival of the documents. It is impossible to extend that as meaning that the seller is bound in all cases to tender a policy of insurance. Now, in considering what these parties meant, it is not, I think, unreasonable to consider what they did. It is in evidence—and it has not been contradicted—that as regards the first two lots the sellers, sent an invoice to the buyers, whereupon the buyers came to the office of the sellers, settled the exchange and took delivery of the bill-of-lading and local invoices. No question of any policy of insurance was then raised and when we turn to the correspondence which began when this dispute arose, what do we find? That correspondence began on 10th November, 1925, and up to 8th January, 1926 the whole controversy turned upon this: that the goods were not of the contract shipment and that the defendants were not bound to accept the certificate of force majeure and had nothing whatever to do with any such certificate. Then, on 13th January, the matter came to the hands of the plaintiffs' solicitors. They wrote and called upon the defendants forthwith to pay for the goods and take delivery of the bills-of-lading and the relative documents. The defendants' solicitors answered on 16th January, and for the first time raised the question of this being a c.i.f contract, and they demanded a complete set of shipping documents. But it is very curious that, although the correspondence was carried on at considerable length, there was never any specific mention of a policy of insurance. The only document which they specifically demanded was a certificate of force majeure and they never distinctly stated anywhere that what they wanted was a policy of insurance. From that conduct it is not unreasonable to infer that the parties themselves believed that the policy of insurance was not obligatory before the payment of the price of the goods.

32. For these reasons I agree that this is not a normal c.i.f contract. It is a contract which must be construed in accordance with its terms, and upon those terms I am unable to hold that it was incumbent on the vendors to tender a policy of insurance to the purchasers. It follows that the appeal must be dismissed with costs.

33. Appeal dismissed.